Top Banner
NATURAL RESOURCE TECHNOLOGY EPA I^egion 5 Records Ctr. 360633 Wisconsin Public Service River Operable Unit Technical Letter Report Campmarina Former Manufactured Gas Plant Sheboygan, Wisconsin WIN000510058 MarclT 22, 2007 Project No: 1665
56

River Operable Unit Technical Letter Report · RAP Remedial Action Plan ROD record of decision ... wood treatment, and paving roads. The gas was passed through purifiers to remove

Sep 29, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: River Operable Unit Technical Letter Report · RAP Remedial Action Plan ROD record of decision ... wood treatment, and paving roads. The gas was passed through purifiers to remove

NATURAL RESOURCE TECHNOLOGY

EPA I^egion 5 Records Ctr.

360633

Wisconsin Public Service

River Operable Unit Technical Letter Report

Campmarina Former Manufactured Gas Plant Sheboygan, Wisconsin WIN000510058

MarclT 22, 2007

Project No: 1665

Page 2: River Operable Unit Technical Letter Report · RAP Remedial Action Plan ROD record of decision ... wood treatment, and paving roads. The gas was passed through purifiers to remove

NATURAL

RESOURCE

TECHNOLOGY

RIVER OPERABLE UNIT TECHNICAL LETTER REPORT CAMPMARINA FORMER MANUFACTURED GAS PLANT

WISCONSIN PUBLIC SERVICE CORPORATION SHEBOYGAN, WISCONSIN USEPA ID: WIN000510058

Project No: 1665

Prepared For:

Wisconsin Public Service Corporation 700 N. Adams Street Green Bay, WI 54307

Prepared By:

Natural Resource Technology, Inc. 23713 W. Paul Road, Suite D

Pewaukee, WI 53072

March 22, 2007

'•(J^^MfA^ Richard H. Weber, PE Managing Engineer

23713 W. Paul Rd., Ste. D • Pewaukee, Wl 53072 • Phone: 262.523.9000 Pewaukee • Madison

Fax: 262.523.9001 • www.naturalrt.com

Page 3: River Operable Unit Technical Letter Report · RAP Remedial Action Plan ROD record of decision ... wood treatment, and paving roads. The gas was passed through purifiers to remove

TABLE OF CONTENTS

1 INTRODUCTION 1 1.1 General Site Information 2 1.2 Site History 3

1.3 Current Site Conditions 5 1.4 Overview of Previously Performed Activities 6

1.4.1 Overview of Remediation Work Performed 6 1.4.2 Status of Site Conditions & Monitoring 7

1.5 Sheboygan River Characteristics 8

1.6 Dredging History 10

2 SHEBOYGAN RIVER AND HARBOR SUPERFUND SITE 12

2.1 Location and Description 12 2.2 Remedial Investigation 13 2.3 Risk Assessments 14 2.4 Sediment Transport Study 14

2.5 Feasibility Study 15 2.6 Record of Decision 15 2.7 Schedule 16

3 PREVIOUSLY PERFORMED RIVER OU INVESTIGATIONS AND RESULTS 17

3.1 BBL-1990 17

3.2 W D O T - 1 9 9 3 17

3.3 W D N R - 1 9 9 5 18

3.4 N R T - 1 9 9 8 18

3.4.1 October 1995 Investigation Activities 19 3.4.2 November 1995/June 1996 Investigation Activities 19

3.5 Chemical Constituents in Sediment 20

3.5.1 BTEX and PAH Results 21

3.5.2 Metals Results 22 3.5.3 PCB Results 22 3.5.4 Cyanide and Phenol Results 22

3.6 Chemical Constituents in Surface Water 23

4 REMEDIAL ACTIONS PERFORMED 24

5 IDENTIFIED RIVER OU PATHWAYS AND CONCLUSIONS 26

5.1 River OU Potential Exposure Scenarios and Receptors 26 5.1.1 Recreational Land Use Scenario - Visitor/Trespasser 26 5.1.2 Benthic Invertebrates-Aquatic Ecological Receptor 26 5.1.3 Other Ecological Receptors 27

