Top Banner
1 ROBOT WELDING SETUP REDUCTION TRAINING November 14, 2013 By Julian Kalac, P.Eng
30

ROBOT WELDING SMED TRAINING NOV 14

Jan 16, 2017

Download

Documents

Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: ROBOT WELDING SMED TRAINING NOV 14

1

ROBOT WELDING SETUP

REDUCTION TRAINING

November 14, 2013

By Julian Kalac, P.Eng

Page 2: ROBOT WELDING SMED TRAINING NOV 14

2

Problem Statement & Objective

Current setup time= 40min

Standard Time= 15min

Target setup Time < 5min

Helping Our Customers Be More Successful . . .

Page 3: ROBOT WELDING SMED TRAINING NOV 14

5

Benefits of SMED

• Reduced setup time

• Higher efficiencies

• Increased capacity

• Reduced WIP’s

• Lower batch sizes

• Increased safety

• Increased flexibility

• Elimination of waiting

• Operators preference

• Stockless production

• Less Scrap & Rework

Page 4: ROBOT WELDING SMED TRAINING NOV 14

6

SMED (Single Minute Exchange Die)

• Setup Time– Starts when last piece of previous job is complete;

ends when first good piece of next job is complete

• Internal set-up: While machine is shut-down– Strive to minimize this as process is not producing

parts

• External set-up: While machine is working– Prepare for set-up, get all tools/parts needed ready

and beside the press before starting set-up

Page 5: ROBOT WELDING SMED TRAINING NOV 14

7

Seven rules for improving Setup

1. Setup improvement begins & ends with 6S.

2. Change Internal (on line) setup into External (off

line) setup then improve any remaining internal

changeover. Ask WHY again & again.

3. Find alternatives to bolts (they are too slow to get

on & off).

4. If you have to use your hands make sure your feet

stay put.

5. Don’t rely on special fine tuning skills.

6. Standardize all changeover operations.

7. Standards are standards / they are not flexible.

Page 6: ROBOT WELDING SMED TRAINING NOV 14

8

Internal Vs. External (cont’d)

• Primary goal is to change all internal setups to external

ones

• Reduce length of internal setup if unable to convert to

external

• Reduce length of all external setups as well

Page 7: ROBOT WELDING SMED TRAINING NOV 14

9

Simple Suggestions

• Analysis of setup procedures using videotapes

• Use more people where available

• Use offline time as maintenance time

• Practice makes perfect

Page 8: ROBOT WELDING SMED TRAINING NOV 14

10

SMED Examples

• Split thread bolts

• Handles

• Toggle clamps

• U-shaped washers

Page 9: ROBOT WELDING SMED TRAINING NOV 14

11

Example Tools (cont’d)

u-shaped washers Split thread bolts

Page 10: ROBOT WELDING SMED TRAINING NOV 14

12

Page 11: ROBOT WELDING SMED TRAINING NOV 14

13

Example of SMED Tools

Page 12: ROBOT WELDING SMED TRAINING NOV 14

14

Page 13: ROBOT WELDING SMED TRAINING NOV 14

15

Page 14: ROBOT WELDING SMED TRAINING NOV 14

16

Quick Connect Toggle Clamps

Page 15: ROBOT WELDING SMED TRAINING NOV 14

17

The spring-loaded, one-

handed clamp with quick-

set, magnetic V-Pad.

Quick and easy to use!

Squeeze to open, set in

position and turn to

tighten.

MagSpring Clamps

Page 16: ROBOT WELDING SMED TRAINING NOV 14

18

Sliding Channel Clamps

Page 17: ROBOT WELDING SMED TRAINING NOV 14

19

Table Mount C-Clamps

Quick Connect Clamps

Page 18: ROBOT WELDING SMED TRAINING NOV 14

20

Robot 9 Set-Up Reduction Project Action Items

1-5S work station (label tools, screws, nuts & fixtures)-->Brent Nov 14

2-Fabricate welding fixture for 6/22 parts, --Andrey Nov 14

3-Program needed changes --> Earl To be scheduled

4-Redo Setup video same part after 5S --Brent/Julian--( to be sched)

5-Program all parts to run on both sides—Earl 9/22 parts ?

