BILL OF QUANTITY
Project : Sharp Electronic Indonesia New Factory Project Works : Employee Facility Building ( Canteen, Musholla, Clinic, Toilet, etc ) Owner : PT. Sharp Indonesia Location : Karawang International Industrial City (KIIC) - Karawang
No. DESCRIPTION SPESIFICATION UNIT QTY UNIT PRICE AMOUNT
REMARKS ( Rp. ) ( Rp. )
I. PREPARATORY WORK 199,230,000
1.1 Survey and Marking ls 1.00 5,250,000 5,250,000 ### 1.2 Temporary Site Office ( Direksi keet & Storage ) ls 1.00 40,500,000 40,500,000 1.3 Temporary Water ls 1.00 12,000,000 12,000,000 1.4 Temporary Power ls 1.00 26,000,000 26,000,000 1.5 Safety & Protection ls 1.00 15,000,000 15,000,000 1.6 Design Fee ls 1.00 24,480,000 24,480,000 1.7 Mobilization & Demobilization Heavy equip, piling machine, others tools ls 1.00 22,000,000 22,000,000 1.8 Cleaning During Construction ls 1.00 12,000,000 12,000,000 1.9 Unloading fee, coordination & security ls 1.00 38,000,000 38,000,000
1.10 Reporting ls 1.00 4,000,000 4,000,000
II CONSTRUCTION WORKS 4,318,893,057
2.1 SITE CLEARING 12,480,000 2.1.1 Site Clearing / Stripping m2 1,560.00 3,500 5,460,000 ### 2.1.2 Disposal outside area m3 234.00 30,000 7,020,000 ###
2.3 FOUNDATION & COLUMN WORK 412,139,756 2.3.1 Pile Cap 95,477,578
2.3.1.1 Excavation, Backfill, diaposal & compaction base soil m3 302.01 60,000 18,120,600 2.3.1.2 Sand gravel, t - 10cm m2 44.55 20,000 891,000 2.3.1.3 Lean concrete, t - 5cm m2 44.55 35,250 1,570,388 2.3.1.4 Formwork for pile cap used brick/bataco m2 123.20 75,000 9,240,000 2.3.1.5 Steel bars for pile cap D-16, D-13 kg 3,773.00 13,000 49,049,000 2.3.1.6 Concrete work for pile cap ( 70*70*80cm ) K 250 kg/cm2 m3 21.56 770,250 16,606,590
Concrete spun pile Ø 300mm, L= 10 m' ( P1 )
BILL OF QUANTITY
Project : Sharp Electronic Indonesia New Factory Project Works : Employee Facility Building ( Canteen, Musholla, Clinic, Toilet, etc ) Owner : PT. Sharp Indonesia Location : Karawang International Industrial City (KIIC) - Karawang
No. DESCRIPTION SPESIFICATION UNIT QTY UNIT PRICE AMOUNT
REMARKS ( Rp. ) ( Rp. )
BILL OF QUANTITY
Project : Sharp Electronic Indonesia New Factory Project Works : Employee Facility Building ( Canteen, Musholla, Clinic, Toilet, etc ) Owner : PT. Sharp Indonesia Location : Karawang International Industrial City (KIIC) - Karawang
No. DESCRIPTION SPESIFICATION UNIT QTY UNIT PRICE AMOUNT
REMARKS ( Rp. ) ( Rp. )
2.3.2 Tie Beam 260,146,240 2.3.2.1 Excavation, Backfill, diaposal & compaction base soil m3 516.56 60,000 30,993,600 2.3.2.2 Sand gravel, t - 10cm m2 19.58 20,000 391,600 2.3.2.3 Lean concrete, t - 5cm m2 9.79 35,250 345,097 2.3.2.4 Formwork for tie beam used brick/bataco m2 435.00 75,000 32,625,000 2.3.2.5 Formwork for tie beam used plywood 12mm & wooden frame m2 90.60 105,000 9,513,000 2.3.2.6 Steel bars for tie beam D-16, D-8 kg 10,704.75 13,000 139,161,750 2.3.2.7 Concrete work for tie beam ( 25cm*50cm ) K 250 kg/cm2 m3 61.17 770,250 47,116,193
