@ A310SERVICE BULLETIN
REVISION TRANSMITTAL SHEET
6 DATE : Dec 03/99 SERVICE BULLETIN No. : A310—28—2140
AIRBUSCUSTOMER SERVICES DIRECTORATE1 Rond Point Maurice Bellonte31707 BLAGNAC CEDEX FRANCETel : (33) 5 61 93 33 33Telex : AIRBU 530526FFax : (33) 5 61 93 42 51
MANDATORY MANDATORY MANDATORYATA SYSTEM : 28
TITLE : FUEL - WING ELECTRIC/ELECTRONIC COMMON INSTALLATION - REROUTE THE WIREHARNESS 636VB IN THE RH WING
MODIFICATION No. : 12173D21810
This page transmits Revision No. 04 of Service Bulletin No. A310-28-2140.
ADDITIONAL WORK
If this Service Bulletin has been accomplished before Revision 02, it isnecessary to do the additional work as described in this Service Bulletin.
REASON
This Revision has been issued to :
— advise operators that this Service Bulletin has been rendered mandatory byAirworthiness Directive (AD) No. F-2004-005 and remove aircraft MSNs 0285,0340, 0433, 0435 and 0440 from the effectivity.
CHANGES
SUMMARY
— REASON/DESCRIPTION/OPERATIONAL CONSEQUENCES
Mandatory sentence added.
— EVALUATION TABLE
Compliance changed from Recommended to Mandatory and AD No. F-2004-005added.
PLANNING INFORMATION
— EFFECTIVITY
Aircraft MSNs 0285, 0340, 0433, 0435 and 0440 removed from theeffectivity.
— REASON
@ A310SERVICE BULLETIN
REVISION TRANSMITTAL SHEET
DATE : Dec 03/99 SERVICE BULLETIN No. : A310—28—2140
NOTE : Layout changes due to computerization of this revision are notidentified.
FILING INSTRUCTIONS
This Service Bulletin has been generated electronically and is reissued as acomplete document. Replace the complete document.
Put this Revision Transmittal Sheet in front of the Service Bulletin.
HISTORY OF PREVIOUS REVISIONS
Revision 01 was issued to inform the operators that the conduits are to beinstalled in a horizontal and not in a vertical line and one larger conduithas to be installed.
Revision 02 was issued to add additional work for the new routing of theconduit with the wires to 2212VC and to the pylon, and to remove aircraftMSN 0424 and 0528 from the effectivity.
Revision 03 was issued to correct some minor discrepancies and to update theeffectivity.
2
@ A310SERVICE BULLETIN
REVISION TRANSMITTAL SHEET
DATE : Dec 03/99 SERVICE BULLETIN No. : A310—28—2140
AIRBUSCUSTOMER SERVICES DIRECTORATE1 Rond Point Maurice Bellonte31707 BLAGNAC CEDEX FRANCETel : (33) 5 61 93 33 33Telex : AIRBU 530526FFax : (33) 5 61 93 42 51
This summary is for information onlyand is not approved for modification of the aircraft
MANDATORY MANDATORY MANDATORYATA SYSTEM : 28
TITLE : FUEL - WING ELECTRIC/ELECTRONIC COMMON INSTALLATION - REROUTE THE WIREHARNESS 636VB IN THE RH WING
MODIFICATION No. : 12173D21810
REASON/DESCRIPTION/OPERATIONAL CONSEQUENCES
An analysis of the wire routing within the framework of the fuel system safetyprogram has shown that the route 2M has to be rerouted to ensure segregation.
The existing routing of the wire routes 2M and 2S located in one conduit is tobe changed so that each wire route 2M and 2S is in one conduit.
This modification assures the proper segregation of the wire routing for thefuel quantity indication system and the 115V anti-collision white strobe lightsin order to avoid interaction in the case of wire damage.
Accomplishment of this Service Bulletin is mandatory as per the latest issue ofConsigne de Navigabilite (CN) (Airworthiness Directive (AD)) No. F-2004-005.
