Road Maintenance Council Contract RMCC Reporting Requirement Maya Amaraweera Project Manager Maintenance Evaluation
7

Road Maintenance Council Contract RMCC Reporting Requirement Maya Amaraweera Project Manager Maintenance Evaluation.

Dec 22, 2015

Download

Documents

Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Road Maintenance Council Contract RMCC Reporting Requirement Maya Amaraweera Project Manager Maintenance Evaluation.

Road Maintenance Council Contract

RMCC Reporting Requirement

Maya AmaraweeraProject Manager Maintenance Evaluation

Page 2: Road Maintenance Council Contract RMCC Reporting Requirement Maya Amaraweera Project Manager Maintenance Evaluation.

Contents

•Existing reporting requirement•Regional practice•Areas of duplication (Councils & RMS)•Proposed improvements•New RMAP•Changes to CIM

Page 3: Road Maintenance Council Contract RMCC Reporting Requirement Maya Amaraweera Project Manager Maintenance Evaluation.

Existing Reporting Mechanism

Maintenance Gang

O Identify defects - furtherO Routine Mandatory Items – fixedO Ordered works – Approved Wos carried out

O Record AccomplishmentO Person hoursO Machines

RFLECT / FIDO

Finance System

G8 ReportRoutine Services

Cost

Contract Information Managemente (CIM) – at each Region

`

Quarterly Update

Quarterly Update

Work Orders (All Ordered

Works)

WO

* Start of the Year RMAP

Routine & Ordered WorksAnnual Plans

Quarterly RMAPsRoutine & Ordered

WorksAnnual Plans

Quarterly RMAPsRoutine & Ordered

WorksAnnual Plans

Quarterly RMAPsRoutine & Ordered

WorksAnnual Plans

Quarterly RMAPs

Record Accomplishment and Man hours

`

REFLECTG7 Report

Detailed Accomplishment (all

work recorded @ Segment)

Record Accomplishment and Man hours

G6 Report Simple

Accomplishment (all work related to the

Services)Quarterly Summary

D o n o

t Up lo

a d

Page 4: Road Maintenance Council Contract RMCC Reporting Requirement Maya Amaraweera Project Manager Maintenance Evaluation.

Proposed Improvements …

Maintenance Gang

O Identify defects - furtherO Routine Mandatory Items – fixedO Ordered works – Approved Wos carried out

O Record AccomplishmentO Person hoursO Machines

RFLECT / FIDO

Record Accomplishment and Man hours

G7 Report Detailed

Accomplishment (all work recorded @

Segment)

Finance System

Accomplishment

`

REFLECT

Cost Reports

Quarterly Summary

Quarterly Summary

Record Accomplishment and Man hours

COUNCIL

Quarterly Update

Quarterly Update

Quarterly RMAPsRoutine & Ordered

WorksAnnual Plans

* Start of the Year RMAP

Routine & Ordered WorksAnnual Plans

Quarterly RMAPsRoutine & Ordered

WorksAnnual Plans

Quarterly RMAPsRoutine & Ordered

WorksAnnual Plans

Quarterly RMAPs

Communication - COUNCIL & RMS

Contract Information Managemente (CIM)each Region

`Information on RMAP

Road Maintenance Benchmarking (RMB)

m2

$$

Quarterly Payments

$$

Annual Update

Page 5: Road Maintenance Council Contract RMCC Reporting Requirement Maya Amaraweera Project Manager Maintenance Evaluation.

RMAP Process…..proposed

•Joint Planning Assessment•RMAP produce (LGA Draft)•Review by RMS•Agreed to RMAP•Quarterly updates with actual work done by Council

–Activity level - Accomplishment & Expenditure•Upload into CIM by RMS (Contract Clerks)•Quarterly Payment •Feed into RMB (Road Maintenance Benchmarking Module)

Page 6: Road Maintenance Council Contract RMCC Reporting Requirement Maya Amaraweera Project Manager Maintenance Evaluation.

New RMAP

There are SIX RMAPS:LGA DraftRMS ReviewOriginal Approved End Q1End Q2End Q3Final

Accomplishment – OW and Incident ResponsesExtra sheet added “OW and Incidents”Accomplishment against all OW and Incidents reports by end of each quarter

Page 7: Road Maintenance Council Contract RMCC Reporting Requirement Maya Amaraweera Project Manager Maintenance Evaluation.

New RMAP

•Functionalities:Minimise manual entryCalculate payments due

Routine Pavement (Mandatory and Supplementary)

Routine Corridor (Mandatory and Supplementary Routine signs (Mandatory)

Payment adjustment for the next quarter

•Changes to CIM - New modulecapture RMAP