Schenectady City School District Mosaic Associates Architects Kersten Lorcher, AIA Hamlin Design Group Shawn Hamlin, AIA Turner Construction Larry E. Tune, CM Phases 1, 1B, & 2 – Capital Project Update 20 June, 2018 1
Schenectady City School District Mosaic Associates Architects
Kersten Lorcher, AIA
Hamlin Design GroupShawn Hamlin, AIA
Turner ConstructionLarry E. Tune, CM
Phases 1, 1B, & 2 – Capital Project Update
20 June, 2018
1
CAPITAL PROJECT UPDATE| Outline
• Overview of Capital Projects• Long Range Planning• PH I – Overview• PH IB – CPMS Exterior Masonry• PH II – Timeline & Status Update• Group B Projects – In depth review
• Next Steps:• Critical & Milestone Dates
2SCSD Capital Project Update – 20 June, 2018
CAPITAL PROJECT UPDATE| Outline
3SCSD Capital Project Update – 20 June, 2018
Long Range Planning – 18 Month Process
Phase I & 1B – Overview - 42 Months
Phase II – Update, In depth Group B Review
CAPITAL PROJECT UPDATE| Long Range Planning
• Origins
4SCSD Capital Project Update – 20 June, 2018
CAPITAL PROJECT UPDATE| Long Range Planning
• Process
5SCSD Capital Project Update – 20 June, 2018
CAPITAL PROJECT UPDATE| Long Range Planning
• Process
6SCSD Capital Project Update – 20 June, 2018
CAPITAL PROJECT UPDATE| Long Range Planning
• Process
7SCSD Capital Project Update – 20 June, 2018
CAPITAL PROJECT UPDATE| Long Range Planning
• Road Map
8SCSD Capital Project Update – 20 June, 2018
CAPITAL PROJECT UPDATE| Long Range Planning
• Road Map
9SCSD Capital Project Update – 20 June, 2018
Middle School FocusConsistent 6-8 configurationacross the District.
Urgent Building Conditions Work
CAPITAL PROJECT UPDATE| Long Range Planning
• Road Map
10SCSD Capital Project Update – 20 June, 2018
Elementary School FocusReprogramming for K-5.
Urgent Building Conditions Work
CAPITAL PROJECT UPDATE| Long Range Planning
• Road Map
11SCSD Capital Project Update – 20 June, 2018
High School School FocusImplementing updatedprogrammatic objectives.
Urgent Building Conditions Work
CAPITAL PROJECT UPDATE| Long Range Planning
• Road Map
12SCSD Capital Project Update – 20 June, 2018
Elementary SchoolsSecond bite at the apple
Middle School refinementsUrgent Building Conditions Work
CAPITAL PROJECT UPDATE| Long Range Planning Time
13SCSD Capital Project Update – 20 June, 2018
We are here !
CAPITAL PROJECT UPDATE| Long Range Planning
• Board of Education Role - Moving Forward
•Provide on-going Educational Vision moving forward.
•Fiscal oversight of the program currently in construction and design.
•Establish budgets for upcoming referendums.
