101-14 Blessed Sacrament School- Phase I 215-14 23 0110 - 1 MECHANICAL GENERAL PROVISIONS SECTION 23 0110 MECHANICAL GENERAL PROVISIONS PART 1 - GENERAL 1.01 RELATED DOCUMENTS: A. Drawings and general provisions of the Contract, including General and Special Conditions and Division 1 Specification Sections, apply to this Section. B. It is recognized that separate sub-contracts may be instituted by THIS CONTRACT'S GENERAL CONTRACTOR with others. It is the responsibility of THIS CONTRACT'S GENERAL CONTRACTOR to completely inform, coordinate and advise those sub- contractors as to all of the requirements, conditions and information associated with providing and installing their portion of the total job. 1.02 IMPOSED REGULATIONS: A. Applicable provisions of the State and Local Codes and of the following codes and standards in addition to those listed elsewhere in the specifications are hereby imposed on a general basis for mechanical work. In each case, the prevailing edition shall be the current adopted edition of the state where the project is located. 1. International Mechanical Code. 2. International Gas Code. 3. International Energy Conservation Code. 4. International Fire Code. 1.03 SCOPE OF WORK: A. Provide all labor, materials, equipment and supervision to construct complete and operable mechanical systems as indicated on the drawings and specified herein. All materials and equipment used shall be new, undamaged and free from any defects. 1.04 EXISTING SERVICES AND FACILITIES: A. Damage to Existing Services: Existing services and facilities damaged by the Contractor through negligence or through use of faulty materials or workmanship shall be promptly repaired, replaced, or otherwise restored to previous conditions by the Contractor without additional cost to the Owner. B. Interruption of Services: Interruptions of services necessary for connection to or modification of existing systems or facilities shall occur only at prearranged times approved by the Owner. Interruptions shall only occur after the provision of all temporary work and the availability of adequate labor and materials will assure that the duration of the interruption will not exceed the time agreed upon. C. Removed Materials: Existing materials made unnecessary by the new installation shall be removed, shall remain the property of the Owner and shall be stored at a location and in a manner as directed, or, if classified by the Owner's authorized representative as unsuitable for
116
Embed
SECTION 23 0110 MECHANICAL GENERAL PROVISIONS PART … · 2016-04-01 · SECTION 23 0110 MECHANICAL GENERAL PROVISIONS PART 1 - GENERAL ... Boston, MA 02210 617/482-8755 . ... 912/241-2284
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
101-14 Blessed Sacrament School- Phase I
215-14 23 0110 - 1 MECHANICAL GENERAL PROVISIONS
SECTION 23 0110
MECHANICAL GENERAL PROVISIONS
PART 1 - GENERAL
1.01 RELATED DOCUMENTS:
A. Drawings and general provisions of the Contract, including General and Special Conditions
and Division 1 Specification Sections, apply to this Section.
B. It is recognized that separate sub-contracts may be instituted by THIS CONTRACT'S
GENERAL CONTRACTOR with others. It is the responsibility of THIS CONTRACT'S
GENERAL CONTRACTOR to completely inform, coordinate and advise those sub-
contractors as to all of the requirements, conditions and information associated with
providing and installing their portion of the total job.
1.02 IMPOSED REGULATIONS:
A. Applicable provisions of the State and Local Codes and of the following codes and standards
in addition to those listed elsewhere in the specifications are hereby imposed on a general
basis for mechanical work. In each case, the prevailing edition shall be the current adopted
edition of the state where the project is located.
1. International Mechanical Code.
2. International Gas Code.
3. International Energy Conservation Code.
4. International Fire Code.
1.03 SCOPE OF WORK:
A. Provide all labor, materials, equipment and supervision to construct complete and operable
mechanical systems as indicated on the drawings and specified herein. All materials and
equipment used shall be new, undamaged and free from any defects.
1.04 EXISTING SERVICES AND FACILITIES:
A. Damage to Existing Services: Existing services and facilities damaged by the Contractor
through negligence or through use of faulty materials or workmanship shall be promptly
repaired, replaced, or otherwise restored to previous conditions by the Contractor without
additional cost to the Owner.
B. Interruption of Services: Interruptions of services necessary for connection to or modification
of existing systems or facilities shall occur only at prearranged times approved by the Owner.
Interruptions shall only occur after the provision of all temporary work and the availability of
adequate labor and materials will assure that the duration of the interruption will not exceed
the time agreed upon.
C. Removed Materials: Existing materials made unnecessary by the new installation shall be
removed, shall remain the property of the Owner and shall be stored at a location and in a
manner as directed, or, if classified by the Owner's authorized representative as unsuitable for
101-14 Blessed Sacrament School- Phase I
215-14 23 0110 - 2 MECHANICAL GENERAL PROVISIONS
further use, shall become the property of the Contractor and shall be removed from the site.
1.05 PRODUCT WARRANTIES:
A. Provide manufacturer's standard printed commitment in reference to a specific product and
normal application, stating that certain acts of restitution will be performed for the Purchaser
or Owner by the manufacturer, when and if the product fails within certain operational
conditions and time limits. Where the warranty requirements of a specific specification
section exceed the manufacturer's standard warranty, the more stringent requirements will
apply and modified manufacturer's warranty shall be provided. In no case shall the
manufacturer's warranty be less than one (1) year.
1.06 PRODUCT SUBSTITUTIONS:
A. General: Materials specified by manufacturer's name shall be used unless prior approval of
an alternate is given by addenda. Requests for substitutions must be received in the office of
the Architect at least 10 days prior to opening of bids.
PART 2 - PRODUCTS
2.01 GENERAL MECHANICAL PRODUCT REQUIREMENTS:
A. Standard Products: Provide not less (quality) than manufacturer's standard products, as
specified by their published product data. In addition to the indication that a particular
product/model number is acceptable, comply with the specified requirements. Do not assume
that the available off-the-shelf condition of a product complies with the requirements; as an
example, a specific finish or color may be required.
B. Uniformity: Where multiple units of a general product are required for the mechanical work,
provide identical products by the same manufacturer, without variations except for sizes and
similar variations as indicated.
C. Product Compatibility, Options: Where more than one product selection is specified, either
generically or proprietarily, selection is Purchaser's or Installer's option. Provide mechanical
adaptations as needed for interfacing of selected products in the work.
D. Equipment Nameplates: Provide a permanent operational data nameplate on each item of
power operated mechanical equipment, indicating the manufacturer, product name, model
number, serial number, speed, capacity, power characteristics, labels of tested compliance,
and similar essential operating data.
E. Locate nameplates in easy-to-read locations. When product is visually exposed in an
occupied area of the building, locate nameplate in a concealed position (where possible)
which is accessible for reading by service personnel.
PART 3 - EXECUTION
3.01 PRODUCT INSTALLATION, GENERAL:
101-14 Blessed Sacrament School- Phase I
215-14 23 0110 - 3 MECHANICAL GENERAL PROVISIONS
A. Except where more stringent requirements are indicated, comply with the product
manufacturer's installation instructions and recommendations, including handling, anchorage,
assembly, connections, cleaning and testing, charging, lubrication, startup, test operation and
shut-down of operating equipment. Consult with manufacturer's technical experts, for
specific instructions on unique product conditions and unforeseen problems.
B. Protection and Identification: Deliver products to project properly identified with names,
models numbers, types, grades, compliance labels and similar information needed for distinct
identifications; adequately packaged or protected to prevent deterioration during shipment,
storage and handling. Store in a dry, well ventilated, indoor space, except where prepared
and protected by the manufacturer specifically for exterior storage.
C. Permits and Tests: Provide labor, material and equipment to perform all tests required by the
governing agencies and submit a record of all tests to the Owner or his representative. Notify
the Architect five days in advance of any testing.
END OF SECTION 23 0110
101-14 Blessed Sacrament School- Phase I
215-14 23 0120 - 1 MECHANICAL STANDARDS
SECTION 23 0120
MECHANICAL STANDARDS
PART 1 - GENERAL
1.01 RELATED DOCUMENTS:
A. Drawings and general provisions of the Contract, including General and Special Conditions
and Division 1 Specification Sections, apply to this Section.
1.02 QUALITY ASSURANCE:
A. Industry Standards: It is a general requirement that mechanical work comply with applicable
requirements and recommendations of standards published by listed agencies and trade
associations, except to the extent more detailed and stringent requirements are indicated or
required by governing regulations.
B. Listing of Associations, Standards, and Abbreviations:
1. AGA American Gas Association
1515 Wilson Blvd.
Arlington, VA 22209
2. AMCA Air Movement & Control Association
30 W. University Dr., Arlington Heights, IL 60004
302/394-0150
3. ARI Air-Conditioning and Refrigeration Institute
4301 North Fairfax Drive, Suite 425, Arlington, VA
22203
703/524-8800
4. ASHRAE American Society of Heating, Refrigerating &
Air Conditioning Engineers, Inc.
1791 Tullie Circle, NE, Atlanta, GA. 30329
404/636-8400
5. AWS American Welding Society, Inc.
2501 NW 7th St., Miami, FL 33125
305/642-7090
6. CISPI Cast Iron Soil Pipe Institute
2020 K. St., NW, Washington, DC
202/233-4536
7. NEBB National Environmental Balancing Bureau
1611 North Kent St.,
Arlington, VA 22209
8. NEC National Electrical Code by NFPA
9. NEMA National Electrical Manufacturers Association
1300 N 17th Street, Suite 1847
Rosslyn, VA 22209
703/841-3200
10. NFPA National Fire Protection Association
407 Atlantic Ave.,
Boston, MA 02210
617/482-8755
101-14 Blessed Sacrament School- Phase I
215-14 23 0120 - 2 MECHANICAL STANDARDS
11. SMACNA Sheet Metal & Air Conditioning Contractors National
Association, Inc.
8224 Old Courthouse Rd., Tysons Corner
Vienna, VA 22180
703/790-9890
12. TIMA Thermal Insulation Manufacturers Association
7 Kirby Plaza
Mt. Kisco, NY 10549
912/241-2284
13. UL Underwriters' Laboratories, Inc.
207 East Ohio St.,
Chicago, IL 60611
312/642-6969
PARTS 2 AND 3 - PRODUCTS AND EXECUTION Not applicable.
END OF SECTION 23 0120
Dalton High School Renovations
215-14 23 0210 - 1 MECHANICAL COORDINATION
SECTION 23 0210
MECHANICAL COORDINATION
PART 1 - GENERAL
1.01 RELATED DOCUMENTS:
A. Drawings and general provisions of the Contract, including General and Special Conditions
and Division 1 Specification Sections, apply to this Section.
1.02 QUALITY ASSURANCE:
A. Coordinate the actual location of all mechanical work visible in finished spaces with the
Architect/Engineer. This includes air distribution devices, exposed ductwork, thermostats,
humidistats, switches, sensors, etc.
PART 2 - PRODUCTS
2.01 MECHANICAL PRODUCT COORDINATION:
A. Power Characteristics: Refer to the electrical sections of the specifications and the electrical
drawings for the power characteristics available for the operation of each power driven item
of equipment. The electrical design was based on the typical power requirements of the
equipment manufacturers scheduled or specified. Any modifications to the electrical system
which are required due to the use of an approved equivalent manufacturer shall be made at no
additional cost to the owner. All changes must be clearly documented and submitted for
review by the Architect/Engineer prior to purchasing equipment. Coordinate purchases to
ensure uniform interface with electrical work. The mechanical contractor shall furnish a
detailed list of equipment electrical characteristics to the electrical contractor for the purpose
of preparing the coordination affidavit required by Division 26.