ADDITIONAL WORK
Revision No. 02 requires additional work which consists in the new routing ofthe conduit with the wires to 2212VC and to the pylon.
NOTE : Operators which are accomplishing this Service Bulletin for the firsttime do not have to do the additional work.
EVALUATION TABLE
COMPLIANCE Mandatory CANCELS INSPECTION SB No
AD F-2004-005 A/C OPERATION AFFECTED No
RELIABILITY AFFECTED No PAX COMFORT AFFECTED No
COST SAVING No ETOPS AFFECTED No
@ A310SERVICE BULLETIN
SUMMARY
DATE : Dec 03/99 SERVICE BULLETIN No. : A310—28—2140
AIRBUSCUSTOMER SERVICES DIRECTORATE1 Rond Point Maurice Bellonte31707 BLAGNAC CEDEX FRANCETel : (33) 5 61 93 33 33Telex : AIRBU 530526FFax : (33) 5 61 93 42 51
MANDATORY MANDATORY MANDATORYATA SYSTEM : 28
TITLE : FUEL - WING ELECTRIC/ELECTRONIC COMMON INSTALLATION - REROUTE THE WIREHARNESS 636VB IN THE RH WING
MODIFICATION No. : 12173D21810
This document contains AIRBUS PROPRIETARY INFORMATION and shall at all timesremain the property of AIRBUS; no intellectual property right or licence isgranted by AIRBUS in connection with any information contained in it. It isdelivered on the express condition that the said document and the informationcontained in it shall be treated as confidential, shall not be used for anypurpose other than that for which it is hereby delivered. It shall not bedisclosed in whole or in part to third parties and shall not be duplicated inany manner (except for the purposes of performing the tasks described hereunderand provided that any recipient of such document shall comply with theconditions herein), without AIRBUS prior written consent.
The Operator/MSN relationship is provided for information onlyand is correct at the time of issue in accordance with theinformation available to AIRBUS. Any future changes resultingfrom transfer of an aircraft from one operator to another willnot be reflected in this list unless the Service Bulletin isrevised for another reason.
An analysis of the wire routing within the framework of the fuelsystem safety program has shown that the route 2M has to bererouted to ensure segregation.
Accomplishment of this Service Bulletin is mandatory as per thelatest issue of Consigne de Navigabilite (CN) (AirworthinessDirective (AD)) No. F-2004-005.
(2) Objective/Action
The existing routing of the wire routes 2M and 2S located in oneconduit is to be changed so that each wire route 2M and 2S is inone conduit.
ADDITIONAL WORK
KIT No. QTY PER A/C CONFIGURATION
282140D01R04 1 None
282140B01R00 1 None
4
@ A310SERVICE BULLETIN
DATE : Dec 03/99 SERVICE BULLETIN No. : A310—28—2140
Revision No. 02 requires additional work which consists in the newrouting of the conduit with the wires to 2212VC and to the pylon.
NOTE : Operators which are accomplishing this Service Bulletin forthe first time do not have to do the additional work.
(3) Advantages
Separation of the fuel quantity indication wires and the 115Vanti-collision white strobe light wires in order to avoidinteraction in case of wire damage.
(4) Operational/Maintenance Consequences
None
D. DESCRIPTION
To accomplish this Service Bulletin it is necessary to :
(1) Kit 282140D01R04
(a) Remove components at the RH wing for new routing of wireroutes 2M and 2S.
(b) Segregate the wires of routes 2M and 2S and put them throughindividual conduits for each route.
(c) Test
(2) Kit 282140B01R00
(a) Replace a bracket.
(3) ADDITIONAL WORK
(a) New routing of the conduit with the wires to 2212VC and to thepylon.
E. COMPLIANCE
(1) Classification
Mandatory
(2) Accomplishment Timescale
Accomplishment of this Service Bulletin is mandatory as per thelatest issue of Consigne de Navigabilite (CN) (AirworthinessDirective (AD)) No. F-2004-005.
