REVISION DATE WORK LOCATION CONTACT NUMBER IN CONSULTATION WITH 07 August 2018 SWMS TITLE WORK ACTIVITY PROJECT NAME WORKS MANAGER SWMS PREPARED BY Installaon of New Dry Systems Installaon of New Detecon, OWS, SSIS and Smoke Detecon Daniel Knoblauch SWMS NO 7 REVIEWED MONITORED Safe Work Method Statement HOW SWMS CONTROLS ARE BY BY Tool Box Meengs Site Visits Site Foreman Senior Management RESPONSIBILITIES Daniel Knoblauch Daniel Knoblauch Jomar Estrella PERSON RESPONSIBLE FOR ENSURING COMPLIANCE WITH SWMS PERSON RESPONSIBLE FOR REVIEWING AND APPROVING THIS SWMS SWMS PREPARED BY NAME POSITION SIGNATURE Senior Mngt Rep Senior Mngt Rep OH&S Admin Asst MINIMUM PERSONAL PROTECTIVE EQUIPMENT (PPE) REQUIREMENTS Hard Hat Hearing protecon Coon clothing Safety boots Safety harness Hig vis clothing Face shield Gloves Dust mask Safety glasses Long sleeve/trouser ü ü ü ü ü PO Box 755, Kingsgrove NSW 1480 31/105A Vanessa Street, Kingsgrove NSW 2208 Tel No.: 1300 88 70 18 ABN: 90 109 866 140 website: www.globalfire.com.au email: [email protected]Page 1 of 11 Revised: 07/08/2018 ü ü PRINCIPAL CONTRACTOR COMPANY NAME CONTACT PERSON ADDRESS PHONE NUMBER
13
Embed
Safe Work Method Statement SWMS NO 7 SWMS …HIGH RISK CONSTRUCTION WORK - If you are working on an environment described below, complete the separate High Risk Construction Work SWMS.
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
REVISION DATE
WORK LOCATION
CONTACT NUMBER
IN CONSULTATION WITH
07 August 2018
SWMS TITLE
WORK ACTIVITY
PROJECT NAME
WORKS MANAGER
SWMS PREPARED BY
Installa�on of New Dry Systems
Installa�on of New Detec�on, OWS, SSIS and Smoke Detec�on
Daniel Knoblauch
SWMS NO 7
REVIEWED
MONITORED
Safe Work Method Statement
PERSON RESPONSIBLE FOR ENSURING COMPLIANCE WITH SWMS
HOW SWMS CONTROLS AREBY
BY
Tool Box Mee�ngs
Site Visits
Site Foreman
Senior Management
RESPONSIBILITIES
Daniel Knoblauch
Daniel Knoblauch
Jomar Estrella
PERSON RESPONSIBLE FOR ENSURING COMPLIANCE WITH SWMS
PERSON RESPONSIBLE FOR REVIEWING AND APPROVING THIS SWMS
SWMS PREPARED BY
NAME POSITION SIGNATURE
Senior Mngt Rep
Senior Mngt Rep
OH&S Admin Asst
MINIMUM PERSONAL PROTECTIVE EQUIPMENT (PPE) REQUIREMENTS
Breakdown Job into steps. Each step should accomplish a major task in logical sequence.
Who is responsible for implemen�ng Control Measure
1 16 Ensure that travel paths are clear, and be aware of any obstacles. Tradesman
2 16Provide signage to make sure drivers are aware of truck being unloaded. Wear high visibility vest.
Tradesman
3 Strain injury from li�ing. 12 TradesmanUse correct li�ing techniques when removing pipe work/tools/materialfrom truck. Avoid li�ing anything beyond your capacity.
4
6
7
8
9
10
11
12
13 18 TechnicianObjects and insects that can cause injury.
Ensure immediate area is clear and wear sturdy gloves.
14 16 TradesmanCuts from removing/demolishing exis�ng plasterboard.
Ensure gloves are worn when removing/demolishing exis�ng plasterboard, and wear eye protec�on.
STEP NO
SEQUENCE OF BASIC JOB STEPS
POTENTIAL SAFETY HAZARDS
Iden�fy the hazards (health & safety) associated with each step, examine each to find all possible risk factors.
RISK SCORE
Use matrixscore risk.
CONTROL MEASURE
Determine what ac�ons are necessary to eliminate or minimise all hazards that could lead to an accident, injury, illness or environmental incident. The risk must be reduced or controlled to a level that is acceptable before work commences.
5Manual handling of good/s to loca�on of installa�on on site.
Unloading tools and materials from vehicle.
Unloading tools and materials from vehicle.
Unloading tools and materials from vehicle.
Unloading tools and materials from vehicle.
Trip hazard
Vehicle movements in car park.
Dropping material or tools onto feet.
16 Tradesman/TechnicianRubber sole steel cap boots to be worn at all �mes.
Trip hazard. 16 TradesmanEnsure immediate area and pathway is clear and free of obstruc�ons and carry good/s in manner to ensure foresight not impeded.
Drilling holes for moun�ng equipment.Electrocu�on by drilling into electrical cabling.
12Tradesman/Site -foreman/Electrician
Liaise with on-site foreman and electrician to ensure proposed loca�on of drill hole will not clash with exis�ng cabling.
Drilling holes for moun�ng equipment.Masonry/concrete/plasterboard dust in eyes of technician.
17 TradesmanWear safety glasses when drilling into masonry/concrete walls and gas mask when drilling above.
Drilling holes for moun�ng equipment. Noise pollu�on from drill. 17 TradesmanWear earplugs when drilling into masonry or concrete walls.
Drilling holes for moun�ng equipment. 12Tradesman/Site foreman
Hi�ng post tensioning ducts in wall.
