HALLIBURTON PROJECT MANAGEMENT
Project : SARULLA GEOTHERMAL DRILLING PROJECT
Client : SARULLA OPERATION LIMITED
Subcontractor : DYFCO
Planned Actual
1 ALL HAL-HPM-SOL-14-DB-001 CIVIL DESIGN BASIS
2 ALL HAL-HPM-SOL-14-STD-001 DESIGN CODE AND STANDARD FOR CIVIL WORKS
3 ALL HAL-HPM-SOL-14-SPC-001 CONCRETE SITE MIX DESIGN & SPECIFICATION
Sub Total
1 NIL 2 HAL-HPM-SOL-14-CALC-001 CALCULATION FOR WELLPAD & CELLAR CONCRETE IN NIL-2 AREA
2 NIL 2 HAL-HPM-SOL-14-CALC-002 CALCULATION FOR SUMP PIT
3 NIL 2 HAL-HPM-SOL-14-CALC-003 CALCULATION FOR WAREHOUSE
4 NIL 2 HAL-HPM-SOL-14-CALC-004 CALCULATION FOR AIR DRILLING UNIT FOUNDATION IN NIL-2 AREA Change design, N/A
5 NIL 2 HAL-HPM-SOL-14-CALC-005 CALCULATION FOR CEMENTING AREA FOUNDATION IN NIL-2 AREA Change design, N/A
6 NIL 2 HAL-HPM-SOL-14-CALC-006 CALCULATION FOR MUD MATERIAL STOCK FOUNDATION IN NIL-2 AREA Storage Only, Not Required Calculation
7 NIL 2 HAL-HPM-SOL-14-CALC-007 CALCULATION FOR RESERVE TANK & ACTIVE TANK FOUNDATION IN NIL-2 AREA Out Of Scope Dyfco
8 NIL 2 HAL-HPM-SOL-14-CALC-008 CALCULATION FOR SHACKER TANK FOUNDATION IN NIL-2 AREA Out Of Scope Dyfco
9 NIL 2 HAL-HPM-SOL-14-CALC-009 CALCULATION FOR FUEL TANK-1 & 2 FOUNDATION IN NIL-2 AREA Out Of Scope Dyfco
10 NIL 2 HAL-HPM-SOL-14-CALC-010 CALCULATION FOR SCR UNIT FOUNDATION IN NIL-2 AREA Out Of Scope Dyfco
11 NIL 2 HAL-HPM-SOL-14-CALC-011 CALCULATION FOR GENERATOR-1, 2 & 3 FOUNDATION IN NIL-2 AREA Out Of Scope Dyfco
12 NIL 2 HAL-HPM-SOL-14-CALC-012 CALCULATION FOR MUD PUMP-1, 2 & 3 FOUNDATION IN NIL-2 AREA Out Of Scope Dyfco
13 NIL 2 HAL-HPM-SOL-14-CALC-013 CALCULATION FOR BRINE PUMP FOUNDATION IN NIL-2 AREA Out Of Scope Dyfco
14 WJR 2 HAL-HPM-SOL-14-CALC-014 CALCULATION FOR WELLPAD & CELLAR CONCRETE IN WJR-2 AREA
15 WJR 2 HAL-HPM-SOL-14-CALC-015 CALCULATION FOR SUMP PIT
16 WJR 2 HAL-HPM-SOL-14-CALC-016 CALCULATION FOR AIR DRILLING UNIT FOUNDATION IN WJR-2 AREA Change design, N/A
17 WJR 2 HAL-HPM-SOL-14-CALC-017 CALCULATION FOR CEMENTING AREA FOUNDATION IN WJR-2 AREA Change design, N/A
18 WJR 2 HAL-HPM-SOL-14-CALC-018 CALCULATION FOR MUD MATERIAL STOCK FOUNDATION IN WJR-2 AREA Storage Only, Not Required Calculation
19 WJR 2 HAL-HPM-SOL-14-CALC-019 CALCULATION FOR INTERMEDIATE TANK & ACTIVE TANK FOUNDATION IN WJR-2 AREA Out Of Scope Dyfco
20 WJR 2 HAL-HPM-SOL-14-CALC-020 CALCULATION FOR SHACKER TANK FOUNDATION IN WJR-2 AREA Out Of Scope Dyfco
