Dr. José Miguel JIMENEZLS2 CoordinatorLHC Performance Workshop (Chamonix 2014)Session 8 - Long Shutdown 2 Strategy and Preparation - Summary 8th Oct’14
Session 8Long Shutdown 2 Strategy and Preparation
Chair: José Miguel JiménezScientific Secretary: Jean-Philippe Tock
2
Dr. José Miguel JIMENEZLS2 CoordinatorLHC Performance Workshop (Chamonix 2014)Session 8 - Long Shutdown 2 Strategy and Preparation - Summary 3
Session breakdown Chair: José Miguel Jiménez; Scientific secretary: Jean-Philippe Tock
• Scope of the LS2 (making best use of the period 2015-2018)• José Miguel Jiménez
• What has been learnt from LS1• Katy Foraz
• Safety & Radiation Aspects• Doris Forkel-Wirth
• LIU Planned Activities • Julie Coupard
• HL-LHC Planned Activities - Accelerator• Isabel Bejar Alonso
• LHC Experiments Upgrade and Maintenance• Werner Riegler
• LHC @ LS2• Marzia Bernardini
8th Oct’14
Dr. José Miguel JIMENEZLS2 CoordinatorLHC Performance Workshop (Chamonix 2014)Session 8 - Long Shutdown 2 Strategy and Preparation - Summary 4
Scope of the LS2 (making best use of the period 2015-2018)José Miguel Jiménez
• The project scope covers all activities carried out and resources needed in the context of Long Shutdown 2 over the whole CERN accelerator facilities.
• The preparation, coordination and follow-up till completion of all LS2 activities in the frame of the LIU, HL-LHC Projects and other CERN approved projects.
• The flexibility to use the end-of-year technical stops before and after the LS2 to decrease the load of the LS2 is left at the discretion of the LS2 coordinator and is also part of the scope of the project.
8th Oct’14
LS1Post
Mortem
LS2Day
LS2Day
LS2Day
PLANis madeavailable
ConsolidatedList of tasks
to Director A&T
1st stepfinal
validation
Finalvalidation
Dr. José Miguel JIMENEZLS2 CoordinatorLHC Performance Workshop (Chamonix 2014)Session 8 - Long Shutdown 2 Strategy and Preparation - Summary 5
What has been learnt from LS1Katy Foraz
8th Oct’14
Collection and prioritization of activities: a) Plan.cern.ch
• Unique repository to ease information exchange between groups Groups had a clearest picture of the support to be given to other groups
• Attenuate bad surprises• Ease the prioritization process for LS1 team, focusing only on discordance
points
But• Should have come earlier…• Not all activities were announced… • Redundancy of resources details between APT and PLAN…
In the future ?• Use again PLAN tool to collect future activities• Give enough time to groups to fill data• Improve the PLAN tool to better fit with needs: redundancy with other tools,
granularity between items
+
+
+
~
~
~
Dr. José Miguel JIMENEZLS2 CoordinatorLHC Performance Workshop (Chamonix 2014)Session 8 - Long Shutdown 2 Strategy and Preparation - Summary 6
What has been learnt from LS1Katy Foraz
“Organize, don't agonize.” Nancy Pelosi
• Coordination• Helps to keep a very good follow-up on fields• Enhances team spirit & eases information flow
• Scheduling• Will keep a member of coordination team (scheduler) within projects• Improves availability of internal production and acceptance tests schedules• Optimizes the start of an activity w.r.t. cooling period
• Documentation• Will continue presenting ECRs in (LSC), LMC, IEFC on regular basis• Will insist to have ECRs edited in due time
• Daily management• Will help to keep working with the same Stakeholders…
• Information exchange• Will improve information flow down to the worksites
• Rationalized project’ information• 1 web page indicating hyperlink to projects ?
• Implement and maintain a repository of services’ unavailability.
8th Oct’14
Dr. José Miguel JIMENEZLS2 CoordinatorLHC Performance Workshop (Chamonix 2014)Session 8 - Long Shutdown 2 Strategy and Preparation - Summary 7
Safety & Radiation AspectsDoris Forkel-Wirth
• Regulatory Landscape is introducing new constraints…• Impact will be evaluated in the coming months…• Training preparation and communication will get high priority.
