Page 1: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 1

MEASURING QUANTITIES, PRICING & COST ANALYSIS

● Mat Naim bin Abdullah @ Mohd Asmoni● Diploma QS (UTM), BSc. QS (Glasgow

Caledonian University), M.Eng. Construction (UTM), PhD Facilities Management (UTM)

[email protected][email protected]● C04-308● 019-7573760

Page 2: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 2

MEASURING QUANTITIES, PRICING & COST ANALYSIS

Assumption No. 1: Total land area = 10m x 10m

Project Title: Construction and completion of guard houseOwner: Panicsonic Sdn BhdArchitect: A to Z Sdn BhdDrawing Title: Ground beam and foundation plan-------------------------------------------------------------------------Drawn by: SheilaChecked by: Aaron

Page 3: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 3

MEASURING QUANTITIES, PRICING & COST ANALYSIS

Page 4: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 4

MEASURING QUANTITIES, PRICING & COST ANALYSIS

Construction Method

1. Preliminaries (Initial site works) - % of total cost2. Site clearance and earthwork3. Foundation construction (E.g. Piling and footing)4. Work below lowest floor finish5. Frame6. Staircase7. Upper Floor8. Roof9. Wall and partition10. Door and window11. Finishes12. Sundries (Built-in furniture)13. Building services (M&E, ICT etc)14. External works (Water reticulation, landscape etc)

Page 5: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 5

MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

1) Site clearance

1.1) Clear the site including grubbing of trees, shrubs and demolish any existing structure and cart away and dump to the specified location.

10.00 10.00 ---------- 100.00 100 m2 ----------

Area of the site:10 x 10 = 100m2

Page 6: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 6

MEASURING QUANTITIES, PRICING & COST ANALYSIS

Page 7: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 7

MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

2) Foundation

2.1) Piling including all related works

6.10 6.10 ---------- 37.21 37 m2 ----------

Area of the building:Length = 3048 + 3048 = 6096Width = 3048 + 3048 = 6096

Page 8: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 8

MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

2) Foundation

2.2) Excavation for pile cap

9/1.22 1.22 1.57 ---------- 21.03 21 m3 ----------

Size of pile cap = 1219 x 1219Depth of excavation: 1524 + 50 (lean concrete) = 1574

Excavation and Lean concrete as base for pile cap

Page 9: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 9

MEASURING QUANTITIES, PRICING & COST ANALYSIS

Page 10: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 10

MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

2) Foundation

2.3) Reinforced concrete Grade 30 for pile cap

9/1.22 1.22 0.31 ---------- 4.15 4 m3 ----------

Size of pile cap:Length = 1219 Width = 1219Thickness = 305

Concrete for pile cap

Page 11: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 11

MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

2) Foundation

2.4) 50mm thick lean concrete Grade 15 for pile cap

9 / 1.22 1.22 0.05 ---------- 0.67 1 m3 ----------

Size of pile cap:Length = 1219 Width = 1219

Excavation and Lean concrete as base for pile cap

Page 12: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 12

MEASURING QUANTITIES, PRICING & COST ANALYSIS

Page 13: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 13

MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

2) Foundation

2.5) Formwork for pile cap

9 / 4 /1.22 0.31 ---------- 13.62 14 m2 ----------

Size of pile cap:Length = 1219 Width = 1219Thickness = 305

9/2/1.22 0.31 6.81

9/2/1.50 0.31 8.37

15.18 15m2

Formwork for pile cap

Page 14: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 14

MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

2) Foundation2.6) Reinforcement bar Y12 for pile cap

9/2/ 12/ 1.53 ---------- 330.48m x 0.89 kg/m = 294.13kg ----------

= 294 kg

Length:

= a + b + c – cover = 305 + 1219 + 305 – 6(50)= 1829 – 300= 1529

No. of bars:= (b/100) + 1= ((1219 – 2(50)cover )/100 )+1 = 12 nos.

a

b

c

Page 15: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 15

MEASURING QUANTITIES, PRICING & COST ANALYSIS

@100 c/c

Page 16: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 16

MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF Taker off : Checked by:3.1) Column stump3.1.1) Reinforced concrete Grade 30 for

column stump

9/0.23 0.23 1.04 ---------- 0.50 1 m3 ----------

Size of column stump:Length = 229Width = 229Height = 1524 – 305 thickness of pile

cap – (351/2) Half of beam’s thickness

= 1043.50

Page 17: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 17

MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF3.1) Column stump3.1.2) Formwork for column stump