21 WJR 2 HAL-HPM-SOL-14-CALC-021 CALCULATION FOR FUEL TANK-1 FOUNDATION IN WJR-2 AREA Out Of Scope Dyfco
22 WJR 2 HAL-HPM-SOL-14-CALC-022 CALCULATION FOR SCR UNIT FOUNDATION IN WJR-2 AREA Out Of Scope Dyfco
23 WJR 2 HAL-HPM-SOL-14-CALC-023 CALCULATION FOR GENERATOR-1, 2 & 3 FOUNDATION IN WJR-2 AREA Out Of Scope Dyfco
24 WJR 2 HAL-HPM-SOL-14-CALC-024 CALCULATION FOR MUD PUMP-1, 2 & 3 FOUNDATION IN WJR-2 AREA Out Of Scope Dyfco
25 WJR 2 HAL-HPM-SOL-14-CALC-025 CALCULATION FOR BRINE PUMP FOUNDATION IN WJR-2 AREA Out Of Scope Dyfco
26 NIL 1 HAL-HPM-SOL-14-CALC-026 CALCULATION FOR WELLPAD & CELLAR CONCRETE IN NIL-1 AREA
27 NIL 1 HAL-HPM-SOL-14-CALC-027 CALCULATION FOR SUMP PIT
28 NIL 1 HAL-HPM-SOL-14-CALC-028 CALCULATION FOR AIR DRILLING UNIT FOUNDATION IN NIL-1 AREA
29 NIL 1 HAL-HPM-SOL-14-CALC-029 CALCULATION FOR CEMENTING AREA FOUNDATION IN NIL-1 AREA
30 NIL 1 HAL-HPM-SOL-14-CALC-030 CALCULATION FOR WATER TANK FOUNDATION FOR NIL-1 AREA Out Of Scope Dyfco
31 NIL 1 HAL-HPM-SOL-14-CALC-031 CALCULATION FOR RESERVE TANK FOUNDATION IN NIL-1 AREA Out Of Scope Dyfco
CALCULATION
SOL
SPECIFICATION
CIVIL DELIVERABLE LIST
No Area No. Drawing TITLE
Issued for Approval
Remarks
Sarulla Project - Civil Deliverablelist Dyfco - 30 June 2014- review Dyfco (1).xlsx Page 1 of 4
HALLIBURTON PROJECT MANAGEMENT
Project : SARULLA GEOTHERMAL DRILLING PROJECT
Client : SARULLA OPERATION LIMITED
Subcontractor : DYFCO
Planned Actual
SOL
CIVIL DELIVERABLE LIST
No Area No. Drawing TITLE
Issued for Approval
Remarks
32 NIL 1 HAL-HPM-SOL-14-CALC-032 CALCULATION FOR FUEL TANK FOUNDATION IN NIL-1 AREA Out Of Scope Dyfco
33 NIL 1 HAL-HPM-SOL-14-CALC-033 CALCULATION FOR ACTIVE TANK FOUNDATION IN NIL-1 AREA Out Of Scope Dyfco
34 NIL 1 HAL-HPM-SOL-14-CALC-034 CALCULATION FOR SHACKER TANK FOUNDATION IN NIL-1 AREA Out Of Scope Dyfco
35 NIL 1 HAL-HPM-SOL-14-CALC-035 CALCULATION FOR COOLING TOWER FOUNDATION IN NIL-1 AREA Out Of Scope Dyfco
36 NIL 1 HAL-HPM-SOL-14-CALC-036 CALCULATION FOR SCR UNIT FOUNDATION FOR NIL-1 AREA Out Of Scope Dyfco
37 NIL 1 HAL-HPM-SOL-14-CALC-037 CALCULATION FOR MUD PUMP-1 FOUNDATION IN NIL-1 AREA Out Of Scope Dyfco
38 NIL 1 HAL-HPM-SOL-14-CALC-038 CALCULATION FOR MUD PUMP-2 FOUNDATION IN NIL-1 AREA Out Of Scope Dyfco
