Sensitivity Analysis on Locations of Energy Storage in Power
Systems With Wind IntegrationSensitivity Analysis on Locations of
Energy Storage in Power Systems With Wind Integration
Nhi T. A. Nguyen, Student Member, IEEE, Duong D. Le, Member, IEEE,
Godfrey G. Moshi, Member, IEEE, Cristian Bovo, Member, IEEE, and
Alberto Berizzi, Member, IEEE
Abstract—The penetration of renewable energy sources, partic-
ularly wind energy, into power systems has been rapidly increas-
ing in recent years. However, the integration of wind power has
posed many challenges for power system operation. For instance,
this type of energy source is relatively variable and
unpredictable. The installation of this renewable source might
require the grid to transmit power at full capacity and some
transmission lines could become congested. As a result, in some
operating conditions, wind power could be curtailed, which will
drive up costs for system operators. One of the actions that can be
taken to support the inte- gration of the wind is using energy
storage systems. In this paper, a multiperiod ac optimal power flow
problem with battery energy storages (BESs) is formulated and sets
of candidate buses for BES installation are identified based on an
economic criterion. Tests are carried out on IEEE 14-bus and IEEE
118-bus systems to assess the robustness of storage location on
system operation.
Index Terms—Curtailed wind, energy storage systems (ESSs),
location, locational marginal price (LMPs), multiperiod, optimal
power flow (OPF), production cost, sensitivity, wind
integration.
NOMENCLATURE
θt i Voltage angle of bus i in hour t.
θt k Voltage angle of bus k in hour t.
Bt i Energy of the ESS at bus i in hour t.
Bt−1 i Energy of the ESS at bus i in hour t−1.
Bmax i Upper limit of energy of the ESS at bus i.
Bmin i Lower limit of energy of the ESS at bus i.
Bik Line susceptance of branch ik. c0i
, c1i , c2i
Cost coefficients of generating units at bus i. cdj
, cchj Cost coefficients for charging and discharging power of the
ESS at bus j.
Gik Line conductance of branch ik.
Manuscript received December 22, 2015; revised April 12, 2016;
accepted June 14, 2016. Date of publication August 16, 2016; date
of current ver- sion November 18, 2016. Paper 2015-IACC-0900.R1,
presented at the 2015 IEEE 15th International Conference on
Environment and Electrical Engineering (EEEIC), Rome, Italy, Jun.
10–13, and approved for publication in the IEEE TRANSACTIONS ON
INDUSTRY APPLICATIONS by the Industrial Automation and Control
Committee of the IEEE Industry Applications Society.
N. T. A. Nguyen, C. Bovo, and A. Berizzi are with the Politecnico
di Milano, 20133 Milano, Italy (e-mail:
[email protected];
[email protected];
[email protected]).
D. D. Le is with the Politecnico di Milano, 20133 Milano, Italy,
and also with the Department of Electrical Engineering, Danang
University of Science and Technology, Danang, Vietnam (e-mail:
[email protected]).
G. G. Moshi is with the Department of Electrical Engineering, Dar
es Salaam Institute of Technology, Dar es Salaam, Tanzania (e-mail:
godfreyglad-
[email protected]).
Color versions of one or more of the figures in this paper are
available online at http://ieeexplore.ieee.org.
It ij Magnitude of the current flowing from bus i to
bus j in hour t. It ji Magnitude of the current flowing from bus j
to
bus i in hour t. Imax ij Upper limit of the current flow from bus i
to
bus j. Imax j i Upper limit of the current flow from bus j to
bus i. n Total number of buses. nbr Total number of branches. ng
Total number of generators. ns Total number of ESSs installed. P
t
i Real power injection at bus i in hour t. Pmax
chi Upper limit of real charging power of the ESS at bus i.
Pmin chi
Lower limit of real charging power of the ESS at bus i.
P t chi
Real charging power of the ESS at bus i in hour t. Pmax
di Upper limit of real discharging power of the ESS at bus i.
Pmin di
Lower limit of real discharging power of the ESS at bus i.
P t di
Real discharging power of the ESS at bus i in hour t.
Pmax Gi
P t Gi
Real generation power at bus i in hour t. P t
Li Real power of load at bus i in hour t.
Qt i Reactive power injection at bus i in hour t.
Qmax chi
Upper limit of reactive charging power of the ESS at bus i.
Qmin chi
Lower limit of reactive charging power of the ESS at bus i.
Qt chi
Reactive charging power of the ESS at bus i in hour t.
Qmax di
Upper limit of reactive discharging power of the ESS at bus
i.
Qmin di
Lower limit of reactive discharging power of the ESS at bus
i.
Qt di
Reactive discharging power of the ESS at bus i in hour t.
Qmax Gi
Qt Gi
Reactive generation power at bus i in hour t. Qt
Li Reactive power of load at bus i in hour t.
T The optimization horizon. V max
i Upper limit of voltage magnitude of bus i.
© 2016 IEEE. Personal use of this material is permitted. Permission
from IEEE must be obtained for all other uses, in any current or
future media, including reprinting/republishing this material for
advertising or promotional purposes, creating new collective works,
for resale or redistribution to servers or lists, or reuse of any
copyrighted component of this work in other works. To access the
final edited and published work see 10.1109/TIA.2016.2600669
V min i Lower limit of voltage magnitude of bus i.
V t i Voltage magnitude of bus i in hour t.
V t k Voltage magnitude of bus k in hour t.
I. INTRODUCTION
ENERGY storage systems (ESSs) can be an alternative to manage wind
power variability, and hence, provide flex-
ibility and reliability for power systems with high wind pene-
tration level. This technology enables electricity to be stored at
times of high wind and low demand, and then, to be released at low
wind, high demand periods. This ability to store electricity of
ESSs can efficiently compensate for the intermittent behavior of
wind power and provide economically optimal operation for wind
generation.
Potential applications of ESSs for grid-connected wind gen- eration
are thoroughly addressed in [1]. ESSs can be applied for mitigating
wind power curtailment due to limited transmission capacity, which
helps avoid any required transmission capacity upgrade. ESSs can
serve to shape a portion of wind genera- tion, i.e., shifting a
portion of wind generation from high wind, off-peak load periods to
low wind, peak load periods, for op- timizing the overall
economics. Other applications of ESSs is hedging wind forecast
uncertainties, and hence, increasing wind generation revenues. An
overview on different energy storage technologies and their uses
with renewable energy is provided in [2]. Additional studies on
other applications of ESSs such as frequency control and risk
mitigation can be found in [3]–[7].