ADDITIONAL WORK
5
@ A310SERVICE BULLETIN
DATE : Dec 03/99 SERVICE BULLETIN No. : A310—28—2140
Accomplishment of this Service Bulletin is mandatory as per thelatest issue of Consigne de Navigabilite (CN) (AirworthinessDirective (AD)) No. F-2004-005.
F. APPROVAL
The technical content of this Service Bulletin has been approved underthe authority of the DGAC Design Organisation Approval No. F.JA.02.
If an aircraft listed in the effectivity has a modification or repairembodied that is not of AIRBUS origin, and which affects the content ofthis Service Bulletin, the operator is responsible for obtainingapproval by its airworthiness authority for any adaptation necessarybefore incorporation of the Service Bulletin.
G. MANPOWER
The manpower estimates given in this Service Bulletin are based on thedirect labor cost to do the work. These estimates assume that the workwill be done by experienced personnel, and may need to be revisedupwards to suit operators' circumstances. The estimates do not includethe time to prepare, plan or inspect the work. Manufacture andprocurement of parts and tools, drying time for paints, sealants, etc.and general administration work are also not included.
Kit 282140D01R04
Kit 282140B01R00
ADDITIONAL WORK
Get Access 2.00
Modification 20.00
Test 6.00
Close-up 2.00
TOTAL MANHOURS 30.00
ELAPSED TIME (HOURS) 17.50
Get Access 0.25
Modification 0.50
Close-up 0.25
TOTAL MANHOURS 1.00
ELAPSED TIME (HOURS) 1.00
Get Access 2.00
Modification 1.50
Test 6.00
Close-up 2.00
6
@ A310SERVICE BULLETIN
DATE : Dec 03/99 SERVICE BULLETIN No. : A310—28—2140
Customers with aircraft shown in the effectivity of this ServiceBulletin should send a purchase order to AIRBUS. Quote the numberof this Service Bulletin. The address is :
AIRBUSMATERIEL SUPPORT CENTERP.O. BOX 63026222312 HAMBURGGERMANY
(2) Price and Availability
Kit 282140D01R04
Cost : 321 US Dollars
Availability : 150 calendar days from receipt of order
The Kit availability given above is the standard lead time from thedate of your purchase order. If you require the Kit(s) before thistime, please include a retrofit planning schedule with your orderso that we can try to comply with your requirements.
The sales terms (costs and availability) are estimated in relationto the economic conditions at the issue date of the ServiceBulletin.
Kit 282140B01R00
Cost : 35 US Dollars
Availability : 150 calendar days from receipt of order
The Kit availability given above is the standard lead time from thedate of your purchase order. If you require the Kit(s) before thistime, please include a retrofit planning schedule with your orderso that we can try to comply with your requirements.
The sales terms (costs and availability) are estimated in relationto the economic conditions at the issue date of the ServiceBulletin.
B. INDUSTRY SUPPORT INFORMATION
Refer to paragraph 2.A.(2): "Price and Availability".
C. LIST OF COMPONENTS
Kit 282140D01R04
9
@ A310SERVICE BULLETIN
DATE : Dec 03/99 SERVICE BULLETIN No. : A310—28—2140
NOTE : Refer to the AIRBUS Standards Manual (SM) if you find partnumbers for the hardware components in the related kit(s) whichyou can not identify in the LIST OF COMPONENTS of this ServiceBulletin. The SM will give you the correct part number to partnumber relationship.
