A simple explanation of effective Asset Management

10 May 2015

Ivan Winter BE Hon

Senior Asset & Engineering Consultant Ingenia

This Presentation and Asset Management Model is the IP and copyright © of Ingenia Pty Ltd 2009 and must not be reproduced without permission.

Page 2: Samm presentation full

Simplified Asset Management Model © Ingenia 2009

2

Mr. Fix It

All maintenance teams “Execute Work”.

Page 3: Samm presentation full

Simplified Asset Management Model © Ingenia 2009

3

Mr. Fix It

All maintenance teams “Execute Work”.

When a piece of equipmentfails, they figure out whatwent wrong

Page 4: Samm presentation full

Simplified Asset Management Model © Ingenia 2009

4

Mr. Fix It

All maintenance teams “Execute Work”.

When a piece of equipmentfails, they figure out whatwent wrong

and then they fix it.

Page 5: Samm presentation full

Simplified Asset Management Model © Ingenia 2009

5

Mr. Fix It

All maintenance teams “Execute Work”.

When a piece of equipmentfails, they figure out whatwent wrong

and then they fix it.

They usually do some regular services to care for the assets.

Page 6: Samm presentation full

Simplified Asset Management Model © Ingenia 2009

6

Most organisations have a maintenance work list

“The Backlog”.

Service Generator

Page 7: Samm presentation full

Simplified Asset Management Model © Ingenia 2009

7

Most organisations have a maintenance work list

“The Backlog”.

They do some planning and scheduling,

Service Generator

Page 8: Samm presentation full

Simplified Asset Management Model © Ingenia 2009

8

Most organisations have a maintenance work list

“The Backlog”.

They do some planning and scheduling,

They source parts and labour,

Service Generator

Page 9: Samm presentation full

Simplified Asset Management Model © Ingenia 2009

9

Most organisations have a maintenance work list

“The Backlog”.

They do some planning and scheduling,

They source parts and labour,

Service Generator

and some routine preventative Jobs

are generated.

Page 10: Samm presentation full

Simplified Asset Management Model © Ingenia 2009

10

Most organisations have a maintenance work list

“The Backlog”.

They do some planning and scheduling,

They source parts and labour,

Service Generator

and some routine preventative Jobs

are generated.This is what most EAM

or CMMS computer systems are designed

to manage.

Page 11: Samm presentation full

Simplified Asset Management Model © Ingenia 2009

11

Most organisations see the need to make a listof work that needs to be done “The Backlog”and they do some planning and scheduling ofthe work.

Parts and services must be sourced for thework.

Most EAM or CMMS computersystems are designed tomanage these activities.

These systems are getting more

sophisticated - but are they effective?

Image – Elate Wiki

Page 12: Samm presentation full

Simplified Asset Management Model © Ingenia 2009

12

“The Backlog” is important.

Service Generator

Page 13: Samm presentation full

Simplified Asset Management Model © Ingenia 2009

13

“The Backlog” is important.

Service Generator

But where do the jobs come from?

Page 14: Samm presentation full

Simplified Asset Management Model © Ingenia 2009

14

“The Backlog” is important.

Service Generator

But where do the jobs come from?

and how do you know they are going to

effectively care for the assets?

Page 15: Samm presentation full

Simplified Asset Management Model © Ingenia 2009

15

Service Generator

These processes are designed to

efficiently deliver tactics.

Page 16: Samm presentation full

Simplified Asset Management Model © Ingenia 2009

16

Service Generator

These processes are designed to

efficiently deliver tactics.

But are they the right tactics?

Page 17: Samm presentation full

Simplified Asset Management Model © Ingenia 2009

17

The first step for developing the right tactics is to study why

each asset fails,

Failure patterns - Nowlan, F. Stanley, and Howard F. Heap. Reliability-Centered Maintenance. Report Number AD-A066579

Page 18: Samm presentation full

Simplified Asset Management Model © Ingenia 2009

18

The first step for developing the right tactics is to study why

each asset fails,

Failure patterns - Nowlan, F. Stanley, and Howard F. Heap. Reliability-Centered Maintenance. Report Number AD-A066579

and it is critical to know when

it fails.

Page 19: Samm presentation full

Simplified Asset Management Model © Ingenia 2009

19

The first step for developing the right tactics is to study why

each asset fails,

Failure patterns - Nowlan, F. Stanley, and Howard F. Heap. Reliability-Centered Maintenance. Report Number AD-A066579

A different tactic is

required for each failure

pattern.

and it is critical to know when

it fails.

Page 20: Samm presentation full

Simplified Asset Management Model © Ingenia 2009

20

The first step for developing the right tactics is to study why

each asset fails,

Failure patterns - Nowlan, F. Stanley, and Howard F. Heap. Reliability-Centered Maintenance. Report Number AD-A066579

A different tactic is

required for each failure

pattern.

If you do more overhauls for this

failure pattern then reliability will get

worse!

and it is critical to know when

it fails.

