Run 16 RHIC Machine/Experiments Meeting 31 July 2016 Summary Slides 1
19

Run 16 RHIC Machine/Experiments Meeting07 April, resume √s = 200 GeV/n AuAu physics. 09 May, end √s = 200 GeV/n AuAu physics run begin setup for √s = 200 GeV/n dAu physics. 12

Sep 10, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Run 16 RHIC Machine/Experiments Meeting07 April, resume √s = 200 GeV/n AuAu physics. 09 May, end √s = 200 GeV/n AuAu physics run begin setup for √s = 200 GeV/n dAu physics. 12

Run 16 RHIC Machine/Experiments Meeting31 July 2016

• Summary Slides

1

Page 2: Run 16 RHIC Machine/Experiments Meeting07 April, resume √s = 200 GeV/n AuAu physics. 09 May, end √s = 200 GeV/n AuAu physics run begin setup for √s = 200 GeV/n dAu physics. 12

Run 16 as run

2

19 January, Begin cool-down to 4.5K 22 January, Cool-down to 6K in Blue 24 January, Blue and Yellow at 4.5 deg K 02 February, Beam in Blue and Yellow at injection 07 February, Begin √s = 200 GeV/n AuAu physics 18 March, Physics program interrupted to troubleshoot then replace Blue Sector 10

dipole 19 Quench Protection Diode. 07 April, resume √s = 200 GeV/n AuAu physics. 09 May, end √s = 200 GeV/n AuAu physics run begin setup for √s = 200 GeV/n dAu

physics. 12 May, Begin √s = 200 GeV/n dAu physics 20 May, end √s = 200 GeV/n dAu physics run begin setup for √s = 62.6 GeV/n dAu

physics. 21 May, Begin √s = 62.6 GeV/n dAu physics 27 May, end √s = 62.6 GeV/n dAu physics run begin setup for √s = 19.6 GeV/n dAu

physics. 28 May, Begin √s = 19.6 GeV/n dAu physics. 08 June, end √s = 19.6 GeV/n dAu physics run begin setup for √s = 38 GeV/n dAu

physics. 10 June, Begin √s = 38 GeV/n dAu physics. 17 June, end √s = 38 GeV/n dAu physics run begin setup for √s = 200 GeV/n AuAu

physics. 17 June, resume √s = 200 GeV/n dAu physics. 27 June, end √s = 200 GeV/n dAu physics run. End Run 16. 28 June, begin Cryo warm up. 01 July, cryo warm up completed.

Page 3: Run 16 RHIC Machine/Experiments Meeting07 April, resume √s = 200 GeV/n AuAu physics. 09 May, end √s = 200 GeV/n AuAu physics run begin setup for √s = 200 GeV/n dAu physics. 12

3

Page 4: Run 16 RHIC Machine/Experiments Meeting07 April, resume √s = 200 GeV/n AuAu physics. 09 May, end √s = 200 GeV/n AuAu physics run begin setup for √s = 200 GeV/n dAu physics. 12

From Ingrassia, http://www.cadops.bnl.gov/AGS/Operations/Run16/

Through final fill 20207, 27 June 2016 max/min projections from Fischer et.al. “RHIC Collider Projections (FY2014-FY2018)”, 4 June 2013

4

Page 5: Run 16 RHIC Machine/Experiments Meeting07 April, resume √s = 200 GeV/n AuAu physics. 09 May, end √s = 200 GeV/n AuAu physics run begin setup for √s = 200 GeV/n dAu physics. 12

5

0

50

100

150

200

250

0 1 2 3 4 5 6 7 8 9

Inte

grat

ed L

umin

osity

[nb^

-1]

Weeks in Physics

Run16 vs Run08 Delivered Luminosity d x Au √s = 200 GeV

Run16 integrated lumi STAR (0.44 ba. Lumi On/Off)Run16 integrated lumi PHENIX (0.50 ba Lumi On/Off)Run08 integrated lumi PHENIX (0.57 ba Physics On/Off)

Page 6: Run 16 RHIC Machine/Experiments Meeting07 April, resume √s = 200 GeV/n AuAu physics. 09 May, end √s = 200 GeV/n AuAu physics run begin setup for √s = 200 GeV/n dAu physics. 12