6-Implement a setup/downtime tracking sheet –Julian Nov 14

7-Implement a suggestion log for operators—Julian Nov 14

8-Etch in GRIDS onto the welding fixture—Brent Nov 14

9-Post “To Do List” at Robot 9 cell—Julian Nov 14

10-Decide if Air Gun or Air Rachet is more feasible—Earl—Nov 20

11- See if Robot cn position for Ream from the front side—Earl—Nov 20

12-Anti Spatter tank Earl –Nov 15

13-Colour Code the fixtures as per the setup sheet –Brent Nov 15

Page 19: ROBOT WELDING SMED TRAINING NOV 14

21

ROBOT 9 ZERO SETUP TIME

PROJECT

Page 20: ROBOT WELDING SMED TRAINING NOV 14

22

Robot 9 Weld Cell Process FlowProcess/Material Flow

Step 1Parts From Brake Press

Step 2Tacking

Step 3Robot 9

Step 4Clean Part

Step 5Out to next operation

Move the welded

parts out ASAP

Page 21: ROBOT WELDING SMED TRAINING NOV 14

Screw weld blocks onto fixture 10-15min why?

WELD

FIXTURE

WHATS THE

PROBLEM?

SPEED OF

RACHET

Page 22: ROBOT WELDING SMED TRAINING NOV 14

24

Screw length

Page 23: ROBOT WELDING SMED TRAINING NOV 14

25

STANDARDIZE SCREWS

PROBLEM SOLUTION WING NUTS

Page 24: ROBOT WELDING SMED TRAINING NOV 14

26

Page 25: ROBOT WELDING SMED TRAINING NOV 14

27

Page 26: ROBOT WELDING SMED TRAINING NOV 14

28

Page 27: ROBOT WELDING SMED TRAINING NOV 14

29

Page 28: ROBOT WELDING SMED TRAINING NOV 14

Robot 9 SMED SOP=ZERO SETUP TIME

SIDE A CHANGEOVERstep # Operation Est Time (min)

1 PREPARE NEXT WO MATERIAL 4

2 GET NEEDED FIXTURES/TOOLS/CLAMPS 3

3 UNLOAD LAST PARTS FROM SIDE 1 1

4 INSPECT AND TOUCH UP PARTS 2

5 TACK PARTS 2 (EXTERNAL SETUP)6 TAKE DOWN FIXTURE FROM SIDE 1 4 BEING DONE

7 LOAD PARTS ONTO SIDE 1 1 WHILE ROBOT rUNNING

8 START WELDING SIDE 1 0

TOTAL TIME FOR SETUP= 16

WELD CYCLE STARTED = 8 T SETUP TIME CLOCK STARTS

AFTER 8 MIN

SIDE B CHANGEOVEREXTERNAL SETUP

7 TAKE DOWN FIXTURE FROM SIDE 2 5 INCLUDED IN

8 LOAD PARTS ONTO SIDE21 1 WELD CYCLE (8MIN)

9 START WELDING SIDE 2 0

TOTAL SETUP TIME SIDE B= 6

TOTAL INTERNAL SETUP TIME= 0

TOTAL EXTERNAL SETUP TIME= 12

OLD SETUP TIME (MIN)= 38

DEC 4 SETUP (MIN) = 0

SETUP TIME IMPROVEMENT (MIN) = -38

WHILE THE ROBOT IS WELDING SIDE B, LOST TIME=0 MINGOAL IS TO CHANGE STATION A BEFORE ROBOT FINISHES WELDING SIDE B

DURING WELD CYCLE (8MIN) THE FOLLOWING WAS DONE

Page 29: ROBOT WELDING SMED TRAINING NOV 14

Robot 9 SetUp Time Savings (228/229 parts)

OLD SetUp Time for Robot 9 SetUp Time

(Min)

SetUp Time

(Hrs)

Number

SetUps/Shift

Total SetUp

Time/Shift

Total SetUp

Time/Day

SetUp

Time/Week

SetUp

Time/Year Machine Rate

Annual Lost

Productivity

38 0.63 2 1.27 2.53 12.67 595.33 $ 100.00 $ 59,533.33

DEC 4TH SetUp Time for Robot 9= ZERO SETUP TIME SetUp Time

(Min)

SetUp Time

(Hrs)

Number

SetUps/Shift

Total SetUp

Time/Shift

Total SetUp

Time/Day

SetUp

Time/Week

SetUp

Time/Year Machine Rate

Annual Lost

Productivity

5 0.08 2 0.17 0.33 1.67 78.33 $ 100.00 $ 7,833.33

Hrs Saved 517.00

$ 51,700.00 ANNUAL SAVINGS =