2.3.3 Column Concrete ( C-1 ) 56,515,938 2.3.3.1 Formwork for column used plywood 12mm & wooden frame m2 110.00 125,000 13,750,000 2.3.3.2 Steel bars for tie beam D-16, D-8 kg 2,475.00 13,000 32,175,000 2.3.3.3 Concrete work for tie beam ( 50cm*50cm* 100cm ) K 250 kg/cm2 m3 13.75 770,250 10,590,938
Project : Sharp Electronic Indonesia New Factory Project Works : Employee Facility Building ( Canteen, Musholla, Clinic, Toilet, etc ) Owner : PT. Sharp Indonesia Location : Karawang International Industrial City (KIIC) - Karawang
No. DESCRIPTION SPESIFICATION UNIT QTY UNIT PRICE AMOUNT
REMARKS ( Rp. ) ( Rp. )
2.4.3 Stair Work 53,422,188 2.4.3.1 Formwork used plywood 12mm & wooden frame m2 55.00 125,000 6,875,000 2.4.3.2 Steel bars D-16, D-13 m' 2,750.00 13,000 35,750,000 2.4.3.3 Concrete work K 250 kg/cm2 m3 13.75 785,250 10,797,188
2.5 STEEL STRUCTURE WORK 1,607,047,831 2.5.1 Anchor bolt, L - 60cm M-22 nos 204.00 85,000 17,340,000 2.5.2 Base plate, size 35cm*35cm*12mm kg 588.51 16,250 9,563,288 2.5.3 Steel main beam & ring beam 2nd floor WF 400, WF 300, WF 250, WF 200 kg 60,451.60 16,250 982,338,500 2.5.7 Steel structure for roofing ( truss, gording, etc ) WF 350, CNP 125, trackstang, turnbukcle kg 25,574.38 16,250 415,583,675 2.5.8 Steel plate for joint & others PL 12mm kg 1,209.03 16,250 19,646,738 2.5.9 Steel structure for bracket gutter CNP, L kg 925.00 16,250 15,031,250
2.5.10 Bolt & Nut HTB lot 1.00 14,421,600 14,421,600 2.5.11 Painting for steel structure Zincromate & finish paint Ftalit kg 88,748.52 1,500 133,122,780
2.6 ROOFING WORK 432,073,000 2.6.1 Roof of Finishes 394,243,000
2.6.2 Gutter 37,830,000 2.6.2.1 Gutter metal Alm sheet, t - 0.50mm m' 185.00 150,000 27,750,000 2.6.2.2 Down spout PVC dia 4", incl accessories PVC, Wavin type AW m' 72.00 140,000 10,080,000
2.7 WALL WORKS 132,600,000 2.7.1 Brick wall + practical column, 1st floor used heble 20*40*12cm m2 1,060.80 175,000 185,640,000 2.7.2 Plaster board GRC, t - 6mm m2 2,121.60 37,500 79,560,000
BILL OF QUANTITY
Project : Sharp Electronic Indonesia New Factory Project Works : Employee Facility Building ( Canteen, Musholla, Clinic, Toilet, etc ) Owner : PT. Sharp Indonesia Location : Karawang International Industrial City (KIIC) - Karawang
No. DESCRIPTION SPESIFICATION UNIT QTY UNIT PRICE AMOUNT
REMARKS ( Rp. ) ( Rp. )
2.8 DOOR AND WINDOW WORKS 99,042,000 2.8.1 Doors 57,162,000