D. LIST OF MATERIALS — OPERATOR SUPPLIED
(1) Consumable Materials
ITEM NEW PART No. QTY UM KEYWORD ITEM OLD PART No. INT INST DISP
NSA935401-04 15 EA TIENSA935401-03 10 EA TIE
1 B9229062120400 1 EA SLEEVE2 B9229062120600 3 EA SLEEVE3 B9229062120000 1 EA SLEEVE4 B9229062120800 2 EA SLEEVE5 B9229062120200 1 EA SLEEVE8 NSA935807C10 7 EA CLAMP9 NSA935805-09 1.5 ME CONDUIT10 NSA935805-10 1.5 ME CONDUIT12 NSA935807-16 7 EA CLAMP13 NSA935808-01 4 EA WASHER14 NAS1096-3-23 1 EA SCREW15 NSA5527-03-02D 7 EA SPACER16 NSA5527-03-05D 6 EA SPACER17 NAS1149D0332K 4 EA WASHER18 NAS1291C3M 1 EA NUT20 NSA935807C09 7 EA CLAMP21 NAS1096-3-25 1 EA SCREW23 NSA5527-03-01D 6 EA SPACER25 NAS1096-3-33 5 EA SCREW
ITEM NEW PART No. QTY UM KEYWORD ITEM OLD PART No. INT INST DISP
30 A5725802500000 1 EA BRACKET (30) A572469560000031 NAS1303-12 2 EA BOLT32 NSA5474-3K7 2 EA NUT
DESCRIPTION REFERENCE TO CMLMAT. No.
QTY PER A/C INST DISP
Special material 05-002 As requiredCorrosion preventive 15-008A As required
10
@ A310SERVICE BULLETIN
DATE : Dec 03/99 SERVICE BULLETIN No. : A310—28—2140
WARNING : MAKE SURE THAT YOU OBEY ALL THE WARNINGS AND CAUTIONS INCLUDEDIN THE REFERENCED PROCEDURES.
CAUTION : ALWAYS OBEY THE PRECAUTIONS THAT FOLLOW TO KEEP ELECTRICALWIRING IN A SATISFACTORY CONDITION (ELECTRICALLY ANDMECHANICALLY SERVICEABLE).
WHEN YOU DO MAINTENANCE WORK, REPAIRS OR MODIFICATIONS, ALWAYSKEEP ELECTRICAL WIRING, COMPONENTS AND THE WORK AREA AS CLEANAS POSSIBLE. TO DO THIS :
— PUT PROTECTION, SUCH AS PLASTIC SHEETING, CLOTHS, ETC. ASNECESSARY ON ELECTRICAL WIRING AND COMPONENTS.
— REGULARLY REMOVE ALL SHAVINGS, UNWANTED MATERIAL AND OTHERCONTAMINATION.
THESE PRECAUTIONS WILL DECREASE THE RISK OF CONTAMINATION ANDDAMAGE TO THE ELECTRICAL WIRING INSTALLATION.
IN CASE OF CONTAMINATION REFER TO ESPM 20-55-00.
(1) Preparation
(a) Make sure that the aircraft is electrically grounded, refer toAMM 24-00-00 Page block 301.
(b) Fully extend the slats, refer to AMM 27-80-00 Page block 301.
(c) Open, safety and tag the circuit breakers, refer to AMM27-80-00 Page block 301.
(d) Put access platform(s) in position.
(e) Open the access panels 612AT, 612KB, 612JB, 623AB and 623BB.
(f) Remove the bleed air duct if necessary, refer to AMM 36-11-00Page block 401.
(2) Standard Practices
(a) Refer to the AIRBUS Standards Manual (SM) if you find partnumbers for the hardware components in the related kit(s)which you can not identify in the LIST OF COMPONENTS of thisService Bulletin. The SM will give you the correct part numberto part number relationship.
(b) For material specifications (Mat. No.) given in this ServiceBulletin, refer to the Consumable Material List (CML ).
(c) Install screws and nuts with special material (Mat No. 05-002)
13
@ A310SERVICE BULLETIN
DATE : Dec 03/99 SERVICE BULLETIN No. : A310—28—2140
NOTE : The connector 2212VC is only affected if ServiceBulletin A310-36-2015 or modification 7633S8497 isembodied.
NOTE : The list of wires routed in 2S and 2M may includeadditional wires which are not actually installed inthe aircraft. This depends on the differentmodifications embodied in the aircraft.