9/4/0.23 1.04 ---------- 8.61 9 m2 ----------

Size of column stump:Length = 229Width = 229Height = 1524 – 305 thickness of pile

cap – (351/2) Half of beam’s thickness

= 1043.50

Page 18: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 18

MEASURING QUANTITIES, PRICING & COST ANALYSIS

@100 c/c

Height of column stump

Page 19: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 19

MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF3.1) Column stump3.1.3) Reinforcement bar Y12 for

column stump

9/4/2.97 ---------- 106.92m x 0.89kg/m = 95.16kg ----------

95kg

Length = a + half beam’s thickness – cover + 2 laps

= 1524 + (351/2) – 50 + (660x2)= 2969.50

lap

a

lap

Page 20: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 20

MEASURING QUANTITIES, PRICING & COST ANALYSIS

General Notes

Page 21: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 21

MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF3.1) Column stump3.1.4) R6 link in for column stump

9/6/0.62 ---------- 33.48m x 0.22kg/m = 7.36kg ----------

7kg

Length of link: (length of CS– 2cover) x 4 +hook

=(229-100)+(229-100)+(229-100)+(229-100)+100=616

No. of link:Height of column stump = 1043.50=(1043.50/229)+1= 6 nos.

Hook

Page 22: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 22

MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF

3.2) Ground beam3.2.1) Excavation for ground beam

2/3/6.10 0.23 0.35 ---------- 2.95m3 ----------

3m3

Size of ground beam:Length=3048+3048=6096Width = 229Thickness = 351

Excavation for ground beam

Page 23: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 23

MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF

3.2) Ground beam3.2.2) Reinforced concrete Grade 30 for

ground beam

2/3/6.10 0.23 0.35 ---------- 2.95m3 3m3 ----------

Size of ground beam:Length=3048+3048=6096Width = 229Thickness = 351

RC for ground beam

Page 24: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 24

MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF

3.2) Ground beam3.2.3) 50mm thick lean concrete Grade

15 for ground beam

2/3/6.10 0.23 0.05 ---------- 0.42m3 1 m3 ----------

Size of ground beam:Length=3048+3048=6096Width = 229Thickness = 351

RC for ground beam

Page 25: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 25

MEASURING QUANTITIES, PRICING & COST ANALYSIS

Assumption No. 1: Total land area = 10m x 10m

Project Title: Construction and completion of guard houseOwner: Panicsonic Sdn BhdArchitect: A to Z Sdn BhdDrawing Title: Ground beam and foundation plan-------------------------------------------------------------------------Drawn by: SheilaChecked by: Aaron

Page 26: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 26

MEASURING QUANTITIES, PRICING & COST ANALYSIS

@100 c/c

Height of column stump

Page 27: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 27

MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF

3.2) Ground beam3.2.4) Formwork for ground beam

2/3/2/6.10 0.35 ---------- 25.62 26m2 ----------

Size of ground beam:Length=3048+3048=6096Width = 229Thickness = 351

Installation of reinforcement bar and formwork for ground beam

Page 28: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 28

MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF3.2) Ground beam3.2.5) Reinforcement bar Y10 for

ground beam

2/3/4/6.50 ---------- 156.00m x 0.62kg/m = 96.72kg ----------

97kg

Length = (length–2cover)+(2bend-2cover)=(6096-(2x50))+(2x351)-(4x50)= 6498

Page 29: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 29

MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF3.2) Ground beam3.2.6) R6 stirrup for ground beam

2/3/28/0.86 ---------- 144.48m x 0.22kg/m = 31.79kg ----------

32kg

Length of stirrup:

=(229-100)+(351-100)+(229-100)+(351-100)+100=860

No. of stirrup:Length of grd beam= 6096=(6096/229)+1= 28 nos.

