Top Banner
General 1. If a PMP colleagues offers you exam questions, just refuse to take it and DO NOT report him to the PMI.  2. Each subsidiary plan contains a part include identification of this specific knowledge area change control  procedures. 3.  All control thresholds must be exist in the PM plans (Cost, Time, Quality, Risk)- the max. amount of variance that after it a corrective action must be taken. 4. Work Authorization System  , PMIS { change control system, configuration management system}  are an EEF not OPA. 5. EEF may be sometimes an opportunity or may be sometimes a threat or constraints. 6. EEF: company culture and existing systems= company baggage that comes with the project  outside PM modifications control (exclude manage and develop team). 7. Work Authorization system (EEF) ensures that work is started at RIGHT TIME and in proper sequence  only when approved, also defines how work is assigned to people 8. Objectives are determined in initiation and refined in planning. 9.  Audit used in execution (inspect sample), Inspection used in M&C (inspect all, appeared only twice: control quality (attribute) , verify scope (deliverables)) 10. Scope management plan determines the stability of the project through expected changes. 11. Each subsidiary plan contains a part include identification of this specific knowledge area change control procedures. 12. "Journey to Abilene" is a situation when we all agree with each other, but the decision doesn't please anyone. The result of this "journey" will be bad for everybody. 13. Laissez-faire is a management style: a manager of this type is not directly involved in the work of the team, but manages and consults as necessary, this can be appropriate for highly skilled people. 14. If a buyer needs are changes, the buyer may issue a change order to the contract.  15. Generally, only the buyer can terminate a contract.  16. Recommended corrective or preventive actions can come from the team or stakeholders in addition to the project manager. 17. 
41

Rofa Pmp Notes

Feb 23, 2018

Download

Documents

mpadala
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Rofa Pmp Notes

7/24/2019 Rofa Pmp Notes

http://slidepdf.com/reader/full/rofa-pmp-notes 1/40

General 

1. 

If a PMP colleagues offers you exam questions, just refuse to take it and DO NOT report him to the PMI. 

2. 

Each subsidiary plan contains a part include identification of this specific knowledge area change control

 procedures. 3. 

 All control thresholds must be exist in the PM plans (Cost, Time, Quality, Risk)- the max. amount of

variance that after it a corrective action must be taken. 

4. 

Work Authorization System , PMIS { change control system, configuration management system} are an EEF

not OPA. 

5. 

EEF may be sometimes an opportunity or may be sometimes a threat or constraints. 

6. 

EEF: company culture and existing systems= company baggage that comes with the project – outside PMmodifications control (exclude manage and develop team). 

7. 

Work Authorization system (EEF) ensures that work is started at RIGHT TIME and in proper sequence – 

only when approved, also defines how work is assigned to people 

8. 

Objectives are determined in initiation and refined in planning. 

9. 

 Audit used in execution (inspect sample), Inspection used in M&C (inspect all, appeared only twice:

control quality (attribute) , verify scope (deliverables)) 

10. 

Scope management plan determines the stability of the project through expected changes. 

11. 

Each subsidiary plan contains a part include identification of this specific knowledge area change control

procedures. 

12. 

"Journey to Abilene" is a situation when we all agree with each other, but the decision doesn't please

anyone. The result of this "journey" will be bad for everybody. 

13. 

Laissez-faire is a management style: a manager of this type is not directly involved in the work of the

team, but manages and consults as necessary, this can be appropriate for highly skilled people. 

14. 

If a buyer needs are changes, the buyer may issue a change order to the contract. 

15. 

Generally, only the buyer can terminate a contract. 

16. 

Recommended corrective or preventive actions can come from the team or stakeholders in addition to

the project manager.

17. 

Page 2: Rofa Pmp Notes

7/24/2019 Rofa Pmp Notes

http://slidepdf.com/reader/full/rofa-pmp-notes 2/40

Schedule is usually cut (by compression), SCOPE NOT. 

18. 

Operations and maintenance are considered ongoing activities, not temporary. Therefore, such work is

not considered a project or part of a project. 

19. 

Scope, time, cost, quality, risk, resources, and customer satisfaction is the most accurate list ofconstraint. 

20. 

if PM report false info, meet him first, before meeting with his boss. 

21. 

ROI It is the time when cumulated net income is equal to the investment. 

22. 

In project management, the sequence of project phases and phase gates is often referred to as project

life cycle. 

23. 

lessons learned should NOT document the key persons or group cause delays or failures. 24. 

effective = right time & right format. 

25. 

It’s usually the sponsor  default for not giving clear directions for project objectives. 

26. 

a milestone is a constraint. 

27. 

The contract may be considered (serve as) a project charter. 

28. 

Output from all 42 processes is stored in PMIS. 

29. 

The five areas of expertise in the project management team include 

 

The project management body of knowledge (PMBOK) 

 

 Application area knowledge, standards and regulations 

 

Understanding the project environment 

 

General management knowledge and skills 

 

Interpersonal skills 

30. 

The management of interpersonal relationships includes

 

1) communication

 

2) influence

Page 3: Rofa Pmp Notes

7/24/2019 Rofa Pmp Notes

http://slidepdf.com/reader/full/rofa-pmp-notes 3/40

 

3) leadership

 

4) motivation

 

5) negotiation 

6) problem solving 

31. 

Chart of accounts: Any numbering system that is used to monitor project costs by category such as

labor, supplies, or materials. 

32. 

PDCA: plan, do, control, act is a continuous process improvement 

33. 

Malcolm Baldrige continuous improvement. 

34. 

 A project may be started without a contract when: the customer is internal, or the project is in hurry

instead LOI (letter of intent). 

35. 

Projects are authorized by someone external to the project: project sponsor, or PMO or portfolio steering

commute. 

36. 

Determining the initial project organization is a project initiating function. 

37. 

Product scope description: The documented narrative description of the product scope 

38. 

Deliverable: any unique and verifiable product, result or capability to perform a service that must be

produced to complete a process, phase or project. 

39. 

We proactively and fully disclose any real or potential conflicts of interest to the appropriate

stakeholders.We treat the appearance of conflict of interest as a conflict of interest. 

40. 

Joke telling MAY be inappropriate in a diff. culture. 

41. 

If you offered a gift from a culture that has giving gifts is custom, consult your management. 

42. 

One generally needs to work within the laws and customs of the host country (e.g. wage rates). 43. 

Understanding the personal characteristics of a team member, is not considered to be a part of

understanding the cultural and social environment. 

44. 

When phases are sequential, the close of a phase ends with some form of transfer or handoff of the work

product produced as the phase deliverable. This phase end represents a natural point to reassess the

Page 4: Rofa Pmp Notes

7/24/2019 Rofa Pmp Notes

http://slidepdf.com/reader/full/rofa-pmp-notes 4/40

effort underway and to change or terminate the project if necessary. These points are referred to

as phase exits, milestones, phase gates, decision gates, stage gates, or kill points. 

Chapter 2 & 3: 

1. 

Payback period: the length of time it takes for the organization to recover its investment in the

projectbefore it starts accumulating profit. (the less the better). Discount rate is not taken into account in

calculations of Payback Period 

2. 

IRR the rate at which the project inflows equal to project out flows (higher the better). 

3. 

IRR at which the net present value = 0. 

4. 

IRR: The inherent discount rate or investment yield rate produced by the project's

deliverables over a pre-defined period of time. لذه

5. 

IRR: The annualized effective compound return. 

6. 

Discount rate: used to assess the uncertainty (risk) in future cash flow. 

7. 

PV = FV / (1+i)^n (PV1-PV2)/ PV1 

8. 

Cost Benefit Analysis: Benefit/cost – benefit is revenue not profit. 

9. 

Opportunity cost is the value of the project that was not selected. 

10. 

Sunk costs: cost that has already been incurred and thus cannot be recovered. (should not be considered

when deciding whether to continue on a project or not) – Costs to bring the project to its current state 

11. 

Working capital: Assets- liabilities (amount of money available for a company to invest). 

12. 

Organizational process assets: process & procedures  – corporate Knowledge database  – Historical

Information  – lessons learned. 

1. 

Project managers in weak matrix organizations acts like (project expeditor, project

coordinator, project leader) - with limited authority. 

13. 

Functional (( Expeditor (less) THEN coordinator (more) )). 

14. 

Project manger exists even in functional organization. 

15. 

Project manager reports to manager of project managers in the strong matrix organization. 

16. 

Page 5: Rofa Pmp Notes

7/24/2019 Rofa Pmp Notes

http://slidepdf.com/reader/full/rofa-pmp-notes 5/40

Who controls project: FM – FM - Mixed – PM – PM. 

17. 

In a matrix organization: the PM can request from the FM to participate in a team member annual performance

review. 

18. 

Composite is like strong matrix with 2 types of projects running. 19. 

Phase to phase relationship: 

20. 

Sequential: 

1. 

phase can only start once the previous phase is complete 

2. 

The step-by-step nature of this approach reduces uncertainty, but may eliminate options for reducing

theschedule. 

21. 

Overlapping: 

1. 

Phase starts prior to completion of the previous one. 

2. 

Example of the schedule compression technique called fast tracking. Overlapping phases may increase risk

and rework. 

22. 

Iterative: 

1. 

Largely undefined, uncertain, or rapidly changing environments such as research. 

2. 

It can reduce the ability to provide long term planning. 

3. 

Scope is managed by continuously delivering increments of the product and prioritizing requirements. 

4. 

Entail having all of the  project team members available throughout the project or, at a minimum, for two

consecutive phases. 

5. 

 An iterative phase‐to‐phase relationship allows you to begin planning for the next phase before the phase

you're working on is completed. 

23. 