39 NIL 1 HAL-HPM-SOL-14-CALC-039 CALCULATION FOR MUD PUMP-3 FOUNDATION IN NIL-1 AREA Out Of Scope Dyfco
40 NIL 1 HAL-HPM-SOL-14-CALC-040 CALCULATION FOR MUD MATERIAL STOCK FOUNDATION IN NIL-1 AREA Storage Only, Not Required Calculation
41 NIL 1 HAL-HPM-SOL-14-CALC-041 CALCULATION FOR BRINE PUMP FOUNDATION IN NIL-1 AREA Out Of Scope Dyfco
Sub Total
1 ALL HAL-HPM-SOL-14-STD-DWG-001 STANDARD DRAWING LIST
2 ALL HAL-HPM-SOL-14-STD-DWG-002 STANDARD DRAWING GENERAL NOTES FOR CIVIL AND STRUCTURE
3 ALL HAL-HPM-SOL-14-STD-DWG-003 STANDARD DRAWING FOR TYPICAL SHALLOW FOUNDATION
4 ALL HAL-HPM-SOL-14-STD-DWG-004 STANDARD DRAWING FOR TYPICAL PIPERACK Out Of Scope Dyfco
5 ALL HAL-HPM-SOL-14-STD-DWG-005 STANDARD DRAWING MEMBER DESIGNATION FOR STEEL STRUCTURE
6 ALL HAL-HPM-SOL-14-STD-DWG-006 STANDARD DRAWING STEEL CONNECTION
7 ALL HAL-HPM-SOL-14-STD-DWG-007 STANDARD DRAWING FOR WELDING DETAILS
8 ALL HAL-HPM-SOL-14-STD-DWG-008 STANDARD DRAWING ANCHOR BOLTS
9 ALL HAL-HPM-SOL-14-STD-DWG-009 STANDARD DRAWING REBAR ARRANGEMENTS
10 ALL HAL-HPM-SOL-14-STD-DWG-010 STANDARD DRAWING SAFETY FENCE
Sub Total
1 NIL 2 HAL-HPM-SOL-14-DWG-001 DRAWING LIST
2 NIL 2 HAL-HPM-SOL-14-DWG-002 LAYOUT, PLAN & VIEW OF FUEL STORAGE SHELTER IN NIL-2 AREA Out Of Scope Dyfco
3 NIL 2 HAL-HPM-SOL-14-DWG-003 PLAN, VIEW & DETAIL OF MOBILE STORAGE SHELTER IN NIL-2 AREA Out Of Scope Dyfco
4 NIL 2 HAL-HPM-SOL-14-DWG-004 PLAN, VIEW & DETAIL OF TEMPORARY TOILET IN NIL-2 AREA
5 NIL 2 HAL-HPM-SOL-14-DWG-005 LAYOUT FOR TEMPORARY FACILITIES IN NIL-2 AREA Out Of Scope Dyfco
6 NIL 2 HAL-HPM-SOL-14-DWG-006 LAY OUT FOR SAFETY FENCE IN NIL-2 AREA
7 NIL 2 HAL-HPM-SOL-14-DWG-007 LAYOUT FOR DRILLING WELLPAD & FACILITIES IN NIL-2 AREA
8 NIL 2 HAL-HPM-SOL-14-DWG-008 PLAN & SECTION OF MUD PIT IN NIL-2 AREA
9 NIL 2 HAL-HPM-SOL-14-DWG-009 PLAN & SECTION OF WATER PIT IN NIL-2 AREA
10 NIL 2 HAL-HPM-SOL-14-DWG-010 PLAN & SECTION OF PRODUCTION TEST PIT IN NIL-2 AREA
11 NIL 2 HAL-HPM-SOL-14-DWG-011 PLAN, VIEW & SECTION OF AIR DRILLING UNIT FOUNDATION IN NIL-2 AREA
12 NIL 2 HAL-HPM-SOL-14-DWG-012 PLAN, VIEW & SECTION OF CEMENTING AREA FOUNDATION IN NIL-2 AREA
13 NIL 2 HAL-HPM-SOL-14-DWG-013 RIG PAD IN WELLPAD NIL 2 PLAN, SECTION AND DETAIL
STANDARD DRAWING
DRAWING
Sarulla Project - Civil Deliverablelist Dyfco - 30 June 2014- review Dyfco (1).xlsx Page 2 of 4
HALLIBURTON PROJECT MANAGEMENT
Project : SARULLA GEOTHERMAL DRILLING PROJECT
