23 USC § 409 NDDOT Reserves All Objections SCOPING REPORT Project No. PCN Sterling to Wing 14 Prepared by NORTH DAKOTA DEPARTMENT OF TRANSPORTATION BISMARCK, NORTH DAKOTA http://www.dot.nd.gov/ DIRECTOR William T. Panos OFFICE OF TRANSPORTATION PROGRAMS Steve Salwei, P.E. Principal Author: Macy Merkel, E.I.T. April, 2021 DocuSign Envelope ID: 02AA01EB-4A44-4826-94E1-5E319FEC6C38
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Functional and Funding Roadway Classification: District Corridor National Highway System: No Speed Limit: 65 mph Freight Level: Level 2 Freight Constraints: Load Restriction Project Schedule: Proposed to be added to STIP as a minor rehabilitation and developed earlier if additional funding becomes available. dTIMS Recommendations: RP 0.000 to RP 13.000 – Constrained: PM Asphalt 2030 Unconstrained: PM Asphalt 2030 RP 13.000 to RP 21.289 – Constrained: PM Asphalt 2026 Unconstrained: PM Asphalt 2026
B. PURPOSE, NEED, AND IMPROVEMENT
Purpose and Need of Project: There is currently a 7 – Ton load restriction on this segment of ND 14. A freight level 2 requires a minimum 8 – Ton load restriction. This corridor is used as a bypass around Bismarck. There are a lot of heavy loads on the roadway, due to there being height restrictions along I-94 from Sterling to Bismarck. An overlay will put a width restriction on this segment. Proposed Improvement: There are two scenarios that apply in removing load restrictions, the first would involve just meeting the freight level requirement of an 8 – Ton limit. The second scenario would go further, taking the roadway to a legal weight requirement. In discussions with the district who is responsible for setting load restrictions, it was determined that a minor rehabilitation is needed to increase the load carrying capacity to 8 – Ton and a major rehabilitation is needed to take the roadway to legal weight. Option 1: Minor Rehabilitation Sliver Grade A minor rehabilitation sliver grade is proposed to extend the useful life of the roadway. This includes widening the roadway to 31’ (2’ widening), milling and overlaying the roadway with 3” of HMA. This would remove the load restriction and increase the load carrying capacity to 8 – Ton to meet freight expectation. Safety issues will be identified and addressed as part of the Statewide Safety Program. Safety features will remain as they exist unless a need is identified. An option is included to widen the roadway to 32’.
Option 2: Major Rehabilitation Cement Stabilized Full-Depth Reclamation A major rehabilitation cement stabilized full-depth reclamation with widening is proposed to bring the highway up to an acceptable condition to extend the service life and provide operational improvements. Based on preliminary pavement designs this includes milling and reclaiming the top 8” of the existing roadway, then overlaying with 4.5” of HMA, resulting in a roadway width of 31’ (2’ widening). Final sections will be determined during project development. This will remove the load restriction and increase the load carrying capacity to legal weight. A 90-1 survey will be completed and areas needing safety improvements will be addressed. Safety hardware will be upgraded to be in compliance with MASH performance criteria. An option is included to widen the roadway to 32’. Proposed Improvements Map:
Crash Analysis: The 5-year study period used was 12/1/2015 – 11/30/2020. Animal crashes are not included. On 8/1/2019 the cost threshold for a reportable crash increased from $1,000 to $4,000, so recent years may show fewer crashes than previous years.
- No fatal crashes, 1 incapacitating injury (single vehicle). - 6 of the single vehicle crashes ran off the roadway. - 4 of the single vehicle crashes occurred in adverse weather conditions (wet or
snow/ice/slush). - There were 4 crashes at the intersection of ND 14 & ND 36. - The 2017-2019 Rural Highway Segment Crash Map shows this segment is in the low
range for weighted crashes per mile. Recommendations: None at this time.
