    Site Acceptance Test(SAT)

    CWI147_SAT_REV0_PWS & LOOP CONTROL

    Project no.: CWI 147 Revision: R0

    TERAPIA-RANBAXY Page 1 of 23

    Author

    Title Name Company Sign / Date

    Validation engineer Mr.Abhijit Thete

    Firstname Lastname

    Christ Nishotech

    Approved by

    Title Name Company Sign / Date

    Project Manager Mr.Yogesh Bendre

    Firstname Lastname

    Christ Nishotech

    Project leader Mr.Bhavik Bhatti

    Firstname Lastname

    Christ Nishotech

    Project leader

    Firstname Lastname

    TERAPIA-RANBAXI

    QA

    Firstname Lastname

    TERAPIA-RANBAXI

    Revision history

    Revision Change Date Initials

    0 First issue 12.03.07 MC

  • 7/30/2019 SAT-S & D System

    2/23

    Site Acceptance Test(SAT)

    CWI147_SAT_REV0_PWS & LOOP CONTROL

    Project no.: CWI 147 Revision: R0

    TERAPIA-RANBAXY Page 2 of 23

    CONTENTS

    1.0 SAT Plan................................................................................................................31.1 Introduction.................................................................................................................31.2 Abbreviation................................................................................................................31.3 Purpose of the tests................................................................................................... 31.4 Object Description......................................................................................................31.5 Performance................................................................................................................3

    1.5.1 Responsibilities......................................................................................................31.5.2 Good Testing Practice...........................................................................................41.5.3 How to fill in the tests /inspections.........................................................................41.5.4 Deviation handling.................................................................................................5

    1.6 Acceptance criteria.....................................................................................................51.7 SAT Results................................................................................................................ 5

    2.0 Tests.......................................................................................................................52.1 Mechanical & Documentation Inspection.................................................................6

    2.1.1 P&ID...................................................................................................................... 62.1.2 Components..........................................................................................................72.1.3 Air gap to drain...................................................................................................... 8

    2.2 Hardware Acceptance Tests (IQ)...............................................................................92.2.1 Main Switch........................................................................................................... 92.2.2 Hardware operating environment.........................................................................10

    2.3 System Acceptance Tests (OQ)...............................................................................112.3.1 Software Version................................................................................................. 112.3.2 Back-up............................................................................................................... 12

    2.4 Operation tests (OQ)................................................................................................ 132.4.1 Leak Test.............................................................................................................132.4.2 Operation of UV 301.1.1......................................................................................142.4.2 Operation of UV 301.1.2......................................................................................152.4.3 Operation, Purified water system in normal mode................................................162.4.4 Sanitisation PW storage & loop control................................................................17

    2.4.5 System Parameters.............................................................................................182.4.6 Water Quality.......................................................................................................192.4.7 Deviation list........................................................................................................ 20

    ........................................................................................................................................ 22

    3.0 SAT Report..........................................................................................................223.1 Purpose of the report...............................................................................................223.2 Deviations................................................................................................................. 223.3 Retests.......................................................................................................................223.4Final Approval............................................................................................................23

    Handover of the water treatment system...............................................................23

  • 7/30/2019 SAT-S & D System

    3/23

    Site Acceptance Test(SAT)

    CWI147_SAT_REV0_PWS & LOOP CONTROL

    Project no.: CWI 147 Revision: R0

    TERAPIA-RANBAXY Page 3 of 23

    1.0 SAT Plan

    1.1 Introduction

    The SAT for Purified water Storage & loop control system shall show that the system is installed andoperates in accordance with the design specifications. The SAT is divided into four test sections:

    Mechanical & Documentation Inspections (IQ).

    Hardware Acceptance Tests (IQ)

    Software Acceptance Tests (OQ)

    Operation Test (OQ)

    1.2 Abbreviation

    GTP Good Testing PracticeIQ Installation QualificationN/A Not ApplicableOQ Operation QualificationP&ID Process & Instrumentation DiagramSAT Site Acceptance Test

    PWS Purified Water System

    1.3 Purpose of the tests

    To test, inspect and show that the PW storage & loop control system is installed correctly accordingto design specifications.

    1.4 Object Description

    Product : Purified water Storage & loop control system.Function : Storage & Distribution of Purified water.Manufacturer : Christ Nishotech Water Systems Pvt. Ltd.Project no. : CWI 147

    Year of manufacture : 2007

    1.5 Performance

    The tester shall first read this SAT Plan section, then perform the tests and finally fill in the Report inthe end of this document. The performance of the specific Site Acceptance Tests is described foreach test in the test sheets.