6

Page 7: Run 16 RHIC Machine/Experiments Meeting07 April, resume √s = 200 GeV/n AuAu physics. 09 May, end √s = 200 GeV/n AuAu physics run begin setup for √s = 200 GeV/n dAu physics. 12

7

Page 8: Run 16 RHIC Machine/Experiments Meeting07 April, resume √s = 200 GeV/n AuAu physics. 09 May, end √s = 200 GeV/n AuAu physics run begin setup for √s = 200 GeV/n dAu physics. 12

8

Page 9: Run 16 RHIC Machine/Experiments Meeting07 April, resume √s = 200 GeV/n AuAu physics. 09 May, end √s = 200 GeV/n AuAu physics run begin setup for √s = 200 GeV/n dAu physics. 12

Through Final Store 20207 26 June 2016

9

Page 10: Run 16 RHIC Machine/Experiments Meeting07 April, resume √s = 200 GeV/n AuAu physics. 09 May, end √s = 200 GeV/n AuAu physics run begin setup for √s = 200 GeV/n dAu physics. 12

Through Final Store 20207 26 June 2016

10

Page 11: Run 16 RHIC Machine/Experiments Meeting07 April, resume √s = 200 GeV/n AuAu physics. 09 May, end √s = 200 GeV/n AuAu physics run begin setup for √s = 200 GeV/n dAu physics. 12

11

0

100

200

300

400

500

600

700

800

2/1

2/8

2/15

2/22

2/29

3/7

3/14

3/21

3/28

4/4

4/11

4/18

4/25

5/2

5/9

5/16

5/23

5/30

6/6

6/13

6/20

6/27

7/4Lu

min

osity

per

day

[µb

-1]

Date in Run16

Run16 Luminosity Delivered to Phenix by day 100x100 GeV AuAu

Page 12: Run 16 RHIC Machine/Experiments Meeting07 April, resume √s = 200 GeV/n AuAu physics. 09 May, end √s = 200 GeV/n AuAu physics run begin setup for √s = 200 GeV/n dAu physics. 12

12

0.0

0.5

1.0

1.5

2.0

2.5

3.0

3.5

0 5 10 15 20 25

Del

iver

ed Lu

min

osity

by

Wee

k [n

b-1]

Weeks in Physics

Run16 Integrated lumi delivered to PHENIX by week 100x100 GeV AuAu

Page 13: Run 16 RHIC Machine/Experiments Meeting07 April, resume √s = 200 GeV/n AuAu physics. 09 May, end √s = 200 GeV/n AuAu physics run begin setup for √s = 200 GeV/n dAu physics. 12

23 January 2016, Blue and Yellow at 4.5 deg K

13

Page 14: Run 16 RHIC Machine/Experiments Meeting07 April, resume √s = 200 GeV/n AuAu physics. 09 May, end √s = 200 GeV/n AuAu physics run begin setup for √s = 200 GeV/n dAu physics. 12

Who’s Who for 2016

14

Page 15: Run 16 RHIC Machine/Experiments Meeting07 April, resume √s = 200 GeV/n AuAu physics. 09 May, end √s = 200 GeV/n AuAu physics run begin setup for √s = 200 GeV/n dAu physics. 12

Power Consumption

15

Page 16: Run 16 RHIC Machine/Experiments Meeting07 April, resume √s = 200 GeV/n AuAu physics. 09 May, end √s = 200 GeV/n AuAu physics run begin setup for √s = 200 GeV/n dAu physics. 12

16

Page 17: Run 16 RHIC Machine/Experiments Meeting07 April, resume √s = 200 GeV/n AuAu physics. 09 May, end √s = 200 GeV/n AuAu physics run begin setup for √s = 200 GeV/n dAu physics. 12

17

Page 18: Run 16 RHIC Machine/Experiments Meeting07 April, resume √s = 200 GeV/n AuAu physics. 09 May, end √s = 200 GeV/n AuAu physics run begin setup for √s = 200 GeV/n dAu physics. 12

18

Page 19: Run 16 RHIC Machine/Experiments Meeting07 April, resume √s = 200 GeV/n AuAu physics. 09 May, end √s = 200 GeV/n AuAu physics run begin setup for √s = 200 GeV/n dAu physics. 12

19