14SCSD Capital Project Update – 20 June, 2018
CAPITAL PROJECT | Phase I
2014 Referendum - $70 M• Central Park Middle School• Oneida Middle School• Mont Pleasant Middle School• Howe Elementary School• Steinmetz Career & Leadership Academy• Keane Elementary• Paige Elementary• Pleasant Valley Elementary
15SCSD Capital Project Update – 20 June, 2018
CAPITAL PROJECT UPDATE| Long Range Planning TimeCompleted Effort - Phase 1
• $70M (Middle School Focus)
16SCSD Capital Project Update – 20 June, 2018
Phase I & 1B – Overview - 42 Months
CAPITAL PROJECT | Phase I
• Completed Work
• Central Park Middle School•Reconstruction for 6-8 grade small learning communities
•New Science Labs, Art Room, Library & Toilet Rooms
17SCSD Capital Project Update – 20 June, 2018
CAPITAL PROJECT | Phase I
18SCSD Capital Project Update – 20 June, 2018
• BEFORE
CAPITAL PROJECT | Phase I
19SCSD Capital Project Update – 20 June, 2018
• AFTER
CAPITAL PROJECT | Phase I
20SCSD Capital Project Update – 20 June, 2018
• BEFORE
CAPITAL PROJECT | Phase I
21SCSD Capital Project Update – 20 June, 2018
• AFTER
CAPITAL PROJECT | Phase I
22SCSD Capital Project Update – 20 June, 2018
• BEFORE
CAPITAL PROJECT | Phase I
23SCSD Capital Project Update – 20 June, 2018
• AFTER
CAPITAL PROJECT | Phase I
24SCSD Capital Project Update – 20 June, 2018
• Completed Work
• Mont Pleasant Middle School• Reconstruction for 6-8 grade small
learning communities• ADA access• HVAC systems• Learning Common
CAPITAL PROJECT | Phase I
25SCSD Capital Project Update – 20 June, 2018
• BEFORE
CAPITAL PROJECT | Phase I
26SCSD Capital Project Update – 20 June, 2018
• AFTER
CAPITAL PROJECT | Phase I
27SCSD Capital Project Update – 20 June, 2018
• Completed Work
• Oneida Middle School• Reconstruction for 6-8 grade small
learning communities• ADA access• HVAC systems• Learning Commons
CAPITAL PROJECT | Phase I
28SCSD Capital Project Update – 20 June, 2018
• BEFORE
CAPITAL PROJECT | Phase I
29SCSD Capital Project Update – 20 June, 2018
• AFTER
CAPITAL PROJECT | Phase I
• Completed Work
• Howe Elementary School - Reconstruction & New Addition
30SCSD Capital Project Update – 20 June, 2018
CAPITAL PROJECT | Phase I
31SCSD Capital Project Update – 20 June, 2018
• BEFORE
CAPITAL PROJECT | Phase I
32SCSD Capital Project Update – 20 June, 2018
• AFTER
CAPITAL PROJECT | Phase I
33SCSD Capital Project Update – 20 June, 2018
• BERFORE
CAPITAL PROJECT | Phase I
34SCSD Capital Project Update – 20 June, 2018
• AFTER
CAPITAL PROJECT | Phase I
• Completed Work
• Steinmetz Career & Leadership Academy - Boiler, Doors, Fencing & Lighting
• Keane Elementary– Boiler Replacement
• Paige Elementary – Partial Roof Reconstruction
• Pleasant Valley Elementary – Boiler & Doors
35SCSD Capital Project Update – 20 June, 2018
CAPITAL PROJECT | Phase I
• Work in Progress
• CPMS – Exterior Masonry• Construction through Summer 2018.• Demolition in progress; per schedule.• Steel / terra cotta installation in progress
36SCSD Capital Project Update – 20 June, 2018
Bottom Row Cornice Install at NW Corner
Temporary Parapet Shoring
Demo of Corniceat NE Corner
CAPITAL PROJECT | Phase II
2017 Referendum – $64.5 M•Lincoln Elementary •Paige Elementary •Van Corlaer Elementary •Zoller Elementary•Schenectady High School
•Dr. Martin Luther King, Jr Elementary•Woodlawn Elementary
•Hamilton Elementary•Pleasant Valley Elementary•Yates Elementary
37SCSD Capital Project Update – 20 June, 2018
CAPITAL PROJECT UPDATE| Long Range Planning Time
Current Effort - Phase 2• $64.5M (Elementary School focus)
38SCSD Capital Project Update – 20 June, 2018
Phase II – Update, In depth Group B Review
CAPITAL PROJECT | Phase II