The combined operation of the ESS and wind generation has drawn
special attention in many studies. In [8], the ESS is used in
combination with wind generation for wind curtailment re- duction
and price arbitrage. That paper investigates the optimal scheduling
of the ESS cooperating with wind farms and con- nected to a
distribution network. Daneshi and Srivastava [9] presented a
security-constrained unit commitment model with wind and battery
energy storage (BES) and discusses the role of BES on locational
pricing, economic, peak load shaving, and transmission congestion
management using an eight-bus system case study. An increasing
interest in optimal operation strate- gies of the ESS in
electricity markets, where electricity price is an uncertainty, has
been found in [10]–[12]. Akhavan-Hejazi and Mohsenian-Rad [10]
presented a stochastic programming framework on optimal bidding of
independent storage units in the day-ahead and hour-ahead energy
and reserve markets, while Hu et al. [11] developed an optimal
operation strategy for the ESS in hourly spot markets so that
profits for the storage system are maximized. In [12], optimal
energy exchange with electric- ity markets for energy storage in
wind power plants has been considered taking into account
transmission constraints.
Dealing with placement of the ESS in power grids, in [13], a
methodology is proposed to allocate the ESS in a distribution
system with high wind penetration. The ESS is optimally placed and
sized to both accommodate wind energy and minimize gen- eration
costs. Song et al. [14] used a sensitivity analysis method to find
optimal locations of ESSs for reducing transmission congestion. Oh
[15] proposed an approach for deploying stor- age devices and
discusses the feasibility and economic impact
of using storage devices. However, the approach proposed is tested
on a small system, using the simplified dc optimal power flow (OPF)
approximation. Ghofrani et al. [16], [17] and Dvi- jotham and
Chertkov [18] proposed approaches to determine optimal placement
and sizes of ESSs using the dc OPF model and perform tests on the
IEEE 24-bus system. Ghofrani et al. [16], [17] used a two-point
estimate method to optimally place ESSs in a deregulated power
system with wind integration and the optimization problem is solved
for each single period during the considered optimization horizon.
Dvijotham and Chertkov [18] incorporate operation of ESSs into the
planning problem with optimal control schemes. The placement of
ESSs in power grids with both conventional and wind generation is
also stud- ied in [19]. The authors use a semidefinite relaxation
ac OPF model to solve the optimal placement problem and perform
tests on the IEEE 14-bus system. In [20], a dc OPF framework is
proposed for storage portfolio optimization, including stor- age
size, technology, and location in transmission-constrained power
networks. The framework is tested with the IEEE 14-bus system.
Xiong and Singh [21] proposed an approach employing a dc power flow
model for determining the optimal location and size of an ESS in a
power system with uncertain wind genera- tion. Case studies are
conducted with the IEEE 96-bus system and Benders decomposition
algorithm is applied to reduce the computational burden.
Proposed approaches for optimal placement of the ESS have been
demonstrated with only small systems. For larger systems,
especially real-size ones, computational burden is still an is-
sue. Therefore, for the best planning of ESSs, it is necessary to
preliminarily identify the most suitable area or the best candi-
date locations for installing the ESSs. This is carried out, in the
methodology proposed in this paper, based on an ac OPF multi-
period model with BESs and wind integration for time shifting [22]
and congestion relieving applications. The main contribu- tion of
this study is identifying the best candidate locations for storage
allocation based on an economic criterion and assess- ing the
influence of storage location and size on production cost, amount
of wind to be curtailed and marginal prices. To this goal,
additionally, in this paper, the full ac OPF model is developed to
capture realistic physical power flows of the system better than
the dc approach and the relaxed models used in [15], [16], and
[18]–[20]. This approach is also much more accurate and reliable
when issues such as congestion and voltage constraints are
concerned. Moreover, in this paper, the multiperiod OPF model is
employed, which takes into account time interdepen- dence, i.e.,
the problem is solved simultaneously for all periods of the
optimization horizon. In this way, the intertemporal con- straints
relevant to the storage are considered. The multiperiod model has
been demonstrated in [23] and [24] to be a more physically suitable
approach to study the operation of a storage device and to provide
better operational schedule: In this pa- per, the proposed model is
adopted, for example, to shift wind power over time and get
reduction of wind curtailment in case of transmission congestions,
thus allowing an efficient utilization of transmission
capacity.
The remainder of this paper is organized as follows: In Section II,
the methodology is described. In Section III, tests with mod-
ified IEEE 14-bus and IEEE 118-bus systems are described and
results are discussed. Finally, Section IV concludes this
paper.
II. METHODOLOGY
In this section, the methodology to define the most suitable
candidate locations for ESSs is described. The optimization is
carried out on the total generation cost that represents trans-
mission system operator’s (TSO) point of view; in other words, the
goal is to improve the system operation regardless of the revenues
of the single companies operating wind farms. ESSs, therefore, can
be installed at any bus by the (TSO) in order to maximize the
efficiency and security of the overall system. Moreover, the total
time horizon considered (which could be either one week or one
month or a set of representative weeks of the year) is discretized
and the hourly operation is optimized considering the presence of
the ESSs; a multiperiod approach is necessary to properly model the
intertemporal constraint char- acteristic of the ESSs. The
multiperiod ac OPF described in Section II-A provides as byproduct
the Lagrange multipliers, which are used in Section II-B to define
the best candidate lo- cations for ESSs.
A. Multiperiod AC OPF Mathematical Formulation
A multiperiod ac OPF model with ESS integration can be formulated
as follows [22].
1) Objective function: The objective function to be min- imized in
this model is the total production cost∑T
t=1(PCt), using as control variables ESS charging/ discharging
power and generation output of all dispatch- able generators in
each period t
OF = Min T∑
= Min T∑
t=1
(PCt). (1)
In order to take into account the variability of load and wind, two
possible approaches are available: The first is to run the model on
a longer time frame, e.g., one year. However, the tractability of
the resulting problem is sub- ject to the size of the system. The
second approach, which is typically used in power system planning,
is to run the model on a weekly basis, considering a number of
weekly scenarios representative of the most significant loading and
wind conditions (high wind-high load, high wind- low load, etc.),
weighting the results based on the weekly energies. Therefore, the
value of T depends on the time horizon adopted in the planning
problem. In particular, in this paper, the optimization problem is
run on a daily basis, thus T = 24 h.
