Top Banner
US Army Corps of Engineers BUILDING STRONG ® JACKSONVILLE DISTRICT Sand Relocation Project (Contract “E”) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE, Jacksonville District February 15, 2013
58

Sand Relocation Project - · PDF fileSand Relocation Project (Contract “E”) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE ... “Contract...

Mar 16, 2018

Download

Documents

phungtuyen
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Sand Relocation Project - · PDF fileSand Relocation Project (Contract “E”) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE ... “Contract E”

US Army Corps of Engineers

BUILDING STRONG®

JACKSONVILLE DISTRICT

Sand Relocation Project

(Contract “E”)

Dade County BEC & HP Project

Tom R. Martin, P.E.

Senior Coastal Engineer

USACE, Jacksonville District

February 15, 2013

Page 2: Sand Relocation Project - · PDF fileSand Relocation Project (Contract “E”) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE ... “Contract E”

BUILDING STRONG®

Dade County Beach Erosion Control & Hurricane

Protection Project (“Dade BEC&HP”)

Page 3: Sand Relocation Project - · PDF fileSand Relocation Project (Contract “E”) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE ... “Contract E”

BUILDING STRONG®

Page 4: Sand Relocation Project - · PDF fileSand Relocation Project (Contract “E”) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE ... “Contract E”

BUILDING STRONG®

Page 5: Sand Relocation Project - · PDF fileSand Relocation Project (Contract “E”) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE ... “Contract E”

BUILDING STRONG®

Before & After – Fed Project

Initial Fill = 15.1 Mcy / Renourishment = 3.3 Mcy

Page 6: Sand Relocation Project - · PDF fileSand Relocation Project (Contract “E”) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE ... “Contract E”

BUILDING STRONG®

Erosion Continues …

Page 7: Sand Relocation Project - · PDF fileSand Relocation Project (Contract “E”) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE ... “Contract E”

BUILDING STRONG®

Page 8: Sand Relocation Project - · PDF fileSand Relocation Project (Contract “E”) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE ... “Contract E”

BUILDING STRONG®

“Hotspot” !

Page 9: Sand Relocation Project - · PDF fileSand Relocation Project (Contract “E”) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE ... “Contract E”

BUILDING STRONG®

“Hotspot” !

Accretionary Zone

Page 10: Sand Relocation Project - · PDF fileSand Relocation Project (Contract “E”) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE ... “Contract E”

BUILDING STRONG®

Page 11: Sand Relocation Project - · PDF fileSand Relocation Project (Contract “E”) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE ... “Contract E”

BUILDING STRONG®

Most frequent area of

renourishment

(9)

Page 12: Sand Relocation Project - · PDF fileSand Relocation Project (Contract “E”) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE ... “Contract E”

BUILDING STRONG®

32nd St

Breakwaters

Northern

erosive area

Southern

erosive area

Page 13: Sand Relocation Project - · PDF fileSand Relocation Project (Contract “E”) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE ... “Contract E”

BUILDING STRONG®

February 2009

Miami Beach -

Erosional Hotspots

Page 14: Sand Relocation Project - · PDF fileSand Relocation Project (Contract “E”) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE ... “Contract E”

BUILDING STRONG®

South Beach – Accretionary Zone

Page 15: Sand Relocation Project - · PDF fileSand Relocation Project (Contract “E”) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE ... “Contract E”

BUILDING STRONG®

Page 16: Sand Relocation Project - · PDF fileSand Relocation Project (Contract “E”) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE ... “Contract E”

BUILDING STRONG®

All Dade offshore BA’s are exhausted.

Future borrow options include :

► “Cleaning out” existing offshore BA’s

► Upland sources

► Offshore BA’s outside of Dade County

► Nondomestic sources

► Relocation of material from existing beaches

Page 17: Sand Relocation Project - · PDF fileSand Relocation Project (Contract “E”) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE ... “Contract E”

BUILDING STRONG®

Basic Backpassing Strategy

Page 18: Sand Relocation Project - · PDF fileSand Relocation Project (Contract “E”) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE ... “Contract E”

BUILDING STRONG®

Previous Backpassing Operations :

Truck Haul Operations in 1996, 2002

Larger-scale pumping operations in 2007,

2012.