Page 21: Samm presentation full

Simplified Asset Management Model © Ingenia 2009

21

The first step for developing the right tactics is to study why

each asset fails,

Failure patterns - Nowlan, F. Stanley, and Howard F. Heap. Reliability-Centered Maintenance. Report Number AD-A066579

A different tactic is

required for each failure

pattern.

If you do more overhauls for this

failure pattern then reliability will get

worse!

and it is critical to know when

it fails.

For wear out failure condition monitoring is

the best tactic

For “wear out” failure condition monitoring is

the best tactic.

Page 22: Samm presentation full

Simplified Asset Management Model © Ingenia 2009

22

Remember failure study requires resource and proper

processes to get results.

Failure patterns - Nowlan, F. Stanley, and Howard F. Heap. Reliability-Centered Maintenance. Report Number AD-A066579

Page 23: Samm presentation full

Simplified Asset Management Model © Ingenia 2009

23

Failure Study Process

Page 24: Samm presentation full

Simplified Asset Management Model © Ingenia 2009

24

We recommend RCA to get up to 85% availability,

Failure Study Process

Page 25: Samm presentation full

Simplified Asset Management Model © Ingenia 2009

25

We recommend RCA to get up to 85% availability,

and RCM / FMECA to get to > 90%

availability.Failure Study Process

Page 26: Samm presentation full

Simplified Asset Management Model © Ingenia 2009

26

Once the failure is fully understood, the best tactic is selected

Page 27: Samm presentation full

Simplified Asset Management Model © Ingenia 2009

27

Once the failure is fully understood, the best tactic is selected

and if the failure cannot be managed

then a design change may be required.

Page 28: Samm presentation full

Simplified Asset Management Model © Ingenia 2009

28

Once the failure is fully understood, the best tactic is selected

and if the failure cannot be managed

then a design change may be required.

Proper tactics and design changes form

a better backlog.

Page 29: Samm presentation full

Simplified Asset Management Model © Ingenia 2009

29

Once the failure is fully understood, the best tactic is selected

and if the failure cannot be managed

then a design change may be required.

Proper tactics and design changes form

a better backlog.

The best tactic may be to change the

operating procedure.

Page 30: Samm presentation full

Simplified Asset Management Model © Ingenia 2009

30

Once the failure is fully understood, the best tactic is selected

and if the failure cannot be managed

then a design change may be required.

Proper tactics and design changes form

a better backlog.

The best tactic may be to change the

operating procedure.

This should improve the tactics delivered

because they are based on real failures.

Page 31: Samm presentation full

Simplified Asset Management Model © Ingenia 2009

31

Page 32: Samm presentation full

Simplified Asset Management Model © Ingenia 2009

32

Doing these processes properly will improve

asset performance.

Page 33: Samm presentation full

Simplified Asset Management Model © Ingenia 2009

33

Doing these processes properly will improve

asset performance.

But they are not enough to ensure

success.

Page 34: Samm presentation full

Simplified Asset Management Model © Ingenia 2009

34

It is important to check that the tactics are

working

Page 35: Samm presentation full

Simplified Asset Management Model © Ingenia 2009

35

It is important to check that the tactics are

working

and make improvements if

they are not.

Page 36: Samm presentation full

Simplified Asset Management Model © Ingenia 2009

36

Also success is not possible without effective

management of safety and employee skills.

Page 37: Samm presentation full

Simplified Asset Management Model © Ingenia 2009

37

Also success is not possible without effective

management of safety and employee skills.

ISO 55000 expects employees to be

competent and safe.

Page 38: Samm presentation full

Simplified Asset Management Model © Ingenia 2009

38

Also success is not possible without effective

management of safety and employee skills.

ISO 55000 expects employees to be

competent and safe.

Improving skills alone gives the most significant improvement in

reliability by reducing failure Pattern F

Page 39: Samm presentation full

Simplified Asset Management Model © Ingenia 2009

39

Page 40: Samm presentation full

Simplified Asset Management Model © Ingenia 2009

40

The Asset Management System should be aligned

with the Organisation’s Policies / Strategy and

Plans.

Page 41: Samm presentation full

Simplified Asset Management Model © Ingenia 2009

41

This ensures the cost of Asset Care is linked to the

Organisation's expected outcomes(another ISO 55000 aim).

The Asset Management System should be aligned

with the Organisation’s Policies / Strategy and

Plans.

Page 42: Samm presentation full

Simplified Asset Management Model © Ingenia 2009

42

Page 43: Samm presentation full

Simplified Asset Management Model © Ingenia 2009

43

Finally for the best result the organisation should forecast

asset requirements over their entire life to meet its

objectives

Page 44: Samm presentation full

Simplified Asset Management Model © Ingenia 2009

44

Finally for the best result the organisation should forecast

asset requirements over their entire life to meet its

objectives

and measure how the asset performs

against these plans.

Page 45: Samm presentation full

Simplified Asset Management Model © Ingenia 2009

45

Page 46: Samm presentation full

Simplified Asset Management Model © Ingenia 2009

46

Commitment to these processes and principles

should give the right asset performance.