1665 river ou tech Itr rev 0 final NATURAL i RESOURCE

TECHNOLOGY

Page 4: River Operable Unit Technical Letter Report · RAP Remedial Action Plan ROD record of decision ... wood treatment, and paving roads. The gas was passed through purifiers to remove

TABLE OF CONTENTS

5.2 Additional Data Needs Summary 27

6 REFERENCES (RECORD FILE) 28

FIGURES

Figure 1 Figure 2

Site Location (1665-AOI.DWG)

Historical Site Layout (1665-3-BOI.DWG)

APPENDICES

Appendix A: Remedial Investigation/Feasibility Study Work Plan, Campmarina Former MGP Site, NRT July 2004 Sheet 1 Site Plan (I665\2-SED\I665-2-DOI.DWG)

Sheet 2 Former MGP Structure Locations (I665\2-SED\I665-2-DO2.DWG)

Sheet 3 Previous Sampling Locations, Distribution, of BTEX and Total PAH and Visual Observations (I665\2-SED\I665-2-DO3.DWG)

Appendix B: Sediment Investigation Report, Campmarina Former MGP Site, NRT February 1998 Table 1 through Table 4 Plate 2 Geologic Cross Section A-A' through J-J' (II83M.3II83-DO2)

Plate 3 Depth to Tar Contour (1183/4.3 II83-DO3)

Appendix C: BBL Sediment Sample Locations Appendix D: Construction Documentation Report, Campmarina Former MGP Site, NRT

February 2003 Table 2 Figure 5 (1313/3.8/AB/1313-B33)

Sheet C040 (1313/3.8/AB/1313DC040AB)

1665 river ou tech Itr rev 0 final NATURAL

RESOURCE

TECHNOLOGY

Page 5: River Operable Unit Technical Letter Report · RAP Remedial Action Plan ROD record of decision ... wood treatment, and paving roads. The gas was passed through purifiers to remove

ACROYNMS

BBL Blasland, Bouck, & Lee, Inc. BTEX benzene, toluene, ethybenzene, xylene CITY City of Sheboygan CERCLA Comprehensive Environmental Response Compensation, and Liability Act COPCs constituents of potential concern cfs cubic feet per second cy cubic yard Garton Garton Toy Company HEC Hydrologic Engineering Center Heileman Heileman Brewing Company msl mean sea level MGP manufactured gas plant NCP National Contingency Plan ND non-detectable NRT Natural Resource Technology, Inc. OUs operable units ppm parts per million PVOCs petroleum volatile organic compounds PCB polychlorinated biphenyl PAHs polynuclear aromatic hydrocarbons RCRA Resource Conservation and Recovery Act RAP Remedial Action Plan ROD record of decision ARARs applicable or relevant and appropriate requirements RI/FS remedial investigation / feasibility study mi square miles Site site SGLC Sheboygan Gas Light Company SWAC surface-weighted average concentration TBCs To Be Considered TOC Total Organic Carbon USAGE U. S. Army Corps of Engineers USEPA United States Environmental Protection Agency USGS United States Geologic Survey WWSF warm water sport fish community WDNR Wisconsin Department of Natural Resources WDOT Wisconsin Department of Transportation WPSC Wisconsin Public Service Corporation

1665 river ou tech Itr rev 0 final ACR- 1

NATURAL

RESOURCE

TECHNOLOGY

Page 6: River Operable Unit Technical Letter Report · RAP Remedial Action Plan ROD record of decision ... wood treatment, and paving roads. The gas was passed through purifiers to remove

River OU-Technical Letter Report - Campmarina Former MGP Revision 0 3/22/2007

Section 1 - Introduction Page 1 of 30

1 INTRODUCTION

The fonner Campmarina Manufactured Gas Plant (MGP) Site (Site), located in Sheboygan, Wisconsin