2.8.1.1 Alm door type AD1, single swing door 800*2100 Al Clear anodize Ex. Alexindo, fix , Glass 5 mm nos 13.00 2,772,000 36,036,000 2.8.1.2 Alm door type AD2, double swing door 1600*2100 Al Clear anodize Ex. Alexindo, fix , Glass 5 mm nos 2.00 5,544,000 11,088,000 2.8.1.3 Alm door type AD3, double swing door 1200*2100 Al Clear anodize Ex. Alexindo, fix , Glass 5 mm nos 1.00 4,158,000 4,158,000 2.8.1.4 Alm door type AD4, double swing door 1600*2100 Al Clear anodize Ex. Alexindo, fix , Glass 5 mm nos 1.00 5,880,000 5,880,000
2.8.2 Windows 41,880,000 2.8.2.1 Aluminium window type AW1, size 800*2100 Al Clear anodize Ex. Alexindo, fix , Glass 5 mm nos 4.00 2,520,000 10,080,000 2.8.2.2 Aluminium window type AW2, size 1600*1200 Al Clear anodize Ex. Alexindo, fix , Glass 5 mm nos 1.00 2,400,000 2,400,000 2.8.2.3 Aluminium window type AW3, size 2400*1200 Al Clear anodize Ex. Alexindo, fix , Glass 5 mm nos 6.00 3,600,000 21,600,000 2.8.2.4 Aluminium window type AW4, size 3200*1200 Al Clear anodize Ex. Alexindo, fix , Glass 5 mm nos 1.00 4,800,000 4,800,000 2.8.2.5 Alum window (Bouvenlight), size 500*1200 Al Clear anodize Ex. Alexindo, fix , Glass 5 mm nos 4.00 750,000 3,000,000
2.9 FLOOR FINISH WORKS 308,788,750 2.9.1 Ceramic tile 1st floor & stair size 30*30 ex. Roman m2 1,332.00 140,000 186,480,000 2.9.2 Scriting ceramic, h - 100mm ex. Roman m' 500.00 32,500 16,250,000 2.9.3 Epoxy floor, 2nd floor ( half of area 2nd floor ) t = 500 micron, ex. maxiFloor m2 499.10 125,000 62,387,500 2.9.4 Floor harderner, 2nd floor ( half of area 2nd floor ) fosroc m2 499.10 87,500 43,671,250
Project : Sharp Electronic Indonesia New Factory Project Works : Employee Facility Building ( Canteen, Musholla, Clinic, Toilet, etc ) Owner : PT. Sharp Indonesia Location : Karawang International Industrial City (KIIC) - Karawang
No. DESCRIPTION SPESIFICATION UNIT QTY UNIT PRICE AMOUNT
REMARKS ( Rp. ) ( Rp. )
2.12 OTHERS WORK 214,102,500 2.12.1 Roster wall ventilation (near ablution area) m2 13.00 175,000 2,275,000 2.12.2 Concrete table for canteen, w - 50cm concrete & ceramic m' 37.00 187,500 6,937,500 2.12.3 Hand washing for canteen, size 50cm*50cm concrete & ceramic m' 12.00 900,000 10,800,000 2.12.4 Ablution, w - 60cm concrete & ceramic m' 7.00 500,000 3,500,000 2.12.5 Path foot around building, w - 100cm excav, sand gravel, concrete, bars, etc m2 160.00 225,000 36,000,000 2.12.6 Drainage u-ditch around building size 30cm*50cm m' 164.00 185,000 30,340,000 2.12.7 Concrete table for wastafel at toilet, w - 50cm m' 12.00 187,500 2,250,000 2.12.8 Cubical toilet partition (incl door) PVC m2 89.60 1,250,000 112,000,000 2.12.9 Partition urinoir, 35cm*76cm PVC ex. Toto nos 8.00 1,250,000 10,000,000
BILL OF QUANTITY
Project : Sharp Electronic Indonesia New Factory Project Works : Workshop, Waste area, Gasoline Tank & Signage Building Owner : PT. Sharp Electronic Indonesia Location : Karawang International Industrial City (KIIC) - Karawang
