MEASURING QUANTITIES, PRICING & COST ANALYSIS
● Mat Naim bin Abdullah @ Mohd Asmoni● Diploma QS (UTM), BSc. QS (Glasgow
Caledonian University), M.Eng. Construction (UTM), PhD Facilities Management (UTM)
www.utm.my innovative ● entrepreneurial ● global 2
MEASURING QUANTITIES, PRICING & COST ANALYSIS
Assumption No. 1: Total land area = 10m x 10m
Project Title: Construction and completion of guard houseOwner: Panicsonic Sdn BhdArchitect: A to Z Sdn BhdDrawing Title: Ground beam and foundation plan-------------------------------------------------------------------------Drawn by: SheilaChecked by: Aaron
www.utm.my innovative ● entrepreneurial ● global 3
MEASURING QUANTITIES, PRICING & COST ANALYSIS
www.utm.my innovative ● entrepreneurial ● global 4
MEASURING QUANTITIES, PRICING & COST ANALYSIS
Construction Method
1. Preliminaries (Initial site works) - % of total cost2. Site clearance and earthwork3. Foundation construction (E.g. Piling and footing)4. Work below lowest floor finish5. Frame6. Staircase7. Upper Floor8. Roof9. Wall and partition10. Door and window11. Finishes12. Sundries (Built-in furniture)13. Building services (M&E, ICT etc)14. External works (Water reticulation, landscape etc)
www.utm.my innovative ● entrepreneurial ● global 5
MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
1) Site clearance
1.1) Clear the site including grubbing of trees, shrubs and demolish any existing structure and cart away and dump to the specified location.
10.00 10.00 ---------- 100.00 100 m2 ----------
Area of the site:10 x 10 = 100m2
www.utm.my innovative ● entrepreneurial ● global 6
MEASURING QUANTITIES, PRICING & COST ANALYSIS
www.utm.my innovative ● entrepreneurial ● global 7
MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
2) Foundation
2.1) Piling including all related works
6.10 6.10 ---------- 37.21 37 m2 ----------
Area of the building:Length = 3048 + 3048 = 6096Width = 3048 + 3048 = 6096
www.utm.my innovative ● entrepreneurial ● global 8
MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
Size of ground beam:Length=3048+3048=6096Width = 229Thickness = 351
RC for ground beam
www.utm.my innovative ● entrepreneurial ● global 25
MEASURING QUANTITIES, PRICING & COST ANALYSIS
Assumption No. 1: Total land area = 10m x 10m
Project Title: Construction and completion of guard houseOwner: Panicsonic Sdn BhdArchitect: A to Z Sdn BhdDrawing Title: Ground beam and foundation plan-------------------------------------------------------------------------Drawn by: SheilaChecked by: Aaron
www.utm.my innovative ● entrepreneurial ● global 26
MEASURING QUANTITIES, PRICING & COST ANALYSIS
@100 c/c
Height of column stump
www.utm.my innovative ● entrepreneurial ● global 27
MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
3) WBLFF
3.2) Ground beam3.2.4) Formwork for ground beam
2/3/2/6.10 0.35 ---------- 25.62 26m2 ----------
Size of ground beam:Length=3048+3048=6096Width = 229Thickness = 351
Installation of reinforcement bar and formwork for ground beam
www.utm.my innovative ● entrepreneurial ● global 28
MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
3) WBLFF3.2) Ground beam3.2.5) Reinforcement bar Y10 for
ground beam
2/3/4/6.50 ---------- 156.00m x 0.62kg/m = 96.72kg ----------
www.utm.my innovative ● entrepreneurial ● global 45
MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
4) FRAME3.2) Roof beam3.2.5) R6 stirrup for roof beam
2/3/28/1.06 ---------- 178.08m x 0.22kg/m = 39.18kg ----------
39kg
Length of stirrup:
=(229-50)+(351-50)+(229-50)+(351-50)+100=1060
No. of stirrup:Length of beam= 6096=(6096/229)+1= 28 nos.
Hook
www.utm.my innovative ● entrepreneurial ● global 46
MEASURING QUANTITIES, PRICING & COST ANALYSIS
Assumption No. 1: Total land area = 10m x 10m
Project Title: Construction and completion of guard houseOwner: Panicsonic Sdn BhdArchitect: A to Z Sdn BhdDrawing Title: Ground beam and foundation plan-------------------------------------------------------------------------Drawn by: SheilaChecked by: Aaron
www.utm.my innovative ● entrepreneurial ● global 47
MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
5) ROOF = area of roof= a x b x 2
a = 42482 + 30002
a = 5200
b = 6096 + 1200 + 1200b = 8496
5.1) Steel roof trusses and corrugated aluminium steel roof covering
2/8.50 5.20 ---------- 88.40m2 88 m2 ----------
Front and rear elevation
Right and left elevation
a
b
3m
www.utm.my innovative ● entrepreneurial ● global 48
MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
6) DOOR and WINDOW Door can bemeasured eitherin m2 or number. If enumerated thenneed to state type and size
6.1) Single leaf panel door size 2100 x 900 including frame and painting
2/2.10 0.90 ---------- 3.78 4 m2 or 2 nos ----------
Front and rear elevation
Right and left elevation
a
b
3m
www.utm.my innovative ● entrepreneurial ● global 49
MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
6) DOOR and WINDOW Window can bemeasured eitherin m2 or number. If enumerated thenneed to state type and size
6.2) Adjustable louvres window 1200 x 600 including frame , painting and glass
2/6/1.20 0.60 ---------- 8.64 8.64 m2 or 12 nos ----------
Front and rear elevation
Right and left elevation
a
b
3m
www.utm.my innovative ● entrepreneurial ● global 50
MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
7) WALL AND PARTITION
7.1) Half brickwall in comon brick
4/ 6.10 3.00 73.20 Less opening (e.g. door and window) 2/2.10 0.90 3.78 (door)
61 m22/6/1.20 0.60 8.64 (window) 60.78
Front and rear elevation
Right and left elevation
a
b
3m
Brickwall
www.utm.my innovative ● entrepreneurial ● global 51
MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
8) FINISHES Area of plasteringand panting =Area of wall x 2
Area of ceiling =area of slab
8.1) Wall - Plastering and painting
2/ 61m2 122 m2
8.2) Floor Finishes – cement render
53 m2
8.3) Ceiling 53 m2
Front and rear elevation
Right and left elevation
a
b
3m
Brickwall
www.utm.my innovative ● entrepreneurial ● global 52
MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
9) SUNDRIES Assumption.
