ROV Case Study EMAS’s Challenge Delta SubSea’s Solutions Mobilized onto MV EMAS Ambassador on November 7 th , 2013 to perform IMR work scopes in GoM. The project commenced on November 7 th , 2013 and DSS finished up the project February 2014 DSS delivered Schilling HD 150hp ROV and logged 849 ROV dive hours without any downtime The Ambassador in April 2014 commenced pigging operations with Baker Hughes in the Lucius field on the connector flowline. The project was completed early May 2014 On going IMR vessel support long-term for one ROV The project work scope entails: 24 hour IMR operations supporting EMAS Ambassador EDL lowering, placing and de-rig EFL installations Survey and well monitoring Remote start up DSS crew member securing LARS DSS Schilling HD 150hp ROV on EMAS Ambassador
1

ROV Case Study EMAS’s Challenge

May 27, 2022

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: ROV Case Study EMAS’s Challenge

ROV Case Study

EMAS’s Challenge

Delta SubSea’s Solutions •  Mobilized onto MV EMAS Ambassador on November 7th, 2013 to

perform IMR work scopes in GoM. The project commenced on November 7th, 2013 and DSS finished up the project February 2014

•  DSS delivered Schilling HD 150hp ROV and logged 849 ROV dive

hours without any downtime

•  The Ambassador in April 2014 commenced pigging operations with Baker Hughes in the Lucius field on the connector flowline. The project was completed early May 2014

•  On going IMR vessel support long-term for one ROV •  The project work scope entails:

–  24 hour IMR operations supporting EMAS Ambassador –  EDL lowering, placing and de-rig –  EFL installations –  Survey and well monitoring –  Remote start up

DSS crew member securing LARS

DSS Schilling HD 150hp ROV on EMAS Ambassador