Overlapping /Fast tracking is where the work of the next phase begins before the phase you're working on is

completed. 

24. 

Costs and staffing levels are LOWEST early in the life cycle, peak while the project work is

underway, and then drop off as the project nears completion. 

25. 

Page 6: Rofa Pmp Notes

7/24/2019 Rofa Pmp Notes

http://slidepdf.com/reader/full/rofa-pmp-notes 6/40

Risk  is highest early in the project since uncertainty is high about the  project’s deliverables, resource needs,

and work required. 

26. 

Standards are guidelines or a preferred approach (i.e. ISO) and regulations are government-imposed

requirements such as laws (i.e. EPA, contract law) 

27. 

Kick off meetings are conducted in the start of each phase. 

28. 

Company code of conduct contains: business practices, guidelines for situations. 

29. 

Stage Cost and staffing Uncertainty Cost of changes

& Risk  &

stakeholder Influence 

30. 

Starting the project/ Initiation Low High

Low31. 

Organizing and preparing/Planning  Increases Decreases

Increases

32. 

Carrying out the work/ execution- M&C  Peaks Decreases

Increases

33. 

Closing the project/closing  Decreases Low High 

34. 

The project manager's influence is greatest in the project closing processes. 

35. 

Project life cycle can exist independent of product life cycle 

36. 

Project life cycle can run concurrently with product life cycle or form part of product life cycle 

37. 

 A single product life cycle can consist of many multiple Project life cycle 

38. 

 A product life cycle can completed during A single-phase Project. 

39. 

Deliverables are determined in part by the customer, not only by the project sponsor. Deliverables

are identified in the project charter. 40. 

Program success is measured by meeting its benefits. 

41. 

The number of years is already included in the calculation of NPV. You simply pick the project with the

highest NPV. 

42. 

Page 7: Rofa Pmp Notes

7/24/2019 Rofa Pmp Notes

http://slidepdf.com/reader/full/rofa-pmp-notes 7/40

Weak matrix organizations tend to experience the least amount of stress during the Closing processes. 

Integration Management 

1. 

Project statement of work- developed by the sponsor as input to develop project charter process: 

1. 

Business case. 

2. 

Product scope description/ deliverable. 

3. 

Strategic plan (organization's strategic goals). 

2. 

 You are carrying out a project to produce either a service or product. The project work itself is the

process and the service or product you produce is the output of this process. 

3. 

Project selection committee/ project selection panel /Portfolio managers/ portfolio review board – mayinclude PMO- is responsible for selecting projects. 

4. 

They review each project for its return on investment, the value of the project, risks associated with

taking on the project, and other attributes of the project. 

5. 

The project manager is not typically involved in project selection (i.e. the PM is neither involved nor

responsible for conducting neither cost benefit ratio nor any selection technique). 

6. 

Change Management plan defines how you will manage changes to the deliverables and resulting

documentation. 

7. 

Change management plan controls the project to the baseline NOT ONLY how to implement a change. 

8. 

Change management plan contains: change control procedures, Board, meeting attendees, authority

level, tool to control. 

9. 

Scoring model, peer review, murder board, economic methods (PV, NPV, Cost Benefit, IRR, payback

period) are comparative methods /benefit measurement methods for selecting a project. 

10. 

Constrains optimization / mathematical (programming). 

11. 

Whenever a large number of changes occur on a project, it is wise to confirm that the business case

(stated in the project charter) is still valid. 

16. 

Each; the seller and the buyer create his own project charter. 

17. 

Page 8: Rofa Pmp Notes

7/24/2019 Rofa Pmp Notes

http://slidepdf.com/reader/full/rofa-pmp-notes 8/40

When a project deviates significantly from a baseline, the project manager should revisit the risk

management process (the problem is incomplete risk identification). 

18. 

Most probably, the changes root cause is poor planning or risk identification. 

19. 

PMIS contains: change control system and configuration management system. a. 

Configuration management system: TECHNICAL procedures to identify and document the functional and

 physical characteristics of a product, result, service, or component. 

b. 

Change control system: procedures to define how project deliverables and documentation will be controlled,

changed and approved. 

c. 

Change control system is subset of configuration management system. 

d. 

Configuration Control and Change Control are distinct in the following ways: i. 

Configuration Control addresses the management of the product (or project's deliverables), whereas

Change Control addresses the management of the project. 

ii. 

Configuration Control manages changes to the  product baseline, whereas Change Control manages

changes to the project baseline. 

iii. 

Configuration Control is applied throughout the lifecycle of the product (concept->design-

>develop/manufacture->service->dispose), whereas Change Control is applied during the lifecycle of the

project subsequent to establishing the project baselines. 

20. 

The change management plan  directs how changes to the “process” need to be done, while theconfiguration

management pl an  directs how changes to the “output” need to be done. 

21. 

Configuration management involves making sure that everyone is working off the same documents. 

22. 

Configuration management validates and improves the project by evaluating the impact of each change. 

23. 

Configuration management is set of procedures developed to ensure that project design criteria are met. 

24. 

 An updated scope statement exists in a change control system, configuration management system (allchanges must be documented there). 

25. 

The project management plan must be approved by the project sponsor , management, project team. 

26. 

The PM must take the resources manager approval for the schedule to guarantee resources availability. 

27. 

Page 9: Rofa Pmp Notes

7/24/2019 Rofa Pmp Notes

http://slidepdf.com/reader/full/rofa-pmp-notes 9/40

 Any (change request) corrective action/ Preventive action/ Defect repair that will require a change to the

project management plan, baselines, procedures and process, charter, contact, statement of work require

a formal change request, to be reviewed and approved or rejected as part of perform integrated change

control. 

28. 

Most project documents are created by the project manager for his or her use during the project, and donot require outside approval for changes (e.g. stakeholder register, Req. trace ability matrix). 

29. 

Project charter  and change in  project charter  must be approved by sponsor. 

30. 

Change control system includes documentation of the process for making changes. 

31. 

Sometimes, certain classifications of changes get automatic approval on a project by PM and do not need

a change control board's approval (e.g. in an emergency) using the outlines in the configuration

management system. 

32. 

The project team might have discretion to approve changes within certain parameters without CCB

approval. 

33. 

Change control system includes procedures to handle changes by PM (e.g. in an emergency) which is

called configuration management system. 

34. 

The PM may have the authority to approve a change if it doesn’t require a change in one of the key

project documents (listed in the previous point). 

35. 

If excessive number of change requests occurs, revalue the business case or consider terminating a

project and start a new one with more complete set of requirements. 

36. 

One of the ways to decide if a change should be approved is to determine whether the work falls within

the project charter, project scope statement, business case, ??. 

37. 

 Any change that has reserve (previously indentified risk event) should be handled as part of the risk

management instead of change management. 

38. 

It is not wise to decrease the impact of every change (thus may lead to decrease the overall project

success probability). 

39. 

Status of the change is recorded in the change control system {{change request status}} (output of

perform integrated change control process). 

40. 

In exam, assume all projects have change control board. 

41. 

Maintain a baseline = update 

42. 

Page 10: Rofa Pmp Notes

7/24/2019 Rofa Pmp Notes

http://slidepdf.com/reader/full/rofa-pmp-notes 10/40

Work performance information, about the completion status of the deliverables and what has been

accomplished, is collected as part of project execution (direct and manage project execution) and is fed

into the performance reporting process. 

43. 

 Adding milestones is a control feature. (i.e. if a milestone is completed on time and on budget, the

project manager has some measure of the status of the project). CONTROL = MEASURE andINSPECT/AUDIT 

44. 

Procurement/ project Closure must make sure the actual product of the project meets the requirements

for the product. 

45. 

PM Directing role occurs while the project management plan is being created (planning). 

46. 

PM integration role occurs during project execution. 

47. 

Once the project charter is completed (the project is formally authorized), so the cost benefit analysisdetermines project is worthy. 

48. 

Project charter authorizes the start of a new project or a new phase. 

49. 

Work must be start in project charter, only if a contract is signed. (or at least letter of intent ) ta2lefa  

50. 

If a product of a project was not used, maybe be that either the project manager did not identify the

requirements of all the stakeholders or that the business need for the project changed dramatically and

the project manager did not notice. 

51. 

Documents are collected throughout the project and archived during the Close Project or Phase process. 

52. 

Changes MUST be approved (output from perform integrated change control- output

approved),implemented (through direct and manage project- input approved), and validated (control

quality  –  Input approved & output validated). 

53. 

Work for each phase must be inspected and accepted before the phase can be closed out. 

54. 

There is no need to request a change request if the project is on the planning phase. 

55. 

The project charter should be broad enough not to change as the project progress. 56. 

Management plan documents the strategy of managing the project. 

57. 

PM plan itself is a deliverable. 

58. 

Process configuration (Process flow chart) A graphic depiction of processes, with interfaces identified,

used to facilitate analysis. 

Page 11: Rofa Pmp Notes

7/24/2019 Rofa Pmp Notes

http://slidepdf.com/reader/full/rofa-pmp-notes 11/40

59. 

Using resources that do not charge against the project is unethical. 

60. 

The need for integration is one of the major driving forces for communication in a project. 

61. 

The project manager should determine if a change is needed and if the change is beneficial. 62. 

Team assist in recording lessons learned, so they can't be released until the lessons learned are

documented and added to the organizational process assets. 

63. 

 A project is complete when all work, including all project management work (e.g. lessons learned) is

complete not just deliverables, is accepted. 

64. 

With only the formal acceptance can the project manager be sure the project work  is really

complete NOTthe project. 

65. 

ADMINISTRAIVE CLOSURE Closing a project (termination, stops, completion): - NO AUDIT 

1. 

Confirm work is done to req. 

2. 

