Top Banner
The first large diameter slurry TBM’s in India Selection of the tunnelling system for Bangalore Metro Moncrieff, R.L. 1. 1. Rona Consulting Co., Ltd., Bangkok, Thailand The design and build contract for the first underground section of Bangalore Metro was awarded to CECSomaCICI Joint Venture in 2010 and tunnelling work commenced in May 2011. Selection of the of the tunnelling system for the 5.6m ID bored tunnels through the varied and difficult ground conditions found beneath the congested central areas of the city was one of the early decisions that the contractor had to make. BMRC Contract UG2, comprises some 2,400m of twinbored tunnels, cut and cover tunnels, two ramps and four underground stations. Bangalore is situated 1,000m above sea level and ground conditions along the tunnel alignment consist of a shallow layer of fill or made ground overlying residual soil, weathered rock and hard fresh rock with compressive strengths in excess of 150 mpa. The rock head varies from below tunnel level to just below surface level. Hard granite, layers of weathered rock with differing geophysical characteristics and soft, residual soil occur at the tunnel horizon. A full rock face, soft ground face and mixed face conditions with up to three types of material can be encountered in the tunnel drives. Ground water level is typically just below the surface. For the twinbored tunnels, closed face TBM’s were specified by the client, however the contractor was able to select what he considered as the most suitable technology for the prevailing conditions. Slurry tunnelling machines were chosen, the first use of this technology on this scale in India. Fig India’s first large diameter slurry TBM The eastwest tunnel alignment on Contract UG2 lies beneath busy roads that serve areas of the city where there are large commercial developments, educational establishments and government buildings. Important buildings close bye include the Karnataka State Parliament, the High Court, the Civil Court and the General Post Office. Horizontal curves down to 220m in radius have to be negotiated and, unavoidably, at more than one location, the tunnels are below or close to buildings. Due to the hilly nature of the city, the overburden varies from 2.5 tunnel diameters to little more than one tunnel diameter. With the sensitivity of adjacent structures in this dense urban conurbation, control of settlement and ground movement during tunnelling is of prime importance. Factors that influenced the choice of tunnelling method and ultimately the selection and the design of the TBM’s and the support equipment required to construct this difficult tunnel alignment are discussed in this paper. Problems resulting from tunnelling through variable mixed ground conditions with ground water present are identified and the detailed process leading to the final selection and procurement of the first large diameter slurry tunnelling machines to be used in India is described.
1

Selecting the TBMs for the First Tunnel Project on Bangalore Metro

Oct 26, 2014

Download

Documents

Bob Moncrieff
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Selecting the TBMs for the First Tunnel Project on Bangalore Metro

The  first  large  diameter  slurry  TBM’s  in  India  -­‐  Selection  of  the  tunnelling  system  for  Bangalore  Metro    Moncrieff,  R.L.  1.  1.  Rona  Consulting  Co.,  Ltd.,  Bangkok,  Thailand    The   design   and   build   contract   for   the   first   underground   section   of   Bangalore  Metro   was  awarded  to  CEC-­‐Soma-­‐CICI   Joint  Venture   in  2010  and  tunnelling  work  commenced  in  May  2011.  Selection  of   the  of   the   tunnelling  system   for   the  5.6m   ID  bored   tunnels   through   the  varied  and  difficult  ground  conditions  found  beneath  the  congested  central  areas  of  the  city  was  one  of  the  early  decisions  that  the  contractor  had  to  make.    BMRC  Contract  UG2,  comprises  some  2,400m  of  twin-­‐bored  tunnels,  cut  and  cover  tunnels,  two  ramps  and  four  underground  stations.  Bangalore  is  situated  1,000m  above  sea  level  and  ground   conditions   along   the   tunnel   alignment   consist   of   a   shallow   layer   of   fill   or   made  ground   overlying   residual   soil,   weathered   rock   and   hard   fresh   rock   with   compressive  strengths  in  excess  of  150  mpa.    The  rock  head  varies  from  below  tunnel  level  to  just  below  surface   level.   Hard   granite,   layers   of   weathered   rock   with   differing   geophysical  characteristics  and  soft,  residual  soil  occur  at  the  tunnel  horizon.  A  full  rock  face,  soft  ground  face  and  mixed  face  conditions  with  up  to  three  types  of  material  can  be  encountered  in  the  tunnel  drives.  Ground  water  level  is  typically  just  below  the  surface.      For   the   twin-­‐bored   tunnels,   closed   face   TBM’s   were   specified   by   the   client,   however   the  contractor  was   able   to   select  what   he   considered   as   the  most   suitable   technology   for   the  prevailing   conditions.   Slurry   tunnelling   machines   were   chosen,   the   first   use   of   this  technology  on  this  scale  in  India.      

   

Fig  -­‐  India’s  first  large  diameter  slurry  TBM    The  east-­‐west  tunnel  alignment  on  Contract  UG2  lies  beneath  busy  roads  that  serve  areas  of  the   city  where   there   are   large   commercial   developments,   educational   establishments   and  government   buildings.   Important   buildings   close   bye   include   the   Karnataka   State  Parliament,   the  High  Court,   the   Civil   Court   and   the  General   Post  Office.  Horizontal   curves  down  to  220m  in  radius  have  to  be  negotiated  and,  unavoidably,  at  more  than  one  location,  the   tunnels   are   below   or   close   to   buildings.   Due   to   the   hilly   nature   of   the   city,   the  overburden  varies  from  2.5  tunnel  diameters  to  little  more  than  one  tunnel  diameter.  With  the  sensitivity  of  adjacent  structures  in  this  dense  urban  conurbation,  control  of  settlement  and  ground  movement  during  tunnelling  is  of  prime  importance.    Factors  that  influenced  the  choice  of  tunnelling  method  and  ultimately  the  selection  and  the  design  of   the  TBM’s  and   the   support   equipment   required   to   construct   this  difficult   tunnel  alignment  are  discussed  in  this  paper.  Problems  resulting  from  tunnelling  through  variable  mixed  ground  conditions  with  ground  water  present  are  identified  and  the  detailed  process  leading  to   the   final  selection  and  procurement  of   the   first   large  diameter  slurry  tunnelling  machines  to  be  used  in  India  is  described.