2017 Referendum – $64.5 M•Lincoln Elementary •Paige Elementary •Van Corlaer Elementary •Zoller Elementary•Schenectady High School
•Dr. Martin Luther King, Jr Elementary•Woodlawn Elementary
•Hamilton Elementary•Pleasant Valley Elementary•Yates Elementary
39SCSD Capital Project Update – 20 June, 2018
Group A
CAPITAL PROJECT | Phase II
2017 Referendum – $64.5 M•Lincoln Elementary •Paige Elementary •Van Corlaer Elementary •Zoller Elementary•Schenectady High School
•Dr. Martin Luther King, Jr Elementary•Woodlawn Elementary
•Hamilton Elementary•Pleasant Valley Elementary•Yates Elementary
40SCSD Capital Project Update – 20 June, 2018
Group A
Group B
CAPITAL PROJECT | Phase II
2017 Referendum – $64.5 M•Lincoln Elementary •Paige Elementary •Van Corlaer Elementary •Zoller Elementary•Schenectady High School
•Dr. Martin Luther King, Jr Elementary•Woodlawn Elementary
•Hamilton Elementary•Pleasant Valley Elementary•Yates Elementary
41SCSD Capital Project Update – 20 June, 2018
Group A
Group B
Group C
Group A1 Lincoln ES
2 Paige ES
3 Schenectady HS
5 Zoller ES
Group BGroup B1 Martin Luther King ES MAA
2 Woodlawn ES MAA
Group C Group C1 Hamilton ES HDA
2 Pleasant Valley ES MAA
3 Yates ES MAA
SED 3rd Party SED Review (Verify Duration)
Bid
Construction
SED 3rd Party SED Review (Verify Duration)
Bid
Construction
2020M J J A S
3rd Party SED Review (Verify Duration)
HDA
MAA
MAA
MAA
HDA
Group A
O N D J F M
2017 2018 2019O N D J F MA M J J A S O N D J F MA M J J A S O N DA M J J A S
Construction
Construction Docs
DD Estimate
4 Van Corlaer ES
SED
Verify Scope Collect Data
Design
Bid
CD Estimate
Verify Scope; Collect Data; Programming
Schematic Design
SD Estimate
Design Development
Verify Scope; Collect Data; Programming
SD Estimate
DD Estimate
CD Estimate
Construction Docs
Schematic Design
Design Development
Timeline - Schenectady CSD 2017 Capital Project - DRAFT August 9, 2017
As of 12/22/2017 - Level 1 Reviews DISCONTINUE
As of 1/24/18 - 35 weeks SED Review. Approx. 1000 projects currently awaiting review
January 24, 2018
Out to bid by mid April to ensure 2018 summer construction
Third Party Review starts February 1st. Review durations UNKNOWN
Mosaic/HDG Prepared to submit inital application to SED
Projected SED addendum Construction….TBD
Bid
42SCSD Capital Project Update – 20 June, 2018
CAPITAL PROJECT | Phase II Schedule
43SCSD Capital Project Update – 20 June, 2018
CAPITAL PROJECT | Phase II – Group A•Lincoln Elementary School [Nom. $ 0.5M]•Paige Elementary School [Nom. $ 2.8M]•Van Corlaer Elementary School [Nom. $ 1.1M]•Zoller Elementary School [Nom. $ 3.5M]•Schenectady High School [Nom. $ 4.1M]
Planning and Design Complete.At SED for Review.
44SCSD Capital Project Update – 20 June, 2018
Lincoln Elementary School - EXPEDITEDBoilerSED reviewed & approved.Bids received & Awarded 6/6/18Construction starts 6/22/18
Schenectady High School - EXPEDITED Tunnel AbatementSED reviewed & approved.Bids received & Awarded 6/6/18Construction starts 7/2/18
CAPITAL PROJECT | Phase II – Group A
45SCSD Capital Project Update – 20 June, 2018
CAPITAL PROJECT | Phase II – Group BDr. Martin Luther King Elementary School [Nom. $ 13.1M]• Main Entry / Main Office• Security• Learning Commons• Classroom Adjacencies
46SCSD Capital Project Update – 20 June, 2018
CAPITAL PROJECT | Phase II – Group BDr. Martin Luther King Elementary School [Nom. $ 13.1M]• Main Entry / Main Office
47SCSD Capital Project Update – 20 June, 2018
CAPITAL PROJECT | Phase II – Group BDr. Martin Luther King Elementary School [Nom. $ 13.1M]• Main Entry / Main Office
48SCSD Capital Project Update – 20 June, 2018
CAPITAL PROJECT | Phase II – Group BDr. Martin Luther King Elementary School [Nom. $ 13.1M]• Main Entry / Main Office• Security