    1.5.1 ResponsibilitiesThe person who performs the tests (Tester) is responsible for the execution of the tests. The testerconfirms with his/her initials that the test is performed correctly. A second person, (witness) checks if

  • 7/30/2019 SAT-S & D System

    4/23

    Site Acceptance Test(SAT)

    CWI147_SAT_REV0_PWS & LOOP CONTROL

    Project no.: CWI 147 Revision: R0

    TERAPIA-RANBAXY Page 4 of 23

    the test was correctly performed and that the result was in accordance with the acceptance criteria

    and if not, that a deviation report is filled in.

    1.5.2 Good Testing Practice

    A (archive resistance) blue pen shall be used for the SAT tests and for approvals. For the correctionsin the attached design documents (such as the P&ID or the circuit diagram) a red pen will be used.Correction fluid and other correction techniques that obscure the original entry should not be used.Spelling mistakes and other changes shall be corrected as follows:

    Ex) Installation 20/01/04 Initials

    Deviations are recorded and traceable. Fields in a test, that are not filled out, shall be clearly markedas N/A (not applicable).Attachments such as P&ID and component list shall be marked with the name of the SAT test, anddate and initials of the tester. This shall be written on the front page.

    Ex) Attachment to SAT 2.1.2 P&ID 20/01/04 Initials

    When the SAT is performed are the documents reviewed for correctness and completeness before

    the SAT Report section is filled in.

    1.5.3 How to fill in the tests /inspections

    Inspection name

    Inspection procedure

    Needed document(s) / equipment

    Acceptance criteria

    OK / Deviation no

    1)Date

    2)

    Initials

    3)

    Witnessed by

    4)

    1) The acceptance criteria is specified in this square and if values are to be recorded there will alsobe a result table here. Fill then in the actual value and Pass or Fail.

    Description Required value Actual value Result (Pass /Fail)

    Ex) Temperature atTT270.6.3

    > 80C

  • 7/30/2019 SAT-S & D System

    5/23

    Site Acceptance Test(SAT)

    CWI147_SAT_REV0_PWS & LOOP CONTROL

    Project no.: CWI 147 Revision: R0

    TERAPIA-RANBAXY Page 5 of 23

    2) If the acceptance criteria is fulfilled Pass is written in this square. If not, Fail and deviation

    number(s) are written, and a deviation report is filled in. (See deviation handling)3) Comment. This field are used for instance for explanation, or relevant information. For deviations,

    a deviation report will be filled in.

    4) Date of the execution of the test /inspection and initials of the tester.

    5) To be signed by the customer if present during the SAT. Otherwise N/A will be written.

    1.5.4 Deviation handling

    A Deviation report regarding SAT is filled in if the result of a test is not according to the acceptancecriteria. It could be more than one deviation report per test, and then all numbers have to be filled in,on the test sheet.

    1.6 Acceptance criteria

    The acceptance criteria for each Site Acceptance Test are specified in the test sheets.

    1.7 SAT Results

    The result of the SAT will be concluded in the SAT Report section.

    2.0 Tests

    Signature list for test /inspection personnel

    Company Name

    (readable in block letters)

    Signature / Date

    Christ Nishotech

    Christ Nishotech

    TERAPIA-RANBAXI

    TERAPIA-RANBAXI

    Attachments to this Site acceptance test

    (To be filled in on the day for SAT start)

    P&ID no. And revision:

    Component List, revision:

    Circuit diagram, revision:

  • 7/30/2019 SAT-S & D System

    6/23

    Site Acceptance Test(SAT)

    CWI147_SAT_REV0_PWS & LOOP CONTROL

    Project no.: CWI 147 Revision: R0

    TERAPIA-RANBAXY Page 6 of 23

    Control Logics, revisions:

    2.1 Mechanical & Documentation Inspection

    Name of test

    2.1.1 P&ID

    Test procedure

    Check that the Purified Water System is built according to the P&ID and that the items are marked with

    the correct P&ID numbers.

    Write, Pass at the valve /instrument /component on the P&ID if both criteria are fulfilled. If not writeFail and the deviation number in the drawing.

    Sign & date the P&ID.

    Attach the used P&ID to this document.

    Parts inspected during FAT will not be re-inspected. If all items are already checked during FAT, writeN/A in the sections below.

    Needed document(s) / equipment

    The P&ID

    Acceptance criteria

    All valves, instruments and components shall be located according to the P&ID and be marked with thecorrect P&ID number.