Complete procurement closure (can be done even before project closure). 

3. 

Gain final deliverable acceptance project work is done 

4. 

Complete financial closure (take my money). 

5. 

Hand off product. 

6. 

Solicit feedback from the customer. 

7. 

Complete final performance reporting. 

8. 

Update lesson learned. 

9. 

Index & archive records (lessons learned & final report are part of project records). 

10. 

Release team. 11. 

Close contract. 

66. 

 A defect is any deliverable that does not meet its requirements; team members' errors only cause some

defects. 

67. 

Preliminary scope statement: In Initiation. 

Page 12: Rofa Pmp Notes

7/24/2019 Rofa Pmp Notes

http://slidepdf.com/reader/full/rofa-pmp-notes 12/40

68. 

The change control board approves changes only after agreeing on its impact with the customer . 

69. 

If a customer needs to make a change, the PM FIRST should request him to submit a request for

changebefore even meet with the team to discuss it. 

70. 

Change control systems are a subset of the configuration management system. 

71. 

The PM may write the project charter, but must be authorized by someone outside the project. 

72. 

Verification. The evaluation of whether or not a product, service, or system complies with a regulation

requirement, specification, or imposed condition. It is often an internal process. 

73. 

Validation. The assurance that a product, service, or system meets the needs of the customer and other

identified stakeholders. It often involves acceptance and suitability with external customers. Contrast

with verification. 74. 

The process of making a change: 

1. 

Prevent the root cause of change. 

2. 

Identify the change. 

3. 

Look for the change impact. BEFORE create a change request. ??? 

4. 

Create the change request (follow the change request procedure). 

5. 

Perform integrated change control 

1. 

Evaluate/ assess the change. 

2. 

Page 13: Rofa Pmp Notes

7/24/2019 Rofa Pmp Notes

http://slidepdf.com/reader/full/rofa-pmp-notes 13/40

Look for options (and bring them to the board if they will take the decision). 

3. 

PM take decision on non-updated changes, board change management take the decision (accept or

reject) for the other changes. PM/sponsor may be member of change board. 

4. 

Update the status of the change in the change control system. 

6. 

THEN adjust the required project document. 

7. 

THEN communicate the change to the affected stakeholders. 

8. 

Manage the project according to the updated documents. 

75. 

First document the requested change, then follow the integrated change control process: ???? 

1. 

Evaluate the impact. 

2. 

Develop options. 

3. 

Get the change request approved internally. 

4. 

Get customer buy-in. 

76. 

WBS is All the work  that must be completed for the project NOT All the tangible items that must be

delivered to the client 

77. 

Page 14: Rofa Pmp Notes

7/24/2019 Rofa Pmp Notes

http://slidepdf.com/reader/full/rofa-pmp-notes 14/40

Morale is improved when smooth transitions to upcoming projects are already planned. A staff

release plan also helps mitigate human resource risks that may occur during or at the end of a

project. 

Scope Management: 

1. 

Code of accounts: It is the collection of unique identifiers generally assigned to WBS items. 

2. 

WBS is All the work that must be completed for the project NOT All the tangible items that must be

delivered to the client 

3. 

Requirements gathered in stakeholder analysis need to be quantifiable (nothing like “increase 

productivity”). 

4. 

 A scope verification plan is part of the scope management plan. 

5. 

Scope management plan determines the stability of the project through expected changes. 6. 

Historical data and lessons learned can be used to collect the requirements for a new project (what

requirements were for a similar projects). 

7. 

WBS and Affinity Diagram help identify new risks (scope). 

8. 

Product analysis/Value analysis/ value engineering: focus on finding less costly way to perform the same work

(scope). 

9. 

Identifying requirements can lead to identify more. 

10. 

Decision Making ways: unanimously , dictatorship, consensus (new diff.

agreement), plurality , majority(more than half). 

11. 

What is the diff. between stakeholders interests, needs, wants, and expectations? 

12. 

Project Scope Statement a narrative description of the project scope, contains: 

1) 

Project scope 

2) 

Product scope 3) 

Deliverables 

4) 

Product acceptance criteria 

5) 

Exclusions 

6) 

Page 15: Rofa Pmp Notes

7/24/2019 Rofa Pmp Notes

http://slidepdf.com/reader/full/rofa-pmp-notes 15/40

Constraints and assumptions. 

16. 

Project charter contains product scope description / deliverable 

13. 

Preliminary project scope statement is done during initiation while project scope statement done duringplanning. 

14. 

Customers do not approve the project scope (what you are going to do to complete their requirements);

instead, they approve the  product scope (their requirements). 

15. 

Balancing stakeholder requirements involves prioritizing requirements (by order of importance) and

resolving conflicts. 

16. 

To resolve competing requirements, accept the requirements that only comply with: 

1) 

Business case. 

2) 

Project charter. 

3) 

Project scope statement. 

4) 

Project constraints. 

17. 

WBS dictionary contains all information about activity: description, assignee, duration, cost, risk,

dependency, assumption, success criteria, due date 

i. 

The WBS PROOF that an end of resource, fund, time. Because WBS dictionary contains due

date/duration/assineeg of a WBS. 

ii. 

WBS dictionary and work authorization system prevents scope creep = uncontrolled changes. Because of

activity description. 

iii. 

WBS must be iterated after cost, schedule, time, risk, resources. Planning is iterative. 

18. 

WBS dictionary can be part of work authorization system (include when to start a task). 

19. 

WBS contains full project scope (not only product scope). 

20. 

WBS can be used to evaluate impact of other changes on project scope. 

21. 

WBS can be used to see if the change request is within the project scope. 

22. 

WBS can be structured as an outline, an organizational chart, a fishbone diagram, or other method. 

23. 

Page 16: Rofa Pmp Notes

7/24/2019 Rofa Pmp Notes

http://slidepdf.com/reader/full/rofa-pmp-notes 16/40

 Verify scope is work with the customer to accept the interim deliverable (or phase deliverable) otherwise

make change request to it (accepted deliverable). 

24. 

Make a verify scope before moving to another phase. 

25. 

The 8/80 hour rule of thumb suggests that, when creating a WBS, you break down the work to workpackages of a minimum of 8 hours and a maximum of 80 hours. Applying this rule contributes to more

accurate estimates later in project planning. The better choice is to compose it until a managed

component. 

26. 

Req. traceability matrix helps link project requirements with other requirements or with project

objectives to ensure strategic goals are accomplished. 

27. 

Req. traceability matrix tracks the requirement through the project life cycle. 

28. 

Subdividing deliverables = creating WBS 29. 

Subdividing work packages = decomposition (creating activities). 

30. 

Project life cycle Deliverable {{control account work packages activities}} WBS 

31. 

Each level of a WBS is a smaller segment of the above level. 

32. 

 A project manager cannot be responsible for the customer's inspection process, only his own. 

33. 

Requirements are used to measure the completion of the product of the project (product scope). 

34. 

 A team member has flexibility at the work package level to make some changes as long as they

are within the overall scope of the WBS dictionary. 

35. 

Scope verification (Verify Scope process) focuses on customer acceptance of a deliverable. Product

verification (Close Procurements process) is focused on making sure all the work is completed satisfactorily. 

36. 

Scope verification is monitoring and control, product verification is a closure activity. 

37. 

Product analysis used to analyze the product and product objectives and turn them into deliverables

(tangible deliverables). 38. 

 All stakeholders determine the project requirements. That’s why stakeholder register is input to collect

requ. 

39. 

The level of uncertainty in scope increases based on the scale of effort required to identify all the scope. 

40. 

Page 17: Rofa Pmp Notes

7/24/2019 Rofa Pmp Notes

http://slidepdf.com/reader/full/rofa-pmp-notes 17/40

If you are building a house, the house itself is the product scope. The planning, coordination and

management of the work to be done to ensure the product scope is achieved are aspects of project

scopemanagement. 

41. 

The scope management plan covers both product and project scope. 

42. 

 A change request is the most effective way of handling the disconnection between what users actually

want and what management thinks they want. 

43. 

Project scope statement is DOU. 

44. 

WBS is not needed in verify scope, instead validated deliverables. 

45. 

Performance requirements: what the product of the project should be able to accomplish. 

46. 

Requirements, constraints, assumptions exist in project scope statement. 47. 

Code of account identifier: code for each activity define the control account it follows. 

48. 

1st appearance Project assumptions in project initiation: project charter, 2nd project assumptions: project scope

statement, 3rd  activity assumption: activity attribute, 4th  requirements assumption: requirements documentation. 

49. 

 Assumptions are not existing in the project charter. 

50. 

Quality control is generally performed before scope verification, but these two processes can be

performed in parallel. 

51. 

Inspection in verify scope measuring, examining, and verifying to determine whether work and deliverables

meet requirements and product acceptance criteria. 

52. 

Impact of scope changes can be determined through WBS NOT scope statement, as WBS dictionary

contains many many information. 

53. 

It is not common that all deliverables need to be audited. 

54. 

We may start execution and not all product requirements are known (completed product req. is done in

execution). 55. 

Prototypes (collect requirements tool) support the concept of progressive elaboration because they are

used in iterative cycles of mock-up creation, user experimentation, feedback generation, and prototype

revision. 

56. 

Using subprojects which may be developed by organizations outside the project team is the least likely in

creating WBS. 

Page 18: Rofa Pmp Notes

7/24/2019 Rofa Pmp Notes

http://slidepdf.com/reader/full/rofa-pmp-notes 18/40

57. 

Requirements management plan: how requirements/product scope will be analyzed, documented, and

managed throughout the project. 

58. 

Scope management plan: how the project scope will be managed and controlled. 

59. 

Completion of the project scope is measured against the project management plan/scope management

plan. 