Hook

Page 30: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 30

MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF

3.3) Ground slab3.3.1) Excavation for ground slab

7.30 7.30 0.50 ---------- 26.65m3 27 m3 ----------

Area of slab including apron = length x widthDepth of excavation = 500mm

6096 + 1200 (apron) = 7296

300mm thick hardcore

BRC A8 150mm thick concrete slab

DPM

50mm thick sand

Installation of formwork,Damp Proof Membrane (DPM) and BRC wire mesh for ground slab

Page 31: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 31

MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF3.3) Ground slab3.3.2) Reinforced concrete G30 in

ground slab

7.30 7.30 0.15 ---------- 7.99m3 ---------- 8 m3

Area of slab = length x widthDepth of excavation = 500mm

300mm thick hardcore

BRC A8 150mm thick concrete slab

DPM

50mm thick sand

Page 32: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 32

MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF3.3) Ground slab3.3.3) Formwork for ground slab

4/7.30 0.15 ---------- 4.38m2 ----------

4 m2

Area of slab = length x widthDepth of excavation = 500mm

300mm thick hardcore

BRC A8 150mm thick concrete slab

DPM

50mm thick sand

Page 33: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 33

MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF

3.3) Ground slab3.3.4) BRC A8 for ground slab

7.30 7.30 ---------- 53.29m2 ----------

53 m2

Area of slab including apronDepth of excavation = 500mm

Length = 6096 + 1200 = 7296

300mm thick hardcore

BRC A8 150mm thick concrete slab

DPM

50mm thick sand

Page 34: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 34

MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd3) WBLFF3.3) Ground slab3.3.5) DPM for ground slab

53 m2

Area of slab = length x widthDepth of excavation = 500mm

300mm thick hardcore

BRC A8 150mm thick concrete slab

DPM

50mm thick sand

Page 35: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 35

MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF3.3) Ground slab3.3.6) 50mm sand blinding for ground

slab

53 m2

Area of slab = length x widthDepth of excavation = 500mm

300mm thick hardcore

BRC A8 150mm thick concrete slab

DPM

50mm thick sand

Page 36: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 36

MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF3.3) Ground slab3.3.7) Hardcore for ground slab

7.30 7.30 0.30 ---------- 15.99m3 ----------

16 m3

Area of slab = length x widthDepth of excavation = 500mm

300mm thick hardcore

BRC A8 150mm thick concrete slab

DPM

50mm thick sand

Page 37: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 37

MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF3.4) Half round glazeware perimeter

drain size 150mm diameter

4/7.30 ---------- 29.20m ----------

29 m

Area of slab = length x widthDepth of excavation = 500mm

300mm thick hardcore

BRC A8 150mm thick concrete slab

DPM

50mm thick sand

Page 38: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 38

MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

4) FRAME Taker off : Checked by:

4.1) Column4.1.1) Reinforced concrete Grade 30 for

column

9/0.23 0.23 3.00 ---------- 1.43 1 m3 ----------

Size of column:Length = 229Width = 229Height = Height of the wall = 3000mm

Installation of reinforcement bar and formwork for column

Page 39: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 39

MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

4) FRAME4.1) Column4.1.2) Formwork for column

9/4/0.23 3.00 ---------- 24.84 25 m2 ----------

Size of column:Length = 229Width = 229Height = 3000

Page 40: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 40

MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

4) FRAME4.1) Column4.1.3) Reinforcement bar Y12 for

column

9/4/4.50 ---------- 162.00m x 0.89kg/m = 144.18kg ----------

144kg

Length = height of column + half of roof beam + 1 lap + bend

= 3000+ (0.5x351) + 660 + 660= 4495.5

bend

Height of wall

lap

Page 41: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 41

MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

4) FRAME4.1) Column4.1.4) R6 link in for column

9/14/0.82 ---------- 103.32m x 0.22kg/m = 22.73kg ----------

23kg

Length of link: (length of CS– 2cover) x 4 +hook

=(229-50)+(229-50)+(229-50)+(229-50)+100=816

No. of link:Height of column = 3000=(3000/229)+1= 14 nos.

Hook

Page 42: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 42

MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

4) FRAME

4.2) Roof beam4.2.1) Reinforced concrete Grade 30 for

roof beam

2/3/6.10 0.23 0.35 ---------- 2.95m3 ----------

3m3

Size of roof beam:Length=3048+3048=6096Width = 229Thickness = 351

Page 43: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 43

MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

4) FRAME

4.2) Roof beam4.2.2) Formwork for roof beam

2/3/6.10 0.93 ---------- 34.04 34m2 ----------

Size of roof beam:Length=3048+3048=6096Width = 229Thickness = 351

= 351 + 229 + 351= 931

Side

Soffit

Page 44: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 44

MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

4) FRAME4.2) Roof beam4.2.3) Reinforcement bar Y10 for roof

beam

2/3/4/6.50 ---------- 156.00m x 0.62kg/m = 96.72kg ----------

97kg

Length = (length–2cover)+(2bend-2cover)=(6096-(2x50))+(2x351)-(4x50)= 6498

Page 45: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 45

MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

4) FRAME3.2) Roof beam3.2.5) R6 stirrup for roof beam

2/3/28/1.06 ---------- 178.08m x 0.22kg/m = 39.18kg ----------

39kg

Length of stirrup:

=(229-50)+(351-50)+(229-50)+(351-50)+100=1060

No. of stirrup:Length of beam= 6096=(6096/229)+1= 28 nos.

