CONVEYOR SYSTEM FOR UNLOADING FACILITIES TERMINAL MULTI PURPOSE TELUK LAMONG PT. PELABUHAN INDONESIA III ( PERSERO ) OWNER : PT. PELINDO III ( PERSERO ) CONTRACTOR :PT. ULAN BUANA ENGINEERING PROJECT TITLE :CONVEYOR FOR UNLOADING FACILITIES LOCATION :EAST JAVA, INDONESIA PROJECT NO. : - MULTI PURPOSE CONVEYOR SYSTEM JETTY TELUK LAMONG DOC. NO. : PIII-UBE-002.PR.062014
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
CONVEYOR SYSTEM FOR UNLOADING FACILITIESTERMINAL MULTI PURPOSE TELUK LAMONGPT. PELABUHAN INDONESIA III ( PERSERO )
OWNER : PT. PELINDO III ( PERSERO )
CONTRACTOR :PT. ULAN BUANA ENGINEERING
PROJECT TITLE :CONVEYOR FOR UNLOADING FACILITIES
LOCATION :EAST JAVA, INDONESIA
PROJECT NO. : -
MULTI PURPOSE CONVEYOR SYSTEMJETTY TELUK LAMONG
DOC. NO. : PIII-UBE-002.PR.062014
Rev. No. Date Description Prep’d Checked Appr’d
SPECIFICATION FOR
CIVIL/STRUCTURE
Job No : Rev.
0Doc. No. :
Date By Check App.
APPENDIX 8-2
SPECIFICATION FOR CIVIL/STRUCTURE
8-2.1 CIVILS AND STRUCTURAL SPECIFICATION
8-2.1.1 DESIGN
All Civil and structural designs shall be based on the Codes, Specifications and Standards
referred to herein. CONTRACTOR’s designs may use other Codes, Specifications and
Standards which it has found from experience to be appropriate providing these are not
less stringent than those referred to herein.
CONTRACTOR’s design shall be based on the following Codes, Specifications and
Standards, latest editions.
- SSPC - Steel Structures Painting Council
- ASTM - American Society of Testing Materials
- AISC - American Institute of Steel Construction
- ACI - American Concrete Institute
- UBC - Uniform Building Code
- ANSI - American National Standard Institute
- SII - Standard Industry Indonesia
- SNI - Standard Nasional Indonesia
- ASCE - American Society of Civil Engineers
- JIS - Japanese Industrial Standard
8-2.2.2 FOUNDATIONS
Foundation for the structure and building will follow the recommendation as per the final
soil report.
Foundations shall be designed for total and differential settlements not to exceed 25 mm
and 15 mm respectively.
This design parameter shall be applicable to structures sensitive to total and differential
settlements shall be reviewed on a case by case basis, and subject to OWNER approval.
SPECIFICATION FOR
CIVIL/STRUCTURE
Job No : Rev.
0Doc. No. :
Date By Check App.
8-2.2.3 PILING CONSTRUCTION DRAWINGS
(1) Specifications and Piling Construction Drawings showing the locations of the piles
referenced to the existing OWNER Coordinate System. Piles shall be identified in
sequence either by a number or letter/number designation. Duplication of
identifying numbers will not be acceptable. CONTRACTOR shall provide OWNER
with 4 (four) copies of all pile load tests (static test), 4 (four) copies of PDA test and
3 (three) copies of complete pile driving records.
Additionally, CONTRACTOR shall, upon completion of piling, provide OWNER
with 5 (five) copies of the complete pile record in the tabular form to be proposed by
OWNER.
Detailed design calculations for each piled foundation which shall clearly show
design assumptions and/or design parameters, loads/forces and references to the
Section of the Code/Standard on which the designs are based.
(2) CONTRACTOR shall prepare and periodically up-grade as design progresses the
following data for each facility and/or unit as a check by OWNER on piling
requirements.