In (1), the first term is the production cost of all gener- ating
units. The second term is introduced so that at the optimal
solution, the ESS is not charged and discharged
at the same time. Hence, cch and cd are fictitious charging and
discharging costs applied to the ESS. When charging, the ESS is
treated as a load with the fictitious charging cost set equal to
zero (cch = 0). To prevent simultaneous charging and discharging,
the discharging cost cd is set to a very small quantity, e.g., cd =
10−2 , as presented in [25].
2) Equality constraints. 1) Power balance equations: Include
equations for real
and reactive power at each node i in each time period t
P t i = P t
Gi − P t
Li + P t
di − P t
k )]
(2)
k )].
(3)
2) ESS energy balance equations: Include energy bal- ance equations
for each ESS i in each period t, con- sidering charging and
discharging efficiencies
Bt i = Bt−1
i + (ηchi P t
3) Inequality constraints. Upper and lower limits for voltage
magnitudes
V min i ≤ V t
i ≤ V max i . (5)
Bounds on real and reactive generation powers
Pmin Gi
(It ji)
ESS charging/discharging power bounds
i ≤ Bmax i . (14)
When the ESS is discharged, constraint (10) must be fulfilled.
Similarly, when it is charged, constraint (11) must be
satisfied.
The aforementioned OPF problem is formulated as a sparse and
complete model, hence, the Lagrange multiplier λpt
i as- sociated to the real power flow equation at bus i in period
t
represents the variation of the total production cost with respect
to the variation of real injected power at the same bus, i.e., it
is the locational marginal price (LMP) at bus i in period t
λpt i = LMPt
. (15)
According to the formulation of the OPF model described previously,
λpt
i includes the effects of both real losses and con- gestions.
The aforementioned ac OPF model can be applied for any ESS
technology, and in Section III, ESSs of battery technology are
employed. This ac OPF formulation has been implemented into a
multiperiod OPF model, using MATLAB 2013b software.
B. Assessment of Sensitivity
From the information provided by the Lagrange multiplier λpt
i previously, best candidate buses and worst candidate buses for
installing ESSs are identified. Indeed, buses with the highest
Lagrange multipliers are selected as the best candidate buses,
where any variation of real injected power has greater impact on
the production cost than other buses. As a result, if the ESSs are
installed at the best candidate buses, their operation will have
higher influence on the production cost. In particular, the
procedure is described as follows.
1) First, a base case OPF (without ESS installed) is solved. In
this way, the Lagrange multiplier λpt
i is determined for each bus i at each hour t. At this step,
constraints on ESSs, including (4) and (10)–(14), are removed from
the OPF problem. Next, the following parameter dfi is computed for
each bus i
dfi = T∑
t=1
|λpt i |. (16)
This parameter is then sorted: The highest values indicate the most
suitable buses for the installation of ESSs. The lowest values, on
the other hand, indicate the less sensi- tive candidates. The
aforementioned parameter takes into account the effect of the ESSs
not only for a specific hour, but considering the whole time
horizon.
2) Second, based on the total number of ESSs available, they are
connected to the system at the best candidate buses and the OPF
problem, with all constraints included, is solved.
In the following section, a set of tests is performed to discuss
both the time-shifting and congestion mitigation applications. In
each test, production costs, total amount of curtailed wind power
and hourly LMP variation are calculated and shown.
III. CASE STUDIES AND DISCUSSION
In this section, tests are performed with modified IEEE 14- bus and
IEEE 118-bus systems. Wind data are taken from real wind records
measured at a wind farm in Sicily, Italy. Load data are also
relevant to the typical load of a winter day in Italy. Both wind
and load data are suitably scaled down to fit the case
studies.
Fig. 1. IEEE 14-bus case study.
TABLE I PARAMETERS FOR THE BES
P m a x c h [MW] P m a x
d [MW] B m a x [MW·h] ηch ηd
30 30 120 0.90 0.90
A. IEEE 14-Bus System
The mathematical model described in Section II is tested on the
modified IEEE 14-bus system (see Fig. 1) [26]. This network has
four conventional generators (at buses 1, 3, 6, and 8) with total
capacity of 832 MW, a wind plant (at bus 2) with installed capacity
of 250 MW and BESs. BESs are added to support wind generation due
to its intermittent behavior to possibly reduce wind curtailment,
congestions, and improve the overall economics.
Parameters for the BES are provided in Table I for different tests
carried out.
In this system, loads with peak value of 732 MW are supplied from
both conventional and wind generation. When the wind is sufficient,
it will be the priority source to supply loads and if there is
still surplus wind power, BESs will be charged. When wind power is
not sufficient, BESs will be discharged to supply loads while
respecting all technical constraints. If both wind and BES stored
energy are not enough for the loads, conventional generators will
be dispatched consequently.
From the OPF formulation described in Section II, the La- grange
multipliers of real power at each bus in each hour are determined.
The parameter dfi is then calculated for each bus i, including the
wind bus and load buses (see Table II).
From this table, the first five buses (14, 10, 9, 13, and 7) with
highest values of Lagrange multipliers are selected as the best
candidate buses to install the BESs. It is worth noticing that the
wind bus (bus 2) is among the worst candidate buses.
Next, different cases where different numbers of BES are placed in
the system are considered to assess the quality of the
sensitivities computed. The tests are categorized as in Table
III.
The large BES in cases 7 and 8 is equivalent to two BESs in cases
1–6 connected to the same bus.
TABLE II VALUES OF THE PARAMETER dfi AT EACH BUS
Best Candidate dfi Worst Candidate dfi
Bus No. [$/MW·h] Bus No. [$/MW·h]
14 1739.16 11 1615.55 10 1662.22 4 1610.09 9 1657.42 12 1605.50 13
1633.53 5 1569.58 7 1622.41 2 1485.79
TABLE III TESTS FOR THE IEEE 14-BUS SYSTEM
Case 0 No BES connected to the network Case 1 One BES connected to
bus 2 (the worst candidate bus) Case 2 One BES connected to bus 14
(the best candidate bus) Case 3 Two BESs, one at bus 2, the other
at bus 14 Case 4 Two BESs connected to buses 9 and 14 (best
candidate buses) Case 5 Three BESs, one at bus 2, the others at
buses 9 and 14 Case 6 Three BESs connected to buses 9, 10 and 14
(best candidate buses) Case 7 One large BES connected to bus 2 Case
8 One large BES connected to bus 14
Fig. 2. Operational schedule of the BES in case 2.