No. DESCRIPTION SPESIFICATION UNIT QTY UNIT PRICE AMOUNT
REMARKS ( Rp. ) ( Rp. )
I. PREPARATORY WORK 50,000,000
1.1 Survey, marking & setting out ls 1.00 3,000,000 3,000,000 1.2 Unloading fee ls 1.00 5,000,000 5,000,000 1.3 Mobilization & Demobilization ls 1.00 10,000,000 10,000,000 1.4 Cleaning During Construction ls 1.00 10,000,000 10,000,000 1.5 Safety & Protection ls 1.00 10,000,000 10,000,000 1.6 Coordination & security ls 1.00 10,000,000 10,000,000 1.7 Reporting ls 1.00 2,000,000 2,000,000
Project : Sharp Electronic Indonesia New Factory Project Works : Workshop, Waste area, Gasoline Tank & Signage Building Owner : PT. Sharp Electronic Indonesia Location : Karawang International Industrial City (KIIC) - Karawang
No. DESCRIPTION SPESIFICATION UNIT QTY UNIT PRICE AMOUNT
Project : Sharp Electronic Indonesia New Factory Project Works : Workshop, Waste area, Gasoline Tank & Signage Building Owner : PT. Sharp Electronic Indonesia Location : Karawang International Industrial City (KIIC) - Karawang
No. DESCRIPTION SPESIFICATION UNIT QTY UNIT PRICE AMOUNT
REMARKS ( Rp. ) ( Rp. )
3.3 FLOOR FINISH WORKS 9,366,840
3.3.1 Lean concrete, t - 50mm m2 165.20 56,700 9,366,840
3.5.1 Alm door , double swing door 1600*2100 nos 1.00 5,544,000 5,544,000 3.5.2 Alm door, single swing door 800*2100 nos 1.00 3,075,000 3,075,000 3.5.3 Aluminium window, size 1600*1200 frame alm 4", glasess 5mm nos 1.00 2,400,000 2,400,000
3.6 ROOFING WORK 70,434,000
3.6.1 Roofing zincalume, t - 0.5mm m2 270.90 260,000 70,434,000
3.7 MECHANICAL WORK lot 1.00 46,620,000 46,620,000
3.8 ELECTRICAL WORK lot 1.00 63,260,000 63,260,000
BILL OF QUANTITY
Project : Sharp Electronic Indonesia New Factory Project Works : Workshop, Waste area, Gasoline Tank & Signage Building Owner : PT. Sharp Electronic Indonesia Location : Karawang International Industrial City (KIIC) - Karawang
No. DESCRIPTION SPESIFICATION UNIT QTY UNIT PRICE AMOUNT
REMARKS ( Rp. ) ( Rp. )
IV. CONSTRUCTION GASOLINE TANK WORKS
4.1 EARTH WORK 8,320,000 4.1.1 Excavation by excavator m3 80.00 60,000 4,800,000 4.1.2 Disposal outside area m3 80.00 39,000 3,120,000 4.1.3 Subgrade preparation compaction base soil by vibro roller m2 80.00 5,000 400,000
4.2 LIMESTONE & BASE COURSE 10,804,000 4.2.1 Limestone, t - 40cm m3 32.00 243,000 7,776,000 4.2.2 Base course, t - 10cm m3 8.00 378,500 3,028,000
4.3 FOUNDATION WORK 10,789,296 4.3.1 Gravel bedding, t - 10cm m2 33.76 35,400 1,195,104 4.3.2 Lean concrete, t - 5cm m2 33.76 56,700 1,914,192 4.3.3 Pile cap, size 80cm*80cm*60cm incl. formwork, steel bars, concrete K-300 m3 1.54 5,000,000 7,680,000
