Rockies Alliance Pipeline Open Season Presentation Denver – June 3, 2008 Houston – June 4, 2008 Chicago – June 5, 2008
36

Rockies Alliance Pipeline Open Season Presentation Alliance...CIG Historical & Forward Basis Source: ... (pipeline/station) • Design considerations ... Rockies Alliance Pipeline

Mar 12, 2018

Download

Documents

dangkiet
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Rockies Alliance Pipeline Open Season Presentation Alliance...CIG Historical & Forward Basis Source: ... (pipeline/station) • Design considerations ... Rockies Alliance Pipeline

Rockies Alliance PipelineOpen Season PresentationDenver – June 3, 2008Houston – June 4, 2008Chicago – June 5, 2008

Page 2: Rockies Alliance Pipeline Open Season Presentation Alliance...CIG Historical & Forward Basis Source: ... (pipeline/station) • Design considerations ... Rockies Alliance Pipeline

Slide 2

Agenda

• Welcome and Introductions

• Rockies Alliance Pipeline (RAP) Offering

• Engineering & Construction

• Environment & Permitting

• Route Development & ROW Acquisition

• Open Season Details

Page 3: Rockies Alliance Pipeline Open Season Presentation Alliance...CIG Historical & Forward Basis Source: ... (pipeline/station) • Design considerations ... Rockies Alliance Pipeline

Slide 3

Rockies Alliance Pipeline Route

Page 4: Rockies Alliance Pipeline Open Season Presentation Alliance...CIG Historical & Forward Basis Source: ... (pipeline/station) • Design considerations ... Rockies Alliance Pipeline

Slide 4

Agenda

• Welcome and Introductions

• Rockies Alliance Pipeline (RAP) Offering

• Engineering & Construction

• Environment & Permitting

• Route Development & ROW Acquisition

• Open Season Details

Page 5: Rockies Alliance Pipeline Open Season Presentation Alliance...CIG Historical & Forward Basis Source: ... (pipeline/station) • Design considerations ... Rockies Alliance Pipeline

Slide 5

RAP New Facilities

• Proposed Pipeline Facilities! Wamsutter to Ventura: ~810 miles of 42 inch pipeline! Ventura to New Hampton: ~ 65 miles of 42 inch pipeline

(Alliance Pipeline interconnection)

• Proposed Compression Facilities! 6 compressor stations! Maximum discharge pressure = 1440 psig (MAOP)

Page 6: Rockies Alliance Pipeline Open Season Presentation Alliance...CIG Historical & Forward Basis Source: ... (pipeline/station) • Design considerations ... Rockies Alliance Pipeline

Slide 6

Questar Overthrust Pipeline

• Questar Overthrust Pipeline (Overthrust) is a subsidiary of Questar Pipeline, a Rocky Mountain company with over 2,500 miles of pipe transporting over 3 Bcf/d.

• Overthrust is a 213-mile, 36”-diameter pipeline from Opal to Wamsutter with contracted capacity of over 1.4 Bcf/d. Overthrust has a concurrent open season proposing expansions of 1 Bcf/d from Opal to Wamsutter and 810 MDth/d from White River Hub (Meeker) to Wamsutter.

• With its positions in the Rockies, Questar Pipeline and its subsidiaries currently deliver to local distribution companies in Utah, Wyoming, Colorado, Idaho, New Mexico, Arizona and California.

Page 7: Rockies Alliance Pipeline Open Season Presentation Alliance...CIG Historical & Forward Basis Source: ... (pipeline/station) • Design considerations ... Rockies Alliance Pipeline

Slide 7

Questar Overthrust Pipeline

• Lowest cost access to major supply points in the Rockies through an existing well-run pipeline system

• Proposed major expansions to increase supply availability • Low fuel requirements to move volumes• Access to Clay Basin Gas Storage via Questar Pipeline• Segmentation and nomination flexibility on the pipeline

Page 8: Rockies Alliance Pipeline Open Season Presentation Alliance...CIG Historical & Forward Basis Source: ... (pipeline/station) • Design considerations ... Rockies Alliance Pipeline

