Top Banner
San Francisco Roadway Bridges Project Dogpatch Neighborhood Association Tuesday, May 13, 2014
22

San Francisco Roadway Bridges Project

Feb 15, 2022

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: San Francisco Roadway Bridges Project

San Francisco Roadway Bridges

Project

Dogpatch Neighborhood Association Tuesday, May 13, 2014

Page 2: San Francisco Roadway Bridges Project

Overview • Scope & Need • Construction Timeline & Sequence • Construction Impacts • Project Elements • Next Steps

2

Page 3: San Francisco Roadway Bridges Project

Scope & Need

Page 4: San Francisco Roadway Bridges Project

Project Scope • Remove and replace three existing

vehicular/pedestrian bridges over the Caltrain tracks at the following locations: - 22nd Street - 23rd Street - Paul Avenue

4

Page 5: San Francisco Roadway Bridges Project

Project Area

5

Replace Three Vehicular/Pedestrian Bridges

Page 6: San Francisco Roadway Bridges Project

Background Why do these bridges need to be replaced? • Rapidly aging vehicular/pedestrian bridges • Bridges deemed structurally deficient; do not meet

existing seismic safety standards • Must be replaced for the safety of community

members and Caltrain customers

6

Page 7: San Francisco Roadway Bridges Project

The E’s of Rail Safety • EDUCATION • ENGINEERING

7

Jerrold Street Bridge - 2011

Presenter
Presentation Notes
RAIL SAFETY SLIDE: per Mark Simon’s request The E’s of Rail Safety – Education – making sure we educate the community about the importance of rail safety; even though this is a vehicular/pedestrian bridge, we’re replacing it for safety purposes Engineering – have to improve our operations through state of good repair (fencing, rail, etc.) and other projects like this one for continued safe operations
Page 8: San Francisco Roadway Bridges Project

Background • Project cost: $20 million • Paid for by Federal Highway Administration

and local funding • Owned by the City of San Francisco • Maintained by Caltrain

8

Page 9: San Francisco Roadway Bridges Project

Construction Timeline & Sequence

Page 10: San Francisco Roadway Bridges Project

Construction Timeline

• Schedule – Construction set to begin in Fall 2014

and last until Fall 2016 – Work is expected to last 9 to 12

months per bridge – Work not concurrent

10

Page 11: San Francisco Roadway Bridges Project

Construction Sequence

23rd Street 22nd Street

11

Fall 2015-16 Fall 2014-15

Page 12: San Francisco Roadway Bridges Project

Construction Sequence

12

Paul Avenue Fall 2014-15

Page 13: San Francisco Roadway Bridges Project

Construction Impacts

Page 14: San Francisco Roadway Bridges Project

Construction Impacts • Majority of work done during day • Some night and weekend work required during

certain construction activities • Localized noise impacts • Notification process

– Mailers sent 14 days before starting construction, loud operations and/or night work

– Notices are mailed to residents and businesses located up to a ½ mile from the project site

14

Page 15: San Francisco Roadway Bridges Project

Construction Impacts • Vehicular and pedestrian restrictions will be

required and posted at each bridge • During closures at 22nd and 23rd streets,

detours and shuttle in place during peak AM/PM hours

• During closure on Paul Avenue, detours • MUNI coordination

15

Page 16: San Francisco Roadway Bridges Project

Project Elements

Page 17: San Francisco Roadway Bridges Project

Project Elements • Retrofit existing abutments to support new

structures • Utility relocations • Temporary street closures • Demolition/construction • Paving and street improvements

17

Page 18: San Francisco Roadway Bridges Project

Next Steps

Page 19: San Francisco Roadway Bridges Project

Community Outreach • Community meetings – Feb. 25 & 27, 2014

- Visitacion Valley Library and Potrero Hill Neighborhood House • Community Based Organizations • Neighborhood Groups • Local Developers • Notification Process

- Notices/mailers (residents, businesses, community based organizations)

- Special project Web page www.caltrain.com/SFRB, with subscribe option

- Social media (Facebook & Twitter) - Responses to individual public requests and questions - News releases

19

Page 20: San Francisco Roadway Bridges Project

Next Steps • Advertise and award of construction contract

- June 2014 to September 2014 • Continue communications and dialogue with

residents and businesses regarding project • Next community meeting to be held prior to

construction (Late Fall 2014)

20

Page 21: San Francisco Roadway Bridges Project

More Info • www.caltrain.com/SFRB

- Subscribe to updates

• Email: [email protected]

• Construction Outreach Hotline: 650.508.7726

21

Page 22: San Francisco Roadway Bridges Project

Questions ?