1 no of counter for frontdesk.9.1) Built-in counter size 1800mm x 900mm x 725mm(h).
1 1 no.
www.utm.my innovative ● entrepreneurial ● global 53
MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
Bills of Quantities Unit Quantity Rate Amount
1. Site Clearance1. 1 Clear the site including grubbing of trees,
shrubs and demolish any existing structure and cart away and dump to the specified location.
M2 100 2.40 240.00
1. Site Clearance 240.00
2. Foundation2.1 Piling works2.2 Excavation for pile cap < 2m deep2.3 Reinforced concrete G302.4 Lean concrete G152.5 Sawn formwork 2.6 Reinforcement bar Y12
M3M3M3M2Kg
2141
14294
39.50286.30194.50
29.603.00
829.501,145.20
194.50414.40882.00
2. Foundation 3,465.60
www.utm.my innovative ● entrepreneurial ● global 54
MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
Bills of Quantities Unit Quantity Rate Amount
3. WBLFF3.1 Column Stump3.1.1 Reinforced Concrete G303.1.2 Sawn formwork3.1.3 Reinforcement bar Y123.1.4 Reinforcement bar R6
3.2 Ground beam3.2.1 Excavation for ground beam < 1m deep3.2.2 Reinforced concrete G303.2.3 Lean concrete G153.2.4 Sawn formwork 3.2.5 Reinforcement bar Y123.2.6 Reinforcement bar R6
M3M2KgKg
19
957
297.1029.80
3.003.00
297.10268.20285.00
21.00
Total 871.30
M3M3M3M2 Kg Kg
331
269732
20.80293.50201.70
29.603.003.00
62.40880.50201.70769.60
29196
Total 2,301.20
www.utm.my innovative ● entrepreneurial ● global 55
MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
www.utm.my innovative ● entrepreneurial ● global 56
MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn BhdBills of Quantities Unit Quantity Rate Amount4. Frame4.1 Column4.1.1 Reinforced Concrete G304.1.2 Sawn formwork4.1.3 Reinforcement bar Y124.1.4 Reinforcement bar R6
4.2 Roof Beam4.2.1 Reinforced Concrete G304.2.2 Sawn formwork to sides & soffit4.2.3 Reinforcement bar Y104.2.4 Reinforcement bar R6
M3M2KgKg
125
14423
297.1029.80
3.003.00
297.10745.00432.00
69.00
Total 1,543.10
M3M2 Kg Kg
3349739
297.1029.80
3.003.00
891.301,013.20
291.00117.00
Total 2,312.50
4. Frame 3,855.60
www.utm.my innovative ● entrepreneurial ● global 57
MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
Bills of Quantities Unit Quantity Rate Amount
5. Roof and covering5. 1 Steel roof trusses and corrugated
9. Sundries9. 1 Built-in counter size 1800mm x 900mm x
725mm(h).No. 1 1500.00 1,500.00
www.utm.my innovative ● entrepreneurial ● global 59
MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
Summary of Bills of Quantities1. Site clearing 2. Foundation3. WBLFF4. Frame5. Roof and covering6. Door and window7. Wall and partition8. Finishes9. Sundries
Amount (RM)240.00
3,271.19,402.803,855.60
11,730.401,940.002,379.003,659.301,500.00
Subtotal #1 37,978.20
10. Building services (5%) 1,898.91
11. External works (3%) 1,139.35
Subtotal #2 41,016.46
12. Preliminaries (3%) 1,230.49
Total 42,246.95
www.utm.my innovative ● entrepreneurial ● global 60
MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn BhdBuilding Cost Analysis
GFA = 37m2Cost/GFA = 1,136.00
Summary 1. Site Clearing2. Foundation3. WBLFF4. Frame5. Roof and covering6. Door and window7. Wall and partition8. Finishes9. Sundries
Amount (RM)240.00
3,271.19,402.803,855.60
11,730.401,940.002,379.003,659.301,500.00
Amount (RM)-under Prelim
3,280.009,400.003,860.00
11,730.001,940.002,400.003,660.001,500.00
Actual % -
8%21%
9%27%
5%6%9%4%
Normal %-
10 -20%5-10%
20-25%5-10%5-10%6-15%
1-5%
Explanation:
Subtotal #1 37,978.20
10. Building services (5%) 1,898.91 1,900.00 5% 10-25%