RP 0.000 to RP 13.000 Actual Age IRI IRI Rating SI or SCI Faulting 57 65 Good 3 N/A Effective Age Distress Distress Score Rutting Rutting Score 21 92 Good 0.07 Excellent
CONSTRUCTION HISTORY Year Construction Depth (in) Width (ft) Oil 1961 GRADE - 38.0 - 1963 AGGEGATE BASE 5.0 34.0 - 1963 HOT BIT PAVEMENT 2.0 24.0 120 – 150 1990 CONTRACT CHIP SEAL - 24.0 HFMS – 2 1995 INT CONT PATCH – 1.0” - 24.0 120 – 150 1998 MAINTENANCE GRAVEL SEAL - 5.0, 24.0, 5.0 MC – 3000 2001 INT CONT PATCH – 1.25” - 24.0 PG 58 – 28 2003 DISTRICT CHIP SEAL - 2.0, 24.0, 2.0 MC – 3000 2009 HOT BIT PAVEMENT 2.0 27.0 PG 58 – 28 2013 FEDERAL AID CHIP SEAL - 27.0 CRS2P
RP 13.000 to RP 21.289 Actual Age IRI IRI Rating SI or SCI Faulting 57 78 Good 4 N/A Effective Age Distress Distress Score Rutting Rutting Score 21 91 Good 0.09 Excellent
CONSTRUCTION HISTORY Year Construction Depth (in) Width (ft) Oil 1961 GRADE - 38.0 - 1963 AGGEGATE BASE 5.0 34.0 - 1963 HOT BIT PAVEMENT 2.0 24.0 120 – 150 1990 CONTRACT CHIP SEAL - 24.0 HFMS – 2 1995 INT CONT PATCH – 1.0” - 24.0 120 – 150 1998 MAINTENANCE GRAVEL SEAL - 5.0, 24.0, 5.0 MC – 3000 2001 INT CONT PATCH – 1.25” - 24.0 PG 58 – 28 2004 DISTRICT CHIP SEAL - 24.0 MC – 3000 2009 HOT BIT PAVEMENT 2.0 27.0 PG 58 – 28 2013 FEDERAL AID CHIP SEAL - 27.0 CRS2P
Existing Foreslopes: 4:1 Existing Typical Section
*Shoulders are breaking off in several locations, leaving the road with an effective width of ~25’.
RP 9.351 65 3820 1657 0.0 0.0 RP 10.103 65 3820 1657 3.4 0.0 RP 11.304 65 3183 1657 4.0 4.8 RP 11.611 65 3183 1657 4.0 4.8 RP 20.482 65 5730 1657 2.1 3.2 RP 20.971 65 3820 1657 3.4 4.2
Vertical Curves: Option 1: Use Existing
Option 2: Use existing. All existing vertical curves meet a design speed of no less than 20 mph below the overall project design speed.
F. EXISTING STRUCTURES
Bridges: None Centerline Pipes: Option 1:
Use existing. Any pipes affected by the sliver widening should be extended and have their end sections re-laid. Option 2: It is estimated 18 pipes will need to be extended ranging from 4 – 14’ to meet clear zone standards.
G. LAND INTERESTS
Communities: Wing; Population = 152 Reservation: None Public Land: None Wildlife Management Area: Rice Lake Wildlife Management Area (~RP 9.7 – 10.3) Waterfall Production Area: None Adjacent Land Usage: Agricultural
H. ISSUES AND APPURTENANCES CHECKLIST 1. Curb and Gutter? Yes No X 2. Sidewalk? Yes No X 3. Multi-Use Path? Yes No X 4. ADA Ramps? Yes No X 5. State Bicycling Network? Yes No X 6. Lighting? Yes X No Lighting at off/on-ramps for I-94 (~RP 0.092). No suggested improvements.
