Earned Value Analysi s
13

Schedule Variance (SV)

Jan 15, 2017

Download

Engineering

Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Schedule Variance (SV)

Earned Value

Analysis

Page 2: Schedule Variance (SV)

Earned Value Analysis• Schedule

Variance• SV = EV - PV• Negative is bad• Positive is good

Page 3: Schedule Variance (SV)

Creating a Time-Phased Budget

Task Activity Budget (PV) Week 1 Week 2 Week 3 Week 4 Week 5 Week 6

Design prototype board $468 $78 $390

Order Sensors $156 $156

BreadBoard Sensors and connections $546 $234 $312

Outline programming requirements $390 $78 $312

Draft Preliminary Program $1,092 $78 $390 $390 $234

Load program and test $156 $156

Setup "Real" Twitter Account $39 $39

Develop Final Test Criteria $78 $78

Test $780 $78 $390 $312

Put into Case $39 $39

Complete Perm Install $156 $78 $78

Write up Details and Post $234 $234

Week Total $234 $1,326 $1,014 $702 $546 $312

Cumulative $234 $1,560 $2,574 $3,276 $3,822 $4,134

Week 1 Week 2 Week 3 Week 4 Week 5 Week 6$0.00

$1,250.00

$2,500.00

$3,750.00

$5,000.00

Planned Value at this time in the project = $2574

Today

Page 4: Schedule Variance (SV)

Actual Costs (AC)

AC = $3,000

Page 5: Schedule Variance (SV)

Percent of work complete50%

Earned Value

Project Total PV = $4,134

EV= Total PV for Project or Activity X % Complete

Today = End of Week Three

Page 6: Schedule Variance (SV)

Percent of work complete50%

Earned Value

EV= 4,134 X 50% = $2,067

Project Total PV = $4,134

Today = End of Week Three

Page 7: Schedule Variance (SV)

0 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6$0.00

$1,250.00

$2,500.00

$3,750.00

$5,000.00 PV AC EV

Page 8: Schedule Variance (SV)

0 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6$0.00

$1,250.00

$2,500.00

$3,750.00

$5,000.00 PV AC EV

SV=EV-PVSV=$2,067-$2574

SV= -$507

Page 9: Schedule Variance (SV)

Be Careful When Using Money to Measure Time

Page 10: Schedule Variance (SV)

Percent of work complete100%

Earned Value

EV= 4,134 X 100% = $4,134

Project Total PV = $4,134

Page 11: Schedule Variance (SV)

0 Week 1

Week 2

Week 3

Week 4

Week 5

Week 6

Week 7

$0.00

$1,250.00

$2,500.00

$3,750.00

$5,000.00 PV AC EV

SV= 0

PV = $2574EV = $2574

Page 12: Schedule Variance (SV)

Be Careful When Using Money to Measure Time

Page 13: Schedule Variance (SV)

Indexes to Monitor Progress