The optimization problem is run for a period of 24 h. Opera- tions
of the BES for case 2, with one BES connected to bus 14 (the best
candidate bus), are represented in Fig. 2.
As shown in the figure, the BES is charged when wind power exceeds
the load, and then, it is discharged when wind power is
insufficient to supply the load. At periods when the wind is much
higher than the load, after the storage has been charged up to its
limits, either power or energy limit, the extra wind is necessarily
curtailed.
To understand the operation of the BESs in each case, the resulting
production costs, amounts of curtailed wind power, and LMPs of the
aforementioned cases will be compared.
1) Production Costs: Production cost is the cost for gener- ating
real power by the generating units only (not including generating
cost by the storages). Generation costs of all eight cases are
shown in Fig. 3. It can be clearly seen from this figure that the
case without BESs yields highest generation cost over the other
cases. Cases with only one BES connected to the net- work result in
a noticeable reduction of generation cost and this
Fig. 3. Production costs of all cases.
Fig. 4. Amount of curtailed wind of all cases.
reduction is higher in the case when the BES is connected to the
best candidate bus (case 1 achieves about 1.9% cost savings, while
case 2 obtains approximately 2.19% cost savings com- pared to case
0). In cases 3 and 4, with two BESs, and cases 5 and 6, with three
BESs connected to the system, the produc- tion cost is further
reduced. In general, the selection of the best candidate buses
improves the system operation, although the effect due to the total
BES capacity looks more significant in this case. Quality of
sensitivities computed can be evaluated by comparing cases 1 and 2
and 7 and 8: The comparison shows that the candidate buses for BES
installation are actually correctly identified. Also, from the
aforementioned analysis, it can be ob- served that higher capacity
of the BES added to the network can significantly improve the
overall economics of the system.
2) Curtailed Wind Energy: Wind is curtailed once there is surplus
wind but BESs have already reached their capacity limit, either
power or energy limit. This curtailment of the wind can be viewed
as an undesirable loss of “cost free” and clean energy.
From Fig. 2, the wind is possibly curtailed from hours 1 to 5, in
which wind is higher than load. Total amount of the curtailed wind
for each case can be seen in Fig. 4. Amounts of curtailed wind
energy in all eight cases vary similarly as the generation costs.
It is worth noticing that case 2 uses more wind power than case 1
even BES in case 2 is located far from the wind bus. The same
occurs when comparing cases 7 and 8. Hence, it is important to
observe that the computed sensitivities correctly take into account
wind curtailment also.
Fig. 5. Hourly LMP variation in case 0.
Fig. 6. Hourly LMP variation in case 1.
3) LMPs: LMP is an important price indicator of unit MW·h injection
at each node and congestion in the transmission net- work [27]. It
consists of marginal unit cost, congestion cost, and cost due to
losses. Castillo and Gayme [25] demonstrated that LMPs play a
significant role in driving storage operation at low levels of ESS
integration. In this study, we examine how LMPs are changed due to
the addition of BESs at different locations.
The hourly LMP variation of all 14 buses in case 0 are pre- sented
in Fig. 5. During peak load periods, LMPs also reach peak values
while during off-peak hours their values become much lower. This is
understandable since at peak load hours, cheap wind power is not
sufficient to supply the load and more expensive conventional
generators are dispatched instead, which causes an increase in
LMPs.
Fig. 6 shows LMPs of case 1, in which a BES is connected to bus 2
(the worst candidate bus). In this case, peak prices are noticeably
reduced for the higher peak (hours 18–20), from peak value of about
140 $/MW·h to around 115 $/MW·h. The lower peak (during hours
10–12) is also slightly reduced (from peak value of about 105
$/MW·h–100 $/MW·h). This indicates that the addition of the BES can
provide additional cheap power to loads during peak periods. The
reduction in LMP values in this case will affect the cost of
supplying load at each bus.
In case 2 (see Fig. 7), both peaks are further reduced. The second
peak (hours 18–20) is considerably reduced and be- comes almost
equal to the first peak (hours 10–12), i.e., about 90 $/MW·h. This
indicates the addition of BESs at a bus in the best candidate buses
has more significant influence on marginal prices than the addition
of BESs at a bus in the worst candidate buses, which means the
computation of sensitivities is correct. For the remaining cases,
similar conclusions can be drawn.
Fig. 7. Hourly LMP variation in case 2.
TABLE IV SELECTED BEST AND WORST CANDIDATE BUSES
Best Candidate dfi Worst Candidate dfi
Bus No. [$/MW·h] Bus No. [$/MW·h]
5 658.28 37 581.38 3 654.75 114 581.21 7 650.06 115 581.18 2 649.77
23 576.83 11 648.80 38 575.17 117 647.73 17 574.39 13 637.95 30
552.03 14 631.46 8 491.40 109 624.09 9 486.10 16 623.80 10
480.64
B. IEEE 118-Bus System
To further investigate the sensitivity of the BES location and size
in congestion relieving application in a large network, an
extensive set of tests is carried out on the modified IEEE 118- bus
system [26]. The test system has 56 conventional generating units
with a total capacity of 2500 MW, two large wind farms connected to
buses 8 and 10 with a total installed capacity of 700 MW. Load with
peak value of 2189 MW is supplied from both conventional and wind
generators. Generation from the wind farms is likely to cause
congestion on the way from wind to loads, which might result in
wind curtailment. In this case, BESs are installed to charge this
otherwise curtailed wind amount for later releasing and allow an
efficient utilization of transmission lines. For this test, a
congestion is observed during peak periods on lines 8–5 and 8–30,
from wind farms to loads. Parameters for the BESs are the same as
in the previous case study.
The calculated parameter dfi , the best candidate, and worst
candidate buses for installing BESs are selected as shown in Table
IV.
From this table, the best candidate buses include buses 5, 3, 7, 2,
11, 117, 13, 14, 109, and 16, while the worst candidate buses
include buses 37, 114, 115, 23, 38, 17, 30, 8, 9, and 10. It is
worth noticing that wind buses (8 and 10) are not in the best
candidate set as the optimization is carried out from a system
point of view. The tests carried out are described in Table
V.