B. Coordination of Options and Substitutions: Where the contract documents permit the
selection from several product options, and where it becomes necessary to authorize a
substitution, do not proceed with purchasing until coordination of interface of equipment has
been checked and satisfactorily established.
C. Firestopping: Refer to architectural drawings for the locations of all fire rated ceilings, floors
and walls. The contractor shall furnish detailed shop drawings of all firestopping details to be
used for both piping and ductwork. All firestopping details shall be U.L. listed and subject to
approval by the Authority having jurisdiction.
PART 3 - EXECUTION
3.01 INSPECTION AND PREPARATION:
A. Substrate Examination: The Installer of each element of the mechanical work must examine
the condition of the substrate to receive the work, and the conditions under which the work
will be performed, and must notify the Contractor in writing of conditions detrimental to the
proper completion of the work. Do not proceed with the work until unsatisfactory conditions
have been corrected in a manner acceptable to the Installer.
B. Do not proceed with the installation of sleeves, anchors, hangers, roof penetrations and
Dalton High School Renovations
215-14 23 0210 - 2 MECHANICAL COORDINATION
similar work until mechanical coordination drawings have been processed and released for
construction. Where work must be installed prior to that time in order to avoid a project
delay, review proposed installation in a project coordination meeting including all parties
involved with the interfacing of the work.
3.02 CUTTING AND PATCHING:
A. Structural Limitations: Do not cut structural framing, walls, floors, decks and other members
intended to withstand stress, except with the Architect's or Engineer's written authorization.
B. Where authorized, cut opening through concrete (for pipe penetrations and similar services)
by core drilling or sawing. Do not cut by hammer-driven chisel or drill.
C. Other work: Do not endanger or damage other work through the procedures and processes of
cutting to accommodate mechanical work. Review the proposed cutting with the Installer of
the work to be cut, and comply with his recommendations to minimize damage. Where
necessary, engage the original Installer or other specialists to execute the cutting in the
recommended manner.
D. Where patching is required to restore other work, because of either cutting or other damage
inflicted during the installation of mechanical work, execute the patching in the manner
recommended by the original Installer. Restore the other work in every respect, including the
elimination of visual defects in exposed finishes, as judged by the Architect. Engage the
original Installer to complete patching of the following categories of work:
1. Exposed concrete finishes and exposed masonry.
2. Waterproofing and vapor barriers.
3. Roofing, flashing and accessories.
4. Interior exposed finishes and casework, where judged by the Architect to be difficult to
achieve an acceptable match by other means.
3.03 COORDINATION OF MECHANICAL INSTALLATION:
A. General: Sequence, coordinate and integrate the various elements of mechanical work so that
the mechanical plant will perform as indicated and be in harmony with the other work of the
building. The Architect/Engineer will not supervise the coordination, which is the exclusive
responsibility of the Contractor. Comply with the following requirements:
1. Install piping, ductwork and similar services straight and true, aligned with other work
and with overhead structures and allowing for insulation. Conceal where possible.
2. Arrange work to facilitate maintenance and repair or replacement of equipment. Locate
services requiring maintenance on valves and similar units in front of services requiring
less maintenance. Connect equipment for ease of disconnecting, with minimum of
interference with other work.
3. Equipment located above ceilings shall be installed in a position and elevation which
allows complete and adequate maintenance access through the ceiling grid or access
panel while standing safely on a ladder. If this is not possible, a suitable maintenance
platform must be provided per IMC.
4. Give the right-of way to piping systems required to slope for drainage (over other service
lines). Piping shall be located to avoid interference with ductwork and light fixtures.
5. Store materials off the ground and protected from standing water and weather.
Dalton High School Renovations
215-14 23 0210 - 3 MECHANICAL COORDINATION
B. Drawings: Conform with the arrangement indicated by the contract documents to the greatest
extent possible, recognizing that portions of the work are shown only in diagrammatic form.
Where coordination requirements conflict with individual system requirements, comply with
the Architect's decision on resolution of the conflict.
C. Electrical Work: Coordinate the mechanical work with electrical work, and properly
interface with the electrical service. In general, and except as otherwise indicated, install
mechanical equipment ready for electrical connection. Refer to electrical sections of the
specifications for electrical connection of mechanical equipment.
D. Duct Smoke Detectors: All HVAC duct smoke detectors, including smoke detectors for
smoke dampers, shall be furnished by Division 26 and installed by Division 23. In buildings
equipped with a fire alarm system, all duct smoke detectors must be compatible with the fire
alarm system and must be connected to the fire alarm system for notification. All fire alarm
wiring and associated devices shall be furnished and installed by the fire alarm system
installer. In buildings not equipped with a fire alarm system, each duct smoke detector must
have a remote device where actuation of the duct smoke detector shall activate a visible and
an audible signal in an approved location. Duct smoke detector trouble conditions shall
activate a visible or audible signal in an approved location and shall be identified as “Air
Duct Detector Trouble.” Each smoke detector shall be wired into the respective fan control
circuit to automatically shut down the fan upon sensing products of combustion.
E. Utility Connections: Coordinate the connection of mechanical systems with exterior
underground utilities and services. Comply with the requirements of governing regulations,
franchised service companies and controlling agencies. Provide a single connection for each
service except where multiple connections are indicated.
3.04 COORDINATION OF MECHANICAL START-UP:
A. Seasonal Requirements: Adjust and coordinate the timing of mechanical system start-ups
with seasonal variations, so that demonstration and testing of specified performance can be
observed and recorded. Exercise proper care in off-season start-ups to ensure that systems
and equipment will not be damaged by the operation.
B. Painting and Air Distribution: Coordinate the initial cleaning and start-up of the air
distribution system, to occur prior to preparatory cleaning and general interior painting and
decorating on the project. The HVAC system should not be operated until drywall work is
completed. Drywall dust must not be allowed to contaminate the interior of air handing units
and ductwork. Use high efficiency temporary filters until project closeout.
END OF SECTION 23 0210
Dalton High School Renovations
215-14 23 0220 - 1 MECHANICAL SUBMITTALS
SECTION 23 0220
MECHANICAL SUBMITTALS
PART 1 - GENERAL
1.01 RELATED DOCUMENTS:
A. Drawings and general provisions of the Contract, including General and Special Conditions
and Division 1 Specification Sections, apply to this Section.
1.02 SUBMITTAL FORMS AND PROCEDURES:
A. The purpose of submittals is to demonstrate to the Architect/Engineer that the Contractor
understands the design concept. The Architect/Engineer's review of such drawings,
schedules, or cuts shall not relieve the Contractor from responsibility for deviation from
drawings or specifications unless he has, in writing, called the Architect/Engineer's attention
to such deviations at the time of submission, and has received from the Architect/Engineer, in
writing, permission for such deviations. All submittals must be completely checked by the
Contractor prior to submission for review.
B. Hard Copy Submittals: Submittal data shall be placed in one or more hard-back 3-ring
binders, arranged and labeled according to specification section. Each binder shall contain a
title page and table of contents. Provide separator tabs, and label by specification section.
Make note in the table of contents, any drawings that accompany the submittal. Title page
5. Alarm and Event Log: Operators shall be able to view all system alarms and changes of
state from any location in the system. Events shall be listed chronologically. An operator
with the proper security level may acknowledge and delete alarms, and archive closed
alarms to the workstation or web server hard disk.
6. Trend Logs: The operator shall be able to configure trend sample or change of value (COV)
interval, start time, and stop time for each system data object and shall be able to retrieve
data for use in spreadsheets and standard database programs. Controller shall sample and
store trend data and shall be able to archive data to the hard disk. Configure trends as
specified in Section 23 09 93 (Sequences of Operation). Trends shall be BACnet trend
objects.
7. Object and Property Status and Control: Provide a method for the operator to view, and
edit if applicable, the status of any object or property in the system. The status shall be
available by menu, on graphics, or through custom programs.
8. Reports and Logs: Operator shall be able to select, to modify, to create, and to print reports
and logs. Operator shall be able to store report data in a format accessible by standard
spreadsheet and word processing programs.
9. Standard Reports: Furnish the following standard system reports:
a. Objects: System objects and current values filtered by object type, by status (in alarm,
locked, normal), by equipment, by geographic location, or by combination of filter
criteria.
b. Alarm Summary: Current alarms and closed alarms. System shall retain closed alarms
for an adjustable period.
Dalton High School Renovations
ENERGY MANAGEMENT CONTROL SYSTEM 23 8310 - 7
c. Logs: System shall log the following to a database or text file and shall retain data for
an adjustable period:
i. Alarm History.
ii. Trend Data. Operator shall be able to select trends to be logged.
iii. Operator Activity. At a minimum, system shall log operator log in and log out,
control parameter changes, schedule changes, and alarm acknowledgment and
deletion. System shall date and time stamp logged activity.
2.04 CONTROLLER SOFTWARE:
A. Furnish the following applications for building and energy management. All software
application shall reside and operate in the system controllers. Applications shall be editable
through operator workstation, web browser interface, or engineering workstation.
B. Scheduling: Provide the capability to execute control functions according to a user created or
edited schedule. Each schedule shall provide the following schedule options as a minimum:
1. Weekly Schedule. Provide separate schedules for each day of the week. Each schedule
shall be able to include up to 5 occupied periods (5 start-stop pairs or 10 events).
2. Exception Schedules. Provide the ability for the operator to designate any day of the year
as an exception schedule. Exception schedules may be defined up to a year in advance.
Once an exception schedule has executed, the system shall discard and replace the
exception schedule with the standard schedule for that day of the week.
3. Holiday Schedules. Provide the capability for the operator to define up to 24 special or
holiday schedules. These schedules will be repeated each year. The operator shall be able
to define the length of each holiday period.
C. Demand Limiting:
1. The demand-limiting program shall monitor building power consumption from a building
power meter (provided by others) which generates pulse signals or a BACnet
communications interface. An acceptable alternative is for the system to monitor a watt
transducer or current transformer attached to the building feeder lines.
2. When power consumption exceeds adjustable levels, system shall automatically adjust
setpoints, de-energize low-priority equipment, and take other programmatic actions to
reduce demand as specified in Section 23 09 93 (Sequences of Operation). When demand
drops below adjustable levels, system shall restore loads as specified.
D. Maintenance Management: The system shall be capable of generating maintenance alarms
when equipment exceeds adjustable runtime, equipment starts, or performance limits.
Configure and enable maintenance alarms as specified in 23 09 93 (Sequences of Operation).
E. PID Control: System shall provide direct- and reverse-acting PID (proportional-integral-
derivative) algorithms. Each algorithm shall have anti-windup and selectable controlled
variable, setpoint, and PID gains. Each algorithm shall calculate a time-varying analog value
that can be used to position an output or to stage a series of outputs. The calculation interval,
PID gains, and other tuning parameters shall be adjustable by a user with the correct security
level.
2.05 CONTROLLERS:
A. BACnet:
Dalton High School Renovations
ENERGY MANAGEMENT CONTROL SYSTEM 23 8310 - 8
1. Building Controllers (BCs): Each BC shall conform to BACnet Building Controller (B-
BC) device profile as specified in ANSI/ASHRAE 135, BACnet Annex L, and shall be
listed as a certified B-BC in the BACnet Testing Laboratories (BTL) Product Listing.
2. Advanced Application Controllers (AACs): Each AAC shall conform to BACnet
Advanced Application Controller (B-AAC) device profile as specified in ANSI/ASHRAE
135, BACnet Annex L and shall be listed as a certified B-AAC in the BACnet Testing
Laboratories (BTL) Product Listing.