(Figure 1), is divided into two operable units (OUs) - the Upland OU and the River OU. Pursuant to the

Administrative Settlement Agreement and Order on Consent (Settlement Agreement) dated January 26,

2007, a Technical Letter Report is to be prepared for each OU to summarize environmental investigation

and remediation activities undertaken at the Site. Natural Resource Technology, Inc. (NRT), on behalf of

WPSC, prepared this Technical Letter Report to address the River OU. The Upland OU is addressed in a

separate Technical Letter Report.

In the early 1990s, the City of Sheboygan (City) installed a dock along the Sheboygan River as part of its

Campmarina Park project. The excavation of footings for the dock uncovered coal tar contamination

associated with the form MGP operations, hi order to address the contamination, on March 24, 1992,

WPSC and the City entered into an environmental investigation/remedial agreement (Contract Number

SF-91-04) in accordance with Section 144.442, Wis. Stats. The Contract required a Remedial

Investigation/Feasibility Study (Rl/FS) be completed consistent with the requirements of the

Comprehensive Environmental Response Compensation, and Liability Act (CERCLA), 42. U.S.C.

§§ 9601 et seq., as amended, and the National Contingency Plan (NCP). WPSC completed an RI/FS for

the upland portion of the Site, which lead to the Wisconsin Upland Record of Decision on January 11,

2001 (2001 ROD). The remedy in the 2001 ROD was constructed in 2001 and is in the operation,

monitoring, and maintenance phase. (The ongoing work is more fully described in the Upland Technical

Letter Report.)

The Campmarina Site is physically related to the larger Sheboygan River and Harbor Site. However, the

Campmarina work is related to releases from the historic MGP operations (which ceased in the 1920s),

while the Sheboygan River and Harbor Site addresses PCB contamination associated with former diecast

operations that occurred up until the early 1970s.

The River OU Technical Letter Report summarizes the previous work undertaken to investigate the River

sediments near the Campmarina Site and discusses the current conditions of the River in the vicinity of

the fonner Campmarina MGP site. In general, the purpose of this Report is to:

1665 river ou tech Itr rev 0 final NATURAL

RESOURCE

TECHNOLOGY

Page 7: River Operable Unit Technical Letter Report · RAP Remedial Action Plan ROD record of decision ... wood treatment, and paving roads. The gas was passed through purifiers to remove

River OU-Technical Letter Report - Campmarina Former MGP Revision 0 3/22/2007

Section 1 - Introduction Page 2 of 30

Briefly describe areas and/or media previously addressed with the Upland OU response actions completed under the State Issued ROD;

Summarize the results and status of the Sheboygan River and Harbor Superfund Site, as it relates to WPSC's Campmarina MGP Site;

Summarize the results of WPSC's preliminary investigations of the River OU;

Summarize remedial actions performed within the River OU;

Identify areas/media within the River OU that may warrant remedial measures and/or response actions; and

• Describe the additional work that will be incorporated into the Site-sp)ecific RI/FS Planning documents.

The report is divided into the following sections:

Section 1: Introduction

Section 2: Sheboygan River and Harbor Superfund Site

Section 3: MGP Related River Investigations and Results

Section 4: Campmarina Remedial Actions Performed

Section 5: River OU Pathways and Conclusions

Section 6: References

1.1 General Site Information

Property Owner:

Former MGP Operator:

City of Sheboygan Contact: Mr. Tom Holtan (920-459-3366) 807 Center Avenue Sheboygan, WI 53081

Wisconsin Public Service Corporation Contact: Mr. Brian Bartoszek (920.433.2643) 700 North Adams Street, P.O. Box 19002 Green Bay, WI 54307-9002