Client : SARULLA OPERATION LIMITED
Subcontractor : DYFCO
Planned Actual
SOL
CIVIL DELIVERABLE LIST
No Area No. Drawing TITLE
Issued for Approval
Remarks
14 NIL 2 HAL-HPM-SOL-14-DWG-014 CELLAR IN WELLPAD NIL 2 PLAN SECTION AND DETAIL
15 NIL 2 HAL-HPM-SOL-14-DWG-015 DRAINAGE IN CELLAR WELLPAD NIL 2 PLAN, SECTION AND DETAIL
16 NIL 2 HAL-HPM-SOL-14-DWG-016 PLAN, VIEW & SECTION OF MUD MATERIAL STOCK FOUNDATION IN NIL-2 AREA
17 NIL 2 HAL-HPM-SOL-14-DWG-017 PLAN, VIEW & SECTION OF RESERVE TANK & ACTIVE TANK FOUNDATION IN NIL-2 AREA Out Of Scope Dyfco
18 NIL 2 HAL-HPM-SOL-14-DWG-018 PLAN, VIEW & SECTION OF SHACKER TANK FOUNDATION IN NIL-2 AREA Out Of Scope Dyfco
19 NIL 2 HAL-HPM-SOL-14-DWG-019 PLAN, VIEW & SECTION OF FUEL TANK-1 & 2 FOUNDATION IN NIL-2 AREA Out Of Scope Dyfco
20 NIL 2 HAL-HPM-SOL-14-DWG-020 PLAN, VIEW & SECTION OF SCR UNIT FOUNDATION IN NIL-2 AREA Out Of Scope Dyfco
21 NIL 2 HAL-HPM-SOL-14-DWG-021 PLAN, VIEW & SECTION OF GENERATOR-1, 2 & 3 FOUNDATION IN NIL-2 AREA Out Of Scope Dyfco
22 NIL 2 HAL-HPM-SOL-14-DWG-022 PLAN, VIEW & SECTION OF MUD PUMP-1, 2 & 3 FOUNDATION IN NIL-2 AREA Out Of Scope Dyfco
23 NIL 2 HAL-HPM-SOL-14-DWG-023 PLAN, VIEW & SECTION OF BRINE PUMP FOUNDATION IN NIL-2 AREA Out Of Scope Dyfco
24 WJR 2 HAL-HPM-SOL-14-DWG-024 PLAN, VIEW & DETAIL OF FUEL STORAGE SHELTER IN WJR-2 AREA
25 WJR 2 HAL-HPM-SOL-14-DWG-025 PLAN, VIEW & DETAIL OF TEMPORARY TOILET IN WJR-2 AREA
26 WJR 2 HAL-HPM-SOL-14-DWG-026 LAY OUT FOR SAFETY FENCE IN WJR - 2 AREA
27 WJR 2 HAL-HPM-SOL-14-DWG-027 LAYOUT FOR DRILLING WELLPAD & FACILITIES IN WJR-2 AREA
28 WJR 2 HAL-HPM-SOL-14-DWG-028 PLAN & SECTION OF MUD PIT IN WJR-2 AREA
29 WJR 2 HAL-HPM-SOL-14-DWG-029 PLAN & SECTION OF WATER PIT IN WJR-2 AREA
30 WJR 2 HAL-HPM-SOL-14-DWG-030 PLAN & SECTION OF PRODUCTION TEST PIT IN WJR-2 AREA
31 WJR 2 HAL-HPM-SOL-14-DWG-031 PLAN, VIEW & SECTION OF AIR DRILLING UNIT FOUNDATION IN WJR-2 AREA
32 WJR 2 HAL-HPM-SOL-14-DWG-032 PLAN, VIEW & SECTION OF CEMENTING AREA FOUNDATION IN WJR-2 AREA
33 WJR 2 HAL-HPM-SOL-14-DWG-033 RIG PAD IN WELLPAD NIL 2 PLAN, SECTION AND DETAIL
34 WJR 2 HAL-HPM-SOL-14-DWG-034 CELLAR IN WELLPAD NIL 2 PLAN SECTION AND DETAIL
35 WJR 2 HAL-HPM-SOL-14-DWG-035 DRAINAGE IN CELLAR WELLPAD NIL 2 PLAN, SECTION AND DETAIL
32 WJR 2 HAL-HPM-SOL-14-DWG-036 PLAN, VIEW & SECTION OF MUD MATERIAL STOCK FOUNDATION IN WJR-2 AREA
