1 SB989 Secondary Containment Testing by Stan Brodecki XXX Environmental Management Non Testable Secondary Containment Systems and When a segment of your Secondary Containment System Fails
32

SB989 Secondary Containment Testing by Stan … SB989 Secondary Containment Testing by Stan Brodecki XXX Environmental Management Non Testable Secondary Containment Systems and When

Mar 08, 2018

Download

Documents

phungnhan
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: SB989 Secondary Containment Testing by Stan … SB989 Secondary Containment Testing by Stan Brodecki XXX Environmental Management Non Testable Secondary Containment Systems and When

1

SB989 Secondary ContainmentTesting

by Stan BrodeckiXXX Environmental Management

Non Testable Secondary ContainmentSystems and

When a segment of your SecondaryContainment System Fails

Page 2: SB989 Secondary Containment Testing by Stan … SB989 Secondary Containment Testing by Stan Brodecki XXX Environmental Management Non Testable Secondary Containment Systems and When

2

SB989 Secondary ContainmentTesting

• History - In 1984 - 1985 the SWRCB adoptednew regulations requiring double wall UST’s andpiping systems.

• These regulations preceded technology as do thenew regulations of today.

• As we all know the first few years that doublewall UST systems were built, only existinghardware and entrepreneurial hardware wasavailable, while more permanent solutions werestill in designed and in testing (UL, Third Party).

Page 3: SB989 Secondary Containment Testing by Stan … SB989 Secondary Containment Testing by Stan Brodecki XXX Environmental Management Non Testable Secondary Containment Systems and When

3

SB989 Secondary ContainmentTesting

• Many Corporations acting in good faith and asgood corporate citizens went out and installed alarge number of double wall UST Systems from1985 -1992.

• 1992 is about when proven technology startedto catch up with the regulations.

• For Standby/Emergency Generators USTSystems - This technology is still beingdeveloped.

Page 4: SB989 Secondary Containment Testing by Stan … SB989 Secondary Containment Testing by Stan Brodecki XXX Environmental Management Non Testable Secondary Containment Systems and When

4

SB989 Secondary ContainmentTesting

• Today we are now required to retest our

existing Secondary Containment systemsmany of them dating as far back as 1985.

• Some of the many problems encountered in

trying to test these UST Systems can befound in the design and hardware that wasavailable at the time of installation.

Page 5: SB989 Secondary Containment Testing by Stan … SB989 Secondary Containment Testing by Stan Brodecki XXX Environmental Management Non Testable Secondary Containment Systems and When

5

SB989 Secondary ContainmentTesting

• Standby/Emergency Generators are particularlydifficult to test because of their design andavailable hardware and technology.

• Following are some of the problems you arefaced with when trying to testStandby/Emergency Generator Systems

• Secondary Contained Piping is particularlydifficult.

Page 6: SB989 Secondary Containment Testing by Stan … SB989 Secondary Containment Testing by Stan Brodecki XXX Environmental Management Non Testable Secondary Containment Systems and When

6

Piping Secondary Containment ends at the building wall.It has been sealed with caulking (Bostick)

Page 7: SB989 Secondary Containment Testing by Stan … SB989 Secondary Containment Testing by Stan Brodecki XXX Environmental Management Non Testable Secondary Containment Systems and When

7

Piping Secondary Containment ends above grade, however theboot and cap will not hold 5 lbs.. PSI air pressure around the

piping.

Page 8: SB989 Secondary Containment Testing by Stan … SB989 Secondary Containment Testing by Stan Brodecki XXX Environmental Management Non Testable Secondary Containment Systems and When

8

Piping secondary ends outside the building SW steel pipingthrough the wall and sealed for weather protection.

Page 9: SB989 Secondary Containment Testing by Stan … SB989 Secondary Containment Testing by Stan Brodecki XXX Environmental Management Non Testable Secondary Containment Systems and When

9

PipingSecondary

containmentends above

grade, howeverduring test bootunable to hold 5

PSI airpressure.

Replaced bootto no avail.