1) Production Costs: In Fig. 8, a plot of production costs of the
system in all cases is provided. Case 0 yields the highest
cost
TABLE V TESTS FOR THE IEEE 118-BUS SYSTEM
Case 0 No BES connected to the network Case 1 One BES connected to
bus 8 (one of the worst candidate buses) Case 2 One BES connected
to bus 5 (best candidate bus) Case 3 Two BESs, one at bus 8 and the
other at bus 5 Case 4 Two BESs connected to buses 5 and 117 (best
candidate buses) Case 5 Three BESs, one at bus 8, the others at
buses 5 and 117 Case 6 Three BESs, two at buses 8 and 10, the other
at bus 5 Case 7 Three BESs connected to buses 2, 5, and 117 Case 8
One large BES system connected to bus 8 Case 9 One large BES system
connected to bus 5
Fig. 8. Production costs of cases 0–9.
compared to the others. From cases 1 to 5, the cost is gradually
reduced. This demonstrates that higher numbers of the BES in-
stalled return more economical operations of the system. The
effectiveness of a good selection of candidate buses by the sen-
sitivity computation is clear by looking at cases 1 and 2: Case 2
results in higher saving as compared to case 1. Similarly, cases 4
and 7, where there are more BESs installed at the best candidate
buses, also result in lower production costs compared to case 3,
and cases 5 and 6, respectively. Cost savings in case 8 is lower
than that in case 3 and case 9. From this analysis, it can be
deduced that in such a congested system, storage devices placed at
the best candidate buses can provide far more economical operation
than those placed at the worst candidate buses. Thus, it is
important to figure out the best candidate locations for the
planning of storage devices. Moreover, in this case, a large BES
connected to a bus in the best candidate buses can operate as
efficiently as several BESs distributed among the best candidate
buses.
2) Curtailed Wind Energy: Amounts of curtailed wind en- ergy in all
cases are represented in Fig. 9. Considering cases 1 and 2, for
instance, the conclusion is that the difference in to- tal cost
(see Fig. 8) is not due to wind curtailment, like for the
aforementioned 14 bus test system, but due to congestions: The
optimal placing of BES allows, in this case, to best relieve the
congestion due to wind power. In this case, the amount of wind
energy to be curtailed is not affected by centralized or
decentralized placement of the storage devices.
3) LMPs: Hourly LMP variation of all buses for each case is also
shown to discuss the impacts of BES location and size on LMPs.
Hourly LMP variation of case 0 is shown in Fig. 10. In
Fig. 9. Amounts of curtailed wind of cases 0 to 9.
Fig. 10. Hourly LMP variation of case 0.
Fig. 11. Hourly LMP variation of case 2.
this figure, curves with the highest peaks belong to load buses on
the receiving side of congested lines and curves with the lowest
prices belong to wind buses. During off-peak periods, LMPs are
about the same for all buses since there is no congestion.
Hourly LMP variation in case 1, when there is one BES con- nected
to bus 8 (one of the worst candidate buses), is basically the same
as in case 0. In case 2, with one BES added at bus 5 (the best
candidate bus), the higher peak prices during the first peak hours
are noticeably lowered and those during the second peak hours are
also considerably lowered at some pe- riods (hours 17 and 20) as
shown in Fig. 11. The peak prices are not reduced at hours 18 and
19 of the second peak period because the limited capacity of the
BES is not enough to supply the high load during these hours. For
these peak prices to get reduced, higher capacity of the BES is
required. In this case,
Fig. 12. Hourly LMP variation of case 4.
Fig. 13. Operation of the BES in case 2.
to avoid transmission congestion, the BES is charged by wind power
during low load periods, when there is no congestion, and then,
discharged to supply the cheap energy to loads during congestion
hours, hence it can help to reduce the marginal cost during peak
hours of these load buses. This operation of the BES has
effectively supported wind generation and efficiently makes use of
the available transmission capacity.
In case 4 (two BESs connected to the best candidate buses), LMP
values of the higher peak curves are further reduced during the
first peak periods and during hours 17 and 20 of the second peak
(see Fig. 12).
Now, a plot is provided (see Fig. 13) showing the opera- tion of
the BES connected to bus 5 (the best candidate bus) to exclusively
examine how it shifts wind to avoid transmission constraint.
From this figure, the BES is charged during off-peak periods (hours
1–5 and hours 14–16), which are also periods without transmission
congestion, and then, discharged during peak pe- riods (hours 10–12
and hours 17–20) when congestion occurs. Clearly, the BES has
thoroughly shifted wind power from wind side to load side to supply
loads when wind power cannot be transferred from wind farms to
loads due to limited transmission capacity.
Also, in Fig. 14, is a plot of power flows on line 8–5, con-
necting wind farms and loads. The dotted line with crosses in the
plot corresponds to the unconstrained case without BES: the power
flow limit (the dotted red line with filled circle) is not en-
forced by the optimization procedure and this would cause the
Fig. 14. Power flow on line 8–5 in case 2.
real-time curtailment of excess wind power. This figure clearly
illustrates the alternative path that the BES provides for wind
power to alleviate the congestion, i.e., the full blue line with
cir- cles. In this way, power flow on line 8–5 during low load
hours (hours 1–5 and 14–16) is increased but still lower than the
flow limit. Such flow increase is due to the wind power flow used
to charge the BES at load bus. This stored energy is released to
supply loads during peak periods, when congestion occurs.
Consequently, wind power can still be supplied to loads while
ensuring the flow limit.
IV. CONCLUSION
In this paper, the problem of selecting the best location for ESS
installation is faced. A multiperiod full ac OPF is used to
determine the sensitivities necessary to identify the buses that,
in case of installation of ESSs, allow the maximum benefit for
power systems from several points of view: the minimum overall
cost, the minimum curtailment of wind power (that could also lead
to minimum CO2 emissions), the maximum mitigation of congestions,
and the maximum benefit, in terms of energy process. The
sensitivities are computed as a byproduct of a multiperiod ac OPF,
thus taking into account not only a single hour but the overall
time horizon and possible time shifts of generated wind power, as
well as issues related to congestions mitigation and reduction of
losses. The proposed methodology has been tested on two test
systems using realistic data, and the sensitivities have been
assessed, showing a very informative content. Moreover, the system
benefits have been proved with reference to LMPs, used here as an
index of the social benefit. The results demonstrate that the
method can be easily applied to large systems and to many different
scenarios to take into account the variability of both wind power
and load.