    Pass /Fail + Deviation no.

    Comment

    Tester, Date /Initials

    Witness, Date /Initials

  • 7/30/2019 SAT-S & D System

    7/23

    Site Acceptance Test(SAT)

    CWI147_SAT_REV0_PWS & LOOP CONTROL

    Project no.: CWI 147 Revision: R0

    TERAPIA-RANBAXY Page 7 of 23

    Name of test

    2.1.2 Components

    Test procedure

    Check that valves, instruments and components in the Component List are in accordance with the

    description in the List.

    Write, Pass at the valve /instrument /component in the list, if the item is in compliance with thespecifications. If not write Fail and the deviation number in the list.

    Sign & date in the bottom of each page.

    Attach the used Component List to this document.

    Needed document(s) / equipment

    Component List

    Acceptance criteria

    All valves, instruments and components shall be in accordance with the specifications in the ComponentList.

    Pass /Fail + Deviation no.

    Comment

    Tester, Date /Initials

  • 7/30/2019 SAT-S & D System

    8/23

    Site Acceptance Test(SAT)

    CWI147_SAT_REV0_PWS & LOOP CONTROL

    Project no.: CWI 147 Revision: R0

    TERAPIA-RANBAXY Page 8 of 23

    Witness, Date /Initials

    Name of test

    2.1.3 Air gap to drain

    Test procedure

    Check by visual inspection that the pipe to drain leaves an air gap to the drainage

    Needed document(s) / equipment

    Measuring device.

    Acceptance criteria

    There shall be an open outlet from the drain pipe to the drain system that is > 5cm

    Pass /Fail + Deviation no.

    Comment

    Tester, Date /Initials

  • 7/30/2019 SAT-S & D System

    9/23

    Site Acceptance Test(SAT)

    CWI147_SAT_REV0_PWS & LOOP CONTROL

    Project no.: CWI 147 Revision: R0

    TERAPIA-RANBAXY Page 9 of 23

    Witness, Date /Initials

    2.2 Hardware Acceptance Tests (IQ)

    Name of test

    2.2.1 Main Switch

    Test procedure

    Check that the system turns on in step ready when the main switch has been set to OFF and thenON again.

    Needed document(s) / equipment

    The Functional Logics, Section special logic.

    Acceptance criteria

    The system shall start up in step 1 ready.

    Pass /Fail + Deviation no.

    Comment

    Tester, Date /Initials

    Witness, Date /Initials

  • 7/30/2019 SAT-S & D System

    10/23

    Site Acceptance Test(SAT)

    CWI147_SAT_REV0_PWS & LOOP CONTROL

    Project no.: CWI 147 Revision: R0

    TERAPIA-RANBAXY Page 10 of 23

    Name of test

    2.2.2 Hardware operating environment

    Test procedure

    Measure the temperature in the Control cabinet. The temperature for the control cabinet equipment shallnot exceed 40C.

    Needed document(s) / equipment

    Temperature instrument.

    Acceptance criteria

    For control cabinets without built in ventilation shall the temperature inside the control cabinet notexceed 40C.

    Pass /Fail + Deviation no.

    Comment

    Tester, Date /Initials

    Witness, Date /Initials

  • 7/30/2019 SAT-S & D System

    11/23

    Site Acceptance Test(SAT)

    CWI147_SAT_REV0_PWS & LOOP CONTROL

    Project no.: CWI 147 Revision: R0

    TERAPIA-RANBAXY Page 11 of 23

    2.3 System Acceptance Tests (OQ)

    Name of test

    2.3.1 Software Version

    Test procedure

    Check the version of the HMI shown in the system menu.Write the version of the HMI:HMI version at SAT:

    Needed document(s) / equipment

    HMI & Programming tools

    Acceptance criteria

    The version of the HMI shall be written above in the Test procedure square.

    Pass /Fail + Deviation no.

    Comment

    Tester, Date /Initials

  • 7/30/2019 SAT-S & D System

    12/23

    Site Acceptance Test(SAT)

    CWI147_SAT_REV0_PWS & LOOP CONTROL

    Project no.: CWI 147 Revision: R0

    TERAPIA-RANBAXY Page 12 of 23

    Witness, Date /Initials

    Name of test

    2.3.2 Back-up

    Test procedure

    Make a comparison of the version of the loaded software for HMI, and the program version of theBack-up disc or CD-Rom.

    Check that the back-up disc is marked correctly with version and date.

    Needed document(s) / equipment

    Back-up disc (or CD-Rom), the downloaded program, programming software and lap-top.