] 665 river ou tech Itr rev 0 final NATURAL

RESOURCE

TECHNOLOGY

Page 8: River Operable Unit Technical Letter Report · RAP Remedial Action Plan ROD record of decision ... wood treatment, and paving roads. The gas was passed through purifiers to remove

River OU-Technical Letter Report - Campmarina Former MGP Revision 0 3/22/2007

Section 1 - Introduction Page 3 of 30

Property Location: NWl/4 of the SW 1/4T15N, R23E, Section 23 732 North Water Street Sheboygan, Wisconsin Sheboygan County

USEPA ID: WIN000510058

WDNR BRRTS #: 02060000095

The Upland OU encompasses an area of approximately 2.3 acres and is bounded by a private boat club

facility on the north, former North Water Street on the east, a vacant lot on the south, and the Sheboygan

River on the west (Appendix A, Sheet 1).

Based on preliminary findings of MGP residuals within sediments, the River OU is approximately 3.4 acres,

adjacent to the Upland OU. This area extends about 80 feet upstream of the former Campmarina northern

property line, as much as 120 feet outward from the shoreline, and about 900 feet downstream of the

fonner Campmarina southern property line, a short distance south of the Pennsylvania Avenue bridge

(Appendix A, Sheet 3).

1.2 Site History

Two methods of coal gas production were used at the Campmarina MGP. The coal gas production

method, used from 1872 to 1886, involved heating the coal in an airtight chamber (retort) which produced

coke and gases containing a variety of volatilized organic constituents. The process also produced tar

which was sold for roofing, wood treatment, and paving roads. The gas was passed through purifiers to

remove impurities such as sulfur, carbon dioxide, cyanide, and ammonia. Dry purifiers contained lime or

hydrated iron oxide mixed with wood chips. The gas was then stored in large holders on the property

prior to distribution for lighting and heating.

The carburetted water gas process, used from 1886 to 1929, involved passing air and steam over the

incandescent coal in a brick-filled vessel to form a combustible gas which was then enriched by injecting

a fme mist of oil over the bricks. The gas was then purified and stored in holders prior to distribution.

The Campmarina MGP operations ceased in 1929. Former aboveground MGP related structures (Figure

2 and Appendix A, Sheet 2) included the following:

1665 river ou tech Itr rev 0 final NATURAL RESOURCE

TECHNOLOGY

Page 9: River Operable Unit Technical Letter Report · RAP Remedial Action Plan ROD record of decision ... wood treatment, and paving roads. The gas was passed through purifiers to remove

River OU-Technical Letter Report - Campmarina Fonner MGP Revision 0 3/22/2007

Section 1 - Introduction Page 4 of 30

Three gas holders ranging in diameter from approximately 35 feet to 70 feet, the larger two with capacities of 70,000 cubic feet and 200,000 cubic feet;

One gas oil tank approximately 15 feet in diameter;

Three tar tanks; two approximately 30 feet by 8 feet and one approximately 20 feet by 5 feet;

One purifier approximately 25 feet in diameter; and

Gas manufacturing buildings including a garage, a gas meter shop, and a boiler room.

Based on review of Sanbom maps, the gas holders were removed between 1950 and 1955. Review of the

1955 Sanbom map indicates that many of the MGP buildings were still present in the Upland OU.

Sometime between 1955 and 1966, the remaining facility structures were razed and removed.

Numerous companies, which eventually became part of the Sheboygan Gas Light Company (SGLC),

owned the fonner Sheboygan MGP. In 1922, SGLC merged with other utilities to form WPSC. In 1966,

WPSC sold the prof)erty to Heileman Brewing Company (Heileman) for use as a parking lot. Heileman

sold the property in 1977, and it was then under ownership of three other non-manufacturing companies

until the City of Sheboygan purchased the property in 1985 when it became known as Campmarina.