REFERENCES
[1] EPRI-DOE, Handbook of Energy Storage for Transmission and
Distribu- tion Applications, Electric Power Research Institute,
Palo Alto, CA, USA, 2004.
[2] R. B. Schainker, “Executive overview: Energy storage options
for a sus- tainable energy future,” in Proc. IEEE Power Eng. Soc.
Gen. Meeting, vol. 2, Jun. 2004, pp. 2309–2314.
[3] C. Abbey and G. Joos, “Supercapacitor energy storage for wind
energy ap- plications,” IEEE Trans. Ind. Appl., vol. 43, no. 3, pp.
769–776, May 2007.
[4] P. Mercier, R. Cherkaoui, and A. Oudalov, “Optimizing a battery
energy storage system for frequency control application in an
isolated power sys- tem,” IEEE Trans. Power Syst., vol. 24, no. 3,
pp. 1469–1477, Aug. 2009.
[5] R. Rajagopal, E. Bitar, P. Varaiya, and F. Wu, “Risk-limiting
dispatch for integrating renewable power,” Int. J. Elect. Power
Energy Syst., vol. 44, no. 1, pp. 615–628, 2013.
[6] E. Sjodin, D. Gayme, and U. Topcu, “Risk-mitigated optimal
power flow for wind powered grids,” in Proc. Amer. Control Conf.,
Jun. 2012, pp. 4431–4437.
[7] C. Brivio, M. Mandelli, and M. Merlo, “Battery energy storage
system for primary control reserve and energy arbitrage,”
Sustainable Energy, Grids Netw., vol. 6, pp. 152–165, Jun.
2016.
[8] S. Gill, G. Ault, and I. Kockar, “The optimal operation of
energy storage in a wind power curtailment scheme,” in Proc. Power
Energy Soc. Gen. Meeting, Jul. 2012, pp. 1–8.
[9] H. Daneshi and A. Srivastava, “Impact of battery energy storage
on power system with high wind penetration,” in Proc. IEEE PES
Transmiss. Distrib. Conf. Expo., May 2012, pp. 1–8.
[10] H. Akhavan-Hejazi and H. Mohsenian-Rad, “Optimal operation of
inde- pendent storage systems in energy and reserve markets with
high wind pen- etration,” IEEE Trans. Smart Grid, vol. 5, no. 2,
pp. 1088–1097, Mar. 2014.
[11] W. Hu, Z. Chen, and B. Bak-Jensen, “Optimal operation strategy
of battery energy storage system to real-time electricity price in
Denmark,” in Proc. Power Energy Soc. Gen. Meeting, Jul. 2010, pp.
1–7.
[12] J. Perez-Diaz, A. Perea, and J. Wilhelmi, “Optimal short-term
operation and sizing of pumped-storage power plants in systems with
high penetra- tion of wind energy,” in Proc. 7th Int. Conf. Eur.
Energy Market, Jun. 2010, pp. 1–6.
[13] Y. Atwa and E. El-Saadany, “Optimal allocation of ESS in
distribution systems with a high penetration of wind energy,” IEEE
Trans. Power Syst., vol. 25, no. 4, pp. 1815–1822, Nov. 2010.
[14] J. Song, T. Brekken, E. Cotilla-Sanchez, A. von Jouanne, and
J. Davidson, “Optimal placement of energy storage and demand
response in the pacific northwest,” in Proc. IEEE Power Energy Soc.
Gen. Meeting, Jul. 2013, pp. 1–5.
[15] H. Oh, “Optimal planning to include storage devices in power
systems,” IEEE Trans. Power Syst., vol. 26, no. 3, pp. 1118–1128,
Aug. 2011.
[16] M. Ghofrani, A. Arabali, M. Etezadi-Amoli, and M. Fadali, “A
framework for optimal placement of energy storage units within a
power system with high wind penetration,” IEEE Trans. Sustainable
Energy, vol. 4, no. 2, pp. 434–442, Apr. 2013.
[17] M. Ghofrani, A. Arabali, M. Etezadi-Amoli, and M. S. Fadali,
“Energy storage application for performance enhancement of wind
integration,” IEEE Trans. Power Syst., vol. 28, no. 4, pp.
4803–4811, Nov. 2013.
[18] S. B. K. Dvijotham and M. Chertkov, “Operations-based planning
for placement and sizing of energy storage in a grid with a high
penetra- tion of renewables,” Los Alamos Nat. Lab., Tech. Rep.
arXiv:1107.1382 [math.OC], 2011.
[19] S. Bose, D. F. Gayme, U. Topcu, and K. M. Chandy, “Optimal
placement of energy storage in the grid,” in Proc. IEEE 51st Annu.
Conf. Decision Control, 2012, pp. 5605–5612.
[20] S. Wogrin and D. F. Gayme, “Optimizing storage siting, sizing,
and tech- nology portfolios in transmission-constrained networks,”
IEEE Trans. Power Syst., vol. 30, no. 6, pp. 3304–3313, Nov.
2015.
[21] P. Xiong and C. Singh, “Optimal planning of storage in power
systems integrated with wind power generation,” IEEE Trans.
Sustain. Energy, vol. 7, no. 1, pp. 232–240, Jan. 2016.
[22] N. Nguyen, D. Le, G. Moshi, C. Bovo, and A. Berizzi,
“Sensitivity analysis on locations of energy storage in power
systems with wind integration,” in Proc. IEEE 15th Int. Conf.
Environ. Elect. Eng., Jun. 2015, pp. 1115–1119.
[23] N. Nguyen, D. Le, C. Bovo, and A. Berizzi, “Optimal power flow
with energy storage systems: Single-period model versus
multi-period model,” in Proc. IEEE Eindhoven PowerTech, 2015, pp.
1–6.
[24] B. Klockl, G. Papaefthymiou, and P. Pinson, “Probabilistic
tools for plan- ning and operating power systems with distributed
energy storage,” E&I Elektrotechnik und Informationstechnik,
vol. 125, no. 12, pp. 460–465, 2008.
[25] A. Castillo and D. Gayme, “Profit maximizing storage
allocation in power grids,” in Proc. IEEE 52nd Annu. Conf. Decision
Control, Dec. 2013, pp. 429–435.
[26] University of Washington. (1993). Power system test case
archive. [On- line]. Available:
https://www.ee.washington.edu/research/pstca
[27] A. Kumar and W. Gao, “Optimal distributed generation location
using mixed integer non-linear programming in hybrid electricity
markets,” IET Gener., Transmiss. Distrib., vol. 4, no. 2, pp.
