Top Banner
Safety Share Line Superintendent Report to IAEC
7

Safety Share Line Superintendent Report to IAEC

Feb 22, 2016

Download

Documents

_tekla_

Safety Share Line Superintendent Report to IAEC. The crew was doing a routine pole change out. They were “lifting ” a pole ( some of us may define it as pulling a pole). . - PowerPoint PPT Presentation
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Safety Share Line Superintendent Report to IAEC

Safety ShareLine Superintendent Report to IAEC

Page 2: Safety Share Line Superintendent Report to IAEC

The crew was doing a routine pole change out. They were “lifting” a pole

(some of us may define it as pulling a pole).

Page 3: Safety Share Line Superintendent Report to IAEC

The boom was nearly extended all the way out, therefore causing even more leverage on the boom. No overload protection devices operated prior to the boom failure.

Page 4: Safety Share Line Superintendent Report to IAEC

My best guess as to the cause of the accident was boom fatigue over time from “pulling” poles and not “lifting” poles. I also speculate that the boom failed prior to the overload protection devices sensing the

overload.

Page 5: Safety Share Line Superintendent Report to IAEC

This is one of those events that no one is going to say anymore than they have to and management cannot prove otherwise. There was no push-back as it was made clear that all pole removals require the use of a pole puller.It is difficult to say if our pulling/lifting actions were the cause or if there was indeed a premature mechanical failure of the boom. The possibility of the men or the truck manufacture coming forward to admit any fault is slim to none.

Page 6: Safety Share Line Superintendent Report to IAEC

From today on at “XYZ CO-OP”, if another bent boom comes in, it will not be because of pulling poles and a very good, proven explanation will have to be provided as to why the boom is bent.

DUECO was the manufacture. Equipment is not designed to perform this task. Twin-screw digger derrick. Estimates are around $50,000.

Page 7: Safety Share Line Superintendent Report to IAEC

WHAT ARE YOU DOING TO REMOVE POLES FROM THE EARTH?

Does your Co-op have an extra $50,000 laying around?

• Should there be disciplinary action?• Is there a need for a policy change?