- Pile types
- Pile capacities
- Estimated length for each type of pile
- Number of piles for each type
- Estimated total linear meters of each type of pile
- Pile design criteria for pilling work
(3) CONTRACTOR in its Lump Sum shall provide for the supply, delivery and
installation of all piles including, but not limited to, supervision, inspection, layout,
blast cleaning/coating and pile driving records
(4) CONTRACTOR in its Lump Sum shall carry out static pile loading test (2 point for
each tension, lateral test and compression test) to ensure pile design criteria before
piling work done. Dynamic pile loading test (PDA Test) shall carry out on 4 (four)
piles at beginning of piling work. PDA test also shall be applied after completion of
SPECIFICATION FOR
CIVIL/STRUCTURE
Job No : Rev.
0Doc. No. :
Date By Check App.
piling work on driven pile that indicated has under specification. Pile capacity at
least on 2 (two) points driven pile.
(5) Pile equivalency will be in accordance to OWNER and CONTRACTOR
clarification staled elsewhere.
In connection with the above:
All design and calculation shall be submitted to OWNER for approval prior to further
stage. Only approved design shall be used for construction.
8-2.2.4 STRUCTURAL STEEL
(1) Structural steel materials shall conform to ASTM-A36, JIS G 31011 SS 41 or
equivalent with minimum yield strength of 36,000 psi, and designed in accordance
with AISC and UBC.
(2) CONTRACTOR shall prepare and periodically upgrade as design progresses the
tonnage of structural steel, as a check by OWNER, for the following:
a) Transfer Tower
b) Bent
c) Gallery Conveyor
d) Railway for Portal Scraper
e) Transformer yard
f) Offsite facilities (if any)
g) Miscellaneous structures
h) Others
8-2.2.5 CONCRETE, CONCRETE FOUNDATIONS AND CONCRETE STRUCTURES
(1) Concrete
- Concrete for general purpose work include pavement shall conform to ACI-
318 and UBC and have an average compressive strength of 3000 psi at 28
days.
- Concrete for foundation, road and structure shall have an average compressive
strenght of 4000 psi at 28 days.
SPECIFICATION FOR
CIVIL/STRUCTURE
Job No : Rev.
0Doc. No. :
Date By Check App.
- Concrete for pre-stressed concrete shall have an average compressive strength
of 7250 psi at 28 days.
- Cement shall conform to ASTM C-150 and be type I for all on land concrete
structure.
- Reinforcement bars for concrete shall conform to SNI 07-2052 2002
equivalent to JIS G3112; BJTD 40, minimum yield strength is 4000 kg/cm2,
and for plain bar BJTP 24, minimum yield strength is 2400 kg/cm2.
- Pre-stressing tendons for pre-stressed concrete shall conform to ASTM A-
421, ASTM A-416 or ASTM A-722 and have the minimum tensile and yield
strengths stipulated in referenced ASTM specifications. (Fc = 7250 Psi)
- Steel wire fabric reinforcement shall conform to ASTM A- 185.
- Sand and aggregate shall conform to ASTM C-33.
(2) Concrete Foundations and Concrete Structures
- Specifications, Material Quantities, and Concrete Foundation. Construction
Drawings for shallow spread footings and raft type foundations (where
applicable) for equipment, structures and buildings supported at grade. Also
similar documents for the foundations supported on piles.
- Specifications, Material Quantities and Construction Design Drawings for all
Reinforced Concrete Structures, above and below grade, consisting of Plans.
Elevations, Sections and Details.
- Specifications, Material Quantities and Design/Construction Drawings for
reinforced concrete structures for all equipment and items of supply of a
special nature such as compressor, clarifier, settling pond, if any.
- Specifications and Design/Construction Drawings shall, in addition to the
Project Design Parameters, include the specific design requirements.
SPECIFICATION FOR
CIVIL/STRUCTURE
Job No : Rev.
0Doc. No. :
Date By Check App.
- Concrete Foundation and Concrete Structure Construction Drawings referred
to above, including Reinforcement Bar Bending Schedules, shall be clear and
complete and show all pertinent requirements and information such as, but not
limited to, dimensioned locations, elevations and dimensions of members,
size/spacing/location of reinforcement, size/location/projection of anchor
bolts, details of concrete inserts, pockets, and types of surface treatment/finish
to permit rapid and easy construction.
- Detailed design calculations for each concrete foundation and each reinforced
concrete structure which shall clearly show design assumptions and/or design
parameters, loads/forces and references to Section of the Code/Standard on
which the designs are based. All calculation shall be use LRFD methode.