Liaise with on-site foreman to ensure proposed loca�on of drill hole will not clash with exis�ng reinforcement or post tension ducts.
15 Tradesman/ElectricianElectrocu�on.Isolate power circuit before carrying out work. Wear rubber sole steel cap boots.
Installa�on of new Detec�on, OWS, SSISand smoke detec�on works.
16 TradesmanFalling off ladder.Ensure that the ladder is serviceable and placed on even ground and that non slip footwear is worn. Do not overstretch the capabili�es of the ladder.
17 TechnicianMasonry/concrete/plasterboard dust or par�cles in eyes of technician.
Wear safety glasses when drilling into masonry/concrete walls and gas mask when drilling above.
Installa�on of new Detec�on, OWS, SSISand smoke detec�on works.
Installa�on of new Detec�on, OWS, SSISand smoke detec�on works.
Installa�on of new Detec�on, OWS, SSISand smoke detec�on works.
Installa�on of new Detec�on, OWS, SSISand smoke detec�on works.
Logical Sequence
Breakdown Job into steps. Each step should accomplish a major task in logical sequence.
Who is responsible for implemen�ng Control Measure
15
16
17Injury from exis�ng obstacles in the near vicinity.
17 Ensure immediate area is clear and free of obstruc�on.
18 Tradesman
STEP NO
SEQUENCE OF BASIC JOB STEPS
POTENTIAL SAFETY HAZARDS
Iden�fy the hazards (health & safety) associated with each step, examine each to find all possible risk factors.
RISK SCORE
Use matrixscore risk.
CONTROL MEASURE
Determine what ac�ons are necessary to eliminate or minimise all hazards that could lead to an accident, injury, illness or environmental incident. The risk must be reduced or controlled to a level that is acceptable before work commences.
Installa�on of new Detec�on, OWS, SSIS and smoke detec�on works.
Tradesman
Iinstalla�on of new Detec�on, OWS, SSIS and smoke detec�on works.
Installa�on of new Detec�on, OWS, SSIS and smoke detec�on works.
Commissioning of new Detec�on, OWS, SSIS and smoke detec�on works.
Hi�ng head on high level obstruc�ons.
19 Ensure personnel is wearing hard hat. Tradesman
Strain injury from working at high level.
19Correct tools to be used. Personnel must not overreach and take regular breaks to stretch.
Tradesman
Sound annoyance emi�ed from ac�vated smoke alarm/OWS.
17No preven�on required unless con�nuous tes�ng in a confined space. Hearing protec�on are an op�on if required.
ADDITIONS TO SWMS FROM WEEKLY SITE INSPECTIONS - Form F002
Logical Sequence
Breakdown Job into steps. Each step should accomplish a major task in logical sequence.
Ini�al of those on site when addi�onis added
DATE ADDED
SEQUENCE OF BASIC JOB STEPS
POTENTIAL SAFETY HAZARDS
Iden�fy the hazards (health & safety) associated with each step, examine each to find all possible risk factors.
RISK SCORE
Use matrixscore risk.
CONTROL MEASURE
Determine what ac�ons are necessary to eliminate or minimise all hazards that could lead to an accident, injury, illness or environmental incident. The risk must be reduced or controlled to a level that is acceptable before work commences.
SIGNATURE
Who is responsible for implemen�ng Control Measure
TRAINING STATEMENT - The following people have been trained in the work activities described in this SWMS.
I, the employee/worker iden�fied below:
1. Have read, had input into and understood this SWMS;2. Have been consulted and trained in the specific safety requirements of the ac�vity for which I am engaged on this site;3. I will work in accordance with this SWMS and understand that I am responsible for my own and fellow workers safety;4. If found necessary to amend this SWMS, I will consult with the Site Manager and help if required in re-issuing this SWMS.
Full Name Signature Date Full Name Signature Date
Person(s) to be involved with the work
Electrician
Sprinkler Fi�er
Asset Maintenance Technician
Other (specify)
ü
ü
Qualifica�ons and Experience of Supervisors, Trainers and Workers
"SWMS 07 - Installation of new dry systems" HistoryDocument uploaded by Jomar Estrella ([email protected]) from Acrobat09/01/2018 - 2:56:03 PM PDT- IP address: 210.8.237.66
Document emailed to Micha Springer ([email protected]) for signature09/01/2018 - 2:59:43 PM PDT
Document viewed by Micha Springer ([email protected])09/01/2018 - 10:09:40 PM PDT- IP address: 188.4.74.94
Document e-signed by Micha Springer ([email protected])Signature Date: 09/01/2018 - 10:10:31 PM PDT - Time Source: server- IP address: 188.4.74.94
Document emailed to simone gelormino ([email protected]) for signature09/01/2018 - 10:10:31 PM PDT
Document viewed by simone gelormino ([email protected])09/02/2018 - 1:54:55 PM PDT- IP address: 120.17.239.136
Document e-signed by simone gelormino ([email protected])Signature Date: 09/02/2018 - 1:55:31 PM PDT - Time Source: server- IP address: 120.17.239.136
Document emailed to Seth ([email protected]) for signature09/02/2018 - 1:55:32 PM PDT
Document viewed by Seth ([email protected])09/02/2018 - 3:28:08 PM PDT- IP address: 120.17.89.55
Document e-signed by Seth ([email protected])Signature Date: 09/02/2018 - 3:29:40 PM PDT - Time Source: server- IP address: 120.17.89.55
Document emailed to Fernando Saada ([email protected]) for signature09/02/2018 - 3:29:40 PM PDT
Document viewed by Fernando Saada ([email protected])09/02/2018 - 6:39:17 PM PDT- IP address: 137.111.13.125
Document e-signed by Fernando Saada ([email protected])Signature Date: 09/02/2018 - 6:45:41 PM PDT - Time Source: server- IP address: 137.111.13.125