33 WJR 2 HAL-HPM-SOL-14-DWG-037 PLAN, VIEW & SECTION OF INTERMEDIATE TANK & ACTIVE TANK FOUNDATION IN WJR-2 AREA Out Of Scope Dyfco
34 WJR 2 HAL-HPM-SOL-14-DWG-038 PLAN, VIEW & SECTION OF SHACKER TANK FOUNDATION IN WJR-2 AREA Out Of Scope Dyfco
35 WJR 2 HAL-HPM-SOL-14-DWG-039 PLAN, VIEW & SECTION OF FUEL TANK-1 FOUNDATION IN WJR-2 AREA Out Of Scope Dyfco
36 WJR 2 HAL-HPM-SOL-14-DWG-040 PLAN, VIEW & SECTION OF SCR UNIT FOUNDATION IN WJR-2 AREA Out Of Scope Dyfco
37 WJR 2 HAL-HPM-SOL-14-DWG-041 PLAN, VIEW & SECTION OF GENERATOR-1, 2 & 3 FOUNDATION IN WJR-2 AREA Out Of Scope Dyfco
38 WJR 2 HAL-HPM-SOL-14-DWG-042 PLAN, VIEW & SECTION OF MUD PUMP-1, 2 & 3 FOUNDATION IN WJR-2 AREA Out Of Scope Dyfco
39 WJR 2 HAL-HPM-SOL-14-DWG-043 PLAN, VIEW & SECTION OF BRINE PUMP FOUNDATION IN WJR-2 AREA Out Of Scope Dyfco
40 WJR 2 HAL-HPM-SOL-14-DWG-044 LAYOUT FOR TEMPORARY FACILITIES IN WJR-2 AREA
41 NIL 1 HAL-HPM-SOL-14-DWG-045 LAYOUT FOR TEMPORARY FACILITIES IN NIL-1 AREA
42 NIL 1 HAL-HPM-SOL-14-DWG-046 PLAN, VIEW & DETAIL OF FUEL STORAGE SHELTER IN NIL-1 AREA
43 NIL 1 HAL-HPM-SOL-14-DWG-047 PLAN, VIEW & DETAIL OF TEMPORARY TOILET IN NIL-1 AREA
44 NIL 1 HAL-HPM-SOL-14-DWG-048 LAY OUT FOR SAFETY FENCE IN NIL-1 AREA
45 NIL 1 HAL-HPM-SOL-14-DWG-049 LAYOUT FOR DRILLING WELLPAD & FACILITIES IN NIL-1 AREA
46 NIL 1 HAL-HPM-SOL-14-DWG-050 PLAN & SECTION OF MUD PIT IN NIL-1 AREA
Sarulla Project - Civil Deliverablelist Dyfco - 30 June 2014- review Dyfco (1).xlsx Page 3 of 4
HALLIBURTON PROJECT MANAGEMENT
Project : SARULLA GEOTHERMAL DRILLING PROJECT
Client : SARULLA OPERATION LIMITED
Subcontractor : DYFCO
Planned Actual
SOL
CIVIL DELIVERABLE LIST
No Area No. Drawing TITLE
Issued for Approval
Remarks
47 NIL 1 HAL-HPM-SOL-14-DWG-051 PLAN & SECTION OF WATER PIT IN NIL-1 AREA
48 NIL 1 HAL-HPM-SOL-14-DWG-052 PLAN & SECTION OF PRODUCTION TEST PIT IN NIL-1 AREA
49 NIL 1 HAL-HPM-SOL-14-DWG-053 PLAN, VIEW & SECTION OF AIR DRILLING UNIT FOUNDATION IN NIL-1 AREA
50 NIL 1 HAL-HPM-SOL-14-DWG-054 PLAN, VIEW & SECTION OF CEMENTING AREA FOUNDATION IN NIL-1 AREA
51 NIL 1 HAL-HPM-SOL-14-DWG-055 RIG PAD IN WELLPAD NIL - 1 PLAN, SECTION AND DETAIL
52 NIL 1 HAL-HPM-SOL-14-DWG-056 CELLAR IN WELLPAD NIL - 1 PLAN SECTION AND DETAIL
53 NIL 1 HAL-HPM-SOL-14-DWG-057 DRAINAGE IN CELLAR WELLPAD NIL - 1 PLAN, SECTION AND DETAIL