Page 19: Sand Relocation Project - · PDF fileSand Relocation Project (Contract “E”) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE ... “Contract E”

BUILDING STRONG®

Backpassing Considerations …

Environmental Impacts (at borrow and fill areas)

RSM / Downdrift Impacts

Disruption (tourism, concessionaires, surrounding hotels

and businesses)

Public Safety

Noise, vibration, pollution, aesthetics

Opposition at the borrow site

Low production rate vs erosion

Truck-haul : Unconsolidated fill vs hydraulic placement

Page 20: Sand Relocation Project - · PDF fileSand Relocation Project (Contract “E”) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE ... “Contract E”

BUILDING STRONG®

Pumping vs Trucking :

Pro’s & Cons…

Pumping is more efficient for moving large volumes

Less traffic : environmental, safety, aesthetic concerns

Slurry fill compacts better; better performance

Less (?) equipment required

Higher mob/demob costs

Pump/Pipes can be maintenance intensive

Pipeline can limit backpass distance

Page 21: Sand Relocation Project - · PDF fileSand Relocation Project (Contract “E”) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE ... “Contract E”

BUILDING STRONG®

Challenging Construction Zone

Page 22: Sand Relocation Project - · PDF fileSand Relocation Project (Contract “E”) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE ... “Contract E”

BUILDING STRONG®

Challenging Politics

Page 23: Sand Relocation Project - · PDF fileSand Relocation Project (Contract “E”) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE ... “Contract E”

BUILDING STRONG®

Challenging Politics

Original Design

Page 24: Sand Relocation Project - · PDF fileSand Relocation Project (Contract “E”) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE ... “Contract E”

BUILDING STRONG®

Challenging Politics

Original Design

Final Design

Page 25: Sand Relocation Project - · PDF fileSand Relocation Project (Contract “E”) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE ... “Contract E”

BUILDING STRONG®

(16th St.)

Page 26: Sand Relocation Project - · PDF fileSand Relocation Project (Contract “E”) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE ... “Contract E”

BUILDING STRONG®

Borrow R64-R69

Basic Layout of Contract “E” Backpassing Operation

N. Fill R53-R54

S. Fill R60-R61

Page 27: Sand Relocation Project - · PDF fileSand Relocation Project (Contract “E”) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE ... “Contract E”

BUILDING STRONG®

“Contract E” – Sand Backpass Operation

Total volume of 84,000 cy backpassed

Length of fill areas = 2,100 feet

Length of borrow area = 5,000 feet

Pumping distances of 1.1 and 2.3 miles

Fill area : 205-ft construction template

Borrow area : 100-ft cut into seaward berm

Methodology : Pipeline transport of slurry

Page 28: Sand Relocation Project - · PDF fileSand Relocation Project (Contract “E”) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE ... “Contract E”

BUILDING STRONG®

Overall Project Layout

Page 29: Sand Relocation Project - · PDF fileSand Relocation Project (Contract “E”) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE ... “Contract E”

BUILDING STRONG®

Overall Project Layout

Borrow zone

Page 30: Sand Relocation Project - · PDF fileSand Relocation Project (Contract “E”) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE ... “Contract E”

BUILDING STRONG®

Overall Project Layout

Borrow zone

Slurry Pump

Page 31: Sand Relocation Project - · PDF fileSand Relocation Project (Contract “E”) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE ... “Contract E”

BUILDING STRONG®

Overall Project Layout

Borrow zone

Slurry Pump

Pipeline

Pipeline

Page 32: Sand Relocation Project - · PDF fileSand Relocation Project (Contract “E”) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE ... “Contract E”

BUILDING STRONG®

Overall Project Layout

Borrow zone

Slurry Pump

Pipeline

Pipeline

Discharge / Earthmoving

equipment

Page 33: Sand Relocation Project - · PDF fileSand Relocation Project (Contract “E”) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE ... “Contract E”

BUILDING STRONG®

Overall Project Layout

Borrow zone

Slurry Pump

Pipeline

Pipeline

Discharge / Earthmoving

equipment

Page 34: Sand Relocation Project - · PDF fileSand Relocation Project (Contract “E”) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE ... “Contract E”

BUILDING STRONG®

Equipment / Setup

Page 35: Sand Relocation Project - · PDF fileSand Relocation Project (Contract “E”) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE ... “Contract E”