• Radioactive storage (surface & handling) and waste management (volume & weight) is a major issue
• Group’s projections need to be more accurate…
• Injectors will dominate personnel dose rates even though situation in LHC will not improve…
• CERN individual dose objective of 3 mSv over 12 consecutive months will be more challenging…
• Even though ALARA has became an essential and natural part of CERN culture.
• Roadmap towards LS2 is identified, thanks to the lessons learnt from LS1.
8th Oct’14
Dr. José Miguel JIMENEZLS2 CoordinatorLHC Performance Workshop (Chamonix 2014)Session 8 - Long Shutdown 2 Strategy and Preparation - Summary 8
LIU Planned Activities Julie Coupard
• Main outcomes• LIU activities fit in the LS2 time window defined for the injectors but
the schedules are very tight with not much margin and already assuming shift activities.
• Consolidation prioritization needs to be coherent with LIU activities…
• Additional studies required:• To evaluate the cabling work load as early as possible in order to estimate
the EN/EL workload and integration.
• For the levelling of the resources of the support/client groups, for example: EN/MME, EN/HE, EN/CV, EN/EL, EN/MEF-SU, GS/CE, TE/VSC.
• With integration studies which need to be completed: 3D models of infrastructures and general services.
• To finalize the needs for design and production of manufacturing drawings.
• To define works that can be anticipated in YETS and EYETS.
8th Oct’14
Dr. José Miguel JIMENEZLS2 CoordinatorLHC Performance Workshop (Chamonix 2014)Session 8 - Long Shutdown 2 Strategy and Preparation - Summary 9
LIU Planned Activities – Room for optimization… Julie Coupard
8th Oct’14
Dr. José Miguel JIMENEZLS2 CoordinatorLHC Performance Workshop (Chamonix 2014)Session 8 - Long Shutdown 2 Strategy and Preparation - Summary 10
HL-LHC Planned Activities - AcceleratorIsabel Bejar Alonso
• Main outcomes• Identify and prepare work that can be done in LS2 on the time
frame allocated for which the technology/solution is mature and can not bring any risk to the run 3 start date.
• Integrate as early as possible HL-LHC work planning in LS2.
8th Oct’14
Dr. José Miguel JIMENEZLS2 CoordinatorLHC Performance Workshop (Chamonix 2014)Session 8 - Long Shutdown 2 Strategy and Preparation - Summary 11
LHC Experiments Upgrade and MaintenanceWerner Riegler
8th Oct’14
Dr. José Miguel JIMENEZLS2 CoordinatorLHC Performance Workshop (Chamonix 2014)Session 8 - Long Shutdown 2 Strategy and Preparation - Summary 12
LHC Experiments Upgrade and MaintenanceWerner Riegler
8th Oct’14
Dr. José Miguel JIMENEZLS2 CoordinatorLHC Performance Workshop (Chamonix 2014)Session 8 - Long Shutdown 2 Strategy and Preparation - Summary 13
LHC Experiments Upgrade and MaintenanceWerner Riegler
8th Oct’14
Dr. José Miguel JIMENEZLS2 CoordinatorLHC Performance Workshop (Chamonix 2014)Session 8 - Long Shutdown 2 Strategy and Preparation - Summary 14
LHC Experiments Upgrade and MaintenanceWerner Riegler
8th Oct’14
Dr. José Miguel JIMENEZLS2 CoordinatorLHC Performance Workshop (Chamonix 2014)Session 8 - Long Shutdown 2 Strategy and Preparation - Summary 15
LHC Experiments Upgrade and MaintenanceWerner Riegler
8th Oct’14
Dr. José Miguel JIMENEZLS2 CoordinatorLHC Performance Workshop (Chamonix 2014)Session 8 - Long Shutdown 2 Strategy and Preparation - Summary 16
LHC @ LS2Marzia Bernardini
• Key messages• LS2 needs to be prepared NOW!
• LS2 is mainly dedicated to Injectors and LHC Detectors…• ...but in the LHC, Maintenance and Consolidations are important.