3. Application Specific Controllers (ASCs): Each ASC shall conform to BACnet Application
Specific Controller (B-ASC) device profile as specified in ANSI/ASHRAE 135, BACnet
Annex L and shall be listed as a certified B-ASC in the BACnet Testing Laboratories (BTL)
Product Listing.
4. Smart Sensors (SSs): Each SS shall conform to BACnet Smart Sensor (B-SS) device
profile as specified in ANSI/ASHRAE 135, BACnet Annex L and shall be listed as a
certified B-SS in the BACnet Testing Laboratories (BTL) Product Listing.
5. BACnet Communication:
a. Each BC shall reside on or be connected to a BACnet network using ISO 8802-3
(Ethernet) Data Link/Physical layer protocol and BACnet/IP addressing.
b. BACnet routing shall be performed by BCs or other BACnet device routers as
necessary to connect BCs to networks of AACs and ASCs.
c. Each AAC shall reside on a BACnet network using ISO 8802-3 (Ethernet) Data
Link/Physical layer protocol with BACnet/IP addressing, or it shall reside on a BACnet
network using the ARCNET or MS/TP Data Link/Physical layer protocol.
d. Each ASC shall reside on a BACnet network using the ARCNET or MS/TP Data
Link/Physical layer protocol.
e. Each SA shall reside on a BACnet network using the ARCNET or MS/TP Data
Link/Physical layer protocol.
f. Each SS shall reside on a BACnet network using ISO 8802-3 (Ethernet) Data
Link/Physical layer protocol with BACnet/IP addressing, or it shall reside on a BACnet
network using ARCNET or MS/TP Data Link/Physical layer protocol.
B. Communication:
1. Service Port. Each controller shall provide a service communication port for connection to
a Portable Operator’s Terminal. Connection shall be extended to space temperature sensor
ports where shown on drawings.
2. Signal Management. BC and ASC operating systems shall manage input and output
communication signals to allow distributed controllers to share real and virtual object
information and to allow for central monitoring and alarms.
3. Data Sharing. Each BC and AAC shall share data as required with each networked BC and
AAC.
4. Stand-Alone Operation. Each piece of equipment specified in Section 23 09 93 shall be
controlled by a single controller to provide stand-alone control in the event of
communication failure. All I/O points specified for a piece of equipment shall be integral
to its controller. Provide stable and reliable stand-alone control using default values or
other method for values normally read over the network such as outdoor air conditions,
supply air or water temperature coming from source equipment, etc.
C. Environment: Controller hardware shall be suitable for anticipated ambient conditions.
1. Controllers used outdoors or in wet ambient conditions shall be mounted in waterproof
enclosures and shall be rated for operation at -29°C to 60°C (-20°F to 140°F).
2. Controllers used in conditioned space shall be mounted in dust-protective enclosures and
shall be rated for operation at 0°C to 50°C (32°F to 120°F).
Dalton High School Renovations
ENERGY MANAGEMENT CONTROL SYSTEM 23 8310 - 9
D. Real-Time Clock: Controllers that perform scheduling shall have a real-time clock.
E. Serviceability: Provide diagnostic LEDs for power, communication, and processor. All wiring
connections shall be made to a field-removable modular terminal strip or to a termination card
connected by a ribbon cable. Each BC and AAC shall continually check its processor and
memory circuit status and shall generate an alarm on abnormal operation. System shall
continuously check controller network and generate alarm for each controller that fails to
respond.
F. Memory:
1. Controller memory shall support operating system, database, and programming
requirements.
2. Each BC and AAC shall retain BIOS and application programming for at least 72 hours in
the event of power loss.
3. Each ASC and SA shall use nonvolatile memory and shall retain BIOS and application
programming in the event of power loss. System shall automatically download dynamic
control parameters following power loss.
G. Immunity to Power and Noise: Controllers shall be able to operate at 90% to 110% of nominal
voltage rating and shall perform an orderly shutdown below 80% nominal voltage. Operation
shall be protected against electrical noise of 5 to 120 Hz and from keyed radios up to 5 W at 1
m (3 ft).
H. Transformer: ASC power supply shall be fused or current limiting and shall be rated at a
minimum of 125% of ASC power consumption.
2.06 AUXILIARY CONTROL DEVICES:
A. Motorized Control Dampers, unless otherwise specified elsewhere, shall be as follows:
1. Type: Control dampers shall be the parallel or opposed-blade type as specified below or
as scheduled on drawings.
2. Outdoor and return air mixing dampers and face-and-bypass dampers shall be parallel-
blade and shall direct airstreams toward each other.
3. Other modulating dampers shall be opposed-blade.
4. Two-position shutoff dampers shall be parallel- or opposed-blade with blade and side seals.
B. Temperature Sensors:
1. Type: Temperature sensors shall be Resistance Temperature Device (RTD) or thermistor.
2. Duct Sensors: Duct sensors shall be single point or averaging as shown. Averaging sensors
shall be a minimum of 1.5 m (5 ft) in length per 1 m2(10 ft2) of duct cross-section. 3. Immersion Sensors: Provide immersion sensors with a separable stainless steel well. Well
pressure rating shall be consistent with system pressure it will be immersed in. Well shall
withstand pipe design flow velocities.
4. Space Sensors: Space sensors shall have setpoint adjustment, override switch, display, and
communication port as shown.
5. Differential Sensors: Provide matched sensors for differential temperature measurement.
C. Humidity Sensors:
1. Duct and room sensors shall have a sensing range of 20%–80%.
2. Duct sensors shall have a sampling chamber.
Dalton High School Renovations
ENERGY MANAGEMENT CONTROL SYSTEM 23 8310 - 10
3. Outdoor air humidity sensors shall have a sensing range of 20%–95% RH and shall be
suitable for ambient conditions of -40°C–75°C (-40°F–170°F).
4. Humidity sensors shall not drift more than 1% of full scale annually.
D. Relays:
1. Control Relays: Control relays shall be plug-in type, UL listed, and shall have dust cover
and LED “energized” indicator. Contact rating, configuration, and coil voltage shall be
suitable for application.
2. Time Delay Relays: Time delay relays shall be solid-state plug-in type, UL listed, and
shall have adjustable time delay. Delay shall be adjustable ±100% from setpoint shown.
Contact rating, configuration, and coil voltage shall be suitable for application. Provide
NEMA 1 enclosure for relays not installed in local control panel.
E. Voltage Transmitters:
1. AC voltage transmitters shall be self-powered single-loop (two-wire) type, 4–20 mA output
with zero and span adjustment.
2. Adjustable full-scale unit ranges shall be 100–130 Vac, 200–250 Vac, 250–330 Vac, and
400–600 Vac. Unit accuracy shall be ±1% full-scale at 500 ohm maximum burden.
3. Transmitters shall meet or exceed ANSI/ISA S50.1 requirements and shall be UL/CSA
recognized at 600 Vac rating.
F. Voltage Transformers:
1. AC voltage transformers shall be UL/CSA recognized, 600 Vac rated, and shall have built-
in fuse protection.
2. Transformers shall be suitable for ambient temperatures of 4°C–55°C (40°F–130°F) and
shall provide ±0.5% accuracy at 24 Vac and 5 VA load.
3. Windings (except for terminals) shall be completely enclosed with metal or plastic.
G. Power Monitors:
1. Selectable rate pulse output for kWh reading, 4–20 mA output for kW reading, N.O. alarm
contact, and ability to operate with 5.0 amp current inputs or 0–0.33 volt inputs.
2. 1.0% full-scale true RMS power accuracy, +0.5 Hz, voltage input range 120–600 V, and
auto range select.
3. Under voltage/phase monitor circuitry.
4. NEMA 1 enclosure.
5. Current transformers having a 0.5% FS accuracy, 600 VAC isolation voltage with 0–0.33
V output. If 0–5 A current transformers are provided, a three-phase disconnect/shorting
switch assembly is required.
H. Current Switches:
1. Current-operated switches shall be self-powered, solid-state with adjustable trip current.
Select switches to match application current and DDC system output requirements.
I. Pressure Transducers:
1. Transducers shall have linear output signal and field-adjustable zero and span.
2. Transducer sensing elements shall withstand continuous operating conditions of positive
or negative pressure 50% greater than calibrated span without damage.
J. Local Control Panels:
Dalton High School Renovations
ENERGY MANAGEMENT CONTROL SYSTEM 23 8310 - 11
1. All indoor control cabinets shall be fully enclosed NEMA 1 construction with (hinged
door) key-lock latch and removable subpanels. A single key shall be common to all field
panels and subpanels.
2. Interconnections between internal and face-mounted devices shall be prewired with color-
for field connections shall be UL listed for 600 volt service, individually identified per
control/ interlock drawings, with adequate clearance for field wiring. Control terminations
for field connection shall be individually identified per control drawings.
3. Provide ON/OFF power switch with overcurrent protection for control power sources to
each local panel.
2.07 WIRING AND RACEWAYS:
A. General. Provide copper wiring, plenum cable, and raceways as specified in applicable
sections of Division 26.
B. Insulated wire shall use copper conductors and shall be UL listed for 200°F minimum service.
2.08 FIBER OPTIC CABLE SYSTEM:
A. Optical Cable: Optical cables shall be duplex 900 mm tight-buffer construction designed for
intra-building environments. Sheath shall be UL listed OFNP in accordance with NEC Article
770. Optical fiber shall meet the requirements of FDDI, ANSI X3T9.5 PMD for 62.5/125mm.
B. Connectors: Field terminate optical fibers with ST type connectors. Connectors shall have
ceramic ferrules and metal bayonet latching.
PART 3 – EXECUTION
3.01 EXAMINATION:
A. The contractor shall inspect the site to verify that equipment may be installed as shown. Any
discrepancies, conflicts, or omissions shall be reported to the engineer for resolution before
rough-in work is started.
B. The contractor shall examine the drawings and specifications for other parts of the work. If
head room or space conditions appear inadequate—or if any discrepancies occur between the
plans and the contractor’s work and the plans and the work of others—the contractor shall
report these discrepancies to the engineer and shall obtain written instructions for any changes
necessary to accommodate the contractor’s work with the work of others. Any changes in the
work covered by this specification made necessary by the failure or neglect of the contractor
to report such discrepancies shall be made by—and at the expense of—this contractor.
3.02 PROTECTION:
A. The contractor shall protect all work and material from damage by his/her work or employees
and shall be liable for all damage thus caused.
B. The contractor shall be responsible for his/her work and equipment until finally inspected,
tested, and accepted. The contractor shall protect any material that is not immediately installed.
Dalton High School Renovations
ENERGY MANAGEMENT CONTROL SYSTEM 23 8310 - 12
The contractor shall close all open ends of work with temporary covers or plugs during storage
and construction to prevent entry of foreign objects.
3.03 COORDINATION:
A. Site:
1. Where the mechanical work will be installed in close proximity to, or will interfere with,
work of other trades, the contractor shall assist in working out space conditions to make a
satisfactory adjustment. If the contractor installs his/her work before coordinating with
other trades, so as to cause any interference with work of other trades, the contractor shall
make the necessary changes in his/her work to correct the condition without extra charge.
2. Coordinate and schedule work with other work in the same area and with work dependent
upon other work to facilitate mutual progress.
B. Test and Balance:
1. The contractor shall furnish a single set of all tools necessary to interface to the control
system for test and balance purposes.
2. The contractor shall provide training in the use of these tools. This training will be planned
for a minimum of 4 hours.
3. In addition, the contractor shall provide a qualified technician to assist in the test and
balance process, until the first 20 terminal units are balanced.
4. The tools used during the test and balance process will be returned at the completion of the
testing and balancing.