- As above for all other civil engineering work including paving and temporary
facilities.
In connection with the above:
All design and calculation shall be submitted to OWNER for approval prior to
further stage. Only approved design shall be used for construction.
(3) CONTRACTOR shall prepare and periodically upgrade as design progresses the
cubic meters of concrete, as a check by OWNER, for the following:
a) Foundations for Structures & Buildings.
b) Concrete upper structures for building.
c) Paved Areas.
d) Roads and ditch.
e) Miscellaneous Concrete.
f) Temporary Facilities.
8-2.2.7 CONCRETE BUILDINGS
(1.) Detailed Requirements
Substation & Control Room Building
Substation buildings shall be concrete block construction with roof, floors and
columns of concrete and walls of concrete block.
SPECIFICATION FOR
CIVIL/STRUCTURE
Job No : Rev.
0Doc. No. :
Date By Check App.
Roofing shall be polypropylene or approved equal type roofing finished with local
gravel. Insulation shall be 50 mm thick Fesco board or other approved equal
incombustible material having a non-capillary structure and resistant to fungus
growth.
Ventilation/Windows shall be aluminum projected and/or fixed sash. Ventilation
shall be completed with exhaust fan.
Each building shall be air conditioned as required.
Exposed surfaces of sash shall have a clear anodized finish of 0.02 mm minimum
thickness.
External door for substation building shall be steel doors (manufactured standard).
Control room shall use raised floor for sufficient cabling.
8-2.2.8 STEEL STRUCTURES
Steel structure work (except steel building & transformer yard) consists of:
- Transfer tower (TT-01, TT-2, TT-03, TT-04).
- Conveyor gallery BC-01, BC-02, BC-03, BC-04.
- BENT or Gallery Support (if any).
Structures such as Transfer Tower and gallery conveyor shall be structural steel. The first
and the end columns on each gallery segment shall be linear with the gallery support.
Specifications and Design Drawings for Structural Steel Structures consisting of Plans,
Elevations, Sections and Details which define completely the Structure(s) requirements
including, but not limited to. dimension elevations, member sizes/weights, location of
fixed/removable handrail, stairs, ladders, equipment framing/floor cut-outs, type(s) of
flooring, hoist/crane, equipment support connection, member forces/reactions/moments
and column anchor bolts to permit a structural steel fabricator to design, detail and prepare
shop drawings, supply and fabricate the structural steel structures.
SPECIFICATION FOR
CIVIL/STRUCTURE
Job No : Rev.
0Doc. No. :
Date By Check App.
Dead, live, wind, earthquake, thermal and operating loads for supported equipment shall
be listed on the design drawings or in appropriate calculations.
- CONTRACTOR shall assume that for special equipment such as conveyors required
in material handling systems, the conveyor galleries and related structural steel will
form part of the CONTRACTOR’s design, and supply the structural steel necessary
to support the special equipment on the Structural Steel Structure.
- Detailed design calculations for each structure which clearly show design assumptions
and/or design parameters, loads/forces and references to Section of the
Code/Standard on which the designs are based.
- Check Vendor’s calculations for shop details and shop erection/detail drawings to
ensure correct interpretation of design Drawings. Specifications and Schedule for
each structure. This shall not relieve the Vendor from complying with its
responsibilities to perform in accordance with the terms of its CONTRACT.
- CONTRACTOR shall done review or recalculation existing structure (such as existing
2852-H, conveyor gallery 2805-V, 2D Building) that will support new facilities such
as new conveyor or new gallery. BENT shall be constructed from Transfer Tower
for supporting new gallery. Gallery 2805-V Modification shall be built with new
steel structure, during dismantling and cutting work CONTRACTOR shall take
account for not make any damage to existing conveyor gallery steel structure.
CONTRACTOR shall substitute roofing, siding and checkered plate.
- CONTRACTOR shall calculate and assume that for transfer tower (TT-6805-H and
TT-6806-H) will support new conveyor (from other’s project), this transfer towers
shall have sufficient strength and stability.
In connection with the above:
All design and calculation shall be submitted to OWNER for approval prior to further
stage. Only approved design shall be used for construction.