• LS2 is an opportunity, for the LHC, to prepare LS3: • Anticipating as much as possible HL-LHC activities from LS3.• Focusing on RP Issues and ALARA procedures stay a priority.
• Support activities will be on the critical path and coordination will be challenged…
• LS2 activities should not compromise LS3 preparation.
• Resources optimisation across the Accelerators and Experiments will be THE key point!
8th Oct’14
Dr. José Miguel JIMENEZLS2 CoordinatorLHC Performance Workshop (Chamonix 2014)Session 8 - Long Shutdown 2 Strategy and Preparation - Summary 17
LHC @ LS2Marzia Bernardini
8th Oct’14
2018 2019
Depending on the cool down and warm up sequence
Windows available for activities Between 9 and 13 Months
WARM UP and TESTS
Lift replacement
CRYO Maintenance
Magnets replacement
Other activities…
Radiation Cool Down @ P7
HL activities @ P2, P4 and TZ76
HL activities @ LSS7
COOL DOWN, TESTS and HWC
July '18 Aug. '18Sept. '18
Oct. '18 Nov. '18 Dec. '18 Jan. '19 Feb. '19March
'19April '19 May '19 June '19 July '19 Aug. '19
Sept. '19
Oct. '19 Nov. '19 Dec. '19
ELECTRICAL Maintenance & Consolidation
Skeleton of LS2 Master Schedule (indicative)
Dr. José Miguel JIMENEZLS2 CoordinatorLHC Performance Workshop (Chamonix 2014)Session 8 - Long Shutdown 2 Strategy and Preparation - Summary 18
Closing remarks
• Priority of LS2 Coordination towards:• Safety & Radiation readiness: rules, training, communication, temporary storage,
waste management…• Classification levels and dose rates will be of primary criticality• Estimation of temporary storages and waste’s volume and weight is urgently required.
• Injectors (LIU) and LHC Experiments (allow them matching the “compressed” schedule).
• Have already a “skeleton” of LS2 master schedule• LIU & Maintenance well defined (LS1 experience)• HL-LHC & Consolidations to be reviewed
• Prioritisation of Consolidations will need to be assessed in the frame of the available LS2 resources, impact on other groups and coherence with LIU project.
• Collection and prioritization of activities will rely on “PLAN” tool• Unique repository, useful for information exchange between groups
• Groups had a clearest picture of the support to be given to other groups• Mitigates probability of bad surprises…• Ease the prioritization process and allows focusing only on discordances.
8th Oct’14
Dr. José Miguel JIMENEZLS2 CoordinatorLHC Performance Workshop (Chamonix 2014)Session 8 - Long Shutdown 2 Strategy and Preparation - Summary 20
Safety & Radiation AspectsDoris Forkel-Wirth
8th Oct’14
Critical changesexpected…
Dr. José Miguel JIMENEZLS2 CoordinatorLHC Performance Workshop (Chamonix 2014)Session 8 - Long Shutdown 2 Strategy and Preparation - Summary
Equipment on the Beam Tunnel equipment Vert. J Surface Eq. Dis.
DF(X-M) + SC Link DSH (X-M)
Cryo line IR+MSAlignment
QPS2
Magnet systemMQXFA MQXFB, MBXF, MBRD, MQYY,
Q5 1.9, Q6 1.9MCBXFB, MCBXFA, MQSXF, MCTXF, MCTSXF,
MCDXF, MCDSXF, MCOXF, MCOSXF, MCSXF,MCSSXF,MCBRD, MCBYY
Beam vacuum
TAXS, TAXN
Interaction Region and MS IP 1,5
Collimation (TCTPM, TCL, TCLM, TCTP)
Beam diagnosticBPMSQW, BMPSQ, BPMSQT, BMLC
DS Collimation for ion IP 2
H.F. dipoles
Cryo-bypass+TCLD
DFH(X-M) + Power converters
SC link/powering IP 7
Hor. SC Link DSH + DFA
Power converters
EE
Crab Cavity cryomodules
RF systemLoads, circulators, RF power, LLRF, HVPS,
central LLRR
DS Collimation pp (TBC RUN II) IP 1,5
H.F. dipoles
Cryo-bypass+TCLD
DS Collimation pp (TBC RUN II) IP 7
H.F. dipoles
Cryo-bypass+TCLD
Rad-hard electronics for BLM and BPM
CC diagnostic and protection
PIC
BIS
DFA+ SC Link DSHA
DFHA + Power converters
SC link/Powering
arcIP 1,5
Cryoplant IP 1,5
CB Warm compressor and other surface eq.
