SAP Quick Tips Cost Control Accounting Post WIP Settlement Role: Cost Supervisor T-code: KKAO Use this T-code to calculate WIP (work in process) for production orders and when product is in semi-finished condition. Verify WIP Settlement 1. Enter the Plant number. 2. Select the following check boxes: With Production Orders With Product Cost Collectors With Process Orders 3. Enter the following values under the Parameters section: WIP to Period Fiscal Year 4. Click the RA Version option. 5. Select the following check boxes: Test Run Output Object List 6. Click the Comp. Code Cur. option as Displayed Currency. 7. Click the Execute icon. The Calculate Work in Process: Object List page appears. 1 of 7
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
SAP Quick TipsCost Control Accounting
Post WIP SettlementRole: Cost Supervisor
T-code: KKAO
Use this T-code to calculate WIP (work in process) for production orders and when product is in semi-finished condition.
Verify WIP Settlement
1. Enter the Plant number.
2. Select the following check boxes:
With Production Orders
With Product Cost Collectors
With Process Orders
3. Enter the following values under the Parameters section:
WIP to Period
Fiscal Year
4. Click the RA Version option.
5. Select the following check boxes:
Test Run
Output Object List
6. Click the Comp. Code Cur. option as Displayed Currency.
7. Click the Execute icon.The Calculate Work in Process: Object List page appears.
1 of 4
SAP Quick TipsCost Control Accounting
Post WIP Settlement (cont.)
8. Click a non-total line item.The details of the Cost object are displayed in the Details window.
9. Verify the details of the Cost Object and close the window.
10.Click the Back icon.The Calculate Work in process: Collective Processing page reappears.
Execute the Settlement
1. Clear the Test Run check box.
2. Click the Execute icon.The Work in Process is processed collectively.
2 of 4
SAP Quick TipsCost Control Accounting
Post WIP Settlement (cont.)T-code: COOIS
Use this T-code to view a report on cost break-up of production orders and when the production activity is complete.
Run Cost Break-up of Production Orders Report
1. Enter TECO in the Syst. Status field.
Note: You can use the Match Code icon to search for the System Status.
2. Click the Execute icon.A list of all the completed production orders appears.
3. Click the Order column.
4. Press the Ctrl and C keys on the keyboard.All the completed production orders are copied.
3 of 4
SAP Quick TipsCost Control Accounting
Post WIP Settlement (cont.)T-code: KOB1
Use this T-code to view actual line items for the orders and after the production activity is complete.
View Actual Line Items for Orders
1. Click the Multiple selection icon next to the Order field.The Multiple selection for Order window appears.
2. Click the Upload from clipboard icon.The completed production orders are copied in to the Single Value column.
3. Click the Copy icon.The Display Actual Cost Line Items for Orders: Initial Screen appears.
4. Click the Execute icon.The Display Actual Cost Line Items for Orders page appears.