4.6 STEEL STRUCTURE 52,517,554 4.6.1 Base plate, Column, beam PL 20mm, WF 250 kg 1,752.06 21,000 36,793,260 4.6.2 Steel structure for Gording CNP 125, trackstang, turnbukcle kg 163.80 21,000 3,439,800 4.6.3 Steel plate for joint & others PL 12mm kg 191.59 21,000 4,023,306 4.6.4 Bolt & Nut HTB lot 1.00 885,127 885,127 4.6.5 Painting for steel structure Zincromate & finish paint Ftalit kg 2,107.45 3,500 7,376,061
BILL OF QUANTITY
Project : Sharp Electronic Indonesia New Factory Project Works : Workshop, Waste area, Gasoline Tank & Signage Building Owner : PT. Sharp Electronic Indonesia Location : Karawang International Industrial City (KIIC) - Karawang
No. DESCRIPTION SPESIFICATION UNIT QTY UNIT PRICE AMOUNT
REMARKS ( Rp. ) ( Rp. )
4.7 ROOFING WORK 29,080,000 4.7.1 Roofing zincalume, t - 0.5mm ex. Lysaght, type clip lock, roll on site m2 80.00 260,000 20,800,000 4.7.2 Self drilling nos 240.00 1,500 360,000 4.7.3 Fascia, spandeck color, t - 0.45mm, H - 500mm m2 18.00 260,000 4,680,000 4.7.4 Flashing, t - 0.45mm m' 36.00 90,000 3,240,000
4.8 FOUNDATION FUEL TANK 40,750,000 4.8.1 Concrete foundation m3 2.50 5,800,000 14,500,000 4.8.2 Steel structure kg 1,250.00 21,000 26,250,000
4.9 MECHANICAL & ELECTRICAL WORK 38,570,000 4.9.1 Mechanical Work lot 1.00 18,190,000 18,190,000 4.9.2 Electrical Work lot 1.00 20,380,000 20,380,000
V. CONSTRUCTION SIGNAGE BUILDING WORKS
5.1 SIGNAGE BUILDING m2 2,027.92 113,100 229,357,752 5.1.1 -. Retaining Wall Dock Leveller
-. Retaining Wall Loading Area -. Wall Exterior Loading Area -. Wall Interior Loading Area -. Column Marking -. Parking Marking
SUMMARYPROGRESS REPORT
Period : 15 February 2013 ~ 21 February 2013
Project : Sharp Electronic Indonesia New Factory Project
Works : Employee Facility Building ( Canteen, Musholla, Clinic, Toilet, etc )
Owner : PT. Sharp Indonesia REPORT No. : 2Location : Karawang International Industrial City (KIIC) - Karawang
Planing Previous Progress This time Progress To Date Progress
ITEM Weighting Progress On Site Weight On Site Weight On Site Weight Deviation
Evaluation of Progress : Karawang, 15 February 2013
Accumulation of Planing Progress : #REF! Approved by; Prepared by;
Accumulation of actual Progress : #REF! PT. Sharp Indonesia PT. Karya Utama Jaya Abadi
-----------------------------------
#REF! #REF!
( Nanang Prakosa Budianto ) ( Gunawan )
Project Manager Site Manager
RENCANA KERJA MINGGU DEPAN( Minggu Ke - 3 )
Periode : 22 February 2013 ~ 28 February 2013
Project : Sharp Electronic Indonesia New Factory Project Works : Employee Facility Building ( Canteen, Musholla, Clinic, Toilet, etc ) Owner : PT. Sharp Indonesia Contractor : PT. Karya Utama Jaya Abadi REPORT No. : 2Location : Karawang International Industrial City (KIIC) - Karawang
Contract Planing Progress for Next week Target Progress for Next Week Planing Actual Deviation