60. 

Completion of the product scope is measured against the product requirements / requirements management

plan. 

61. 

Requirements documentation: 

1) 

Business need. 

2) Project objective. 

3) 

Functional requirements. 

4) 

Non-functional requirements. 

5) 

Quality requirements. 

6) 

 Acceptance criteria. 

7) 

Training requirements. 

8) 

Requirements assumptions and constraints. 

62. 

Do not simply accept project charter or project statement of work, instead first check for stakeholder

involvement. 

Project Time Management 

1.  Rolling wave planning (form of Progressive elaboration) is a tool in define activities. 

2.  Unrealistic schedule is due to planning is not performed in iterations. 

3.  Most project schedules are compressed by the project manager during project planning. 

4.  Rolling wave planning, you plan activities to the detail needed to manage the

work only when you start that phase. 

5.  Sponsor may impose milestones and include it in the project charter, but generally

milestones - during initiation- in the project scope statement (form of schedule constraint). ? 

6.   After setting some milestones in the "define activity" process, some milestones may be

added during the "sequence activity" or "schedule activity" processes. 

7.  While fast track, look at discretionary dependencies. 

Page 19: Rofa Pmp Notes

7/24/2019 Rofa Pmp Notes

http://slidepdf.com/reader/full/rofa-pmp-notes 19/40

8.  fast track increase risk and rework. 

9.  Sequencing activities may reveal new risks that added to the risk register. 

10.  One point estimates should only be used for projects that do not need detailed and reliable

schedule. 

11.  Bottom up estimation –estimate activity RESOURCES  – divide each activity into

smaller components in order to estimate it.- Most accurate 

12.  Analogous estimation (Top Down): - least accurate 

1- 

Look at activities from previous similar activities. 

2- 

The degree of similarity affects accuracy. 

3- 

Used early in the estimating cycle when there is not much detail known about the activity. 

4- 

Uses historical information and expert judgment. 

5- 

It is less costly, less time consuming than others, and least accurate. 

6- 

For reporting purposes to sponsor or senior management (high level estimation). 

13.  The project manager needs more than an analogous (high-level) estimate to determine

whether or not the project will meet the schedule. 

14.  Analogous project estimate help PM have an understanding about management's

expectations of what the project will cost. 

15.  The results of parametric estimating can be rule of thumb (total var. = 0.3*dev. Var.) 

16.  Parametric estimates don’t require input from team  --  just historical data (3 data points) 

17.  PERT = 3 estimates 

18.  Activity with the highest variance has the highest risk. 

19.  Negative project float means that the estimated completion date is after the desired date. 

20.  Options to shorten the schedule: 

a. 

Re-estimate – through revisiting risks (look for activity with the most unknowns and revisit risk). 

b. 

Compress – through fast track or crash. 

c. 

Cut scope. 

d. 

Reduce quality. 

e. 

Stay to your ground. 

f. 

Work overtime. 

21.  Monte Carlo simulation (what if scenario analysis) use PERT (3 point estimates). 

Page 20: Rofa Pmp Notes

7/24/2019 Rofa Pmp Notes

http://slidepdf.com/reader/full/rofa-pmp-notes 20/40

22.  Resource leveling: keep the number of resources the same and letting time and cost be flexible

(e.g. limited availability, limited resources) 

23.  Resource leveling: when shared or critical resource are only available at certain times or are only

available in limited quantities (one team member assigned to tasks to occur at the same time). 

24.  Resource leveling can be applied to any resource (human, equipment, …) 

25.  WBS is better than BAR chart = GANT chart as it is a weak planning tool, but a good tool

forcontrol (track progress) and reporting to the team as it doesn’t show dependency nor resources. 

26.  Logic bar chart: time scaled schedule network diagram showing dependencies among activities. 

27.  Milestone chart (form of schedule) = customer and senior management. 

28.  Network diagram: shows dependency. 

29.  Project team performance is measured against project schedule. 

30.  Recommend terminating the project due to schedule problems is part of control schedule. 

31.  The only certain impact of a scope change is a schedule change to shorten or lengthen

subsequent activities. 

32.  Control schedule means looking for the things that are causing changes and influencing thesources of change. 

33.  Expected risk did not materialize, may lead to a finish a project earlier. 

34.  Critical chain method focuses on managing remaining buffer duration against the remaining

duration of activity chain. 

35.  Critical chain is a schedule network analysis technique that modifies the project

schedule to account for limited resources. The critical chain method adds duration buffers that

are non-work schedule activities to manage uncertainty. (FS only) (project- feeding – 

resources buffers). 

36.  It is not practical to limit the scope of the changes. Each change request needs to be

evaluated as a separate entity. 

37.  Total float (or slack) is the amount of time an activity can be delayed without impacting the

project completion date. 

38.  Total float = EF- ES 

39.  Free float: the amount of time an activity can be delayed without delaying the early start dateof

the successor activity. 

40.  Free float = ES (of successor) - EF (current activity) 

41.  Free float is usually less than or equal to total float. 

42.  Project Float: It's only applicable when there's a duration constraint on the entire project. If the

critical path (longest duration) is 17, if the project had a constraint of 20, = the project float = 3. 

43.  Project float is a delay of a project that cannot delay the start of the next project. 

44.  When options of both free float and total float, we need to go to free float as free float

affects immediately following activities. 

45.  If an indentified risk occurs, which has an already contingency reserve, the PM

(not the sponsor) can approve the change, as it doesn’t change the PMP. 

46.  To shorten the duration of a project, shorten the earliest activity on the critical path. 

Page 21: Rofa Pmp Notes

7/24/2019 Rofa Pmp Notes

http://slidepdf.com/reader/full/rofa-pmp-notes 21/40

47.  Crashing focus on critical path activity to obtain the greatest amount of compression for the

least incremental cost, even if there is a late and risky critical path activity. 

48.  Project schedule is a living document reflecting the actual state of the schedule and updated

frequently. 

1- 

Schedule baseline is a frozen document, revised only as a result of change request. 

2- 

To measure schedule performance compare schedule baseline (plan) with the project schedule (actual). 

3- 

In the beginning of project execution, the project schedule is the same as schedule baseline. 

4- 

Schedule Baseline is an "approved" version of the Project Schedule. 

49.  In beginning of execution, project schedule = schedule baseline. As the project schedule is

being updated to reflect changes in scope or actual data, the schedule baseline is maintainedas

the original baseline for  post- project evaluation. 

50.  More interdependencies on a project increase the need for communication. 

51.  Effort: the number of labor units required to complete a schedule activity or WBS component.

Usually expressed as staff  hours, staff  days, or staff  weeks. (Requirements for effort

estimation: The Expert Judgment, Task Complexity, Skill Level, and Expectations). 

52.  Duration: the total number of work periods (not including holidays and non-working

 periods)required to complete a schedule activity or WBS component. Usually expressed

as workdaysor workweeks. (Requirements for Duration estimation: Resource Availability and

Resource Capability). 

53.  Elapsed Time: Waiting periods (weekends and vacations). 

54.  Schedule network analysis: - Develop schedule- tool generates the project schedule,

(use critical path method, critical chain method, what-if analysis, and resource leveling) to

calculate the early and late start and finish dates for the uncompleted

portionsof   project activities. develop schedule before execution and during execution. 

55.  Stdev = square root ( ((p-o)/6)̂ 2 + (p-o)/6)^2 + (p-o)/6)^2 + …) 

56.  Circle = change, Square = Decision 

57.  Milestone list is added to: Project charter, PMP plan, Project scope statement, WBS

dictionary à in form of constraint. 

58.  when activity is completed even if completed one month later, so PV=EV, SPI =1, SV

= 0

59.  After a project completion , if SV doesn’t equal to 0 , so project is terminated. 60.  As the number of critical paths increase, the estimated due completion date become less

achievable. 

61.  External (government, rules,…) and mandatory = Hard (inherent in the project orproduct

nature or contractually) 

62.  Discretionary dependency can make arbitrary total float and limit your scheduling options. 

Page 22: Rofa Pmp Notes

7/24/2019 Rofa Pmp Notes

http://slidepdf.com/reader/full/rofa-pmp-notes 22/40

63.  Hammock activity is the one span between two points in the schedule and summarize the detailed

activities between them. 

64.  The schedule data for the project schedule includes at least the schedule milestones,

schedule activities, activity attributes, and documentation of all identified assumptions and

constraints. 

65.  Activity list is not an extension of and a component of the WBS (WBS stops at the work

package level). 

66.  AOA = ADM 

67.  AON = PDM = schedule network = one time estimate 

68.  GERT allow for loops and conditions. 

69.  Analogs estimation is fort of expert judgment. 

70.  Convergence = many to 1 – divergence = 1 activities to many 

71.  Calculating free floats and total float are not reasonable for a finished activity. 

Cost Management: 

1.  Fringe benefits are included in overhead and are part of indirect costs. 2.  ROM +-50 (initiation), definitive Budget -10 25 % (planning), Definitive +-

10% (-5% 10%) (planning). 

3.  Parametric estimates can be used in estimate cost, or can be used as sanity check  in determine

 budget. 

4.   A fixed cost is a non-recurring cost that will not change as the project progresses 

5.  Life Cycle Costing includes Acquisition, Operation, Maintenance, and Disposal Costs. 

6.  Team budgeted 3000 $ for work performed: EV. EV = BCWP 

7.  Team budgeted 2000 $ for work scheduled: PV. PV = BCWS = the cost of the work that has

been authorized and budgeted for a WBS component 

8.   AC = ACWP. 

9.  EAC means anticipated total cost at project completion. 

10.  Cost risk  is the risk that project costs could go higher than planned.

11.  Cost variance and schedule variance are negative, but the cost variance is lower than the

schedule variance: The project under spent because all work was not completed, but

overspent for work that was done. 