    Acceptance criteria

    There shall not be any differences in code between the HMI program on the floppy disk and CPU.Parameters could differ.The disc /CD-Rom shall be marked with the correct version and date.

    Pass /Fail + Deviation no.

    Comment

    Tester, Date /Initials

    Witness, Date /Initials

  • 7/30/2019 SAT-S & D System

    13/23

    Site Acceptance Test(SAT)

    CWI147_SAT_REV0_PWS & LOOP CONTROL

    Project no.: CWI 147 Revision: R0

    TERAPIA-RANBAXY Page 13 of 23

    2.4 Operation tests (OQ)

    Name of test

    2.4.1 Leak Test

    Test procedure

    Put the Purified Water System into Normal (Auto) mode.During operation, the operating pressure is present at the following components:

    1. UV2. Storage Tank3. Pump

    Let the system run for 1hour.Check the plant connections and the components by visual inspection.

    Needed document(s) / equipment

    N/A

    Acceptance criteria

    No leaks shall be present in the system.

    Pass /Fail + Deviation no.

    Comment

  • 7/30/2019 SAT-S & D System

    14/23

    Site Acceptance Test(SAT)

    CWI147_SAT_REV0_PWS & LOOP CONTROL

    Project no.: CWI 147 Revision: R0

    TERAPIA-RANBAXY Page 14 of 23

    Tester, Date /Initials

    Witness, Date /Initials

    Name of test

    2.4.2 Operation of UV 301.1.1

    Test procedure

    Check that the plant is in the operation step.

    1 During operation check working of hour meter2 During operation check working of intensity meter3 Check operation of UV as per control logic.

    Needed document(s) / equipment

    Control logic.

    Acceptance criteria

    1. Hour meter indicate working hours.

    2. Intensity >= 1.6 milliwatt/cm2

    Pass /Fail + Deviation no.

    Comment

  • 7/30/2019 SAT-S & D System

    15/23

    Site Acceptance Test(SAT)

    CWI147_SAT_REV0_PWS & LOOP CONTROL

    Project no.: CWI 147 Revision: R0

    TERAPIA-RANBAXY Page 15 of 23

    Tester, Date /Initials

    Witness, Date /Initials

    Name of test

    2.4.2 Operation of UV 301.1.2

    Test procedure

    Check that the plant is in the operation step.

    4 During operation check working of hour meter5 During operation check working of intensity meter6 Check operation of UV as per control logic.

    Needed document(s) / equipment

    Control logic.

    Acceptance criteria

    3. Hour meter indicate working hours.

    4. Intensity >= 1.6 milliwatt/cm2

    Pass /Fail + Deviation no.

    Comment

  • 7/30/2019 SAT-S & D System

    16/23

    Site Acceptance Test(SAT)

    CWI147_SAT_REV0_PWS & LOOP CONTROL

    Project no.: CWI 147 Revision: R0

    TERAPIA-RANBAXY Page 16 of 23

    Tester, Date /Initials

    Witness, Date /Initials

    Name of test

    2.4.3 Operation, Purified water system in normal mode

    Test procedure

    1. Check the operation of PW System in normal auto mode.

    Needed document(s) / equipment

    Operating manuals, Control logic.

    Acceptance criteriaSystem is operating as per the steps mentioned in control logic.

    Pass /Fail + Deviation no.

    Comment

  • 7/30/2019 SAT-S & D System

    17/23

    Site Acceptance Test(SAT)

    CWI147_SAT_REV0_PWS & LOOP CONTROL

    Project no.: CWI 147 Revision: R0

    TERAPIA-RANBAXY Page 17 of 23

    Tester, Date /Initials

    Witness, Date /Initials

    Name of test

    2.4.4 Sanitisation PW storage & loop control

    Test procedure

    Check that the program steps are executed as described in the Functional description. Carry out theSanitisation as specified in the Operating Instructions.Check that the necessary sanitising temperature is reached and maintained for the entire period.

    Check that the necessary sanitising temperature is reached and maintained by saving the temperaturelogs printout from the recorder.If there is no recorder for the system, check the temperature value for TE 301.1.5 in the HMI and recordthe result in the table below. Start the counting when the temperature is reached and measure during6 0 minutes.