Page 10: SB989 Secondary Containment Testing by Stan … SB989 Secondary Containment Testing by Stan Brodecki XXX Environmental Management Non Testable Secondary Containment Systems and When

10

No test boots, piping system will have to be taken off line andnew boots installed, if they will fit older design.

Page 11: SB989 Secondary Containment Testing by Stan … SB989 Secondary Containment Testing by Stan Brodecki XXX Environmental Management Non Testable Secondary Containment Systems and When

11

No test boots, piping system will have to be taken off line andnew boots installed, if they will fit older design.

Page 12: SB989 Secondary Containment Testing by Stan … SB989 Secondary Containment Testing by Stan Brodecki XXX Environmental Management Non Testable Secondary Containment Systems and When

12

Test boot left on. But in what condition? Will it work?

Page 13: SB989 Secondary Containment Testing by Stan … SB989 Secondary Containment Testing by Stan Brodecki XXX Environmental Management Non Testable Secondary Containment Systems and When

13Everything left on, however this system leak air around this boot.

Boot being replaced, however no guarantee system will pass.

Page 14: SB989 Secondary Containment Testing by Stan … SB989 Secondary Containment Testing by Stan Brodecki XXX Environmental Management Non Testable Secondary Containment Systems and When

14

Page 15: SB989 Secondary Containment Testing by Stan … SB989 Secondary Containment Testing by Stan Brodecki XXX Environmental Management Non Testable Secondary Containment Systems and When

15

Old style sump, bolted to the tank manway. Gasket candeteriorate and allow small leakage's.

Page 16: SB989 Secondary Containment Testing by Stan … SB989 Secondary Containment Testing by Stan Brodecki XXX Environmental Management Non Testable Secondary Containment Systems and When

16

Old style secondary containment. Not enough material to place aboot on for testing.

Page 17: SB989 Secondary Containment Testing by Stan … SB989 Secondary Containment Testing by Stan Brodecki XXX Environmental Management Non Testable Secondary Containment Systems and When

17

Old style secondary containment. Not enough material to install atest boot on. Also not sealed to sump.

Page 18: SB989 Secondary Containment Testing by Stan … SB989 Secondary Containment Testing by Stan Brodecki XXX Environmental Management Non Testable Secondary Containment Systems and When

18

UST Installed long distance frombuilding. Generator is on the roof.

Page 19: SB989 Secondary Containment Testing by Stan … SB989 Secondary Containment Testing by Stan Brodecki XXX Environmental Management Non Testable Secondary Containment Systems and When

19

Pressuresystem to

push fuel upto the

Generator onthe roof.

Page 20: SB989 Secondary Containment Testing by Stan … SB989 Secondary Containment Testing by Stan Brodecki XXX Environmental Management Non Testable Secondary Containment Systems and When

20

Piping secondarycontainment fromUnderground thruwall on its way to

the Roof.

Page 21: SB989 Secondary Containment Testing by Stan … SB989 Secondary Containment Testing by Stan Brodecki XXX Environmental Management Non Testable Secondary Containment Systems and When

21

Side view

Page 22: SB989 Secondary Containment Testing by Stan … SB989 Secondary Containment Testing by Stan Brodecki XXX Environmental Management Non Testable Secondary Containment Systems and When

22

Piping upthru deckon way tothe Roof.

Page 23: SB989 Secondary Containment Testing by Stan … SB989 Secondary Containment Testing by Stan Brodecki XXX Environmental Management Non Testable Secondary Containment Systems and When

23

Piping going up outside wall to the Roof

Page 24: SB989 Secondary Containment Testing by Stan … SB989 Secondary Containment Testing by Stan Brodecki XXX Environmental Management Non Testable Secondary Containment Systems and When

24

SB989 Secondary ContainmentTesting

• The repair/corrective action to these types ofUST Systems is many times a complete tank topupgrade with new compatible materials at a costof $50,000 to $60,000.

• The minimum corrective action in many cases isreplace the supply and return piping systemand/or replacing the sump(s). This requirescutting concrete and replacing the manways ontop of the tank.