12.  Labor rates, resources used, and poor communications could all have contributed to the cost

overrun. Lag 

13.  Funding limit reconciliation concerns reconciling the funds to be spent on the project with

funding limits placed on the funding commitments for the project. 

14.  Funding limit reconciliation most likely will affect the project schedule, since work will need

to be moved to when funds will be available. 

15.  Funding limit reconciliation occurs after fast tracking the project. 

16.  1st: Cost aggregation, 2nd: funding limit reconciliation, 3rd: charter constraint reconciliation 

17.  Schedule -Resource limit à Resource leveling. 

18.  Cost Plus used when degree of uncertainty and require a large investment early in the project

life cycle. 

Page 23: Rofa Pmp Notes

7/24/2019 Rofa Pmp Notes

http://slidepdf.com/reader/full/rofa-pmp-notes 23/40

19.  It is estimate cost NOT estimate activity cost. 

20.  A control account can be placed at any level of the WBS and is used for earned value

measurement calculations regarding project costs 

Quality management plan: 

1.  The reason of quality activities is to make sure project meets its objective. 

2.  (quality assurance) Process analysis follows the steps outlined in the process improvement

plan to identify needed improvements. 

3.  Proprietary Quality Management Methodologies (Lean Six Sigma, QFD, CMMI). 

4.  Tolerances focus on whether the product is acceptable, while Control Limits focus on

whether the process itself is acceptable. 

5.  "Quality Control Measurements" results of your inspections (e.g. numbers of defects found,

numbers of tests passed). 

6.  • 1σ = 68.25% • 2σ = 95.46% • 3σ = 99.73% • 6σ = 99.99966% 

7.   Accuracy: true value, precision: repeated value. 8.  Precision is measured by standard deviation is a chart. (how far from mean, not how far

from a true value). 

9.  Plan-Do-Check-Act has been defined by SHEWHARD and modified by DEMING. 

10.  Joseph Juran: Fitness-for-use, Juran Trilogy (Quality of Design, Quality of Conformance, and

Quality Characteristics), Juran Trilogy approach Plan-Improve-Control. 

11.  Dr. Genichi Taguchi developed the concept of 'Loss Function' when variation from

target increase, loss also increase. 

12.  Marginal analysis: don't want to exceed a point beyond (unnecessary quality) which the costs of

the improvements aren't offset by the anticipated increase in revenue (sales or profits). 

13.  Gold Plating: teams impression of what is valued by the customer, and the customer might not

agree. 

14.  If a project was gold plated, it is considered to be unsuccessful even if it met the

objectives. 

15.  Investigate root causes is  process analysis/improvement which occurs during  perform quality

assurance process (Root cause analysis is sort of process analysis). 

16.  Quality policy is part of QPM. 

17.  The quality management plan does not provide result about how the project quality is

doing. 

18.  For a good process, the control limits are within the specification limits. 

19.  Out of control process à Stop Production !! 

20.  Cost benefit analysis in quality management: A business case for each quality

activity compares the cost of the quality step to the expected benefit. 

21.  Quality cost: conformance (appraisal, prevention), non conformance/cost of poor quality (internal,

external). 

22.  Grade is a category assigned to products or services having the same functional use

butdifferent technical characteristics 

Page 24: Rofa Pmp Notes

7/24/2019 Rofa Pmp Notes

http://slidepdf.com/reader/full/rofa-pmp-notes 24/40

23.  Cost of quality: conformance (appraisal – prevention), non-conformance (internal – 

external). 

24.  Cost of non quality 12-20 % of sales 

25.  Grade definition = characteristics. Quality = functions. 

26.  Difference between quality control and quality assurance: 

  Quality assurance is proactive, while Quality control is reactive. 

  Conforming to the requirements and quality standard  Quality control.

Conforming to the requirements and standard Quality Assurance. 

  Quality assurance is concerned with quality processes while quality control is

concerned with quality deliverables. 

  Specific work package à quality control. Overall project

requirement Quality assurance. 

  Inspection (Quality control) keeps errors in the product from reaching

the customer. Prevention (Quality Assurance) keeps errors from occurring inthe process. 

27.  Quality control: evaluation quality against process. 

28.  Quality Assurance and Quality Control processes are dependent on each

other.The Quality Control receives the input from the Quality Assurance, and in turns gives

feedback to the Quality Assurance so that Quality Assurance could validate the process. 

29.  Perform Quality Assurance is the process where project managers have the greatest amount

of influence over quality. 

30.  One of the overarching goals of the Perform Quality Assurance process is to provide a

foundation for continuous process improvements. 

31.  Quality control is the process responsible for ensuring that approved change requests are

implemented correctly, though a tool called “approved change requests review” 

32.  In perform quality assurance process, the team should reevaluate whether the quality

standards are valid. 

33.  Perform Quality Assurance determine if  (standards/process is being followed). 

34.  Quality Metric: Operational definition (e.g. on-time performance, budget control,

defect frequency, failure rate, availability, reliability, and test coverage). 

35.  ISO is guidelines and implementation differs from one organization to another. 

36.  3 sigma is the most commonly used. 

37.  Quality injects risk. 

38.  Cause & effect diagram, process or system chart, influence diagram, domino diagram are all

diagramming techniques used to identify risk . 

39.  Risk categorization tool exist in perform qualitative risk analysis NOT identify risk. 

40.  Perform qualitative risk analysis must be redo after identify risk responses. 

41.  Hi precession and low accuracy  adjust the process NOT improve it. 

42.  Quality audits can confirm the implementation of approved change requests including

corrective actions, defect repairs, and preventive actions. 

Page 25: Rofa Pmp Notes

7/24/2019 Rofa Pmp Notes

http://slidepdf.com/reader/full/rofa-pmp-notes 25/40

 

HR Management plan: 1.  Personal rates exist in HR plan. 

2.  Perk = Prerequisite XX Fringe benefits 

3.  Herzberg’s: Motivation factors (Achievement, Recognition, Work, Responsibility, Advancement,

and Growth). Hygiene factors (Company Policy, Supervision, Good relationship with boss, working

conditions, Paycheck, Personal life, Status, Security, and Relationship with co-workers) 

4.   Victor Vroom’s Expectancy Theory: If workers believe their efforts are going to be successful

and rewarded, they will tend to be highly motivated and productive. He suggested that employees

are really motivated by goals only when three beliefs are present : Valence: The person wants to

achieve the goal, Expectancy: The person believes it's possible to attain the goal, Instrumentality:

Instrumentality is a judgment the person makes about whether he or she believes that the reward

will be given 

5.  David McLelland’s -  Achievement Theory (Theory of three needs): this Theory says that

people need achievement, power, and affiliation (seeking approval  –   to be motivated. 

6.  Douglas McGregor’s Theory X and Theory Y : Theory X - Team members are Selfish,

Unmotivated, Dislike work (constant supervision is required - 'authoritarian management' style).

Theory Y -Naturally motivated to do good work (manager trusts team members - 'participative

management' style). 

7.  Dr. William Ouchi’s Theory of –  “Z Theory”: Productivity can be increased by how well

theworkers and management get along and trust each other= worker need to be involved in

management practice.. Japanese style of management 

8.  Contingency Theory (Fred E. Fiedler): In stressful times, a task-oriented leader  will be

more effective, while in relatively calm times a relationship-oriented leader  will function more

effectively. 

9.  Hersey and Blanchard's Life Cycle Theory: Leadership style must change with the maturity of

individual employees. The PM's style should move from Directing, to Coaching, to Supporting, Then to

Delegating as the project moves through its life cycle. 

10.  Maslow’s hierarchy of needs: LOWER needs :Physiological Needs,

Security/Safety,Acceptance/Social. HIGHER Needs  : Esteem, Self-Actualization/self fulfillment

(Cognitive stimulation: Intellectual stimulation, access to knowledge and Aesthetic stimulation: Access to imagery, beauty, and art). 

11.  Characteristics of self-actualizing people: Don't deny or avoid facts • Effective perception of

reality • Spontaneous in ideas and actions • Creative • Problem-solving • Social interest in

other people  • Objective • Trusting • Acceptance of others • Independent with a need for

solitude. 

12.  Sponsor approves the final project plan and deliverables. 

Page 26: Rofa Pmp Notes

7/24/2019 Rofa Pmp Notes

http://slidepdf.com/reader/full/rofa-pmp-notes 26/40

13.  Organization Charts- a way to documenting roles and responsibilities: 

A.  Hierarchical-type charts. 

B.  Matrix-based charts (RAM –Responsibility Assignment matrix). 

C.  Text-oriented formats. 

14.  Staffing management Plan includes: 1.Staff acquisitions, 2.Resource

calendars /histogram, 3.Staff release plan, 4.Training needs, 5.Recognition & Rewards,

6.Compliance, and 7.Safety. 

15.  Resource histograms: shows role, person and time period (Not Dates). 

16.  Coach = achieve goals. 

17.  Oder of preference: Confronting, compromise, smoothing, forcing, withdrawal. 

18.  Problem solving and compromising are considered the two best conflict techniques, in

that order.

19.  Smoothing: down playing the issue, focus on positive, focusing on points of agreement(let's

calm done and got the job done). 20.  Compromise is when all parties perform some give-and-take to reach a middle settlement.

LOSE LOSE. 

21.  Collaborating means working with other people to make sure that their viewpoints and

perspectives are taken into account. To get real commitment from every one. 

22.  Forcing is the worst ever, 

23.  Sources of conflict: schedule, priorities, resources, technical opinions, cost, personalities. 

24.  To solve a conflict: Team members involved  PM  Sponsor/functional manager (if the

issue is technical one, team members  functional manager). 