54 NIL 1 HAL-HPM-SOL-14-DWG-058 PLAN, VIEW & SECTION OF MUD MATERIAL STOCK FOUNDATION IN NIL-1 AREA
55 NIL 1 HAL-HPM-SOL-14-DWG-059 PLAN, VIEW & SECTION OF WATER TANK FOUNDATION FOR NIL-1 AREA Out Of Scope Dyfco
56 NIL 1 HAL-HPM-SOL-14-DWG-060 PLAN, VIEW & SECTION OF RESERVE TANK FOUNDATION IN NIL-1 AREA Out Of Scope Dyfco
57 NIL 1 HAL-HPM-SOL-14-DWG-061 PLAN, VIEW & SECTION OF FUEL TANK FOUNDATION IN NIL-1 AREA Out Of Scope Dyfco
58 NIL 1 HAL-HPM-SOL-14-DWG-062 PLAN, VIEW & SECTION OF ACTIVE TANK FOUNDATION IN NIL-1 AREA Out Of Scope Dyfco
59 NIL 1 HAL-HPM-SOL-14-DWG-063 PLAN, VIEW & SECTION OF SHACKER TANK FOUNDATION IN NIL-1 AREA Out Of Scope Dyfco
60 NIL 1 HAL-HPM-SOL-14-DWG-064 PLAN, VIEW & SECTION OF COOLING TOWER FOUNDATION IN NIL-1 AREA Out Of Scope Dyfco
61 NIL 1 HAL-HPM-SOL-14-DWG-065 PLAN, VIEW & SECTION OF SCR UNIT FOUNDATION FOR NIL-1 AREA Out Of Scope Dyfco
62 NIL 1 HAL-HPM-SOL-14-DWG-066 PLAN, VIEW & SECTION OF MUD PUMP-1 FOUNDATION IN NIL-1 AREA Out Of Scope Dyfco
63 NIL 1 HAL-HPM-SOL-14-DWG-067 PLAN, VIEW & SECTION OF MUD PUMP-2 FOUNDATION IN NIL-1 AREA Out Of Scope Dyfco
64 NIL 1 HAL-HPM-SOL-14-DWG-068 PLAN, VIEW & SECTION OF MUD PUMP-3 FOUNDATION IN NIL-1 AREA Out Of Scope Dyfco
65 NIL 1 HAL-HPM-SOL-14-DWG-069 PLAN, VIEW & SECTION OF MUD MATERIAL STOCK FOUNDATION IN NIL-1 AREA Out Of Scope Dyfco
66 NIL 1 HAL-HPM-SOL-14-DWG-070 PLAN, VIEW & SECTION OF BRINE PUMP FOUNDATION IN NIL-1 AREA Out Of Scope Dyfco
63 NIL 3 HAL-HPM-SOL-14-DWG-071 SAFETY FENCE LAYOUT IN NIL-3 AREA
64 NIL 3 HAL-HPM-SOL-14-DWG-072 LAYOUT OF RIG BASECAMP IN NIL-3 AREA
65 ALL HAL-HPM-SOL-14-DWG-073 LAYOUT OF WAREHOUSE & BUILDING OFFICE
66 ALL HAL-HPM-SOL-14-DWG-074 PLAN, VIEW & SECTION OF WAREHOUSE STRUCTURE & FOUNDATION
67 ALL HAL-HPM-SOL-14-DWG-075 PLAN, VIEW & SECTION OF SITE SECURITY STRUCTURE & FOUNDATION IN NIL AREA
68 ALL HAL-HPM-SOL-14-DWG-076 PLAN, VIEW & SECTION OF SITE SECURITY STRUCTURE & FOUNDATION IN SIL AREA
69 ALL HAL-HPM-SOL-14-DWG-077 LAYOUT OF PIPE YARD IN NIL AREA
70 ALL HAL-HPM-SOL-14-DWG-078 LAYOUT OF PIPE YARD IN SIL AREA
71 ALL HAL-HPM-SOL-14-DWG-079 LAYOUT OF WATER PIPELINE FOR DRILLING IN NIL AREA
72 ALL HAL-HPM-SOL-14-DWG-080 LAYOUT OF WATER PIPELINE FOR DRILLING IN SIL AREA
Sub Total
Grand Total
Sarulla Project - Civil Deliverablelist Dyfco - 30 June 2014- review Dyfco (1).xlsx Page 4 of 4