3 Remove these items as shown in Figure 1 , Sheet 3 , DetailB :
4 Remove these items as shown in Figure 1 , Sheet 4 , DetailC :
5 Remove these items as shown in Figure 1 , Sheet 5 , DetailD :
6 Temporarily secure the conduit as shown in Figure 1 , Sheet5 , Detail D.
7 Remove these items as shown in Figure 1 , Sheet 6 , DetailE :
8 Remove these items as shown in Figure 1 , Sheet 7 , DetailF :
9 Remove these items as shown in Figure 1 , Sheet 8 , DetailG :
10 Remove these items as shown in Figure 1 , Sheet 1 , DetailH :
11 Install these items as shown in Figure 1 , Sheet 2 , DetailH :
12 Remove the receptacle identification sleeves 38VC, 40VC and5006VC and the protection conduits, item (10), from theelectrical wires of routes 2M and 2S.
4 Put the wires of routes 2M and 2S through the separateconduits according to the routes, refer to para.3.B.(1)(a)2.
5 Install the conduits, item 9 and item 10, with the wires ofthe routes 2S and 2M and conduit with the wires to 2212VCand to the pylon for the new routing, as shown in Figure 1, Sheet 2 , Detail A.
6 For the wire routing use :
7 Install these items as shown in Figure 1 , Sheet 3 , DetailB :
8 Install these items as shown in Figure 1 , Sheet 4 , DetailC :
9 Install the conduit and these items as shown in Figure 1 ,Sheet 5 , Detail D :
10 cable tie NSA935401-0315 cable tie NSA935401-04
If operational documentation is affected (see Paragraph 1.K of this SB): Ifinformation is needed prior to next normal revision or prior to SB embodiment,please indicate required service(s):Either: Advance Data . . . . . . . . . . . . . . . . . . . . . YES/NOOr : Intermediate/Temporary revision. . . . . . . . . . . . YES/NO
Important Information: This SB will only be incorporated in your maintenance andoperational documentation if this sheet is returned to Airbus and signed by aduly authorised representative. With the next feasible revision, this willresult in
- updating of maintenance documentation to show pre and post SB data.- updating of maintenance and operational documentation to show post SB dataafter embodiment.
If this SB requires previous or simultaneous accomplishment of other SBs,Airbus shall automatically include them in the manual revisions. Refer to SIL00-037 for detailed information.
Please return this completed sheet to:
AIRBUS CUSTOMER SERVICES DIRECTORATE 1 Rond Point Maurice Bellonte 31707 BLAGNAC CEDEX FRANCE
Attn: SDC32 Technical Data and Documentation Services FAX: (+33) 5 61 93 28 06 or via your Resident Customer Support Office.
Alternatively, SB lists via letters or fax are also accepted.
@ A310SERVICE BULLETIN
QUALITY PERCEPTION FORM
6 DATE : Dec 03/99 SERVICE BULLETIN No. : A310—28—2140
Use this form to tell us what is your perception of the quality of this ServiceBulletin. The reported data that you provide us will be used to analyse areas ofdifficulties and to take corrective action to further improve the quality of ourService Bulletins.We thank you for the time you have taken in completing this form.
(Please rate on a scale of 1 to 4, with 4 being the highest score)
- Quality rating of this SB 4 3 2 1
- Quality rating of the Accomplishment Instructions 4 3 2 1
- Quality rating of the Illustrations 4 3 2 1
- Is this SB easy to understand ? Y / N
If you have had difficulties in the accomplishment of this SB please quote belowthe area(s) and give a short description of the issue.
Planning Material Instructions
X Effectivity X Kit content X PreparationX Reason X List of Materials X Mod/InspectionX Manpower Operator Supplied X TestX References X Re-identification X Close-UpX Publication X Tooling X Illustrations
Comments :
Operator : Date:
Name/Title :
Please return this form to :
AIRBUSCUSTOMER SERVICES DIRECTORATE1 Rond Point Maurice Bellonte31707 BLAGNACAttn : SET1 Service Bulletins ManagementFAX : (33) 5 61 93 42 51