Slide 8

RAP Contracted Facilities –Questar Overthrust Pipeline

RAP to contract for capacity on Questar Overthrust Pipeline to provide the following interconnections:

Opal area" Opal Plant # Pioneer Plant$ Blacks Fork Plant % Granger Plant& Multiple interstate pipelines

Wamsutter area" Echo Springs # Lost Cabin$ Multiple interstate pipelines

White River Hub (Meeker)" Enterprise# Multiple interstate pipelines

Cheyenne (direct to RAP)" Powder River pipelines# Multiple interstate pipelines

Page 9: Rockies Alliance Pipeline Open Season Presentation Alliance...CIG Historical & Forward Basis Source: ... (pipeline/station) • Design considerations ... Rockies Alliance Pipeline

Slide 9

Alliance Pipeline

• Largest construction project in North America at the time - larger than Rockies Express! US$4.5B project delivered

on time and on budget! Largest project financing

in North American history! 2,311 miles from NE BC to

Chicago! Operational since 2000

Page 10: Rockies Alliance Pipeline Open Season Presentation Alliance...CIG Historical & Forward Basis Source: ... (pipeline/station) • Design considerations ... Rockies Alliance Pipeline

Slide 10

Alliance Pipeline

• High pressure (1935 psig) 36” pipeline• Operating at full capacity (1.6 Bcf/d)• Consistently ranked # 1 in reliability and availability

across entire fleet of GE gas turbines worldwide • Environmentally responsible – low GHG emissions• Lead waste heat power generation – six compressor

station sites either operating or under development• Developed and implemented new US MAOP

standards• Industry leading safety record

Page 11: Rockies Alliance Pipeline Open Season Presentation Alliance...CIG Historical & Forward Basis Source: ... (pipeline/station) • Design considerations ... Rockies Alliance Pipeline

Slide 11

RAP Contracted Facilities –Alliance Pipeline

RAP to contract for capacity on Alliance Pipelineto provide direct access to Chicago market:

• Alliance Pipeline Interconnection:! At New Hampton (~ 280 mi. upstream of Joliet)

• Expansion Facilities: ! 2 new compressor stations! Total ~ 40,000 installed HP

• Incremental Capacity:! 600 mmcf/d firm capacity

• Existing Interconnections:" Nicor & Midwestern# NGPL ' Peoples$ Vector ( Guardian% ANR

Page 12: Rockies Alliance Pipeline Open Season Presentation Alliance...CIG Historical & Forward Basis Source: ... (pipeline/station) • Design considerations ... Rockies Alliance Pipeline

Slide 12

RAP Project, Goals & Strategy

• 1.3 Bcf/d firm transport capacity to Ventura and Chicago hub (expandable to 1.8 Bcf/d)

• Develop integrated pipeline solution to deliver Rockies gas to market

• Competitive rates to move Rockies gas to the Midwest region (North American gas transportation hub with over 35 Bcf/d of interconnected transport capacity)

• Brings together supply and market – financial balance• Optimize and utilize existing system capability• Back haul opportunities upstream on Alliance Pipeline

to access other markets

Page 13: Rockies Alliance Pipeline Open Season Presentation Alliance...CIG Historical & Forward Basis Source: ... (pipeline/station) • Design considerations ... Rockies Alliance Pipeline

Slide 13

Market OutlookRockies Production vs Transmission Capacity

Rockies Production Net Export Pipeline CapacityExport Capacity + Local Demand

Source: Supply: Wood Mackenzie, Local Demand: EIA* Rockies production defined as WY, CO & UT.