C. Life Safety:
1. Duct smoke detectors required for air handler shutdown are provided under Division 26.
Interlock smoke detectors to air handlers for shutdown as specified in Sequences of
Operation.
2. Smoke dampers and actuators required for duct smoke isolation are provided under
Division 23. Interlock smoke dampers to air handlers as specified in Sequences of
Operation.
3. Fire and smoke dampers and actuators required for fire-rated walls are provided under
Division 23. Fire and smoke damper control is provided under Division 26.
D. Coordination with controls specified in other sections or divisions. Other sections and/or
divisions of this specification include controls and control devices that are to be part of or
interfaced to the control system specified in this section. These controls shall be integrated
into the system and coordinated by the contractor as follows:
1. All communication media and equipment shall be provided as specified in Communication.
2. Each supplier of a controls product is responsible for the configuration, programming, start
up, and testing of that product to meet the Sequences of Operation.
3. The contractor shall coordinate and resolve any incompatibility issues that arise between
control products provided under this section and those provided under other sections or
divisions of this specification.
4. The contractor is responsible for providing all controls described in the contract documents
regardless of where within the contract documents these controls are described.
5. The contractor is responsible for the interface of control products provided by multiple
suppliers regardless of where this interface is described within the contract documents.
3.04 GENERAL WORKMANSHIP:
Dalton High School Renovations
ENERGY MANAGEMENT CONTROL SYSTEM 23 8310 - 13
A. Install equipment, piping, and wiring/raceway parallel to building lines (i.e. horizontal,
vertical, and parallel to walls) wherever possible.
B. Provide sufficient slack and flexible connections to allow for vibration of piping and
equipment.
C. Install equipment in readily accessible locations as defined by Chapter 1 Article 100 Part A of
the National Electrical Code (NEC).
D. Verify integrity of all wiring to ensure continuity and freedom from shorts and grounds.
E. All equipment, installation, and wiring shall comply with industry specifications and standards
for performance, reliability, and compatibility and be executed in strict adherence to local codes
and standard practices.
3.05 FIELD QUALITY CONTROL:
A. All work, materials, and equipment shall comply with rules and regulations of applicable local,
state, and federal codes and ordinances as identified in Codes and Standards.
B. Contractor shall continually monitor the field installation for code compliance and quality of
workmanship.
C. Contractor shall have work inspection by local and/or state authorities having jurisdiction over
the work.
3.06 WIRING:
A. All control and interlock wiring shall comply with national and local electrical codes, and
Division 26 of this specification. Where the requirements of this section differ from Division
26, the requirements of this section shall take precedence.
B. All NEC Class 1 (line voltage) wiring shall be UL listed in approved raceway according to
NEC and Division 26 requirements.
C. All low-voltage wiring shall meet NEC Class 2 requirements. Low-voltage power circuits shall
be subfused when required to meet Class 2 current limit.
D. Where NEC Class 2 (current-limited) wires are in concealed and accessible locations, including
ceiling return air plenums, approved cables not in raceway may be used provided that cables
are UL listed for the intended application.
E. All wiring in mechanical, electrical, or service rooms – or where subject to mechanical damage
– shall be installed in raceway at levels below 10ft.
F. Do not install Class 2 wiring in raceways containing Class 1 wiring. Boxes and panels
containing high-voltage wiring and equipment may not be used for low-voltage wiring except
for the purpose of interfacing the two (e.g. relays and transformers).
G. Do not install wiring in raceway containing tubing.
Dalton High School Renovations
ENERGY MANAGEMENT CONTROL SYSTEM 23 8310 - 14
H. Where Class 2 wiring is run exposed, wiring is to be run parallel along a surface or
perpendicular to it and neatly tied at 10 ft intervals.
I. Where plenum cables are used without raceway, they shall be supported from or anchored to
structural members. Cables shall not be supported by or anchored to ductwork, electrical
raceways, piping, or ceiling suspension systems.
J. All wire-to-device connections shall be made at a terminal block or terminal strip. All wire-to-
wire connections shall be at a terminal block.
K. All wiring within enclosures shall be neatly bundled and anchored to permit access and prevent
restriction to devices and terminals.
L. Maximum allowable voltage for control wiring shall be 120 V. If only higher voltages are
available, the contractor shall provide step-down transformers.
M. All wiring shall be installed as continuous lengths, with no splices permitted between
termination points.
N. Install plenum wiring in sleeves where it passes through walls and floors. Maintain fire rating
at all penetrations.
O. Size of raceway and size and type of wire type shall be the responsibility of the contractor in
keeping with the manufacturer’s recommendations and NEC requirements, except as noted
elsewhere.
P. Include one pull string in each raceway 1 in. or larger.
Q. Use color-coded conductors throughout with conductors of different colors.
R. Control and status relays are to be located in designated enclosures only. These enclosures
include packaged equipment control panel enclosures unless they also contain Class 1 starters.
S. Conceal all raceways except within mechanical, electrical, or service rooms. Install raceway to
maintain a minimum clearance of 6 in. from high-temperature equipment (e.g. steam pipes or
flues).
T. Secure raceways with raceway clamps fastened to the structure and spaced according to code
requirements. Raceways and pull boxes may not be hung on flexible duct strap or tie rods.
Raceways may not be run on or attached to ductwork.
U. Adhere to this specification's Division 26 requirements where raceway crosses building
expansion joints.
V. Install insulated bushings on all raceway ends and openings to enclosures. Seal top end of
vertical raceways.
W. The contractor shall terminate all control and/or interlock wiring and shall maintain updated
(as-built) wiring diagrams with terminations identified at the job site.
Dalton High School Renovations
ENERGY MANAGEMENT CONTROL SYSTEM 23 8310 - 15
X. Flexible metal raceways and liquid-tight flexible metal raceways shall not exceed 3 ft in length
and shall be supported at each end. Flexible metal raceway less than ½ in. electrical trade size
shall not be used. In areas exposed to moisture, liquid-tight, flexible metal raceways shall be
used.
Y. Raceway must be rigidly installed, adequately supported, properly reamed at both ends, and
left clean and free of obstructions. Raceway sections shall be joined with couplings (according
to code). Terminations must be made with fittings at boxes, and ends not terminating in boxes
shall have bushings installed.
3.07 COMMUNICATION WIRING:
A. The contractor shall adhere to the items listed in the "Wiring" article in Part 3 of the
specification.
B. All cabling shall be installed in a neat and workmanlike manner. Follow manufacturer's
installation recommendations for all communication cabling.
C. Do not install communication wiring in raceways and enclosures containing Class 1 or other
Class 2 wiring.
D. Maximum pulling, tension, and bend radius for the cable installation, as specified by the cable
manufacturer, shall not be exceeded during installation.
E. Contractor shall verify the integrity of the entire network following cable installation. Use
appropriate test measures for each particular cable.
F. When a cable enters or exits a building, a lightning arrestor must be installed between the lines
and ground. The lighting arrestor shall be installed according to manufacturer’s instructions.
G. All runs of communication wiring shall be unspliced length when that length is commercially
available.
H. All communication wiring shall be labeled to indicate origination and destination data.
I. All communication wiring shall be labeled to indicate origination and destination data.
J. Grounding of coaxial cable shall be in accordance with NEC regulations article on
"Communications Circuits, Cable, and Protector Grounding."
K. BACnet MS/TP communications wiring shall be installed in accordance with ASHRAE/ANSI
Standard 135. This includes but is not limited to:
1. The network shall use shielded, twisted-pair cable with characteristic impedance between
100 and 120 ohms. Distributed capacitance between conductors shall be less than 30 pF
per foot.
2. The maximum length of an MS/TP segment is 4000 ft with AWG 18 cable. The use of
greater distances and/or different wire gauges shall comply with the electrical
specifications of EIA-485.
3. The maximum number of nodes per segment shall be 32, as specified in the EIA 485
standard. Additional nodes may be accommodated by the use of repeaters.
4. An MS/TP EIA-485 network shall have no T connections.
Dalton High School Renovations
ENERGY MANAGEMENT CONTROL SYSTEM 23 8310 - 16
3.08 FIBER OPTIC CABLE:
A. Maximum pulling tensions as specified by the cable manufacturer shall not be exceeded during
installation. Post-installation residual cable tension shall be within cable manufacturer's
specifications.
B. All cabling and associated components shall be installed in accordance with manufacturers'
instructions. Minimum cable and unjacketed fiber bend radii, as specified by cable
manufacturer, shall be maintained.
3.09 INSTALLATION OF SENSORS:
A. Install sensors in accordance with the manufacturer's recommendations.
B. Mount sensors rigidly and adequately for environment within which the sensor operates.
C. Room temperature sensors shall be installed on concealed junction boxes properly supported
by wall framing. Where temperature sensors and RH sensors are shown side-by-side, a single
combination sensor shall be provided.
D. All wires attached to sensors shall be sealed in their raceways or in the wall to stop air
transmitted from other areas from affecting sensor readings.
E. Sensors used in mixing plenums and hot and cold decks shall be of the averaging type.
Averaging sensors shall be installed in a serpentine manner vertically across the duct. Each
bend shall be supported with a capillary clip.
F. Low-limit sensors used in mixing plenums shall be installed in a serpentine manner
horizontally across duct. Each bend shall be supported with a capillary clip. Provide 1 ft of
sensing element for each 1 ft2 of coil area.
G. Install outdoor air temperature sensors on north wall, complete with sun shield at designated
location.
3.010 ACTUATORS:
A. General: Mount and link control damper actuators according to manufacturer's instructions.
1. To compress seals when spring-return actuators are used on normally closed dampers,
power actuator to approximately 5° open position, manually close the damper, and then
tighten the linkage.
2. Check operation of damper/actuator combination to confirm that actuator modulates
damper smoothly throughout stroke to both open and closed positions.
3. Provide all mounting hardware and linkages for actuator installation.
B. Electric/Electronic:
1. Dampers: Actuators shall be direct mounted on damper shaft or jackshaft unless shown as
a linkage installation. For low-leakage dampers with seals, the actuator shall be mounted
with a minimum 5° travel available for tightening the damper seal. Actuators shall be
mounted following manufacturer’s recommendations.
Dalton High School Renovations
ENERGY MANAGEMENT CONTROL SYSTEM 23 8310 - 17
3.011 WARNING LABELS:
A. Permanent warning labels shall be affixed to all equipment that can be automatically started
by the control system.
1. Labels shall use white lettering (12-point type or larger) on a red background.
2. Warning labels shall read as follows.
C A U T I O N
This equipment is operating under automatic control and may start or stop at any
time without warning. Switch disconnect to"Off"position before servicing.
B. Permanent warning labels shall be affixed to all motor starters and control panels that are
connected to multiple power sources utilizing separate disconnects.
1. Labels shall use white lettering (12-point type or larger) on a red background.
2. Warning labels shall read as follows.
C A U T I O N
This equipment is fed from more than one power source with separate disconnects.
Disconnect all power sources before servicing.
3.012 IDENTIFICATION OF HARDWARE AND WIRING:
A. All wiring and cabling, including that within factory-fabricated panels shall be labeled at each
end within 2 in. of termination with control system address or termination number.
B. Permanently label or code each point of field terminal strips to show the instrument or item
served.
C. Identify control panels with minimum ½ in. letters on laminated plastic nameplates.
D. Identify all other control components with permanent labels. All plug-in components shall be
labeled such that label removal of the component does not remove the label.
E. Identify room sensors related to terminal boxes or valves with nameplates.
F. Manufacturers' nameplates and UL or CSA labels shall be visible and legible after equipment
is installed.