25.  Organization Charts and Position Descriptions (RBS,OBS, RAM) is a tool in develop

human resource plan. 

26.  RBS is output from estimate activity resource. 

27.  Organizational breakdown structure (Project  Dept  WBS). Resource Breakdown

structure (Project  category of resource  WBS). 

28.  Problem solving steps: 

A.  Define the problem 

B.   Analyze the problem 

C.  Identify solutions. 

D.  Pick a solution. 

E.  Implement solution 

F.   Validate solution. 

29.  In matrix organization, the only power that the PM doesn't have is legitimate power. 

30.  Ethnocentric: look at the world primarily from the perspective of one's own culture. 

31.  Sponsor may solve problems that behind PM control. 

32.  Sponsor may review WBS. 

33.  Sponsor may force quality policies. 

Page 27: Rofa Pmp Notes

7/24/2019 Rofa Pmp Notes

http://slidepdf.com/reader/full/rofa-pmp-notes 27/40

34.  Technical issues are managed by the team members' managers. 

35.  A benchmark analysis provides information about the methods and performance used by

other companies and departments. 

36.  Removing a team member from a project is drastic action.

37.  Autocratic: in this manager has power to do whatever he wants. The manager may coach or

delegate, but everyone is doing what manager wants them to do. 

38.  Team performance issues are senior and functional management's responsibility. 

39.  project effectiveness = project performance assessment. 

40.  Manage team requires more managerial skills than develop team.  

41.  Reward power, Expert power, Referent power, Punishment power (Coercive),

and legitimatepower (Formal power) - Reward and Expert as the most effective forms of power

andPunishment/Coercive as the least effective. 

42.  Accountable = sign off for approval =answerable for the satisfactory completion of the task. 

43.  Team-building strategies are particularly valuable when team members operate from remote

locations without the benefit of face-to-face contact. 44.  One of the most important skills in developing a team environment involves handling project

team problems and discussing these as team issues. 

  Discussing ground rules allows team members to discover values that are important to one

another. 

  Sponsor role: give fund, provide and clarify scope, monitor progress. 

  Some roles exist in other PMPs rather than the project management plan (quality, risk,

communication, quality management plans). 

  (plan human resource tool): states that organization culture affects how people behave. 

plan:ManagementCommunication

1.   “Performance reports”  are created in the Report Performance process, but they are

distributed to the relevant stakeholders through the Distribute Information process.

2.  Reports help distribute information, not just report on progress.

3.  Report Performance is a monitoring and controlling process, and is also done during the

Close Project or Phase process to report the final project performance. 

4.  Report performance: collection and analysis of baseline versus actual data

tounderstand and communicate the project progress and performance as well as

toforecast the project results. 

5.  Distribute information: making them available through meetings, mails, … 

6.  Stakeholder identification levels: interest, expectations, importance and influence.

(importance = impact??) 

7.  Project reports - Formal and informal project reports describe project status and

include lessons learned, issues logs, project closure reports, and outputs from other

Knowledge. 

8.  informal communication is part of team building. 

Page 28: Rofa Pmp Notes

7/24/2019 Rofa Pmp Notes

http://slidepdf.com/reader/full/rofa-pmp-notes 28/40

9.   All project team members share responsibility for enforcing the rules once they are

established. 

10.  Types of reports: (status-detailed/how stands now, progress report -what have

beenaccomplished, trend-over time) 

11.  A change log is used to document changes that occur during a project. Input to manage

stakeholder expectation because These changes and their impact to the project in terms

of time, cost, and risk, must be communicated to the appropriate stakeholders. 

12.  Communication technology takes into account: Urgency of the need for information,

Project environment, Duration of the project. 

  Communication management plan takes into account: Reasons for the

distribution of information. 

  Communication requirements analysis (tool in plan quality): assess the value of

the information to be communicated to stakeholders. 

  Meeting minute’s templates and glossary of terminologies exist in the

communication management plan.   Manage stakeholder expectation increase the probability of project success by

ensuring that the stakeholder understands projects benefits and risks. 

  Project performance appraisal = (as inputs) performance reports + team

performance assessment. 

  Project reports  output from distribute information. 

  Performance reports  output from report performance. 

  Increasing support and minimize negative impact is part of manage stakeholder

expectations. 

  Para lingual cues are signs, pause, tone of voice or simply silence (85%). 

  WBS can be used as communication tool vertically & horizontally within projectand outside project. 

  Issue log/action plan: manage team, manage stakeholder expectations. 

Risk Management: 

1.  Risk Response strategies: Avoid - transfer/Deflect , Mitigate Accept (Negative/Positive) -.

If the cost or impact of the other strategies is too greater, acceptance is the best strategy ,,,

Exploit - Share  –  improve- Enhance 

2.  Risk response occur before risk, contingency plan fallback plan after risk. 

3.  Any time a risk's impact is greater than planned, additional risk responses are developed and

documented. 

4.  Assumption analysis is part of risk management process 

5.  Contingent Response Strategies Some responses are designed for use only if certain

events occur. 

6.  residual risks: accepted risks - constancy plan & fallback plan. 

7.  Secondary: risk occur due to implementing a response plan for a main risk. 

Page 29: Rofa Pmp Notes

7/24/2019 Rofa Pmp Notes

http://slidepdf.com/reader/full/rofa-pmp-notes 29/40

8.  Risk Breakdown Structure (RBS): It is not breaking down the actual risks, instead, we are

 breaking down the CATEGORIES of risks that we will evaluate. 

9.  Risk tolerance levels of the organization and the stakeholder exists in EEF. 

10.  Risk manager , monitor and control risk. 

11.  The PMBOK® Guide notes that the probability and impact matrix values are usually set by

the organization and are part of the organizational process assets. 

12.  A Tornado diagram (special type of Bar chart) where the data categories are listed

vertically instead of the standard horizontal presentation, and the categories are ordered (the

largest bar appears at the top of the chart, the second largest appears second from the top).

This diagram is useful for sensitivity analysis - comparing therelative importance of

variables. 

13.  Sensitivity Analysis. A quantitative risk analysis and modeling technique used to

helpdetermine which risks have the most potential impact on the project.

Itexamines the extent to which the uncertainty of each project element affects the objective

 being examined when all other uncertain elements are held at their baselinevalues. Thetypical display of results is in the form of a tornado diagram. 

14.  Monte carlo simulation takes into account path convergence on Network Diagram. 

15.  Simulation techniques are used to predict schedule or cost risks. 

16.  Normal and lognormal distributions use mean and standard deviations to quantify risk,

which also require gathering the optimistic, most likely, and pessimistic estimates.  

17.  A negative EMV is a risk cost and a positive EVM is a benefit. 

18.  Expected Monetary Value Analysis (EMV): The EMV of OPPORTUNITIES will generally

 be expressed as POSITIVE VALUES, while those of THREATS will be NEGATIVE. EMV

requires a Risk-Neutral assumption, neither risk averse, nor risk seeking. A common type is

"Decision Tree Analysis. 

19.  Risk responses are identified in both Identify risk  and Plan risk responses. 

20.  The risk response occurs BEFORE the risk and tries to alter the probability and/or impact whilethe

contingency plan only occurs AFTER  the trigger (usually the risk event) and focuses only on changing

the impact. 

21.  Risk actions are of 3 types (( risk response ----(if fail)   contingency plan ---(if

fail)  fallback plan)):  

1) 

Risk response:- The risk response determines the strategy for influencing the probability and impact of

the risk before it occurs. 

i. 

For negative risks, its aim is to eliminate the risk or reduce its impact should it occur. For positive risks,

the response tries to increase the probability or impact of the risk . 

2) 

For residual risk: Contingent response/contingent plan:- it establishes what activities will take

place should a specific event or situation occur. A contingency plan aims to influence the impact of a risk

that is occurring. 

Page 30: Rofa Pmp Notes

7/24/2019 Rofa Pmp Notes

http://slidepdf.com/reader/full/rofa-pmp-notes 30/40

3) 

For residual risk: Fallback plan:- The fallback plan spells out steps will be taken to recover if the

contingency plan fails. 

22.  Residual risk  is a leftover risk . 

1) 

 After you’ve implemented a risk response strategy (e.g. mitigation, transfer) —some minor risk

might still remain. The contingency reserve is set up to handle situations like this. 

2) 

 ACCPTED RISKS {{whose probability and impact are such that they're acceptable to the performing

organization's level of risk tolerance. They can also be those risks in which there are no reasonable

responses for}}.- ACTIVE Acceptance 

23.  Contingency reserve is established through the concept of EVM by aggregating the EMV

for each known risk. 

24.  Contingency reserves are the reserves used for the identified risks occur after the response

 plans are being taken {{ residual risk }}. 

25.  Residual risk and active acceptance risk has contingency plan contingency

reserve. 

26.  Secondary risk has response plan. 

27.  Risk audits (TT in risk control): examine and document the effectiveness of risk

responses in dealing with identified risks and their root causes, as well as

theeffectiveness of the risk management process. 

28.  Reserve analysis (TT in risk control): Reserve analysis compares the amount of the

contingency reserves remaining to the amount of risk remaining. 

29.  work around  –  plan to deal with  passively accepted risks and unknowns risks 

30.  Use of non-linear values implies the organization wishes to avoid high- impact

threats or exploit high-impact opportunities even if they have relatively low

probability. In using non linear values, it is important to understand what each of

the numbers mean, their relationship to one another, how they were derived, and

the effect they may have on different objectives of the project. 

31.  (or ordinal scale) is the most simple and uses indicators such as low, medium, and

high. 