2.3.1.4 Formwork for pile cap m2 123.20 0.205% - 0.00% 0.000% #REF! #REF! #REF! #REF! #REF! #REF!
2.3.1.5 Steel bars for pile cap kg 3,773.00 1.086% - 0.00% 0.000% #REF! #REF! #REF! #REF! #REF! #REF!
2.3.1.6 Concrete work for pile cap ( 70*70*80cm ) m3 21.56 0.368% 0.00 0.00% 0.000% #REF! #REF! #REF! #REF! #REF! #REF!
RENCANA KERJA MINGGU DEPAN( Minggu Ke - 3 )
Periode : 22 February 2013 ~ 28 February 2013
Project : Sharp Electronic Indonesia New Factory Project Works : Employee Facility Building ( Canteen, Musholla, Clinic, Toilet, etc ) Owner : PT. Sharp Indonesia Contractor : PT. Karya Utama Jaya Abadi REPORT No. : 2Location : Karawang International Industrial City (KIIC) - Karawang
Contract Planing Progress for Next week Target Progress for Next Week Planing Actual Deviation
Project : Sharp Electronic Indonesia New Factory Project Works : Employee Facility Building ( Canteen, Musholla, Clinic, Toilet, etc ) Owner : PT. Sharp Indonesia Contractor : PT. Karya Utama Jaya Abadi REPORT No. : 2Location : Karawang International Industrial City (KIIC) - Karawang
Contract Planing Progress for Next week Target Progress for Next Week Planing Actual Deviation
Project : Sharp Electronic Indonesia New Factory Project Works : Employee Facility Building ( Canteen, Musholla, Clinic, Toilet, etc ) Owner : PT. Sharp Indonesia Contractor : PT. Karya Utama Jaya Abadi REPORT No. : 2Location : Karawang International Industrial City (KIIC) - Karawang
Contract Planing Progress for Next week Target Progress for Next Week Planing Actual Deviation
Project : Sharp Electronic Indonesia New Factory Project Works : Employee Facility Building ( Canteen, Musholla, Clinic, Toilet, etc ) Owner : PT. Sharp Indonesia Contractor : PT. Karya Utama Jaya Abadi REPORT No. : 2Location : Karawang International Industrial City (KIIC) - Karawang
Contract Planing Progress for Next week Target Progress for Next Week Planing Actual Deviation
Project : Sharp Electronic Indonesia New Factory Project Works : Employee Facility Building ( Canteen, Musholla, Clinic, Toilet, etc ) Owner : PT. Sharp Indonesia Contractor : PT. Karya Utama Jaya Abadi REPORT No. : 2Location : Karawang International Industrial City (KIIC) - Karawang
Contract Planing Progress for Next week Target Progress for Next Week Planing Actual Deviation
Project : Sharp Electronic Indonesia New Factory Project Works : Workshop, Waste area, Gasoline Tank & Signage Building Owner : PT. Sharp Electronic Indonesia Location : Karawang International Industrial City (KIIC) - Karawang
No. DESCRIPTION SPESIFICATION UNIT QTY UNIT PRICE AMOUNT
REMARKS ( Rp. ) ( Rp. )
I. PREPARATORY WORK 50,000,000
1.1 Survey, marking & setting out ls 1.00 3,000,000 3,000,000 1.2 Unloading fee ls 1.00 5,000,000 5,000,000 1.3 Mobilization & Demobilization ls 1.00 10,000,000 10,000,000 1.4 Cleaning During Construction ls 1.00 10,000,000 10,000,000 1.5 Safety & Protection ls 1.00 10,000,000 10,000,000 1.6 Coordination & security ls 1.00 10,000,000 10,000,000 1.7 Reporting ls 1.00 2,000,000 2,000,000
Project : Sharp Electronic Indonesia New Factory Project Works : Workshop, Waste area, Gasoline Tank & Signage Building Owner : PT. Sharp Electronic Indonesia Location : Karawang International Industrial City (KIIC) - Karawang
No. DESCRIPTION SPESIFICATION UNIT QTY UNIT PRICE AMOUNT
Project : Sharp Electronic Indonesia New Factory Project Works : Workshop, Waste area, Gasoline Tank & Signage Building Owner : PT. Sharp Electronic Indonesia Location : Karawang International Industrial City (KIIC) - Karawang