Pipeline Export Capacity Shortfall

2006

2007

2008

2009

2010

2011

2012

2013

2014

2015

2016

2017

2018

2019

2020

Total ~ 8.75 Bcf/d Export Capacity REX NE

Trailblazer

El Paso Nat

Other

17%

3%

21%

19%

8%

32%MidwestREX

Gas TransKern River

5.00

6.00

7.00

8.00

9.00

10.00

11.00

12.00

13.00

(Bcf

/d)

Page 14: Rockies Alliance Pipeline Open Season Presentation Alliance...CIG Historical & Forward Basis Source: ... (pipeline/station) • Design considerations ... Rockies Alliance Pipeline

Slide 14

CIG Historical & Forward Basis

Source: Platts 240M Forward Data – April 2008

$0.00

$0.50

$1.00

$1.50

$2.00

$2.50

$3.00

Jan-

05

Jan-

07

Jan-

09

Jan-

11

Jan-

13

Jan-

15

Jan-

17

Jan-

19

Jan-

21

Jan-

23

Jan-

25

Jan-

27

12M Ventura 12M Chicago

Ventura and Chicago Basis averages above $1.50/Dth

Page 15: Rockies Alliance Pipeline Open Season Presentation Alliance...CIG Historical & Forward Basis Source: ... (pipeline/station) • Design considerations ... Rockies Alliance Pipeline

Slide 15

RAP Competitive Rates with Multiple Options

Fuel will be assessed on a system wide or postage stamp basis which is estimated to be approximately 2.5% and will be adjusted to reflect actual fuel requirements. Fuel charges associated with transport upstream of Wamsutter will be assessed separately.

15 Year Term - Negotiated Reservation Rates

Receipt Area VenturaAllianceMainline Chicago

VenturaCheyenneWamsutterOpal/Overthrust

White River Hubat Meeker

0.40 0.450.95 1.15 1.201.10 1.30 1.351.22 1.42 1.47

1.32 1.52 1.57

Delivery Area

Page 16: Rockies Alliance Pipeline Open Season Presentation Alliance...CIG Historical & Forward Basis Source: ... (pipeline/station) • Design considerations ... Rockies Alliance Pipeline

Slide 16

Market OutlookMarket Basis vs RAP Rates

$1.68

$2.02

$1.45

$1.77

$1.30

$1.55

$0.00

$0.50

$1.00

$1.50

$2.00

$2.50

Ventura Chicago

Forecast BasisHistorical BasisRAP Rates

$1.10

$1.35

Fuel Charges(2.5%x$8.00/DTH)

• Forecast Basis based on Platts 20 year monthly Forecast from 2008 to the end of 2028.• Historical Basis based on actual monthly indices for the past 5 years.• Reservation Rates based on proposed rates for 15 year contracts.

Page 17: Rockies Alliance Pipeline Open Season Presentation Alliance...CIG Historical & Forward Basis Source: ... (pipeline/station) • Design considerations ... Rockies Alliance Pipeline

Slide 17

Agenda

• Welcome and Introductions

• Rockies Alliance Pipeline (RAP) Offering

• Engineering & Construction

• Environment & Permitting

• Route Development & ROW Acquisition

• Open Season Details

Page 18: Rockies Alliance Pipeline Open Season Presentation Alliance...CIG Historical & Forward Basis Source: ... (pipeline/station) • Design considerations ... Rockies Alliance Pipeline

Slide 18

Summary RAP New Facilities

• Pipe design parameters! Length: 875 miles! Pipe size: 42” OD! Pipe grade: X70! Design factor: 80% SMYS! Wall thickness: 0.540”/0.726”! Maximum Operating Pressure: 1440 psig (1935 psig Ventura

to New Hampton)

• Compression design specifics! Number of stations: 6! HP requirements: 10,000 – 36,000/station

Page 19: Rockies Alliance Pipeline Open Season Presentation Alliance...CIG Historical & Forward Basis Source: ... (pipeline/station) • Design considerations ... Rockies Alliance Pipeline

Slide 19

RAP Preliminary Project Schedule

Page 20: Rockies Alliance Pipeline Open Season Presentation Alliance...CIG Historical & Forward Basis Source: ... (pipeline/station) • Design considerations ... Rockies Alliance Pipeline

Slide 20

Preliminary Pipeline Construction Plan

Page 21: Rockies Alliance Pipeline Open Season Presentation Alliance...CIG Historical & Forward Basis Source: ... (pipeline/station) • Design considerations ... Rockies Alliance Pipeline