Hook

Page 46: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 46

MEASURING QUANTITIES, PRICING & COST ANALYSIS

Assumption No. 1: Total land area = 10m x 10m

Project Title: Construction and completion of guard houseOwner: Panicsonic Sdn BhdArchitect: A to Z Sdn BhdDrawing Title: Ground beam and foundation plan-------------------------------------------------------------------------Drawn by: SheilaChecked by: Aaron

Page 47: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 47

MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

5) ROOF = area of roof= a x b x 2

a = 42482 + 30002

a = 5200

b = 6096 + 1200 + 1200b = 8496

5.1) Steel roof trusses and corrugated aluminium steel roof covering

2/8.50 5.20 ---------- 88.40m2 88 m2 ----------

Front and rear elevation

Right and left elevation

a

b

3m

Page 48: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 48

MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

6) DOOR and WINDOW Door can bemeasured eitherin m2 or number. If enumerated thenneed to state type and size

6.1) Single leaf panel door size 2100 x 900 including frame and painting

2/2.10 0.90 ---------- 3.78 4 m2 or 2 nos ----------

Front and rear elevation

Right and left elevation

a

b

3m

Page 49: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 49

MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

6) DOOR and WINDOW Window can bemeasured eitherin m2 or number. If enumerated thenneed to state type and size

6.2) Adjustable louvres window 1200 x 600 including frame , painting and glass

2/6/1.20 0.60 ---------- 8.64 8.64 m2 or 12 nos ----------

Front and rear elevation

Right and left elevation

a

b

3m

Page 50: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 50

MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

7) WALL AND PARTITION

7.1) Half brickwall in comon brick

4/ 6.10 3.00 73.20 Less opening (e.g. door and window) 2/2.10 0.90 3.78 (door)

61 m22/6/1.20 0.60 8.64 (window) 60.78

Front and rear elevation

Right and left elevation

a

b

3m

Brickwall

Page 51: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 51

MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

8) FINISHES Area of plasteringand panting =Area of wall x 2

Area of ceiling =area of slab

8.1) Wall - Plastering and painting

2/ 61m2 122 m2

8.2) Floor Finishes – cement render

53 m2

8.3) Ceiling 53 m2

Front and rear elevation

Right and left elevation

a

b

3m

Brickwall

Page 52: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 52

MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

9) SUNDRIES Assumption.

1 no of counter for frontdesk.9.1) Built-in counter size 1800mm x 900mm x 725mm(h).

1 1 no.

Page 53: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 53

MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

Bills of Quantities Unit Quantity Rate Amount

1. Site Clearance1. 1 Clear the site including grubbing of trees,

shrubs and demolish any existing structure and cart away and dump to the specified location.

M2 100 2.40 240.00

1. Site Clearance 240.00

2. Foundation2.1 Piling works2.2 Excavation for pile cap < 2m deep2.3 Reinforced concrete G302.4 Lean concrete G152.5 Sawn formwork 2.6 Reinforcement bar Y12

M3M3M3M2Kg

2141

14294

39.50286.30194.50

29.603.00

829.501,145.20

194.50414.40882.00

2. Foundation 3,465.60

Page 54: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 54

MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

Bills of Quantities Unit Quantity Rate Amount

3. WBLFF3.1 Column Stump3.1.1 Reinforced Concrete G303.1.2 Sawn formwork3.1.3 Reinforcement bar Y123.1.4 Reinforcement bar R6

3.2 Ground beam3.2.1 Excavation for ground beam < 1m deep3.2.2 Reinforced concrete G303.2.3 Lean concrete G153.2.4 Sawn formwork 3.2.5 Reinforcement bar Y123.2.6 Reinforcement bar R6