In orange Works
during LS2
Dr. José Miguel JIMENEZLS2 CoordinatorLHC Performance Workshop (Chamonix 2014)Session 8 - Long Shutdown 2 Strategy and Preparation - Summary
Equipment on the Beam Tunnel equipment Vert. J Surface equip. Dis.
Cryo line for RF
Beam diagnostic IP 4
Fast wire scanners BWSF
New light extraction line BSRT
Beam gas vertex detector BGV
Injection protection IP 2 8
TDI (TBC)
TCLIA, TCLIB (TBC)
TCDD TCDDM (TBC)
TCLIM (TBC)
MKI (TBC)
Q5 at point 6 IP 6
Dump (TBC) IP 6
TCDS (TBC)
MKB, TDE (TBC)
PIC
BIS
High rad warm magnets (TBC) IP 7
Collimation upgrade
Secondary TCSPM
Primary TCP TCPP
TCSG, TCLA, TCAP
IP 3 7
IP 3 7
IP 3 7
TCSP IP 6
Mini-TAN IP 8
CB
Cryoplant IP 4
Warm compressor and other surface eq.
In orange Works during
LS2
Dr. José Miguel JIMENEZLS2 CoordinatorLHC Performance Workshop (Chamonix 2014)Session 8 - Long Shutdown 2 Strategy and Preparation - Summary 23
LHC @ LS2Marzia Bernardini
8th Oct’14
Mai
nten
ance C
onsolidation
Dr. José Miguel JIMENEZLS2 CoordinatorLHC Performance Workshop (Chamonix 2014)Session 8 - Long Shutdown 2 Strategy and Preparation - Summary
LHC Experiments Upgrade and MaintenanceWerner Riegler
• ATLAS Support Needs• Beampipes, Vacuum, Collimators • Detector Cooling
• CMS Support Needs• Beampipes, Vacuum, Collimators • Cooling, Electricity & other services• Magnet• Cranes, Elevators• Complete opening of detector
• ALICE Support Needs• Extension of the computing farm • Beampipes, Vacuum, Collimators • Fibers• Detector Cooling• Change of elevator• PbPb Luminosity
• LHCb Support Needs• New computing farm (2MW)• Beampipes , Vacuum, Collimators (EN, TE)• Fibers• Services and Integration:• Detector Cooling• Change of elevator, crane ? But not during LS2
8th Oct’14
Dr. José Miguel JIMENEZLS2 CoordinatorLHC Performance Workshop (Chamonix 2014)Session 8 - Long Shutdown 2 Strategy and Preparation - Summary 8th Oct’14
• Beampipes, Vacuum, Collimators • ATLAS has performed the consolidation of the beampipes and vacuum
equipment already during LS1. Only maintenance foreseen in LS2.
• Detector Cooling• Cooling system consolidation was performed during LS1.• Mainly maintenance during LS2
ATLAS Support Needs
25
Dr. José Miguel JIMENEZLS2 CoordinatorLHC Performance Workshop (Chamonix 2014)Session 8 - Long Shutdown 2 Strategy and Preparation - Summary 8th Oct’14
• Beampipes, Vacuum, Collimators • Central pipe was changed in LS1, Change Beampipes (EC HF CT2 FWD) to Al 2219 in
LS2 (TE-VSC). Possible change in pipe geometry (decision 2015) – re-design from scratch.