Slide 21

Procurement – Pipe/Facilities

• Finalizing design• Short listing potential pipe mills

! North America! Overseas

• Finalizing specifications! Compressor stations! Meter stations

• Short listing potential compressor vendors

Page 22: Rockies Alliance Pipeline Open Season Presentation Alliance...CIG Historical & Forward Basis Source: ... (pipeline/station) • Design considerations ... Rockies Alliance Pipeline

Slide 22

Industry Leaders/Experience

• Engineering and construction! Large diameter, long distance projects

• Design, construction, logistics, commissioning! High pressure! X70 pipe grade; fracture control design! Mechanized welding! Ultrasonic inspection! 80% SMYS design

• DOT (PHMSA) conditions! In Line Inspection (ILI)

• Environment award winners• Right-of-way acquisition and management

Page 23: Rockies Alliance Pipeline Open Season Presentation Alliance...CIG Historical & Forward Basis Source: ... (pipeline/station) • Design considerations ... Rockies Alliance Pipeline

Slide 23

RAP Progress To Date

• Route selection! Identification of key routing matters! Identification of constructability considerations

• Compressor station locations• Preliminary discussions with

! Pipe mills (ID/OD coating mills)! Compressor vendors! Valve manufacturers! Construction contractors (pipeline/station)

• Design considerations• Construction planning

Page 24: Rockies Alliance Pipeline Open Season Presentation Alliance...CIG Historical & Forward Basis Source: ... (pipeline/station) • Design considerations ... Rockies Alliance Pipeline

Slide 24

Agenda

• Welcome and Introductions

• Rockies Alliance Pipeline (RAP) Offering

• Engineering & Construction

• Environment & Permitting

• Route Development & ROW Acquisition

• Open Season Details

Page 25: Rockies Alliance Pipeline Open Season Presentation Alliance...CIG Historical & Forward Basis Source: ... (pipeline/station) • Design considerations ... Rockies Alliance Pipeline

Slide 25

Environment and RAP

• We have done this before! Large projects

• Alliance Pipeline Inc. – 888 miles / 36” / 1935 psig • Alliance Pipeline Ltd. – 1,423 miles / 36” and 42” / 1743 psig

! Recent Rockies projects• Overthrust Pipeline – 105 miles / 36” / 1440 psig• Questar Pipeline – 60 miles / 24” / 1440 psig• White River Hub – 3 Bcf/d / 30” / 1440 psig

• We have done it right! Acknowledged successes

• 2008 Earth Day award presented to Questar• 2007 SGA Environmental Excellence Award presented to Alliance

Page 26: Rockies Alliance Pipeline Open Season Presentation Alliance...CIG Historical & Forward Basis Source: ... (pipeline/station) • Design considerations ... Rockies Alliance Pipeline

Slide 26

Alliance and Questar Synergies

• Regional expertise

• Proven ability to navigate environmental process in order to maintain project schedule! Alliance Pipeline: 2 countries, 3 provinces and 4 states - over

twice the scope of Rockies Alliance Pipeline! Built on schedule and on budget

• Reputation for following through on commitments

• Excellent relationships/reputation with FERC, Forest Service, BLM, and other regulatory agencies and stakeholders

• Recognized industry leaders

Page 27: Rockies Alliance Pipeline Open Season Presentation Alliance...CIG Historical & Forward Basis Source: ... (pipeline/station) • Design considerations ... Rockies Alliance Pipeline

Slide 27

Keys to Success on RAP

• Early stakeholder identification and communication

• Early identification and resolution of environmental issues

• Develop strong support team of regional experts

• Maximize use of FERC’s Pre-Filing Process in order to shorten application approval time

Page 28: Rockies Alliance Pipeline Open Season Presentation Alliance...CIG Historical & Forward Basis Source: ... (pipeline/station) • Design considerations ... Rockies Alliance Pipeline

Slide 28

RAP Progress To Date

• Scheduling! Cultural and environmental field surveys! FERC environmental process