32.  A linear scale (or cardinal scale) is numeric, and is commonly used to express the

probability of the risk, so a rating of 1 would imply a very low probability while a

rating of 9 would indicate a very high probability. 

33.  A non-linear scale is also numeric, but the intervals between the designations aren'tequal (e.g., 1, 2, 4, 8, 16). 

34.  Risk audits examine and document the effectiveness of risk responses in dealing with

identified risks and their root causes, as well as the effectiveness of the risk management

 process. 

35.  Project risk  that has been occurred can be also considered as issue. 

Page 31: Rofa Pmp Notes

7/24/2019 Rofa Pmp Notes

http://slidepdf.com/reader/full/rofa-pmp-notes 31/40

36.  Prototype= mitigate risk *** Insurance = transfer risk ** joint venture = sharing a positive

risk ** Enhance = adding more resources to finish earlier ** warranty = ?? 

37.  The risk of loss that incurred by force majeure is born by seller. 

38.  Data gathering (interviews) and representation technique (probability distribution) is a tool

in perform quantitative risk analysis. 

39.  Representation technique (probability distribution): Distributions graphically display

theprobability of risk to the project objectives as well as the time or cost elements. 

40.  The probability and impact matrix multiplies the probability and impact to

determine a risk score. Using this score and a predetermined matrix, you determine if

the scores is a high, medium, or low designation. 

41.  RBS exist in risk management plan. 

Procurement Documents: 

1.  The complexity and level of detail of the procurement documents should be

consistent with the value of, and risks associated with, the planned procurement. 2.  Procurement Documents: the procurement contract with all

supporting schedules,requested unapproved contract changes, and approved change requests,

seller-developed technical documentation and other wok performance information

(deliverables, seller performance reports, warranties, financial documents including invoices

and payment records), and the results of contract-related inspections. 

3.  Creation of a request for proposal occurs in plan procurement. 

4.  Records Management system = for procurement. 

5.  Close a procurement/Contract closure: product verification, procurement

audit, financial closure, negotiated settlement, file a procurement, final contract

performance reporting, updates to records, lessons learned. 

6.  Buyers Risk (from Highest to Lowest) - CPFF - T&M - CPIF - FPIF – FFP. 

7.  Cost plus transfer risk to buyer. 

8.  ---The Time & Materials (T&M) contract is the riskiest one for the BUYER. ?? 

9.  --- A FIXED price contract is the riskiest sort of contract for the SELLER. 

10.  Administer procurement acts like execute the contract and M&C and integrated change

control. 

11.  Claims/dispute/ appeal: Administration: are Contested changes and potential

constructive changes are those requested changes where the buyer and seller cannot

reach an agreement on compensation for the change, or cannot agree that a change has

occurred. 

12.  Claims are documented, processed, monitored, and managed throughout the

contract life cycle, If the parties themselves do not resolve a claim, alternative

dispute resolution (ADR ) typically following procedures established in the contract.

Settlement of all claims and disputes through negotiation is the preferred method. 

13.  A records management system is used by the project manager to manage contract and

 procurement documentation and records. 

Page 32: Rofa Pmp Notes

7/24/2019 Rofa Pmp Notes

http://slidepdf.com/reader/full/rofa-pmp-notes 32/40

14.  procurement is considered to be complete when … 

15.  Close procurement Procurement audit: to identify successes and failures that warrant

recognition in other procurements. Conducted by procurement manager, PM (sometime

seller). 

16.  close procurement Product validation: Validate each and every deliverable or the

final deliverable for defects- 

17.  Claim administration is in administering procurement in M&C. 

18.  Records management system updates is wrong, instead procurement

documentation. 

19.  Early termination of a contract is a special case of procurement closure that can

result from a mutual agreement of both parties, from the default of one party, or for

convenience of the buyer if provided for in the contract. The rights and responsibilities

of the parties in the event of an early termination are contained in a terminations

clause of the contract. 

20.  RFP=CR || RFB=Fixed Price || RFQ= cost & material 21.  Make payment to seller is made in administer procurement. 

22. 

 A source selection criterion is basic minimum criteria the sellers have to be fulfilled to getshortlisted. (e.g.

Minimum 5 years of Industry experience), Once you've shortlisted the sellers, you will run "Proposal

Evaluation" on them, to decide which seller to award contract to. 

23.  A procurement statement of work may be revised and refined as it moves through

the procurement process. 

24.  PM doesn’t have the authority to change order (only the procurement manager) ---

> change order always initiated from the buyer side. 

25.  Diff. between breach, default, and waiver: 1) 

 A breach (default) occurs when any obligation of the contract is not met. the response to a breach must

be to issue a formal letter (not official note) notifying the other party of the breach. 

2) 

Waivers are statements saying the rights under the contract may not be waived or modified other than

by express agreement. (The act of voluntarily giving up a right or covenant.) 

26.  Null and void: No longer valid or enforceable. 

27.  The response of breach must be always to issue a letter formally notifying the other

party of the breach. 

28.  Time is of essence, any delay considered to ma material breach (a breach thatcannot continue with). 

29.  Main items to negotiate in a contact is : scope, schedule, price. 

30.  Only procurement manager has the authority to approve change in contract. 

31.  Default letter = default = breach. 

32.  Objectives of negotiations: 

1) 

Page 33: Rofa Pmp Notes

7/24/2019 Rofa Pmp Notes

http://slidepdf.com/reader/full/rofa-pmp-notes 33/40

Obtain fair & reasonable price. 

2) 

Develop good relationship. 

33.  The contract should have provision for termination. 

34.  Claim is the assertion that the buyer did something that hurt the seller and the

seller is asking for compensation. 

35.  Constructive changes: changes occur when the buser through action or inaction get

in the sellers way to perform the work. 

36.  Procurement statement of work basically written by the buyer, however it might be

written by seller and the buyer review it. 

Detailed: 

Integration Management 

• 

Subsidiary plans include, but are not limited to: 

• 

Scope management plan (introduction to Chapter 5), 

• 

Scope verification plan. 

• 

Requirements management plan (Section 5.1.3.2) :describes how to identify, analyze, and document

requirements as well as how those requirements will be managed and controlled. 

• 

Schedule management plan (introduction to Chapter 6), 

• 

Cost management plan (introduction to Chapter 7), 

Page 34: Rofa Pmp Notes

7/24/2019 Rofa Pmp Notes

http://slidepdf.com/reader/full/rofa-pmp-notes 34/40

• 

Quality management plan (Section 8.1.3.1), 

• 

Process improvement plan (Section 8.1.3.4), 

• 

Human resource plan (Section 9.1.3.1), 

• 

Communications management plan (Section 10.2.3.1), 

• 

Risk management plan (Section 11.1.3.1), and 

 

Procurement management plan (Section 12.1.3.1). 

 

Configuration management plan (defines those items that are configurable and those items that

require formal change control) 

 

Change management plan (components exits in p.114 Rita) 

 

Project Performance Baselines 

To control changes in the project, the PM should: 

o Obtain final requirements ASAP. 

o Spend enough time in risk planning. 

o Establish time and cost reserve. 

o Have process to control change. 

Some of the configuration management activities included in the integrated change

control process are as follows: 

Page 35: Rofa Pmp Notes

7/24/2019 Rofa Pmp Notes

http://slidepdf.com/reader/full/rofa-pmp-notes 35/40

 

Configuration identification. Selection and identification of a configuration item provides the basis for

which product configuration is defined and verified, products and documents are labeled, changes are managed, and

accountability is maintained. 

 

Configuration status accounting. Information is recorded and reported as to when appropriate data about

the configuration item should be provided. This information includes a listing of approved configuration

identification, status of proposed changes to the configuration, and the implementation status of approved changes. 

 

Configuration verification and audit. Configuration verification and configuration audits ensure the

composition of a project’s configuration items is correct and that corresponding changes are registered,

assessed, approved, tracked, and correctly implemented. This ensures the functional requirements

defined in the configuration documentation have been met. 

WPI, WPM, Performance Reports: 

1) 

WPI is gathered as project being executed = raw data, output of direct and manage project execution

(e.g. project deliverables, change requests status, risks status, costs incurred). 

2) 

WPI used to generate: WPM (e.g. CPI, SPI, CV, SV) and forecasts (e.g. ETC, EAC). 

3) 

WPI + WPM + budget forecast = Performance Reports. 

4) 

Senior management , customer , sponsor need to look at Performance reports not WPI, nor WPM, norforecasts. 

5) 

WPI used later in M&C, input to most M&C process: 

i. 

Perform quality assurance 

ii. 

Perform integrated change control 

iii. 

Control scope 

iv. 

Control schedule 

v. 

Control cost 

vi. 

Report performance 

vii. 

Monitor and control risk  

Page 36: Rofa Pmp Notes

7/24/2019 Rofa Pmp Notes

http://slidepdf.com/reader/full/rofa-pmp-notes 36/40

  viii. 

 Administer procurement 

6) 

WPM is input to perform quality control. 

7) 

Performance Reports is input to 3 process only Monitor and control process, monitor and control risk, administer

 procurement. 

8) 

Oliver comments: 

2.  understanding of individual characteristics is not part of social and cultural

understanding environment 

3.  precision hi, accuracy low, adjust process 

4.  Lessons learned should be organized during project cycle and at the end. 

5.  RACI matrix is not input to product acceptance ( it describes accountabilities in case

of product rejection) 

6.  facilitator should always give guidance as required without interfering 

7.  if stakeholders have diff. opinions, first let them discuss if no result, PM should

make priorities 

8.  technical inability and poor risk management frequently leads to not meeting

customer expectation 

9.  It is called cost of conformance (prevention - appraisal) cost of non conformance

(failures - internal & external) 

10.  team can increase level of maturity from independence to interdependence 

11.  Baseline in system configuration is not called delta 

12.  high-context cultures means a message has little meaning without an understanding

of surrounding context 

13.  best way to calculate Profit from internal project is the EVA (economic value added)

to the organization taking into account taxes and capital cost. Does the project returns

to the organization more value than the initiative costs. 