    Needed document(s) / equipment

    S & D operating instruction, section Sanitisation. The Functional Logics

    Acceptance criteria

  • 7/30/2019 SAT-S & D System

    18/23

    Site Acceptance Test(SAT)

    CWI147_SAT_REV0_PWS & LOOP CONTROL

    Project no.: CWI 147 Revision: R0

    TERAPIA-RANBAXY Page 18 of 23

    Description Required

    value

    Actual value Result (Pass / Fail)

    The Sanitisation shall proceed acc to theFunctional Logics

    N/A N/A

    Temperature at TE 301.1.5 at start 80C

    Temperature at TE 301.1.5 after 10 min 80C

    Temperature at TE 301.1.5 after 20 min 80C

    Temperature at TE 301.1.5 after 30 min 80C

    Temperature at TE 301.1.5 after 40 min 80C

    Temperature at TE 301.1.5 after 50 min 80C

    Temperature at TE 301.1.5 after 60 min 80C

    Pass / Fail + Deviation nos

    Comment

    Tester, Date / Initials

    Witness, Date / Initials

    Name of test

    2.4.5 System Parameters

    Test procedure

    Run the system in operation mode.

    Fill in the Instrumentation list for all parameters and set points.

    Needed document(s) / equipment

    The Instrumentation List (Functional Logic)

    Acceptance criteria

    Pass /Fail + Deviation no.

  • 7/30/2019 SAT-S & D System

    19/23

    Site Acceptance Test(SAT)

    CWI147_SAT_REV0_PWS & LOOP CONTROL

    Project no.: CWI 147 Revision: R0

    TERAPIA-RANBAXY Page 19 of 23

    Comment

    Tester, Date /Initials

    Witness, Date /Initials

    Name of test

    2.4.6 Water Quality

    Test procedure

    Check the conductivity at V301.1.18Check the TOC value at sample V301.1.18 (analysis by customer)Check the microbiological situation at sample V301.1.18 (analysis by customer)

    Needed document(s) / equipment

    N/A

    Acceptance criteria

    Description Required Actual Result (Pass /Fail)

    Conductivity 1.3 s/cm @25C

  • 7/30/2019 SAT-S & D System

    20/23

    Site Acceptance Test(SAT)

    CWI147_SAT_REV0_PWS & LOOP CONTROL

    Project no.: CWI 147 Revision: R0

    TERAPIA-RANBAXY Page 20 of 23

    TOC

  • 7/30/2019 SAT-S & D System

    21/23

    Site Acceptance Test(SAT)

    CWI147_SAT_REV0_PWS & LOOP CONTROL

    Project no.: CWI 147 Revision: R0

    TERAPIA-RANBAXY Page 21 of 23

  • 7/30/2019 SAT-S & D System

    22/23

    Site Acceptance Test(SAT)

    CWI147_SAT_REV0_PWS & LOOP CONTROL

    Project no.: CWI 147 Revision: R0

    TERAPIA-RANBAXY Page 22 of 23

    3.0 SAT Report

    3.1 Purpose of the report

    To conclude the performed Site Acceptance Test of the PW storage & loop control system system.

    3.2 Deviations

    The deviations shall be measured until, Date: _______

    Deviation summary

    Total amount of attached deviations:

    3.3 Retests

    All tests shall be completed at end of SAT.

    No. Test name Test Completed

    2.1 Mechanical & Documentation inspections (IQ) (Yes /No)2.1.1 P&ID

    2.1.2 Components

    2.1.3 Air gap to drain

    2.2 Hardware Acceptance Tests (IQ)

    2.2.1 Main switch

    2.2.2 Hardware, operating environment

    2.3 System Acceptance Tests (OQ)

    2.3.1 Software version

    2.3.2 Back-up

    2.4 Operation tests (OQ)

    2.4.1 Leak test

    2.4.2 Operation of UV

    2.4.3 Operation of Purified water system in normal mode2.4.4 Sanitization PW storage & loop control

    2.4.5 System Parameters

    2.4.6 Water Quality

    2.4.7 Deviation list

  • 7/30/2019 SAT-S & D System

    23/23

    Site Acceptance Test(SAT)

    CWI147_SAT_REV0_PWS & LOOP CONTROL

    Project no.: CWI 147 Revision: R0

    TERAPIA-RANBAXY Page 23 of 23

    3.4 Final Approval

    To be signed by SAT participants.

    The unit is approved for Operation

    Title Name Company Sign / Date

    Christ Nishotech

    Christ Nishotech

    TERAPIA-RANBAXI

    TERAPIA-RANBAXI

    Handover of the water treatment system

    To be signed by the SAT participants.

    The system is approved for hand-over.

    Title Name Company Sign / Date

    CHRIST-NISHOTECH

    CHRIST-NISHOTECH

    TERAPIA-RANBAXI

    TERAPIA-RANBAXI