G. Identifiers shall match record documents.
3.013 CONTROLLERS:
A. Provide a separate controller for each HVAC system. A DDC controller may control more
than one system provided that all points associated with the system are assigned to the same
DDC controller. Points used for control loop reset, such as outside air or space temperature,
are exempt from this requirement.
B. Building Controllers and Custom Application Controllers shall be selected to provide the
required I/O point capacity required to monitor all of the hardware points listed in Sequences
of Operation.
3.014 PROGRAMMING:
Dalton High School Renovations
ENERGY MANAGEMENT CONTROL SYSTEM 23 8310 - 18
A. Provide sufficient internal memory for the specified sequences of operation and trend logging.
B. Point Naming: Name points as shown on the equipment points list provided with each
sequence of operation. See Sequences of Operation. If character limitations or space
restrictions make it advisable to shorten the name, abbreviations may be used. Where multiple
points with the same name reside in the same controller, each point name may be customized
with its associated Program Object number. For example, "Zone Temp 1" for Zone 1, "Zone
Temp 2" for Zone 2.
C. Software Programming: Provide programming for the system and adhere to the sequences of
operation provided. All other system programming necessary for the operation of the system,
but not specified in this document, also shall be provided by the contractor. Embed into the
control program sufficient comment statements to clearly describe each section of the program.
The comment statements shall reflect the language used in the sequences of operation. Use the
appropriate technique based on the following programming types:
a. Text-based:
a. Must provide actions for all possible situations
b. Must be modular and structured
c. Must be commented
b. Graphic-based:
a. Must provide actions for all possible situations
b. Must be documented
c. Parameter-based:
a. Must provide actions for all possible situations
b. Must be documented.
D. Operator Interface:
1. Standard Graphics. Provide graphics for all mechanical systems and floor plans of the
building. This includes each chilled water system, hot water system, chiller, boiler, air
handler, and all terminal equipment. Point information on the graphic displays shall
dynamically update. Show on each graphic all input and output points for the system. Also
show relevant calculated points such as setpoints. As a minimum, show on each equipment
graphic the input and output points and relevant calculated points as indicated on the
applicable Points List in Section 23 09 93.
2. The contractor shall provide all the labor necessary to install, initialize, start up, and
troubleshoot all operator interface software and its functions as described in this section.
This includes any operating system software, the operator interface database, and any third-
party software installation and integration required for successful operation of the operator
interface.
3.015 CONTROL SYSTEM CHECKOUT AND TESTING:
A. Startup Testing: All testing listed in this article shall be performed by the contractor and shall
make up part of the necessary verification of an operating control system. This testing shall be
completed before the owner’s representative is notified of the system demonstration.
1. The contractor shall furnish all labor and test apparatus required to calibrate and prepare
for service of all instruments, controls, and accessory equipment furnished under this
specification.
2. Verify that all control wiring is properly connected and free of all shorts and ground faults.
Verify that terminations are tight.
Dalton High School Renovations
ENERGY MANAGEMENT CONTROL SYSTEM 23 8310 - 19
3. Enable the control systems and verify calibration of all input devices individually. Perform
calibration procedures according to manufacturers’ recommendations.
4. Verify that all binary output devices (relays, solenoid valves, two-position actuators and
control valves, magnetic starters, etc.) operate properly and that the normal positions are
correct.
5. Verify that all analog output devices (I/Ps, actuators, etc.) are functional, that start and span
are correct, and that direction and normal positions are correct. The contractor shall check
all control valves and automatic dampers to ensure proper action and closure. The
contractor shall make any necessary adjustments to valve stem and damper blade travel.
6. Verify that the system operation adheres to the sequences of operation. Simulate and
observe all modes of operation by overriding and varying inputs and schedules. Tune all
DDC loops.
7. Alarms and Interlocks:
a. Check each alarm separately by including an appropriate signal at a value that will trip
the alarm.
b. Interlocks shall be tripped using field contacts to check the logic, as well as to ensure
that the fail-safe condition for all actuators is in the proper direction.
c. Interlock actions shall be tested by simulating alarm conditions to check the initiating
value of the variable and interlock action.
3.016 CONTROL SYSTEM DEMONSTRATION AND ACCEPTANCE:
A. Demonstration:
1. Prior to acceptance, the control system shall undergo a series of performance tests to verify
operation and compliance with this specification. These tests shall occur after the
Contractor has completed the installation, started up the system, and performed his/her own
tests.
2. The tests described in this section are to be performed in addition to the tests that the
contractor performs as a necessary part of the installation, start-up, and debugging process
and as specified in the "Control System Checkout and Testing" article in Part 3 of this
specification. The engineer will be present to observe and review these tests. The engineer
shall be notified at least 10 days in advance of the start of the testing procedures.
3. The demonstration process shall follow that approved in Part 1, "Submittals." The
approved checklists and forms shall be completed for all systems as part of the
demonstration.
4. The contractor shall provide at least two persons equipped with two-way communication
and shall demonstrate actual field operation of each control and sensing point for all modes
of operation including day, night, occupied, unoccupied, fire/smoke alarm, seasonal
changeover, and power failure modes. The purpose is to demonstrate the calibration,
response, and action of every point and system. Any test equipment required to prove the
proper operation shall be provided by and operated by the contractor.
5. As each control input and output is checked, a log shall be completed showing the date,
technician’s initials, and any corrective action taken or needed.
6. Demonstrate compliance with Part 1, "System Performance."
7. Demonstrate compliance with sequences of operation through all modes of operation.
8. Demonstrate complete operation of operator interface.
9. Additionally, the following items shall be demonstrated:
a. DDC loop response. The contractor shall supply trend data output in a graphical form
showing the step response of each DDC loop. The test shall show the loop’s response
to a change in set point, which represents a change of actuator position of at least 25%
of its full range. The sampling rate of the trend shall be from 10 seconds to 3 minutes,
Dalton High School Renovations
ENERGY MANAGEMENT CONTROL SYSTEM 23 8310 - 20
depending on the speed of the loop. The trend data shall show for each sample the set
point, actuator position, and controlled variable values. Any loop that yields
unreasonably under-damped or over-damped control shall require further tuning by the
Contractor.
b. Demand limiting. The contractor shall supply a trend data output showing the action
of the demand limiting algorithm. The data shall document the action on a minute-by-
minute basis over at least a 30-minute period. Included in the trend shall be building
kW, demand limiting set point, and the status of sheddable equipment outputs.
c. Optimum start/stop. The contractor shall supply a trend data output showing the
capability of the algorithm. The change-of-value or change-of-state trends shall include
the output status of all optimally started and stopped equipment, as well as temperature
sensor inputs of affected areas.
d. Interface to the building fire alarm system.
e. Operational logs for each system that indicate all set points, operating points, valve
positions, mode, and equipment status shall be submitted to the architect/engineer.
These logs shall cover three 48-hour periods and have a sample frequency of not more
than 10 minutes. The logs shall be provided in both printed and disk formats.
10. Any tests that fail to demonstrate the operation of the system shall be repeated at a
later date. The contractor shall be responsible for any necessary repairs or revisions to
the hardware or software to successfully complete all tests.
B. Acceptance:
1. All tests described in this specification shall have been performed to the satisfaction of
both the engineer and owner prior to the acceptance of the control system as meeting the
requirements of completion. Any tests that cannot be performed due to circumstances
beyond the control of the contractor may be exempt from the completion requirements if
stated as such in writing by the engineer. Such tests shall then be performed as part of the
warranty.
2. The system shall not be accepted until all forms and checklists completed as part of the
demonstration are submitted and approved as required in Part 1, "Submittals."
3.017 CLEANING:
A. The contractor shall clean up all debris resulting from his/her activities daily. The contractor
shall remove all cartons, containers, crates, etc., under his/her control as soon as their contents
have been removed. Waste shall be collected and placed in a designated location.
B. At the completion of work in any area, the contractor shall clean all work, equipment, etc.,
keeping it free from dust, dirt, and debris, etc.
C. At the completion of work, all equipment furnished under this section shall be checked for
paint damage, and any factory-finished paint that has been damaged shall be repaired to match
the adjacent areas. Any cabinet or enclosure that has been deformed shall be replaced with new
material and repainted to match the adjacent areas.
3.018 TRAINING:
A. Provide training for a designated staff of Owner’s representatives. Training shall be provided
via self-paced training, web-based or computer-based training, classroom training, or a
combination of training methods.
Dalton High School Renovations
ENERGY MANAGEMENT CONTROL SYSTEM 23 8310 - 21
B. Classroom training shall be done using a network of working controllers representative of
installed hardware.
3.019 DUCT SMOKE DETECTION:
A. Submit data for coordination of duct smoke detector interface to HVAC systems as required
in Part 1, "Submittals."
B. This Contractor shall provide a dry-contact alarm output in the same room as the HVAC
equipment to be controlled.
3.020 CONTROLS COMMUNICATION PROTOCOL:
A. General: The electronic controls packaged with this equipment shall communicate with the
building direct digital control (DDC) system. The DDC system shall communicate with these
controls to read the information and change the control setpoints as shown in the points list,
sequences of operation, and control schematics. The information to be communicated between
the DDC system and these controls shall be in the standard object format as defined in
ANSI/ASHRAE Standard 135 (BACnet). Controllers shall communicate with other BACnet
objects on the internetwork using the Read (Execute) Property service as defined in Clause
15.5 of Standard 135.
B. Distributed Processing: The controller shall be capable of stand-alone operation and shall
continue to provide control functions if the network connection is lost.
C. I/O Capacity: The controller shall contain sufficient I/ O capacity to control the target system.
D. The Controller shall have a physical connection for a laptop computer or a portable operator’s
tool.
E. Environment: The hardware shall be suitable for the anticipated ambient conditions.
1. Controllers used outdoors and/or in wet ambient conditions shall be mounted within
waterproof enclosures and shall be rated for operation at 40°F to 140°F.
2. Controllers used in conditioned space shall be mounted in dust-proof enclosures and shall
be rated for operation at 32°F to 120°F.
F. Serviceability: Provide diagnostic LEDs for power, communication, and processor. All wiring
connections shall be made to field removable, modular terminal strips or to a termination card
connected by a ribbon cable.
G. Memory: The Controller shall maintain all BIOS and programming information in the event
of a power loss for at least 30 days.
H. Power: Controller shall be able to operate at 90% to 110% of nominal voltage rating.
I. Transformer: Power supply for the Controller must be rated at minimum of 125% of ASC
power consumption and shall be fused or current limiting type.
3.021 START-UP AND CHECKOUT PROCEDURES:
Dalton High School Renovations
ENERGY MANAGEMENT CONTROL SYSTEM 23 8310 - 22
A. Start up, check out, and test all hardware and software and verify communication between all
components.
1. Verify that all control wiring is properly connected and free of all shorts and ground faults.
Verify that terminations are tight.
2. Verify that all analog and binary input/output points read properly.
3. Verify alarms and interlocks.
4. Verify operation of the integrated system.
B. Provide a Master HVAC System Shutdown Switch in the Administration area where shown
on the plans. The manual switch shall shut down all HVAC equipment in the building.
Dalton High School Renovations
ENERGY MANAGEMENT CONTROL SYSTEM 23 8310 - 23
PART 4 - SEQUENCES OF OPERATION
4.01 VRF HEAT PUMP SYSTEM (TYPICAL):
A. During the Occupied Mode the VRF system will be enabled in the Auto Mode. The fan will
run continuously and the compressors will operate in a cooling or heating mode in response
to the local room temperature interface.
B. Upon entering the Occupied Mode the initial fan speed setting will be high (configurable)
and will revert to local control should the fan speed be overridden by the local interface.