Page 25: SB989 Secondary Containment Testing by Stan … SB989 Secondary Containment Testing by Stan Brodecki XXX Environmental Management Non Testable Secondary Containment Systems and When

25

SB989 Secondary ContainmentTesting

• The population of Standby/Emergency GeneratorUST’s is equal to the number of petroleumindustry UST’s.

• However these UST’s pose a lot less risk. Mosthave suction systems and use diesel fuel.

• These UST’s are owned and operated by manyNon Petroleum Corporations who are not in thepetroleum business. These Generators/engineswith UST’s do not generate any revenue and arean expense against the bottom line.

Page 26: SB989 Secondary Containment Testing by Stan … SB989 Secondary Containment Testing by Stan Brodecki XXX Environmental Management Non Testable Secondary Containment Systems and When

26

SB989 Secondary ContainmentTesting

• Because these systems do not contribute to thebottom line they are classified (tax wise)differently. Many times a certain type of work ordollar amount requires that Capital Dollars usedand expensed.

• Obtaining Capital dollars expenditure for a nonprofit center is difficult at the best of times.

Page 27: SB989 Secondary Containment Testing by Stan … SB989 Secondary Containment Testing by Stan Brodecki XXX Environmental Management Non Testable Secondary Containment Systems and When

27

SB989 Secondary ContainmentTesting

• With the current recession the Xxxxxxxxxxxindustry has cut back its capital expenditures by20 %.

• At XXX All Capital Dollar expenditures must besubmitted as a business case to CapitalManagement, City, State. Capital projectsexceeding $2 Million Dollars require a longform Business Case be submitted and approvedby a Senior VP.

Page 28: SB989 Secondary Containment Testing by Stan … SB989 Secondary Containment Testing by Stan Brodecki XXX Environmental Management Non Testable Secondary Containment Systems and When

28

SB989 Secondary ContainmentTesting

• The long form Business Case requires a NetPresent Value Model be submitted. (fun)

• XXXX has 200 plus UST installed before 1992.And 300 Plus installed after 1992 that are beingSecondary Containment Tested with numeroustesting problems and dispenser pan installationon fleet vehicle refueling UST’s. XXX’sCalifornia cost is expected to reach over $16Million Dollars by the end of the program.

Page 29: SB989 Secondary Containment Testing by Stan … SB989 Secondary Containment Testing by Stan Brodecki XXX Environmental Management Non Testable Secondary Containment Systems and When

29

SB989 Secondary ContainmentTesting

• This is a major expense in such a short timeframe. More time is required to obtain capitaldollar approval and then time (drawing, permits,contractors availability, etc.) to completed therequired corrective actions for over 400 UST’s.

• Suggestion - UST Systems that are not testableand/or have some component fail secondarytesting be treated as single wall systems untilsuch time they can be brought into compliance.

Page 30: SB989 Secondary Containment Testing by Stan … SB989 Secondary Containment Testing by Stan Brodecki XXX Environmental Management Non Testable Secondary Containment Systems and When

30

SB989 Secondary ContainmentTesting

• Current Regulations (Section 2637(a)(1) Title23 Division 3 Chapter 16 CCR) allows for thereplacement of secondary containmentsystems with a system that can be tested byJuly 1, 2005.

• This is two and a half years after the Dec. 31,2002 deadline.

Page 31: SB989 Secondary Containment Testing by Stan … SB989 Secondary Containment Testing by Stan Brodecki XXX Environmental Management Non Testable Secondary Containment Systems and When

31

SB989 Secondary ContainmentTesting

• I would like to propose that UST Systemsinstalled before 1/1/2001 that are nottestable or have a secondary componentfailure be allowed to operate under Sec.2637(a)(1).

• The additional two and half years is very

valuable time that is required tosuccessfully complete this program.

Page 32: SB989 Secondary Containment Testing by Stan … SB989 Secondary Containment Testing by Stan Brodecki XXX Environmental Management Non Testable Secondary Containment Systems and When

32

SB989 Secondary ContainmentTesting

• I would like to Thank the Panel and the Boardfor their time today and ask that you take intoconsideration the conclusions of thispresentation.

• If you have any questions or need anyadditional information please contact me at 925823 6161. E-mail [email protected]