No. DESCRIPTION SPESIFICATION UNIT QTY UNIT PRICE AMOUNT
REMARKS ( Rp. ) ( Rp. )
3.3 FLOOR FINISH WORKS 9,366,840
3.3.1 Lean concrete, t - 50mm m2 165.20 56,700 9,366,840
3.5.1 Alm door , double swing door 1600*2100 nos 1.00 5,544,000 5,544,000 3.5.2 Alm door, single swing door 800*2100 nos 1.00 3,075,000 3,075,000 3.5.3 Aluminium window, size 1600*1200 frame alm 4", glasess 5mm nos 1.00 2,400,000 2,400,000
3.6 ROOFING WORK 70,434,000
3.6.1 Roofing zincalume, t - 0.5mm m2 270.90 260,000 70,434,000
3.7 MECHANICAL WORK lot 1.00 46,620,000 46,620,000
3.8 ELECTRICAL WORK lot 1.00 63,260,000 63,260,000
BILL OF QUANTITY
Project : Sharp Electronic Indonesia New Factory Project Works : Workshop, Waste area, Gasoline Tank & Signage Building Owner : PT. Sharp Electronic Indonesia Location : Karawang International Industrial City (KIIC) - Karawang
No. DESCRIPTION SPESIFICATION UNIT QTY UNIT PRICE AMOUNT
REMARKS ( Rp. ) ( Rp. )
IV. CONSTRUCTION GASOLINE TANK WORKS
4.1 EARTH WORK 8,320,000 4.1.1 Excavation by excavator m3 80.00 60,000 4,800,000 4.1.2 Disposal outside area m3 80.00 39,000 3,120,000 4.1.3 Subgrade preparation compaction base soil by vibro roller m2 80.00 5,000 400,000
4.2 LIMESTONE & BASE COURSE 10,804,000 4.2.1 Limestone, t - 40cm m3 32.00 243,000 7,776,000 4.2.2 Base course, t - 10cm m3 8.00 378,500 3,028,000
4.3 FOUNDATION WORK 10,789,296 4.3.1 Gravel bedding, t - 10cm m2 33.76 35,400 1,195,104 4.3.2 Lean concrete, t - 5cm m2 33.76 56,700 1,914,192 4.3.3 Pile cap, size 80cm*80cm*60cm incl. formwork, steel bars, concrete K-300 m3 1.54 5,000,000 7,680,000
4.6 STEEL STRUCTURE 52,517,554 4.6.1 Base plate, Column, beam PL 20mm, WF 250 kg 1,752.06 21,000 36,793,260 4.6.2 Steel structure for Gording CNP 125, trackstang, turnbukcle kg 163.80 21,000 3,439,800 4.6.3 Steel plate for joint & others PL 12mm kg 191.59 21,000 4,023,306 4.6.4 Bolt & Nut HTB lot 1.00 885,127 885,127 4.6.5 Painting for steel structure Zincromate & finish paint Ftalit kg 2,107.45 3,500 7,376,061
BILL OF QUANTITY
Project : Sharp Electronic Indonesia New Factory Project Works : Workshop, Waste area, Gasoline Tank & Signage Building Owner : PT. Sharp Electronic Indonesia Location : Karawang International Industrial City (KIIC) - Karawang
No. DESCRIPTION SPESIFICATION UNIT QTY UNIT PRICE AMOUNT
REMARKS ( Rp. ) ( Rp. )
4.7 ROOFING WORK 29,080,000 4.7.1 Roofing zincalume, t - 0.5mm ex. Lysaght, type clip lock, roll on site m2 80.00 260,000 20,800,000 4.7.2 Self drilling nos 240.00 1,500 360,000 4.7.3 Fascia, spandeck color, t - 0.45mm, H - 500mm m2 18.00 260,000 4,680,000 4.7.4 Flashing, t - 0.45mm m' 36.00 90,000 3,240,000
4.8 FOUNDATION FUEL TANK 40,750,000 4.8.1 Concrete foundation m3 2.50 5,800,000 14,500,000 4.8.2 Steel structure kg 1,250.00 21,000 26,250,000
4.9 MECHANICAL & ELECTRICAL WORK 38,570,000 4.9.1 Mechanical Work lot 1.00 18,190,000 18,190,000 4.9.2 Electrical Work lot 1.00 20,380,000 20,380,000
V. CONSTRUCTION SIGNAGE BUILDING WORKS
5.1 SIGNAGE BUILDING 229,357,752 5.1.1 -. Retaining Wall Dock Leveller m2 2,027.92 113,100 229,357,752
-. Retaining Wall Loading Area -. Wall Exterior Loading Area -. Wall Interior Loading Area -. Column Marking -. Parking Marking
SCHEDULE OF WORK
Project : Sharp Electronic Indonesia New Factory Project
Works : Canopy Parking Manager
Owner : PT. Sharp Indonesia
Location : Karawang International Industrial City (KIIC) - Karawang