C. Upon entering the Occupied Mode the setpoint will be overwritten with the occupied set-
point (configurable) and will revert to local control should the setpoint be adjusted from the
local interface. Heating and Cooling Temperature Limits (configurable) will be available to
prevent the local occupant from adjusting the heating and cooling setpoint too drastically. D. Upon entering the Unoccupied Mode the fan will be commanded to low speed (configura-
ble). E. During the Unoccupied Mode the unit will remain off unless the space temperature exceeds
the unoccupied heating and cooling setpoints. If the unit turns on to maintain Unoccupied
setpoints it will remain on until it satisfies the Unoccupied setpoints by 2° (adjustable) be-
fore being turned off. F. Unit status, alarm information and error codes will be available through the EMCS.
BACnet points to be integrated from VRF system
Object Description Object Type Effective Cool-ing Setpoint
BAV
Effective Heat-ing Setpoint
BAV
Cooling Set-point Limited (High)
BBV
Cooling Set-point Limited (Low)
BBV
Heating Set-point Limited (High)
BBV
Heating Set-point Limited (Low)
BBV
schedule BBV
Setpoint Write Enable
BBV
Airflow Direc-tion Setup
BMSV
Error Codes BMSV
Fan Speed BMSV
occ_fan_speed BMSV
Occupancy Source
BMSV
Occupied Unit Operation Mode
BMSV
Operation Mode
BMSV
un-occ_fan_speed
BMSV
Dalton High School Renovations
ENERGY MANAGEMENT CONTROL SYSTEM 23 8310 - 24
Unoccupied Mode (Local Only)
BMSV
Unoccupied Unit Operation Mode
BMSV
Update Status BMSV
Vane Direction BMSV
High Space Temp
BALM
Low Space Temp
BALM
Mnet Alarm - Air System
BALM
Mnet Alarm - Communica-tion
BALM
Mnet Alarm - Condensate
BALM
Mnet Alarm - Electronic
BALM
Mnet Alarm - Other
BALM
Mnet Alarm - Refrigeration
BALM
Mnet Alarm - Sensor
BALM
Mnet Alarm - System
BALM
Airflow Direc-tion Setup
ANO
Alarm Signal BNI
Current Set-point ANI
ANI
Emergency Shutdown Net Input
BNI2
Error Code ANI
Fan Speed Setup
ANO
Fan Speed Status
ANI
Filter Reset BNO
Filter Signal BNI
Local Opera-tion
BNO
Network Inter-lock (Occu-pancy)
BNI2
OAT ANI
On/Off Setup BNO
On/Off State BNI
Operation Mode
ANI
Operation Mode
ANO
Room Temp ANI
Set Temp ANO2
Unit Shutdown BNO2
Dalton High School Renovations
ENERGY MANAGEMENT CONTROL SYSTEM 23 8310 - 25
Vane Direction Status
ANI
Dalton High School Renovations
ENERGY MANAGEMENT CONTROL SYSTEM 23 8310 - 26
4.02 ENERGY RECOVERY VENTILATOR - SUPPLY AIR TEMP (TYPICAL):
A. Occupied Mode: The supply fan and exhaust fan shall run continuously during Occupied
Mode.
B. Unoccupied Mode (night setback): The unit shall be “off.”
C. The unit shall shut down and generate an alarm upon receiving an emergency shutdown signal.
D. The unit shall shut down and generate an alarm upon receiving a smoke detector status.
E. The outside air damper shall open anytime the unit runs and shall close anytime the unit stops.
The supply fan and exhaust fan shall start only after the damper status has proven the damper
is open. The outside air damper shall close 4sec (adj.) after the supply fan stops.
F. Outside Air Damper Failure Alarm: Commanded open, but the status is closed.
G. Outside Air Damper in Hand Alarm: Commanded closed, but the status is open.
H. Cooling Energy Recovery Mode: The controller shall measure the total energy wheel
discharge air temperature and run the wheel to maintain a setpoint 2°F (adj.) less than the unit
supply air temperature setpoint. The wheel shall run for cool recovery whenever the unit return
air temperature is 5°F (adj.) or more below the outside air temperature and the unit is in a
cooling mode and the supply fan is on.
I. Heating Energy Recovery Mode: The controller shall measure the total energy
wheel discharge air temperature and run the wheel to maintain a setpoint 2°F (adj.) greater than
the unit supply air temperature setpoint. The wheel shall run for heat recovery whenever unit
return air temperature is 5°F (adj.) or more above the outside air temperature and the unit is in
a heating mode and the supply fan is on.
J. Periodic Self-Cleaning: The total energy wheel shall run for 10sec (adj.) every 4hrs (adj.) the
unit runs.
K. Alarms shall be provided for:
1. Total Energy Wheel Rotation Failure: Commanded on, but the status is off.
2. Total Energy Wheel in Hand: Commanded off, but the status is on.
3. Total Energy Wheel Runtime Exceeded: Status runtime exceeds a user definable limit
(adj.).
L. Alarms shall be provided as follows:
1. Supply / Exhaust Fan Failure: Commanded on, but the status is off.
2. Supply / Exhaust Fan in Hand: Commanded off, but the status is on.
3. Supply / Exhaust Fan Runtime Exceeded: Status runtime exceeds a user definable limit
(adj.).
M. Supply Air Temperature Setpoint - Outside Air Reset: The controller shall monitor the supply
air temperature and shall maintain supply air temperature setpoint. The supply air temperature
setpoint shall reset for cooling as follows: As outside air temperature drops from 95°F (adj.)
to 20°F (adj.), the supply air temperature setpoint shall reset upwards from 55°F (adj.) to
95°F (adj.).
N. Cooling Coil: The controller shall measure the supply air temperature and stage the DX
cooling to maintain its cooling setpoint. The cooling shall be enabled whenever outside air
temperature is greater than 50°F (adj.) and the supply air temperature is above cooling setpoint
and the fan status is on.
Dalton High School Renovations
ENERGY MANAGEMENT CONTROL SYSTEM 23 8310 - 27
O. Gas Heating Stages: The controller shall measure the supply air temperature and stage the
heating to maintain its heating setpoint. To prevent short cycling, there shall be a user
definable (adj.) delay between stages, and each stage shall have a user definable
(adj.) minimum runtime. The heating shall be enabled whenever outside air temperature is
less than 55°F (adj.) and the supply air temperature is below heating setpoint and the fan status
is on.
P. Filter Status: The controller shall monitor the status for outside air filter, supply air filter and
exhaust air filter. Filter alarms shall be provided when differential pressure exceeds a user
definable limit (adj.).
Q. Supply Air Temperature: The controller shall monitor the supply air temperature. Alarms
shall be provided for High Supply Air Temp (If the supply air temperature is greater than
120°F (adj.)) and Low Supply Air Temp (If the supply air temperature is less than 40°F (adj.))
Hardware
Points Software Points
Point Name AI A
O BI
B
O
A
V BV Loop Sched Trend
Alar
m
Show On
Graphic
Outside Air Temp x x x
Exhaust Air Temp x x x
Heat Wheel Discharge Air Temp x x x
Return Air Temp x x x
Supply Air Temp x x x
Cooling Valve x x x
Smoke Detector x x x x
Outside Air Damper Status x x x
Heat Wheel Status x x x
Supply Fan Status x x x
Exhaust Fan Status x x x
Prefilter Status x x
Final Filter Status x x
Outside Air Damper x x x
Heat Wheel Start/Stop x x x
Heat Wheel Bypass Dampers x x x
Supply Fan Start/Stop x x x
Exhaust Fan Start/Stop x x x
Heating Stage 1 x x x
Heating Stage 2 x x x
Heating Stage 3 x x x
Dalton High School Renovations
ENERGY MANAGEMENT CONTROL SYSTEM 23 8310 - 28
Hardware
Points Software Points
Point Name AI A
O BI
B
O
A
V BV Loop Sched Trend
Alar
m
Show On
Graphic
Heating Stage 4 x x x
Supply Air Temp Setpoint x x x
Outside Air Temp x x
Emergency Shutdown x x x x
Schedule x
Outside Air Damper Failure x
Outside Air Damper in Hand x
Heat Wheel Rotation Failure x
Heat Wheel in Hand x
Heat Wheel Runtime Exceeded x
Supply Fan Failure x
Supply Fan in Hand x
Supply Fan Runtime Exceeded x
Exhaust Fan Failure x
Exhaust Fan in Hand x
Exhaust Fan Runtime Exceeded x
Prefilter Change Required x x
Final Filter Change Required x x
High Supply Air Temp x
Low Supply Air Temp x
Totals 5 1 7 9 2 1 0 1 23 18 25
Total Hardware (22) Total Software (45)
Dalton High School Renovations
ENERGY MANAGEMENT CONTROL SYSTEM 23 8310 - 29
4.03 ROOFTOP AIR CONDITIONER (TYPICAL):
A. Occupied Mode: The supply fan shall run continuously during Occupied Mode and
maintain 74°F (adj.) space cooling setpoint and 70°F (adj.) space heating setpoint.
B. Unoccupied Mode (night setback): The supply fan shall run intermittently and maintain 85°F
(adj.) space cooling setpoint and 55°F (adj.) space heating setpoint.
C. High Zone Temp Alarm: If the zone temperature is greater than the cooling setpoint by a user
definable amount (adj.).
D. Low Zone Temp Alarm: If the zone temperature is less than the heating setpoint by a user
definable amount (adj.).
E. Zone Setpoint Adjust: The occupant shall be able to adjust the zone temperature heating and
cooling setpoints at the zone sensor.
F. Zone Optimal Start: The unit shall use an optimal start algorithm for morning start-up. This
algorithm shall minimize the unoccupied warm-up or cool-down period while still achieving
comfort conditions by the start of scheduled occupied period.
G. Zone Unoccupied Override: A timed local override control shall allow an occupant to override
the schedule and place the unit into an occupied mode for an adjustable period of time. At the
expiration of this time, control of the unit shall automatically return to the schedule.
H. Emergency Shutdown: The unit shall shut down and generate an alarm upon receiving an
emergency shutdown signal.
I. Supply Air Smoke Detection: The unit shall shut down and generate an alarm upon receiving
a supply air smoke detector status.
J. Alarms shall be provided as follows:
1. Supply Fan Failure: Commanded on, but the status is off.
2. Supply Fan in Hand: Commanded off, but the status is on.
3. Supply Fan Runtime Exceeded: Status runtime exceeds a user definable limit (adj.).
K. Cooling Stages: The controller shall measure the zone temperature and stage the cooling to
maintain its cooling setpoint. To prevent short cycling, there shall be a user definable (adj.)
delay between stages, and each stage shall have a user definable (adj.) minimum runtime.
Cooling shall be enabled whenever outside air temperature is greater than 45°F (adj.) and the
economizer (if present) is disabled or fully open and the zone temperature is above cooling
setpoint and the supply fan status is on and the heating is not active.
L. Gas Heating Stages: The controller shall measure the zone temperature and stage the heating
to maintain its heating setpoint. To prevent short cycling, there shall be a user definable (adj.)
delay between stages, and each stage shall have a user definable (adj.) minimum runtime.
Heating shall be enabled whenever outside air temperature is less than 65°F (adj.) and the zone
temperature is below heating setpoint and the supply fan status is on and the cooling is not
active.
M. Economizer: The controller shall measure the zone temperature and modulate the economizer
dampers in sequence to maintain a setpoint 2°F less than the zone cooling setpoint. The outside
air dampers shall maintain a minimum adjustable position of 10% (adj.) open whenever
occupied. The economizer shall be enabled whenever outside air temperature is less than
55°F (adj.) and the outside air temperature is less than the return air temperature and the supply
Dalton High School Renovations
ENERGY MANAGEMENT CONTROL SYSTEM 23 8310 - 30
fan status is on. The economizer shall close whenever mixed air temperature drops from
45°F to 40°F (adj.) or on loss of supply fan status.
