June 1st 2013 Safaricom Digital City Urban Fiber Works after 2 months
20

Safaricom fiber construction after 2 months

Apr 13, 2017

Download

Engineering

Osvaldo Coelho
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Safaricom fiber construction after 2 months

June 1st 2013

Safaricom Digital City

Urban Fiber Works after 2 months

Page 2: Safaricom fiber construction after 2 months

June 1st 2013

Ole Dumbe Road

June 1st April 12th Ole Dumbe Road

Page 3: Safaricom fiber construction after 2 months

June 1st 2013

CTO Visit to works

June 1st

February 13th

Page 4: Safaricom fiber construction after 2 months

June 1st 2013

Ole Dumbe Rd

April 12th

Ole Dumbe Rd

June 1st

Page 5: Safaricom fiber construction after 2 months

June 1st 2013

Rongai

April 18th

Rongai

June 1st

Page 6: Safaricom fiber construction after 2 months

June 1st 2013

Ole Dumbe Road

June 1st April 12th

Ole Dumbe Road

Page 7: Safaricom fiber construction after 2 months

June 1st 2013

Rongai

June 1st

Rongai

April 18th

Page 8: Safaricom fiber construction after 2 months

June 1st 2013

Ngong City

March 20th

Ngong City

June 1st

Page 9: Safaricom fiber construction after 2 months

June 1st 2013

Rongai

April 18th

Ole Dumbe Rd

April 12th Ole Dumbe Rd

June 1st

Page 10: Safaricom fiber construction after 2 months

June 1st 2013

Ngong City

June 1st

Ngong City

March 20th

Page 11: Safaricom fiber construction after 2 months

June 1st 2013

April 18th

April 18th

June 1st

June 1st

Page 12: Safaricom fiber construction after 2 months

June 1st 2013

June 1st

Langatta High School

Langatta High School

April 12th

Page 13: Safaricom fiber construction after 2 months

June 1st 2013

Ole Dumbe Road

April 12th

Ole Dumbe Road

June 1st

Page 14: Safaricom fiber construction after 2 months

June 1st 2013

Ngong City

June 1st

Ngong City

Mach 20th

Page 15: Safaricom fiber construction after 2 months

June 1st 2013

Ole Dumbe Rd

April 12th

Ole Dumbe Rd

June 1st

Page 16: Safaricom fiber construction after 2 months

June 1st 2013

Kitengela

May 29th

Kitengela

April 24th

Page 17: Safaricom fiber construction after 2 months

June 1st 2013

June 1st

Ngong Rd

Orange HQ

Ngong Rd

Orange HQ

April 12th

Page 18: Safaricom fiber construction after 2 months

June 1st 2013

Hekima College

March 31th Hekima School

June 1st

Hekima College June 1st

Page 19: Safaricom fiber construction after 2 months

June 1st 2013

The enemy of the fiber guy

Result: Torn Tires

Page 20: Safaricom fiber construction after 2 months

June 1st 2013

And that was only the beginning…

2013/14 Program

62.8

95.2

62.1

Total 220.1

87.7

99.3

Total 187

Mombasa 113

Nakuru 204

Eldoret 97

Kisumu 88

Total 502

Grand total 902

Rest of Kenya

Total Km HLD

ERICSSON NAIROBI

Total Km HLD

HUAWEI NAIROBI

Total Km HLD