7. Signals? Yes No X 8. Storm Sewer? Yes No X 9. Manholes? Yes No X 10. Other Underground Work? Yes No X 11. Parking Facilities? Yes No X 12. Frontage Roads? Yes No X 13. Utility Issues? Yes X No There are buried telephone, fiber optic, electric, and overhead electric lines throughout the
corridor. 14. Landscaping? Yes No X 15. Approach or Ditch Block Flattening? Yes No X 16. T Intersection Recovery Approaches? Yes No X 17. Fence? Yes No X 18. Railroad Crossings? Yes No X 19. Detours? Yes No X 20. Automatic Traffic Recorder Locations? Yes No X 21. Weigh-In-Motion Sites? Yes No X 22. ITS (Deicing, Snow Gates, VMS, RWIS, etc.)? Yes No X 23. Highway Patrol/Truck Pullouts or Rest Areas? Yes No X 24. Additional Right of Way? Yes No X ROW ranges from 100 – 500’. It is anticipated additional ROW may be needed for deep fill
sections and hill cut back areas. 25. Drainage Issues? Yes No X 26. Snow Impact Areas? Yes No X 27. Subgrade Issues? Yes No X 28. Noise Analysis: Type I Project? Yes No X Maybe 29. Maintenance Issues? Yes No X
There are two scenarios that apply in removing load restrictions, the first would involve just meeting the freight level requirement of an 8 – Ton limit. The second scenario would go further, taking the roadway to a legal weight requirement. In discussions with the district who is responsible for setting load restrictions, it was determined that a minor rehabilitation is needed to increase the load carrying capacity to 8 – Ton and a major rehabilitation is needed to take the roadway to legal weight. Option 1: Minor Rehabilitation Sliver Grade A minor rehabilitation sliver grade is proposed to extend the useful life of the roadway. This includes widening the roadway to 31’ (2’ widening), milling and overlaying the roadway with 3” of HMA. This would remove the load restriction and increase the load carrying capacity to 8 – Ton to meet freight expectation. Safety issues will be identified and addressed as part of the Statewide Safety Program. Safety features will remain as they exist unless a need is identified. An option is included to widen the roadway to 32’.
Option 2: Major Rehabilitation Cement Stabilized Full-Depth Reclamation A major rehabilitation cement stabilized full-depth reclamation with widening is proposed to bring the highway up to an acceptable condition to extend the service life and provide operational improvements. Based on preliminary pavement designs this includes milling and reclaiming the top 8” of the existing roadway, then overlaying with 4.5” of HMA, resulting in a roadway width of 31’ (2’ widening). Final sections will be determined during project development. This will remove the load restriction and increase the load carrying capacity to legal weight. A 90-1 survey will be completed and areas needing safety improvements will be addressed. Safety hardware will be upgraded to be in compliance with MASH performance criteria. An option is included to widen the roadway to 32’. Proposed Typical Sections Proposed typical sections shown are for estimating purposes only. Actual typical section dimensions should be determined in the design phase. Option 1: Minor Rehabilitation Sliver Grade (31’)
Option 1: Minor Rehabilitation Sliver Grade (32’)
Option 2: Major Rehabilitation Cement Stabilized Full-Depth Reclamation (31’)
Estimated Total Cost / Mile = $ 813,000.00 $ 842,000.00 Cost Summary & Per Mile Comparison
Option Per Mile Cost Total Cost Option 1: Minor Rehabilitation Sliver Grade (31’) $ 680,000 $ 14,490,000 Option 1: Minor Rehabilitation Sliver Grade (32’) $ 705,000 $ 15,018,000 Option 2: Major Rehabilitation Cement Stabilized Full-Depth Reclamation (31’) $ 813,000 $ 17,308,000 Option 2: Major Rehabilitation Cement Stabilized Full-Depth Reclamation (32’) $ 842,000 $ 17,919,000
Future Outlook Pavement management philosophies change as new treatments/technology becomes available but as a preliminary forecast of future projects the Bismarck district anticipates the following work over the next 20 years for both options:
Year Treatment 2 Chip Seal
10 Chip Seal or Microsurface 15 PM Overlay
Each option provides an identical short-term future. Roadway widths provide differences in the long-term future. The following table compares the variations in future overlay details based on current requirements of the NDDOT’s Freight Plan and Design Guidelines.