N. The outside and exhaust air dampers shall close and the return air damper shall open when the
unit is off. If Optimal Start Up is available, the mixed air damper shall operate as described in
the occupied mode except that the outside air damper shall modulate to fully closed.
O. Minimum Outside Air Ventilation - Fixed Percentage: The outside air dampers shall maintain
a minimum position (adj.) during building occupied hours and be closed during unoccupied
hours.
P. Dehumidification: The controller shall measure the return air humidity and override the
cooling sequence to maintain return air humidity at or below 60% rh (adj.). Dehumidification
shall be enabled whenever the supply fan status is on.
Q. Mixed Air Temperature: The controller shall monitor the mixed air temperature and use as
required for economizer control (if present) or preheating control (if present). Alarms shall be
provided for High Mixed Air Temp (If the mixed air temperature is greater than 110°F (adj.))
and Low Mixed Air Temp (If the mixed air temperature is less than 40°F (adj.)).
R. Return Air Humidity: The controller shall monitor the return air humidity and use as
required for economizer control (if present) or humidity control (if present). Alarms shall be
provided for High Return Air Humidity (If the return air humidity is greater than 70% (adj.))
and Low Return Air Humidity (If the return air humidity is less than 20% (adj.)).
S. Return Air Temperature: The controller shall monitor the return air temperature and use as
required for economizer control (if present). Alarms shall be provided for High Return Air
Temp (If the return air temperature is greater than 90°F (adj.)) and Low Return Air Temp (If
the return air temperature is less than 50°F (adj.)).
T. Supply Air Temperature: The controller shall monitor the supply air temperature. Alarms
shall be provided for High Supply Air Temp (If the supply air temperature is greater than 125°F
(adj.)) and Low Supply Air Temp (If the supply air temperature is less than 35°F (adj.)).
Hardware
Points Software Points
Point Name AI A
O BI
B
O
A
V BV Loop Sched Trend
Alar
m
Show On
Graphic
Zone Temp x x x
Zone Setpoint Adjust x x
Mixed Air Temp x x x
Return Air Humidity x x x
Return Air Temp x x x
Supply Air Temp x x x
Mixed Air Dampers x x x
Zone Override x x x
Supply Air Smoke Detector x x x x
Supply Fan Status x x x
Dalton High School Renovations
ENERGY MANAGEMENT CONTROL SYSTEM 23 8310 - 31
Hardware
Points Software Points
Point Name AI A
O BI
B
O
A
V BV Loop Sched Trend
Alar
m
Show On
Graphic
Supply Fan Start/Stop x x x
Cooling Stage 1 x x x
Cooling Stage 2 x x x
Heating Stage 1 x x x
Heating Stage 2 x x x
Economizer Zone Temp Setpoint x x x
Dehumidification Setpoint x x x
Environmental Index x x
Percent of Time Satisfied x x
Emergency Shutdown x x x
Schedule x
Heating Setpoint x x
Cooling Setpoint x x
High Zone Temp x
Low Zone Temp x
Supply Fan Failure x
Supply Fan in Hand x
Supply Fan Runtime Exceeded x
Compressor Runtime Exceeded x
Final Filter Change Required x x
High Mixed Air Temp x
Low Mixed Air Temp x
High Return Air Humidity x
Low Return Air Humidity x
High Return Air Temp x
Low Return Air Temp x
High Supply Air Temp x
Low Supply Air Temp x
Totals 6 1 3 5 4 1 0 1 20 17 21
Total Hardware (15) Total Software (43)
4.04 UNIT HEATER (TYPICAL):
Dalton High School Renovations
ENERGY MANAGEMENT CONTROL SYSTEM 23 8310 - 32
A. Occupied Mode: The unit shall maintain a heating setpoint of 55°F (adj.).
B. Unoccupied Mode (night setback): Same as Occupied Mode.
C. Low Zone Temp Alarm: If the zone temperature is less than the heating setpoint by a user
definable amount (adj.).
D. The fan shall run anytime the zone temperature drops below heating setpoint, unless shutdown
on safeties.
E. The controller shall measure the zone temperature and stage the heating to maintain its heating
setpoint. To prevent short cycling, the stage shall have a user definable
(adj.) minimum runtime.
F. The heating shall be enabled whenever outside air temperature is less than 55°F (adj.) and the
zone temperature is below heating setpoint and the fan is on.
Hardware
Points Software Points
Point Name AI A
O BI
B
O
A
V BV Loop Sched Trend
Alar
m
Show On
Graphic
Zone Temp x x x
Fan Start/Stop x x x
Heating Stage 1 x x x
Environmental Index x x
Percent of Time Satisfied x x
Schedule x
Heating Setpoint x x
Low Zone Temp x
Totals 1 0 0 2 2 0 0 1 6 1 4
Total Hardware (3) Total Software (10)
Dalton High School Renovations
ENERGY MANAGEMENT CONTROL SYSTEM 23 8310 - 33
4.05 CABINET HEATER (TYPICAL):
A. Occupied Mode: The unit shall maintain a heating setpoint of 65°F (adj.).
B. Unoccupied Mode (night setback): Same as Occupied Mode.
C. Low Zone Temp Alarm: If the zone temperature is less than the heating setpoint by a user
definable amount (adj.).
D. The fan shall run anytime the zone temperature is below heating setpoint, unless shutdown on
safeties.
E. The controller shall measure the zone temperature and stage the heating to maintain its heating
setpoint. To prevent short cycling, the stage shall have a user definable (adj.)
minimum runtime.
F. The heating shall be enabled whenever outside air temperature is less than 65°F (adj.) and the
zone temperature is below heating setpoint and the fan is on.
Hardware
Points Software Points
Point Name AI A
O BI
B
O
A
V BV Loop Sched Trend
Alar
m
Show On
Graphic
Zone Temp x x x
Fan Start/Stop x x x
Heating Stage 1 x x x
Environmental Index x x
Percent of Time Satisfied x x
Schedule x
Heating Setpoint x x
Low Zone Temp x
Totals 1 0 0 2 2 0 0 1 6 1 4
Total Hardware (3) Total Software (10)
Dalton High School Renovations
ENERGY MANAGEMENT CONTROL SYSTEM 23 8310 - 34
4.06 ELECTRIC METER:
A. Electric Meter: The controller shall monitor the electric meter for electric consumption on a
continual basis. These values shall be made available to the system at all times.
B. Alarm shall be generated when sensor reading indicates an invalid value from the electric
meter.
C. Peak Demand History: The controller shall monitor and record the peak (high and low) demand
readings from the electric meter. Peak readings shall be recorded on a daily, month-to-date,
and year-to-date basis.
D. Usage History: The controller shall monitor and record electric meter readings so as to provide
a power consumption history. Usage readings shall be recorded on a daily, month-to-date, and
year-to-date basis.
Hardware
Points Software Points
Point Name AI A
O BI
B
O
A
V BV Loop Sched Trend
Alar
m
Show On
Graphic
kW Meter x x
KW Demand x x
kW Peak Today x x
kW Peak Month-to-Date x x
kW Peak Year-to-Date x x
kWh Today x x
MWh Month-to-Date x x
MWh Year-to-Date x x
Meter Alarm x
Totals 1 0 0 0 0 0 0 0 7 1 8
Total Hardware (1) Total Software (8)
Dalton High School Renovations
ENERGY MANAGEMENT CONTROL SYSTEM 23 8310 - 35
4.07 GAS METER:
A. Gas Meter: The controller shall monitor the gas meter for gas consumption on a continual
basis. These values shall be made available to the system at all times.
B. Alarm shall be generated when sensor reading indicates an invalid value from the gas meter.
C. Peak Demand History: The controller shall monitor and record the peak (high and low) demand
readings from the gas meter. Peak readings shall be recorded on a daily, month-to-date, and
year-to-date basis.
D. Usage History: The controller shall monitor and record gas meter readings so as to provide a
gas consumption history. Usage readings shall be recorded on a daily, month-to-date, and year-
to-date basis.
Hardware
Points Software Points
Point Name AI A
O BI
B
O
A
V BV Loop Sched Trend
Alar
m
Show On
Graphic
Gas Flow Rate x
Demand x x
Peak Today x x
Peak Month-to-Date x x
Peak Year-to-Date x x
Usage Today x x
Usage Month-to-Date x x
Usage Year-to-Date x x
Invalid Value x
Totals 1 0 0 0 0 0 0 0 7 1 7
Total Hardware (1) Total Software (8)
Dalton High School Renovations
ENERGY MANAGEMENT CONTROL SYSTEM 23 8310 - 36
4.08 OUTSIDE AIR SENSOR:
A. Outside Air Conditions: The controller shall monitor the outside air temperature and humidity
and calculate the outside air enthalpy on a continual basis. These values shall be made available
to the system at all times.
B. Alarm shall be generated when sensor reading indicates shorted or disconnected sensor. In the
event of a sensor failure, an alternate outside air conditions sensor shall be made available to
the system without interruption in sensor readings.
C. If an OA Temp Sensor cannot be read, a default value of 65°F will be used.
D. If an OA Humidity Sensor cannot be read, a default value of 50 % will be used.
E. Outside Air Temperature History: The controller shall monitor and record the high and low
temperature readings for the outside air. These readings shall be recorded on a daily, month-
to-date, and year-to-date basis.
F. Cooling Degree Day: The controller shall provide a Degree Day history index that reflects the
energy consumption for the facilities cooling demand. Computations shall use a mean daily
temperature of 65°F (adj.). The Degree Day peak value readings shall be recorded on a daily,
month-to-date, and year-to-date basis.
G. Heating Degree Day: The controller shall provide a Degree Day history index that reflects the
energy consumption for the facilities heating demand. Computations shall use a mean daily
temperature of 65°F (adj.). The Degree Day peak value readings shall be recorded on a daily,
month-to-date, and year-to-date basis.
Hardware
Points Software Points
Point Name AI A
O BI
B
O
A
V BV Loop Sched Trend
Alar
m
Show On
Graphic
Outside Air Temp x x x
Outside Air Humidity x x x
Outside Air Temp (Alternate) x x
Outside Air Humidity (Alternate) x x
Outside Air Enthalpy x x x
High Temp Today x x
High Temp Month-to-Date x x
High Temp Year-to-Date x x
Low Temp Today x x
Low Temp Month-to-Date x x
Low Temp Year-to-Date x x
Sensor Failure x
Totals 2 0 0 0 3 0 0 0 11 1 9
Total Hardware (2) Total Software (15)
Dalton High School Renovations
ENERGY MANAGEMENT CONTROL SYSTEM 23 8310 - 37
4.09 EXHAUST FAN - ON/OFF (See Fan Schedule on plans):
A. Occupied Mode: The exhaust fan shall run continuously during Occupied Mode.
B. Unoccupied Mode: The exhaust fan shall be “off.”
C. The controller shall monitor the fan status.
D. Alarms shall be provided as follows:
1. Fan Failure: Commanded on, but the status is off.
2. Fan in Hand: Commanded off, but the status is on.
3. Fan Runtime Exceeded: Fan status runtime exceeds a user definable limit (adj.).
Hardware
Points Software Points
Point Name AI A
O BI
B
O
A
V BV Loop Sched Trend
Alar
m
Show On
Graphic
Fan Status x x x
Fan Start/Stop x x x
Fan Failure x
Fan in Hand x
Fan Runtime Exceeded x
Totals 0 0 1 1 0 0 0 0 2 3 2
Total Hardware (2) Total Software (5)
Dalton High School Renovations
ENERGY MANAGEMENT CONTROL SYSTEM 23 8310 - 38
4.10 EXHAUST FAN – TEMPERATURE CONTROL (See Fan Schedule on plans):
A. Occupied Mode: The unit shall maintain a zone temperature setpoint of 85°F (adj.).
B. Unoccupied Mode (night setback): Same as Occupied Mode.
C. The fan shall run anytime the zone temperature rises above setpoint, unless shutdown on
safeties. The fan speeds shall be indexed as follows:
D. Low speed shall run anytime the zone temperature rises above setpoint.
E. High speed shall run anytime the zone temperature rises further above setpoint by a user
definable amount (adj.).