281–298, Feb. 2010.
<< /ASCII85EncodePages false /AllowTransparency false
/AutoPositionEPSFiles true /AutoRotatePages /None /Binding /Left
/CalGrayProfile (Gray Gamma 2.2) /CalRGBProfile (sRGB IEC61966-2.1)
/CalCMYKProfile (U.S. Web Coated \050SWOP\051 v2) /sRGBProfile
(sRGB IEC61966-2.1) /CannotEmbedFontPolicy /Warning
/CompatibilityLevel 1.4 /CompressObjects /Off /CompressPages true
/ConvertImagesToIndexed true /PassThroughJPEGImages true
/CreateJobTicket false /DefaultRenderingIntent /Default
/DetectBlends true /DetectCurves 0.0000 /ColorConversionStrategy
/sRGB /DoThumbnails true /EmbedAllFonts true /EmbedOpenType false
/ParseICCProfilesInComments true /EmbedJobOptions true
/DSCReportingLevel 0 /EmitDSCWarnings false /EndPage -1
/ImageMemory 1048576 /LockDistillerParams true /MaxSubsetPct 100
/Optimize true /OPM 0 /ParseDSCComments false
/ParseDSCCommentsForDocInfo true /PreserveCopyPage true
/PreserveDICMYKValues true /PreserveEPSInfo false /PreserveFlatness
true /PreserveHalftoneInfo true /PreserveOPIComments false
/PreserveOverprintSettings true /StartPage 1 /SubsetFonts false
/TransferFunctionInfo /Remove /UCRandBGInfo /Preserve /UsePrologue
false /ColorSettingsFile () /AlwaysEmbed [ true /Algerian
/Arial-Black /Arial-BlackItalic /Arial-BoldItalicMT /Arial-BoldMT
/Arial-ItalicMT /ArialMT /ArialNarrow /ArialNarrow-Bold
/ArialNarrow-BoldItalic /ArialNarrow-Italic /ArialUnicodeMS
/BaskOldFace /Batang /Bauhaus93 /BellMT /BellMTBold /BellMTItalic
/BerlinSansFB-Bold /BerlinSansFBDemi-Bold /BerlinSansFB-Reg
/BernardMT-Condensed /BodoniMTPosterCompressed /BookAntiqua
/BookAntiqua-Bold /BookAntiqua-BoldItalic /BookAntiqua-Italic
/BookmanOldStyle /BookmanOldStyle-Bold /BookmanOldStyle-BoldItalic
/BookmanOldStyle-Italic /BookshelfSymbolSeven /BritannicBold
/Broadway /BrushScriptMT /CalifornianFB-Bold /CalifornianFB-Italic
/CalifornianFB-Reg /Centaur /Century /CenturyGothic
/CenturyGothic-Bold /CenturyGothic-BoldItalic /CenturyGothic-Italic
/CenturySchoolbook /CenturySchoolbook-Bold
/CenturySchoolbook-BoldItalic /CenturySchoolbook-Italic
/Chiller-Regular /ColonnaMT /ComicSansMS /ComicSansMS-Bold
/CooperBlack /CourierNewPS-BoldItalicMT /CourierNewPS-BoldMT
/CourierNewPS-ItalicMT /CourierNewPSMT /EstrangeloEdessa
/FootlightMTLight /FreestyleScript-Regular /Garamond /Garamond-Bold
/Garamond-Italic /Georgia /Georgia-Bold /Georgia-BoldItalic
/Georgia-Italic /Haettenschweiler /HarlowSolid /Harrington
/HighTowerText-Italic /HighTowerText-Reg /Impact
/InformalRoman-Regular /Jokerman-Regular /JuiceITC-Regular
/KristenITC-Regular /KuenstlerScript-Black /KuenstlerScript-Medium
/KuenstlerScript-TwoBold /KunstlerScript /LatinWide /LetterGothicMT
/LetterGothicMT-Bold /LetterGothicMT-BoldOblique
/LetterGothicMT-Oblique /LucidaBright /LucidaBright-Demi
/LucidaBright-DemiItalic /LucidaBright-Italic
/LucidaCalligraphy-Italic /LucidaConsole /LucidaFax /LucidaFax-Demi
/LucidaFax-DemiItalic /LucidaFax-Italic /LucidaHandwriting-Italic
/LucidaSansUnicode /Magneto-Bold /MaturaMTScriptCapitals
/MediciScriptLTStd /MicrosoftSansSerif /Mistral /Modern-Regular
/MonotypeCorsiva /MS-Mincho /MSReferenceSansSerif
/MSReferenceSpecialty /NiagaraEngraved-Reg /NiagaraSolid-Reg
/NuptialScript /OldEnglishTextMT /Onyx /PalatinoLinotype-Bold
/PalatinoLinotype-BoldItalic /PalatinoLinotype-Italic
/PalatinoLinotype-Roman /Parchment-Regular /Playbill /PMingLiU
/PoorRichard-Regular /Ravie /ShowcardGothic-Reg /SimSun
/SnapITC-Regular /Stencil /SymbolMT /Tahoma /Tahoma-Bold
/TempusSansITC /TimesNewRomanMT-ExtraBold /TimesNewRomanMTStd
/TimesNewRomanMTStd-Bold /TimesNewRomanMTStd-BoldCond
/TimesNewRomanMTStd-BoldIt /TimesNewRomanMTStd-Cond
/TimesNewRomanMTStd-CondIt /TimesNewRomanMTStd-Italic
/TimesNewRomanPS-BoldItalicMT /TimesNewRomanPS-BoldMT
/TimesNewRomanPS-ItalicMT /TimesNewRomanPSMT /Times-Roman
/Trebuchet-BoldItalic /TrebuchetMS /TrebuchetMS-Bold
/TrebuchetMS-Italic /Verdana /Verdana-Bold /Verdana-BoldItalic
/Verdana-Italic /VinerHandITC /Vivaldii /VladimirScript /Webdings
/Wingdings2 /Wingdings3 /Wingdings-Regular /ZapfChanceryStd-Demi
/ZWAdobeF ] /NeverEmbed [ true ] /AntiAliasColorImages false
/CropColorImages true /ColorImageMinResolution 150
/ColorImageMinResolutionPolicy /OK /DownsampleColorImages true
/ColorImageDownsampleType /Bicubic /ColorImageResolution 150
/ColorImageDepth -1 /ColorImageMinDownsampleDepth 1
/ColorImageDownsampleThreshold 1.50000 /EncodeColorImages true
/ColorImageFilter /DCTEncode /AutoFilterColorImages false
/ColorImageAutoFilterStrategy /JPEG /ColorACSImageDict <<
/QFactor 0.76 /HSamples [2 1 1 2] /VSamples [2 1 1 2] >>
/ColorImageDict << /QFactor 0.40 /HSamples [1 1 1 1]
/VSamples [1 1 1 1] >> /JPEG2000ColorACSImageDict <<
/TileWidth 256 /TileHeight 256 /Quality 15 >>
/JPEG2000ColorImageDict << /TileWidth 256 /TileHeight 256