• Cooling, Electricity & other services• 4 (+1) x500kVA UPS --> 7 (+1) x 500kVA and upgrade of electrical infrastructure (EN-EL)
possible re-siting of battery banks• Revise & extend control room, moving UPS out.• Increase of chilled water production (+1.5MW) (EN-CV) for Phase 2 detectors• Dry gas (air/N2) system (EN-CV) upgrade for Phase 2 detectors• Multi-purpose extension of surface assembly hall (1000m2), EN-CV, EN-EL needs
• Magnet• Refurbishment of magnet control and safety system (PH-DT, TE)• Implement freewheel thyristor for immunity from power converter glitches (TE)
• Cranes, Elevators• Installation of a second UXC crane with suspended cage for personnel access (EN-HE)• Replace Elevator (EN-HE)
• Complete opening of detector • Upgrades + detector maintenance on same scale as LS1 + new beampipes
--> transport, rigging, survey & FSU support on same scale as LS1
CMS Support Needs
26
Dr. José Miguel JIMENEZLS2 CoordinatorLHC Performance Workshop (Chamonix 2014)Session 8 - Long Shutdown 2 Strategy and Preparation - Summary 8th Oct’14
• Extension of the computing farm • To be studied whether available space and infrastructure are sufficient (EN-
EL, EN-CV)
• Beampipes, Vacuum, Collimators • New central beampipe + mobile bakeout equipment (TE-VSC)• Modification of Miniframe beampipe, displacement of gauge, ion pump in
Aluminum (TE-VSC)• LSS vacuum consolidation to minimize vacuum pressure (TE-VSC)• New TDI to limit high vacuum pressure from outgassing (EN-STI)• Collimators in dispersion suppressor region to allow maximum PbPb
Luminosity (...)
• Fibers• Possibly already during EYETS 2016/2017
• Detector Cooling• New detector cooling plant for upgraded Inner Tracking System (EN-CV)• Possible upgrade of ITS dry air ventilation system (EN-CV)
• Change of elevator
• PbPb Luminosity• Infrastructure for increase of PbPb luminosity to >6x1027
ALICE Support Needs
27
Dr. José Miguel JIMENEZLS2 CoordinatorLHC Performance Workshop (Chamonix 2014)Session 8 - Long Shutdown 2 Strategy and Preparation - Summary 8th Oct’14
• New computing farm (2MW)• Housed in new surface building or container (GS)• Strategy for operational temperature and cooling (EN-CV)• Possible needs for UPS (EN-EL)
• Beampipes , Vacuum, Collimators (EN, TE)• All beampipes in the cavern must be removed and then reinstalled during LS2, no new
beampipes are planned.• Probably a TAS will have to be installed around LHCb• TDI in TI8 injection line to be changed (LS2 ?)
• Fibers• Possibly already during EYETS 2016/2017. (EN-EL ?, other companies ?) make sure
CERN frame contracts are adapted.
• Services and Integration:• For integration of cables, cable trays, cooling lines, access platforms as well as
supervision of the service installation activities LHCb relies on EN-MEF
• Detector Cooling• New Fiber Tracker (SciFi) cooling plant (-40C monophase Freon for SiPMs) (EN-CV) &
adapt OT/PS/SPD cooling plant for SciFi electronics• Possible adaption of TT cooling plant to Fiber Tracker electronics cooling (EN-CV)• (Velo and UT CO2 cooling is done throughP H-DT), but primary cooling with support
from EN-CV.
• Change of elevator, crane ? But not during LS2
LHCb Support Needs
28
Dr. José Miguel JIMENEZLS2 CoordinatorLHC Performance Workshop (Chamonix 2014)Session 8 - Long Shutdown 2 Strategy and Preparation - Summary 29
LHC @ LS2Marzia Bernardini
• Outcomes• Maintenance vs Consolidation need to be reworked in the coming
months• No official baseline for consolidation project
• Retuning will be required after decision are taken by PL of Consolidation project
• Replacement of all lifts: 3 months unavailability at least for material transport
• “Optimised” schedule, assuming ALARA lefts only 9 months for HL-LHC in LSS7!
• Resources levelling will be needed
• Temporary storage areas will be installed at the surface max 6 months before and 6 months after LS2
• Existing buffer zones are probably not sufficient
• Performance optimisation of He exchanger in triplets in 1&5• Reassess needs to consolidate them in triplet +&% and 2&8 (ALARA)
8th Oct’14