F. The controller shall monitor the fan status.
G. Alarms shall be provided as follows:
1. High Zone temperature.
2. Fan Failure: Commanded on, but the status is off.
3. Fan in Hand: Commanded off, but the status is on.
4. Fan Runtime Exceeded: Fan status runtime exceeds a user definable limit (adj.).
Hardware
Points Software Points
Point Name AI A
O BI
B
O
A
V BV Loop Sched Trend
Alar
m
Show On
Graphic
Zone Temp x x x
Fan Status x x x
Fan Low Speed x x x
Fan High Speed x x x
Setpoint x x x
Environmental Index x x
Percent of Time Satisfied x x
Schedule x
High Zone Temp x
Fan Failure x
Fan in Hand x
Fan Runtime Exceeded x
Totals 1 0 1 2 3 0 0 1 7 4 5
Total Hardware (4) Total Software (15)
101-14 Blessed Sacrament School- Phase I
215-14 23 9110 - 1 MECHANICAL SOUND, VIBRATION, WIND AND SEISMIC CONTROL
SECTION 23 9110
MECHANICAL SOUND, VIBRATION, WIND AND SEISMIC CONTROL
PART 1 - GENERAL
1.1 SCOPE OF WORK:
A. Furnish all labor, materials, tools and equipment and perform all work necessary to complete
the installation of the systems required by these specifications and as detailed on the
drawings.
B. All foundations and supports required for the installation of Division 23 equipment shall be
furnished by the Division 23 contractor shall unless specifically specified otherwise.
C. The following criteria applies to all mechanical systems and components:
1. Wind Pressure Velocity: 110 MPH
2. Seismic Design Category: C
3. Importance Factor: 1.0
D. Based on the criteria listed above, no seismic restraints are required.
1.2 RELATED DOCUMENTS:
A. The drawings and general provisions of this division of the Contract, including the General
and Special Conditions and Division 1 Specifications, apply to this Section.
1.3 QUALITY ASSURANCE:
A. Codes and Standards: The installation of the mechanical systems shall be installed in
accordance with the following codes and standards:
1. 2012 International Building Code (IBC)
2. ASHRAE
B. The mechanical sound, vibration and wind control equipment and products shall be sized and
provided by one of the manufacturers listed below.
C. Kinetics Noise Control is the Basis of Design manufacturer. Equivalent equipment by
AeroSonics, Mason, MGM Products, Vibration Eliminator, Vibro-Acoustics and Vibration
Mountings and Controls that meets performance, capacity, space and other requirements of
the design documents shall be acceptable.
D. The manufacturer and/or his representative shall select all vibration isolation products in-
accordance with the Vibration Isolation Schedule listed in these specifications. All products
shall provide the specified deflection as indicated based on the actual equipment weights and
installation requirements of the approved equipment. The manufacturer shall provide
installation instructions for all provided isolators, wind restraints and bracing. Locations of
vibration isolation products shall be coordinated with equipment details shown on the
drawings and also as specified in these specifications for maximum support locations for
piping and other equipment.
101-14 Blessed Sacrament School- Phase I
215-14 23 9110 - 2 MECHANICAL SOUND, VIBRATION, WIND AND SEISMIC CONTROL
E. Submittals:
1. The contractor shall submit for approval by the engineer all products intended to be used
to meet the requirements of these specifications. Submittal data shall include a proposed
schedule for vibration isolation products, manufacturer’s data and cut sheets of the
specific vibration isolation or sound barrier materials. Proposed vibration isolation
schedule shall list all equipment specified to be isolated, the equipment weight, proposed
isolator type or base type, number of isolators required, spring or isolator color, and
deflection of the spring or vibration isolator based on the equipment weight.
2. The contractor shall submit for approval by the engineer, wind anchorage requirements
for all equipment and curbs. Anchorage calculations shall be prepared by a registered
engineer in the state where the project will be constructed. The engineer shall stamp
calculations. Wind anchorage requirements shall be submitted for all curb mounted
equipment and roof mounted equipment. Fasteners shall be selected and detailed for curb
connections to the building structure and also for equipment connections to the curb.
Calculations shall be based on the approved equipment for the project.
PART 2 - PRODUCTS
2.1 GENERAL:
A. All equipment shall be mounted or suspended from approved foundations and supports as
specified herein or as detailed on the drawings.
B. The vibration isolation products and systems shall have a deflection as recommended by the
manufacturer but not less than the deflection indicated in the Vibration Isolation Schedule.
2.2 ISOLATOR TYPES:
A. Type 2 - Floor Mounted Equipment: Vibration isolators shall be neoprene, molded from oil-
resistant compounds. Isolators shall consist of two layers of neoprene material. Top and
bottom surfaces of each layer shall have molded ribs. Each layer shall be separated by a 16
gauge galvanized steel load plate bonded to each neoprene layer to form a sandwich
arrangement. Vibration isolator size shall be coordinated with the equipment supports.
Minimum size shall be 2”x2”.
B. Type 4 - Floor-Mounted Equipment: Vibration isolators shall be free standing, un-housed,
laterally stable springs wound from high strength spring steel. Springs shall have a lateral
stiffness greater than 0.8 times the rated vertical stiffness and shall be designed to provide up
to 50% overload capacity. Springs shall be selected to provide operating static deflections
shown on the Vibration Isolation Schedule or as indicated on the project documents. Springs
shall be color coded or otherwise identified to indicate load capacity. In capacities up to 5,000
lbs., springs shall be replaceable. In capacities over 5,000 lbs., springs shall be welded to the
top and bottom load plate assemblies. Springs shall be assembled between a top and bottom
steel load plate. The upper load plate shall be provided with steel leveling bolt lock nut and
washer for attachment to the supported equipment. The lower load plate shall have a non-skid
noise isolation pad bonded to the bottom and have provisions for bolting the isolator to the
supporting structure.
101-14 Blessed Sacrament School- Phase I
215-14 23 9110 - 3 MECHANICAL SOUND, VIBRATION, WIND AND SEISMIC CONTROL
C. Type 10 - Suspended Equipment, Piping and Ductwork: Vibration Isolators shall consist of a
steel spring and neoprene element in series mounted in a stamped or welded steel bracket for
insertion into the hanger rod assembly. The elastomer insert shall be neoprene, molded from
oil resistant compounds and shall be color coded to indicate load capacity and selected to
operate within its published load range. The steel spring shall consist of large diameter
laterally stable steel springs assembled into formed or welded steel housing assemblies
designed to limit movement. Springs shall have a lateral stiffness greater than 0.8 times the
rated vertical stiffness and shall be designed to provide up to 50% overload capacity. The
steel bracket shall be fabricated from steel and provided with a corrosion resistance finished.
The hanger bracket shall be designed to carry a 500% overload without failure and to allow a
support rod misalignment through a 30-degree arc without metal-to-metal contact or other
short circuit. The hanger bracket shall incorporate spring caps with indexed steps, which
correspond to the washer diameter of the hanger rod to keep the rod centered in the spring
cap.
2.3 BASES, RAILS AND CURBS:
A. Type C - Roof Mounted Equipment Vibration Isolation Rails: Vibration isolation rails shall
be extruded aluminum or G90 galvanized steel consisting of a lower support rail, upper
support rail, steel springs located between the support rails and a continuous weatherproof
seal located between the upper and lower support rails. Vibration isolation rails shall be
fabricated and designed to be installed and secured on top of the equipment manufacturer’s
roof curb. Isolation rails shall provide continuous support for the roof-mounted equipment.
Isolation rails shall be designed and engineered to provide isolation against casing radiated
vibration and structure born vibration from rotating equipment. The steel springs shall
consist of large diameter laterally stable steel springs that have a lateral stiffness greater than
1.0 times the rated vertical stiffness and shall be designed to provide up to 50% overload
capacity. Isolation rails shall have seismic restraints fabricated and attached to the isolation
rail assembly to resist the horizontal forces. Seismic restraints shall be certified by the
manufacturer and stamped by a registered engineer. Isolation rail assemblies shall include
supply and return duct block-outs as an integral part of the isolation rail assembly. Springs
must be removable and adjustable without disturbing the roof while equipment is in place.
2.4 SOUND CONTROL PRODUCTS:
A. Duct Sound Attenuators:
1. Attenuators shall be double wall construction with the outer shell being fabricated from
22 gage galvanized steel and the inner shell fabricated from 24 gauge perforated
galvanized steel. Interior steel partitions shall be double wall construction fabricated
from 24 gauge perforated galvanized steel.
2. Acoustic fill material shall be installed between the inner and outer shell and also in the
interior partitions. Acoustic fill shall be fiberglass.
3. Duct sound attenuators shall meet the fire hazard classification ratings in accordance with
ASTM-E84. Fire hazard ratings shall be a flame spread of 25 and smoke development of
20.
B. Acoustical Sound Barrier:
1. Acoustic Sound Barrier shall be constructed of vinyl material with a reinforced fiberglass
screen loaded with barium sulfate, 1.0 lb/sf. Tensile strength shall be 300 lb/inch and tear
101-14 Blessed Sacrament School- Phase I
215-14 23 9110 - 4 MECHANICAL SOUND, VIBRATION, WIND AND SEISMIC CONTROL
strength shall be 100 lbs/inch.
C. Acoustical Duct Wrap Barrier:
1. Acoustic Duct Wrap Barrier shall be fabricated of a composite material consisting of an
acoustic barrier material bonded to a thin layer of aluminum foil on one side and a
decoupling layer of fiberglass batting material. Acoustic Barrier material shall be 0.10”
thick barium sulphate loaded limp vinyl with “K” value of 0.29, STC rating of 28 and
nominal density of 1.0 lb/sf.
2.5 VIBRATION ISOLATION SCHEDULE FOR MECHANICAL SYSTEMS:
Equipment Type Isolator Type Base Type Deflection
In-line Suspended Fans Type 10 None 1.0”
Rooftop Air Conditioners Type 4 Type C 2.0”
Kitchen Hood Makeup Air Unit Type 4 Type C 2.0”
Energy Recovery Ventilators Type 4 Type C 2.0”
VRF Heat Pumps: Type 4 Structure 1.0”
Ductless Heat Pumps: Type 2 Curb 0.25”
PART 3 - EXECUTION
3.1 GENERAL:
A. If the equipment provided is not furnished with integral structural steel supports, mounting
feet or lifting lugs, the contractor shall provide miscellaneous steel shapes as required to
install or suspend the equipment and attach the vibration isolation as specified herein.
B. Support steel shall include but not be limited to rails, brackets, angles, channels, and similar
components.
C. All equipment specified to be isolated shall be installed and isolators shall be attached to the
building structure or floor and the vibration isolators shall be adjusted and leveled so that the
vibration isolators are performing properly.
D. All vibration isolation products and sound control products shall be installed as outlined in
the manufacturer’s printed installation instructions.
E. For equipment scheduled to receive external vibration isolation, all factory-installed internal