49SCSD Capital Project Update – 20 June, 2018
CAPITAL PROJECT | Phase II – Group BDr. Martin Luther King Elementary School [Nom. $ 13.1M]• Main Entry / Main Office• Security
50SCSD Capital Project Update – 20 June, 2018
CAPITAL PROJECT | Phase II – Group BDr. Martin Luther King Elementary School [Nom. $ 13.1M]• Main Entry / Security
51SCSD Capital Project Update – 20 June, 2018
CAPITAL PROJECT | Phase II – Group BDr. Martin Luther King Elementary School [Nom. $ 13.1M]• Main Entry / Security
52SCSD Capital Project Update – 20 June, 2018
CAPITAL PROJECT | Phase II – Group BDr. Martin Luther King Elementary School [Nom. $ 13.1M]• Learning Commons
53SCSD Capital Project Update – 20 June, 2018
CAPITAL PROJECT | Phase II – Group BDr. Martin Luther King Elementary School [Nom. $ 13.1M]• Learning Commons
54SCSD Capital Project Update – 20 June, 2018
CAPITAL PROJECT | Phase II – Group BDr. Martin Luther King Elementary School [Nom. $ 13.1M]• Learning Commons
55SCSD Capital Project Update – 20 June, 2018
CAPITAL PROJECT | Phase II – Group BDr. Martin Luther King Elementary School [Nom. $ 13.1M]• Learning Commons
56SCSD Capital Project Update – 20 June, 2018
CAPITAL PROJECT | Phase II – Group BDr. Martin Luther King Elementary School [Nom. $ 13.1M]• Classroom Adjacencies
`
K 1
2 3 4
5
GuidanceNurseCommunity
57SCSD Capital Project Update – 20 June, 2018
CAPITAL PROJECT | Phase II – Group BWoodlawn Elementary School [Nom. $ 13.3M]• Main Entry • Learning Commons• Classroom Configurations & Adjacencies
57SCSD Capital Project Update – 20 June, 2018
CAPITAL PROJECT | Phase II – Group BWoodlawn Elementary School [Nom. $ 13.3M]• Main Entry
59SCSD Capital Project Update – 20 June, 2018
CAPITAL PROJECT | Phase II – Group BWoodlawn Elementary School [Nom. $ 13.3M]• Main Entry
59SCSD Capital Project Update – 20 June, 2018
CAPITAL PROJECT | Phase II – Group BWoodlawn Elementary School [Nom. $ 13.3M]• Learning Commons
61SCSD Capital Project Update – 20 June, 2018
CAPITAL PROJECT | Phase II – Group BWoodlawn Elementary School [Nom. $ 13.3M]• Learning Commons
61SCSD Capital Project Update – 20 June, 2018
CAPITAL PROJECT | Phase II – Group BWoodlawn Elementary School [Nom. $ 13.3M]• Classroom Configurations & Adjacencies
34
5
Spec
ial
Educ
atio
n K
12
GuidanceSpec
ial
Educ
atio
n
JUNE 06, 2018 SCHENECTADY CITY SCHOOL DISTRICT - Hamilton Elementary School A 02
63SCSD Capital Project Update – 20 June, 2018
CAPITAL PROJECT | Phase II – Group CHamilton Elementary School [Nom $ 9.6M]
Schematic Design In Progress - Meetings underway with BAC•Main Entry / Main Office• Social, Emotional, Community support / Nurse• Learning Commons• Limited Classroom modifications
64SCSD Capital Project Update – 20 June, 2018
CAPITAL PROJECT | Phase II – Group CPleasant Valley Elementary School [Nom $ 7.8M]
Schematic Design In Progress with targeted BAC input• Main Entry / Main Office• Social, Emotional, Community support / Nurse• Learning Commons• Limited Classroom modifications
65SCSD Capital Project Update – 20 June, 2018
CAPITAL PROJECT | Phase II – Group CYates Elementary School [Nom $ 8.0M]
Schematic Design In Progress with targeted BAC input• Main Entry / Main Office• Social, Emotional, Community support / Nurse• Limited Classroom modifications
CAPITAL PROJECT UPDATE| Next Steps & Milestones
•June 2018 Award Lincoln Boiler & SHS Tunnel Abatement.
•Summer 2018 Group C schematic design & design development.
•Fall 2018 Group A - SED Review
•September 2018 Submission of Group B projects to SED.
•December 2018 Group A out to bid.
•March/April 2019 Commence construction of Group A projects.
66SCSD Capital Project Update – 20 June, 2018
THANK YOU | Any Questions?