• Routing! Rangeland – T&E, cultural sites, reclamation! Nebraska Sand Hills – unique ecosystems, reclamation ! Agricultural land – construction and reclamation plan! Rivers – Platte and Missouri

• Air quality

Page 29: Rockies Alliance Pipeline Open Season Presentation Alliance...CIG Historical & Forward Basis Source: ... (pipeline/station) • Design considerations ... Rockies Alliance Pipeline

Slide 29

Agenda

• Welcome and Introductions

• Rockies Alliance Pipeline (RAP) Offering

• Engineering & Construction

• Environment & Permitting

• Route Development & ROW Acquisition

• Open Season Details

Page 30: Rockies Alliance Pipeline Open Season Presentation Alliance...CIG Historical & Forward Basis Source: ... (pipeline/station) • Design considerations ... Rockies Alliance Pipeline

Slide 30

Right of Way and RAP

• Similar scope! Managed acquisition,

construction and remediation activities on similar ROW with similar land use

• We know how to do it right! Landowner issues

and concerns! Unique land use and

soil issues! On time and on budget

Page 31: Rockies Alliance Pipeline Open Season Presentation Alliance...CIG Historical & Forward Basis Source: ... (pipeline/station) • Design considerations ... Rockies Alliance Pipeline

Slide 31

Identified Issues

• Schedule! Survey support ! Accelerated acquisition

• Unique project issues ! Parallel construction! Pivot irrigation systems ! Drain tile systems

Page 32: Rockies Alliance Pipeline Open Season Presentation Alliance...CIG Historical & Forward Basis Source: ... (pipeline/station) • Design considerations ... Rockies Alliance Pipeline

Slide 32

Keys to Success on RAP

• Good relations with landowners/affected stakeholders

• Knowledgeable agents/field staff

• Strong support from regional experts

Page 33: Rockies Alliance Pipeline Open Season Presentation Alliance...CIG Historical & Forward Basis Source: ... (pipeline/station) • Design considerations ... Rockies Alliance Pipeline

Slide 33

Agenda

• Welcome and Introductions

• Rockies Alliance Pipeline (RAP) Offering

• Engineering & Construction

• Environment & Permitting

• Route Development & ROW Acquisition

• Open Season Details

Page 34: Rockies Alliance Pipeline Open Season Presentation Alliance...CIG Historical & Forward Basis Source: ... (pipeline/station) • Design considerations ... Rockies Alliance Pipeline

Slide 34

Open Season Details

• RAP Open Season ends June 16, 2008

• Targeted in-service November 1, 2011

• Capacity 1.3 Bcf/d expandable to 1.8 Bcf/d

• Term differentiated rate options of 10, 15, and 20 years with option for maximum recourse reservation rate or fixed negotiated reservation rates

• RAP has right to revise rates by November 1, 2008 if costs exceed US$4.1B

• Any rate increases are subject to negotiation and approval by shippers on or before November 1, 2008

• RAP to make determination of sufficient capacity subscription by March 31, 2009

• Shipper Board of Director approvals must be obtained by March 31, 2009

• RAP Board of Director approvals must be obtained by May 30, 2009

• FERC 7(C) application to be filed no later than April 30, 2010

Page 35: Rockies Alliance Pipeline Open Season Presentation Alliance...CIG Historical & Forward Basis Source: ... (pipeline/station) • Design considerations ... Rockies Alliance Pipeline

Slide 35

Rockies Alliance Pipeline Open Season

Questions concerning RAP and this Open Season should be directed to:Alliance Pipeline:• Eric Besseling (403)-517-6551• Lorraine Lindberg (713)-821-1746

Overthrust Pipeline:• Shelley Wright (801) 324-2509• Gaylen Haag (801) 324-5133

E-mail:• [email protected]

Page 36: Rockies Alliance Pipeline Open Season Presentation Alliance...CIG Historical & Forward Basis Source: ... (pipeline/station) • Design considerations ... Rockies Alliance Pipeline