BUILDING STRONG®

Overall Layout

Page 36: Sand Relocation Project - · PDF fileSand Relocation Project (Contract “E”) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE ... “Contract E”

BUILDING STRONG®

Overall Layout

Page 37: Sand Relocation Project - · PDF fileSand Relocation Project (Contract “E”) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE ... “Contract E”

BUILDING STRONG®

Overall Layout

100’

Page 38: Sand Relocation Project - · PDF fileSand Relocation Project (Contract “E”) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE ... “Contract E”

BUILDING STRONG®

Overall Layout

Page 39: Sand Relocation Project - · PDF fileSand Relocation Project (Contract “E”) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE ... “Contract E”

BUILDING STRONG®

Overall Layout

Page 40: Sand Relocation Project - · PDF fileSand Relocation Project (Contract “E”) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE ... “Contract E”

BUILDING STRONG®

Overall Layout

Page 41: Sand Relocation Project - · PDF fileSand Relocation Project (Contract “E”) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE ... “Contract E”

BUILDING STRONG®

Overall Layout

Page 42: Sand Relocation Project - · PDF fileSand Relocation Project (Contract “E”) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE ... “Contract E”

BUILDING STRONG®

Overall Layout

Page 43: Sand Relocation Project - · PDF fileSand Relocation Project (Contract “E”) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE ... “Contract E”

BUILDING STRONG®

Excavation at the Borrow Site

Page 44: Sand Relocation Project - · PDF fileSand Relocation Project (Contract “E”) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE ... “Contract E”

BUILDING STRONG®

Stockpiling Borrow Material

Page 45: Sand Relocation Project - · PDF fileSand Relocation Project (Contract “E”) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE ... “Contract E”

BUILDING STRONG®

Safety Zone Around Loader

Page 46: Sand Relocation Project - · PDF fileSand Relocation Project (Contract “E”) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE ... “Contract E”

BUILDING STRONG®

Pump and Hydraulic Loader

Page 47: Sand Relocation Project - · PDF fileSand Relocation Project (Contract “E”) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE ... “Contract E”

BUILDING STRONG®

Loading the Hopper

Page 48: Sand Relocation Project - · PDF fileSand Relocation Project (Contract “E”) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE ... “Contract E”

BUILDING STRONG®

Discharge Pipeline

Page 49: Sand Relocation Project - · PDF fileSand Relocation Project (Contract “E”) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE ... “Contract E”

BUILDING STRONG®

Booster Pump

Page 50: Sand Relocation Project - · PDF fileSand Relocation Project (Contract “E”) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE ... “Contract E”

BUILDING STRONG®

Slurry Discharge

Page 51: Sand Relocation Project - · PDF fileSand Relocation Project (Contract “E”) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE ... “Contract E”

BUILDING STRONG®

Discharge / Fill Area

Page 52: Sand Relocation Project - · PDF fileSand Relocation Project (Contract “E”) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE ... “Contract E”

BUILDING STRONG®

Discharge / Fill Area

Page 53: Sand Relocation Project - · PDF fileSand Relocation Project (Contract “E”) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE ... “Contract E”

BUILDING STRONG®

Final Placement and Shaping

Page 54: Sand Relocation Project - · PDF fileSand Relocation Project (Contract “E”) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE ... “Contract E”

BUILDING STRONG®

Finished Project

Page 55: Sand Relocation Project - · PDF fileSand Relocation Project (Contract “E”) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE ... “Contract E”

BUILDING STRONG®

B/A -C

Page 56: Sand Relocation Project - · PDF fileSand Relocation Project (Contract “E”) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE ... “Contract E”

BUILDING STRONG®

Page 57: Sand Relocation Project - · PDF fileSand Relocation Project (Contract “E”) Dade County BEC & HP Project Tom R. Martin, P.E. Senior Coastal Engineer USACE ... “Contract E”

BUILDING STRONG®

Lessons Learned

Backpassing can be a viable method if : ► Downdrift effects are not important

► Distance between borrow and fill areas not too great

► Disruptions to beach use/operations not too great

Requires special attention to : ► Public/political aspects : noise, disruption, safety, etc.

► Tradeoffs between trucking and pumping