/Quality 15 >> /AntiAliasGrayImages false /CropGrayImages
true /GrayImageMinResolution 150 /GrayImageMinResolutionPolicy /OK
/DownsampleGrayImages true /GrayImageDownsampleType /Bicubic
/GrayImageResolution 300 /GrayImageDepth -1
/GrayImageMinDownsampleDepth 2 /GrayImageDownsampleThreshold
1.50000 /EncodeGrayImages true /GrayImageFilter /DCTEncode
/AutoFilterGrayImages false /GrayImageAutoFilterStrategy /JPEG
/GrayACSImageDict << /QFactor 0.76 /HSamples [2 1 1 2]
/VSamples [2 1 1 2] >> /GrayImageDict << /QFactor 0.40
/HSamples [1 1 1 1] /VSamples [1 1 1 1] >>
/JPEG2000GrayACSImageDict << /TileWidth 256 /TileHeight 256
/Quality 15 >> /JPEG2000GrayImageDict << /TileWidth 256
/TileHeight 256 /Quality 15 >> /AntiAliasMonoImages false
/CropMonoImages true /MonoImageMinResolution 1200
/MonoImageMinResolutionPolicy /OK /DownsampleMonoImages true
/MonoImageDownsampleType /Bicubic /MonoImageResolution 600
/MonoImageDepth -1 /MonoImageDownsampleThreshold 1.50000
/EncodeMonoImages true /MonoImageFilter /CCITTFaxEncode
/MonoImageDict << /K -1 >> /AllowPSXObjects false
/CheckCompliance [ /None ] /PDFX1aCheck false /PDFX3Check false
/PDFXCompliantPDFOnly false /PDFXNoTrimBoxError true
/PDFXTrimBoxToMediaBoxOffset [ 0.00000 0.00000 0.00000 0.00000 ]
/PDFXSetBleedBoxToMediaBox true /PDFXBleedBoxToTrimBoxOffset [
0.00000 0.00000 0.00000 0.00000 ] /PDFXOutputIntentProfile (None)
/PDFXOutputConditionIdentifier () /PDFXOutputCondition ()
/PDFXRegistryName () /PDFXTrapped /False /CreateJDFFile false
/Description << /CHS
<FEFF4f7f75288fd94e9b8bbe5b9a521b5efa7684002000410064006f006200650020005000440046002065876863900275284e8e55464e1a65876863768467e5770b548c62535370300260a853ef4ee54f7f75280020004100630072006f0062006100740020548c002000410064006f00620065002000520065006100640065007200200035002e003000204ee553ca66f49ad87248672c676562535f00521b5efa768400200050004400460020658768633002>
/CHT
<FEFF4f7f752890194e9b8a2d7f6e5efa7acb7684002000410064006f006200650020005000440046002065874ef69069752865bc666e901a554652d965874ef6768467e5770b548c52175370300260a853ef4ee54f7f75280020004100630072006f0062006100740020548c002000410064006f00620065002000520065006100640065007200200035002e003000204ee553ca66f49ad87248672c4f86958b555f5df25efa7acb76840020005000440046002065874ef63002>
/DAN
<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>
/DEU
<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>
/ESP
<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>
/FRA
<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>
/ITA (Utilizzare queste impostazioni per creare documenti Adobe PDF
adatti per visualizzare e stampare documenti aziendali in modo
affidabile. I documenti PDF creati possono essere aperti con
Acrobat e Adobe Reader 5.0 e versioni successive.) /JPN
<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>
/KOR
<FEFFc7740020c124c815c7440020c0acc6a9d558c5ec0020be44c988b2c8c2a40020bb38c11cb97c0020c548c815c801c73cb85c0020bcf4ace00020c778c1c4d558b2940020b3700020ac00c7a50020c801d569d55c002000410064006f0062006500200050004400460020bb38c11cb97c0020c791c131d569b2c8b2e4002e0020c774b807ac8c0020c791c131b41c00200050004400460020bb38c11cb2940020004100630072006f0062006100740020bc0f002000410064006f00620065002000520065006100640065007200200035002e00300020c774c0c1c5d0c11c0020c5f40020c2180020c788c2b5b2c8b2e4002e>
/NLD (Gebruik deze instellingen om Adobe PDF-documenten te maken
waarmee zakelijke documenten betrouwbaar kunnen worden weergegeven
en afgedrukt. De gemaakte PDF-documenten kunnen worden geopend met
Acrobat en Adobe Reader 5.0 en hoger.) /NOR
<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>
/PTB
<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>
/SUO
<FEFF004b00e40079007400e40020006e00e40069007400e4002000610073006500740075006b007300690061002c0020006b0075006e0020006c0075006f0074002000410064006f0062006500200050004400460020002d0064006f006b0075006d0065006e007400740065006a0061002c0020006a006f0074006b006100200073006f0070006900760061007400200079007200690074007900730061007300690061006b00690072006a006f006a0065006e0020006c0075006f00740065007400740061007600610061006e0020006e00e400790074007400e4006d0069007300650065006e0020006a0061002000740075006c006f007300740061006d0069007300650065006e002e0020004c0075006f0064007500740020005000440046002d0064006f006b0075006d0065006e00740069007400200076006f0069006400610061006e0020006100760061007400610020004100630072006f0062006100740069006c006c00610020006a0061002000410064006f00620065002000520065006100640065007200200035002e0030003a006c006c00610020006a006100200075007500640065006d006d0069006c006c0061002e>
/SVE
<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>
/ENU (Use these settings to create PDFs that match the "Suggested"
settings for PDF Specification 4.0) >> >>
setdistillerparams << /HWResolution [600 600] /PageSize
[612.000 792.000] >> setpagedevice