Royal Opera House Risk Assessment Form RA Number: RA TH01 Address: Studio 4, ACME Artists’ Studios, High House Production Park, Purfleet, Thurrock, RM19 1AS Bob and Tamar Manoukian Production Workshop and High House Production Park site,. Person(s) responsible for Show/ Task: Gabrielle Forster-Still/Stacey Campkin/ Joanne Dungate Show/Task: Inspiration Days Location/Area: Studio 4, the Bob and Tamar Manoukian Production Workshop and the High House Production Park site. Brief Description Of Show/Task: Assessment of safety for individuals and groups taking part in Inspiration Days. No. Hazard Those at Risk Risk Score Without control measures Control Measures – Must be implemented & communicated to all who may be affected Risk Score With control measures Additional control measures required Who will ensure actions are done? Required By Date actions complete Severity Likelihood Risk Severity Likelihood Risk 1 Slip/trip hazard Visitors and Staff 3 4 12 • ROH staff to ensure the spaces where community members are allowed are clearly marked out. • ROH staff to ensure designated spaces are clear of any obstacles. • Clear passage ways maintained at all times or avoided. • Acceptable light levels to be maintained throughout the building. • Any spillages to be cleared up immediately. 2 2 4 N/A Learning and Participation Manager / Officer / Apprentice / Host
4
Embed
Royal Opera House Risk Assessment Formstatic.roh.org.uk/learning/inspiration-day/... · Learning and Participatio n Manager / Officer / Apprentice/ Host 7 Physical Exertion Visitors
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Royal Opera House Risk Assessment Form
RA Number: RA TH01 Address: Studio 4, ACME Artists’ Studios, High House
Production Park, Purfleet, Thurrock, RM19 1AS Bob and Tamar Manoukian Production Workshop and High House Production Park site,.
Person(s) responsible for Show/ Task: Gabrielle Forster-Still/Stacey Campkin/ Joanne Dungate
Show/Task: Inspiration Days Location/Area: Studio 4, the Bob and Tamar Manoukian Production Workshop and the High House Production Park site.
Brief Description Of Show/Task: Assessment of safety for individuals and groups taking part in Inspiration Days.
No.
Hazard
Those at Risk
Risk Score Without control
measures
Control Measures –
Must be implemented & communicated to all who may be
affected
Risk Score With control
measures
Additional control
measures required
Who will ensure
actions are done?
Required by?
Required B
y D
ate actions com
plete Severity
Likelihood
Risk
Severity
Likelihood
Risk
1
Slip/trip hazard
Visitors and Staff
3 4 12 • ROH staff to ensure the spaces where community members are allowed are clearly marked out.
• ROH staff to ensure designated spaces are clear of any obstacles.
• Clear passage ways maintained at all times or avoided.
• Acceptable light levels to be maintained throughout the building.
3 2 6 • ROH staff to be briefed on first aid procedures • Designated first aiders on hand on site • All ROH staff to be aware of where the Security
reception is located and inform them in case of emergency
• All staff to make sure to report any first aid incidents according to ROH procedures
• Participants to be instructed how to use all equipment safely e.g. craft knives, irons, glue guns etc. Parents/carers to be responsible for supervising their children at all times including the use of any potentially dangerous equipment.
• ROH staff to issue child-friendly resources (e.g. prit sticks) to alleviate the need to use more advanced equipment.
2 2 4 ROH staff to use handheld radios to communicate with onsite security in the event of a severe first aid situation in order to seek additional help.
Learning and Participation Manager / Officer / Apprentice/Host
7 Physical Exertion
Visitors and Staff
2 2 4 • Patrons visit the viewing area of the paint shop which is on the second floor. To access this viewing area, patrons have the option to climb the stairs for the less energetic, take the lift. There is a chair in the viewing area for persons to rest, who may underestimate the stairs and over exert themselves.
2 2 4 • Disposable ear plugs are available for people who request them
Learning and Participation Manager / Officer / Apprentice/Host
ACCEPTANCE by Manager Responsible
I will ensure that the controls are implemented and, as a result, the above task/show under my control can proceed. Signature: Matt Lane
Date: July 3rd 2015
or
Risk Matrix
PROHIBITION by Manager Responsible
I am not satisfied the risk(s) identified are acceptable without the additional control measures being in place. I have therefore taken action to prevent the activity continuing until the requirements detailed in this action plan have been implemented.
Does the Show/Task need to be Risk Assessed again when the above controls are in place?