Application of an evolutionary solver to the optimisation of an open pit mine Lorrie Fava, MIRARCO, Laurentian University
Application of an evolutionary solver to the optimisation of an open pit mine
Lorrie Fava, MIRARCO, Laurentian University
Overview
• The evolutionary solver
• Parva Mine
• Integrated optimisation process
• Case Study outcomes:
Optimised schedule, Ultimate pit and Nested pits
• Sensitivity analysis
• Conclusion
• Future Work
An evolutionary solver for optimisation of life-of-mine schedules
• SOT (Schedule Optimization Tool)
• Context of selective underground mining
• Schedules of access development and production activities
• Precedence constraints
• Operational resource constraints
• Maximise NPV (net present value)
Parva Mine • portion of a real, undisclosed mine
• 58,141 blocks; 245 with mineralisation
• 25 × 25 ×25
• Constraints:
precedences
ore: 386,000 tonnes/year
total: 7.8 Mt/year
3 active faces: 1 ore, 2 waste
Integrated Optimisation
• Objective: maximise NPV
• In a single optimisation process, the evolutionary solver generates:
– ultimate pit,
– schedule of individual blocks and
– mineable nested pit shells.
Optimised Life-of-Mine Schedule Year
Ore mined (kilotonnes)
Waste mined (kilotonnes)
Gold production (kilograms)
Discounted cashflow (million $)
NPV (million $)
2013 675.0 14,095.6 2,210.3 4.6 4.60
2014 1,156.6 13,877.5 4,018.0 95.3 99.87
2015 651.4 13,188.0 2,459.8 47.2 147.06
2016 621.6 13,201.4 2,665.6 49.8 196.90
2017 439.2 12,523.6 1,740.2 24.5 221.39
2018 464.1 12,730.0 1,966.6 27.7 249.11
2019 791.7 12,012.4 2,945.3 45.9 295.01
2020 389.5 12,324.3 1,220.0 9.2 304.20
2021 295.3 12,395.9 1,084.5 6.5 310.67
2022 759.4 11,734.2 3,711.2 50.7 361.33
2023 590.6 6,368.6 3,557.3 50.0 411.32
Ultimate Pit
3,364 blocks
162 ore blocks
$411.32 million
Number of pit shells generated = total number of ore blocks
Nested pits are generated without artificially varying the economic value of blocks
Sensitivity Analysis: Number of active faces
Faces active
Waste faces Active
Cost of fleet (million $)
Mine life (years)
NPV (million $)
1 2 9.00 11.0 411.3
1 3 12.38 8.0 463.9
1 4 15.76 6.0 493.6
2 3 14.62 8.0 464.2
2 4 18.00 6.0 494.4
2 5 21.38 5.0 511.0
Future Work
• On-the-fly aggregation of blocks into working faces
• Constraints to limit proximity of working faces
• Application of solver to detailed schedule optimisation after haulage roads have been designed
• Stockpile management
• Grade control blending
Conclusion
• SOT can select the blocks of the ultimate pit and schedule them in one optimisation process
• As part of the same process, nested pits are generated
– No need to artificially vary the economic value of blocks
• Accommodates depth-varying costs and discounted cash flows
Thank you!