14.  variable sampling includes collection of quantitative data in the degree of conformity

for each item of a sample 

15.  Individualism is the significance of a person that of a group 

16.  Burn rate = 1/CPI 17.  changes on the product can affect warranty clauses, ensure that these clauses are

aligned with the final specification 

18.  ??? How come PM should not master project culture 

19.  a milestone is a significant point in the project with zero duration NOT a fixed or

imposed date during the project life cycle 

Page 37: Rofa Pmp Notes

7/24/2019 Rofa Pmp Notes

http://slidepdf.com/reader/full/rofa-pmp-notes 37/40

20.  Tornado diagram: comparing the relative importance of variables that have hi

degree of uncertainty with those that are more stable 

21.  "Modern quality management focus in: 

1- 

customer satisfaction 

2- 

management responsibility 

3- 

prevention over detection 

4- 

continuous improvement" 

22.  revise the baseline if many number of deltas occur 

23.  strange answer 

24.  Monitor & control work: ensuring that rejected changes will not getting executed by

mistake 

25.  Quality documentation is required to perform quality audit 

26.  to use a phase gate: the order of phases must be strictly consecutive without

overlapping in order to allow for gates 

27.  warranty parts may not be replaced for free- but some team members must be

available to handel the customer complaints in the warranty period 

28.  If a procurement item is readily available from many accepted sellers, focus on the

price 

29.  diff cultures --> define joint quality policy 

30.  CV of project manager is not required with the proposal 

31.  you can not close contract if immaterial breach occurred 

32.  when it become obvious that the attendees will not reach to jointly accepted

decision => postpone the meeting 

33.  during closing a project, a team member may be willing to move to a new project-

as PM make a smooth transition even if the team member is v imp source 

34.  cost estimate is not exist in activity attribute 

35.  Do not pay, but follow the chain of command and solicit a decision 

36.  calculating a free float and total float is not reasonable for finished activities 

37.  CWBS: contract WBS that become part of the contract. 

38.  PM team responsibility to obtain customer approval in verifies scope process. 

39.  Adminstrative closure procedures don’t include analyzing success or failure. 40.  Administrative closure procedures include approving the second phase. 

41.  Statement of work may be developed by the customer. 

42.  The probability that the project will finish on time or earlier is 80%. 

PMStudy comments: 

1.  In the teaming agreement, both the buyer and the seller collectively prepare

Contract, Procurement statement of work  

Page 38: Rofa Pmp Notes

7/24/2019 Rofa Pmp Notes

http://slidepdf.com/reader/full/rofa-pmp-notes 38/40

2.   A project phase is generally concluded and formally closed with a review of the

deliverables to determine completeness and acceptance. A phase-end review can

achieve the combined goal of obtaining authorization to close the current phase and

start the subsequent one. The end of a phase represents a natural point to reassess

the effort underway and to change or terminate the project if necessary. A review

of both key deliverables and project performance to date to a) determine if

the project should continue into its next phase and b) detect and correct errors cost

effectively should be regarded as good practice.

3.  Formal phase completion does not necessarily include authorizing the

subsequent phase. For instance, if the risk is deemed to be too great for the

project to continue or if the objectives are no longer required, a phase can be closed

with the decision to not initiate any other phases. 

4.  Triggers = warning signs = risk symptoms. 

5.  look at the positives and negatives of their approaches and submit their recommendations,

which could be a "middle path". 

6.  Performance reports are the output from the Report Performance

 process and notfrom Distribute Information process. 

8.  To measure disbursements, a spending plan can be used as a cost-baseline. 

9.  In EVM: Performance measurement baseline (PMB) is approved integrated scope-schedule-cost

performance. 

10. Pareto & control chart Quality control. 

1.  Contracts may be used for the transference of liability for specified risks to another party. 

2.   A fixed price contract transfers risk to the seller if requirements are well defined and seller ha

3.  no of communication channels increases in exponential proportion when the number of peop4.  Perform Integrated Change Control process includes coordinating changes across the entire pro

5.  Quality metrics are used in the Perform Quality Assurance and Perform Quality Control proce

6.  Common formats for performance reports include  bar charts, S-curves, histograms, and tables NO

7.  Contingency reserves are needed to bring the risk of overrunning stated project objectives to a le

when compared to the $41 million US sum of the most likely estimates shown}} 

8.   Assigning tasks in the start of every week in a small project is not improper management. 

9.  Organizational theory: provides information regarding the way in which people, teams, and orga

10. The PMI Code of Ethics and Professional Conduct require a project manager to address thing

countries. So, it is not the responsibility of the project manager to enforce the work-ethics o

11. Rectification of a minor flaw can lead to delay of 2 months in the project: so, the project man

12. the work authorization system is not created to Prevent team members from starting the wo

13. Quality audit is structured review to determine whether product activities comply with o

14.  A procurement audit is a structured review of the procurement process originating from Pla

15. Monitor and Control Risks is the process of implementing risk response plans, tracki

 process effectiveness(risk audit) throughout the project. 

16. Monitor & Control Risk: Diff between risk reassessment and risk audit: 

Page 39: Rofa Pmp Notes

7/24/2019 Rofa Pmp Notes

http://slidepdf.com/reader/full/rofa-pmp-notes 39/40

1- 

Risk audits examine and document the effectiveness of risk responses in dealing with identified risks and their roo2- 

Risk reassessment identification of new risks, reassessment of current risks, and the closing of risks that are outda

19.  Achievement - power- affiliation 

20. In execution process will work defined be completed and all the specifications of your project be sa

21. Taking corrective or preventive action to control the project performance is part of monitor a

22. Preventive action: A documented direction to perform an activity that can reduce the probab

23. Collecting work performance information about the completion status of the deliverables and wh

24. Do not report your partner if he asked you to use your version of the software. 

25. Fait accompli = non negotiable = done deal 

26. Control chart is not a reporting format. 

27. Payback period is the number of years required to get back the initial investment in the project

28.  Variance analysis is an after-the-fact look at what caused a difference between the baseline an

29. Unresolved issues can be a major source of conflict and project delays. 

30. Influence diagram Graphical representations of situations showing causal influences, time order31. Determining and delivering the required levels of quality for the project is the respon

32. Work breakdown structure helps in providing a basis for time and cost estimates. 

33. Even if you will refrain from a conflict of interest situation you should notify the interested par

34. We should refrain from a conflict of interest NOT tell the management and le

35. Kill point = phase end review. 

36. If you been handover to a project that over budget and behind schedule, DO NOT Bring the

37. The ability to influence cost is greatest at the early stages of the project, making early scope

38. Select potential sellers occurs in conduct procurement. 

Exam central comments: 

1.  Quality assurance can be conducted throughout the project but should be conducted at regu

2.  Project performance should be set by the stakeholders not predicted by the project mana78. 

4 types of project closure: a. 

Starvation: withdrawal of life support. b. 

 Addition: added to a parent company project. c. 

Integration: assets absorbed by a parent company project. d. 

Extinction: reach to normal closing either by success of failure 

3.  List of stakeholders names, positions, locations, potential influence on the project impact, and level of

4.  Prioritize the change requests is the PM Job. 

5.  In a matrix organization, the functional manager does administrative functions for his staff. 

6.  Level 1 in the WBS may be deliverable, project phase, subprojects, or combinations. 

7.  Deming said that quality is 85 % of time due to management problem. 

8.  Depreciation cost is added to estimate activity cost not determine budget. 

Page 40: Rofa Pmp Notes

7/24/2019 Rofa Pmp Notes

http://slidepdf.com/reader/full/rofa-pmp-notes 40/40

10.  Negotiations mainly on scope- schedule  –  price. 

11.  EMV is used to calculate the benefit or cost (+ve or –ve) of a positive of negative

risk. 

12.  We report unethical or illegal conduct to the appropriate management – without

giving the criminal 48 Hours !!. 

13.  Initiation phase can kickoff the project. 14.  Corrective action similar to Rework . 

15.  The biggest disadvantage or parametric estimate that the solution may not scale = the

estimation that may work for a large projects may not work for a small project. 

16.  Undocumented scope creep = Gold plating. 

17.  you discovered that the change request is an enhancement, this doesn’t mean that

he is really

18.  Blanchcards: situational continuum 

19.  Senior management must be consulted when changing one of the triple

constraints(change request that affect the triple constraints). 

20.  Customer is the one who has the greatest influence in project scopechanges {{ cause he is the one who will pay }}. 

21.  Shannon weaver model is a communication model. 

22.  Agile = iterative model 

23.  The most important thing in a needed change is impact of change NOT the need for

chanage. 

24.  Project is baselined == all required stakeholders signed off it. 

25.  FF = (AB) B cannot finish before A finishes 

26.  It is the sender responsibility that the message correctly received. 

27.  If you finish a project within budget, time, on specifications. However the customer

is not happy. CLOSE the procurement.

28.  Effective communication means that the information is provided in the right

format, at the right time, and with the right impact. Efficient

communication means providing only the information that is needed. 

29.  Learning curve estimation uses the principal that the cost per unit will decrease as more units

of work are manufactured. 

30.  Statistical Sampling is the standard technique that is used to test only a small sample of

products instead of all the products manufactured. 

31.  Continuous small improvements is part of Kaizen theory 

32.  Cost budget = project funding requirements 

33.  0/50/100 – Work Package completion. No credit until 50% complete. No additional

credit until 100% complete.