M3M2KgKg

19

957

297.1029.80

3.003.00

297.10268.20285.00

21.00

Total 871.30

M3M3M3M2 Kg Kg

331

269732

20.80293.50201.70

29.603.003.00

62.40880.50201.70769.60

29196

Total 2,301.20

Page 55: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 55

MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

Bills of Quantities Unit Quantity Rate Amount

3. WBLFF3.3 Ground slab3.2.1 Excavation for ground slab < 1m deep3.2.2 Reinforced concrete G303.2.3 Sawn formwork 3.2.4 BRC A83.2.5 DPM3.2.6 Sand blinding3.2.7 Hardcore

3.4 Perimeter DrainHalf round glazeware 150mm dia.

M3M3M2M2 M2 M2 M3

2784

53535316

20.80293.50

29.6023.1012.90

2.6051.80

561.602,348.00

118.401,224.30

683.70137.80828.80

Total 5,902.60

M 29 11.30 327.70

3. WBLFF 9,402.80

Page 56: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 56

MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn BhdBills of Quantities Unit Quantity Rate Amount4. Frame4.1 Column4.1.1 Reinforced Concrete G304.1.2 Sawn formwork4.1.3 Reinforcement bar Y124.1.4 Reinforcement bar R6

4.2 Roof Beam4.2.1 Reinforced Concrete G304.2.2 Sawn formwork to sides & soffit4.2.3 Reinforcement bar Y104.2.4 Reinforcement bar R6

M3M2KgKg

125

14423

297.1029.80

3.003.00

297.10745.00432.00

69.00

Total 1,543.10

M3M2 Kg Kg

3349739

297.1029.80

3.003.00

891.301,013.20

291.00117.00

Total 2,312.50

4. Frame 3,855.60

Page 57: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 57

MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

Bills of Quantities Unit Quantity Rate Amount

5. Roof and covering5. 1 Steel roof trusses and corrugated

aluminium steel roof covering M2 88 133.30 11,730.40

5. Roof and covering 11,730.40

6. Door and Window6.1 Single leaf panel door size 2100 x 900

including frame and painting6.2 Adjustable louvres window 1200 x 600

including frame , painting and glass

No

No

2

12

250.00

120.00

500.00

1,440.00

6. Door and window 1,940.00

Page 58: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 58

MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

Bills of Quantities Unit Quantity Rate Amount

7. Wall and partition7. 1 Half brickwall in common brick M2 61 39.00 2,379.00

7. Wall and partition 2,379.00

8. Finishes8.1 Wall finishes – plastering & painting 8.2 Floor finishes – cement rendering8.3 Ceiling – gypsum plaster board

M2 M2 M2

1225353

17.7010.6017.70

2,159.40561.80938.10

8. Finishes 3,659.30

9. Sundries9. 1 Built-in counter size 1800mm x 900mm x

725mm(h).No. 1 1500.00 1,500.00

Page 59: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 59

MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

Summary of Bills of Quantities1. Site clearing 2. Foundation3. WBLFF4. Frame5. Roof and covering6. Door and window7. Wall and partition8. Finishes9. Sundries

Amount (RM)240.00

3,271.19,402.803,855.60

11,730.401,940.002,379.003,659.301,500.00

Subtotal #1 37,978.20

10. Building services (5%) 1,898.91

11. External works (3%) 1,139.35

Subtotal #2 41,016.46

12. Preliminaries (3%) 1,230.49

Total 42,246.95

Page 60: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 60

MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn BhdBuilding Cost Analysis

GFA = 37m2Cost/GFA = 1,136.00

Summary 1. Site Clearing2. Foundation3. WBLFF4. Frame5. Roof and covering6. Door and window7. Wall and partition8. Finishes9. Sundries

Amount (RM)240.00

3,271.19,402.803,855.60

11,730.401,940.002,379.003,659.301,500.00

Amount (RM)-under Prelim

3,280.009,400.003,860.00

11,730.001,940.002,400.003,660.001,500.00

Actual % -

8%21%

9%27%

5%6%9%4%

Normal %-

10 -20%5-10%

20-25%5-10%5-10%6-15%

1-5%

Explanation:

Subtotal #1 37,978.20

10. Building services (5%) 1,898.91 1,900.00 5% 10-25%

11. External works (5%) 1,139.35 1,140.00 3% 3-7%

Subtotal #2 41,016.46

12. Preliminaries (5%) 1,230.49 1,230.00 3% 3-7%

Total 42,246.95 42,040.00 100