Campmarina was equippied with gravel parking areas, electrical power and potable water for recreational

vehicle (RV) use. A docking area was also provided for recreational boat use on the Sheboygan River. In

2001 after WPSC completed upland remediation work, the City redeveloped Campmarina, North Water

Street adjacent to the property, and the property to the south (Center Avenue right-of-way) into a

neighborhood park called Worker's Water Street Park (Appendix A, Sheet 1).

Sanbom maps show the shorelines for the Sheboygan River at the former MGP property. Between 1891

and 1903, the channel appears to have been straightened by fill that extended approximately 60 feet into

the river. Subsequent Sanbom maps show that the shoreline did not change substantially from its present

location indicated on Figure 2.

During the Upland OU remediation (summarized in Section 1.4.1), a sheet pile banier wall was installed

along the Sheboygan River shoreline and the river bank was excavated and restored with filter gravel,

structural fill, and riprap. Details of the remedial action are provided in the Documentation Report (2(X)3,

NRT) and summarized in Section 4.

1665 river ou tech Itr rev 0 final NATURAL RESOURCE

TECHNOLOGY

Page 10: River Operable Unit Technical Letter Report · RAP Remedial Action Plan ROD record of decision ... wood treatment, and paving roads. The gas was passed through purifiers to remove

River OU-Technical Letter Report - Campmarina Former MGP Revision 0 3/22/2007

Section 1 - Introduction Page 5 of 30

Based on review of the Sanbom maps. Boat Island is a man-made land mass located approximately 150

feet from the Site shoreline. The island is approximately 375 feet long by 105 feet wide (at its widest

point) and has several buildings which are used to store materials and supplies for the adjacent marina, the

Outboard Motor Club, located to the north of the Upland OU. The City of Sheboygan owns Boat Island .

The island has seasonal docking for boats.

Historical development activities adjacent (upstream) to the Upland OU included a property formerly

used as a tannery and a toy factory. Tannery operations terminated sometime between 1903 and 1940 and

the property was sold to Garton Toy Company (Garton). The 1950 Sanbom map indicates Garton used a

portion of the property adjacent to the river, directly across New York Avenue, for paint and lacquer

spraying.

1.3 Current Site Conditions

The Upland OU is now within Worker's Water Street Park with landscaped lawn, recreational areas,

seating, and sidewalks. The Park generally extends from the river on the west to 10* Street/North Water

Street on the east, and from the extension of Center Avenue on the south to Wisconsin Avenue on the

north. The Park footprint includes the former MGP property and abandoned right-of-ways for North

Water Street, Center Street, and New York Avenue.

An asphalt parking lot is located on the north side of the Park, with access from Wisconsin Avenue. A

small building constructed adjacent to this parking lot is shared by the Outboard Motor Club and WPSC. '

WPSC's use is related to the remediation work in the Upland OU, while the Outboard Motor Club uses it

to store equipment. The adjacent parking lot provides access to shoreline boat docks as well as additional

docks on Boat Island. North of the Park adjacent to the river is the former tannery and toy factory

building, which has been rehabilitated into multi-tenant housing.

South of the Park is a nanow parcel with a condominium unit at the northwest comer of Water Street and

Pennsylania Avenue. The Pennsylvania Avenue Bridge crosses the river just downstream of the Park and

former MGP. North Commerce Street parallels the river on its west side, with industrial/commercial

buildings located between the street and river.

1665 river ou tech Itr rev 0 final NATURAL RESOLHRCE

TECHNOLOGY

Page 11: River Operable Unit Technical Letter Report · RAP Remedial Action Plan ROD record of decision ... wood treatment, and paving roads. The gas was passed through purifiers to remove

River OU-Technical Letter Report - Campmarina Former MGP Revision 0 3/22/2007

Section 1 - Introduction Page 6 of 30

Based on the United States Geologic Survey (USGS) Sheboygan North Quadrangle, photo revised 1973,

relief within one mile of the Site is approximately 95 feet, ranging from approximately 580 feet mean sea

level (msl) at Lake Michigan to approximately 675 feet msl northwest of the Site in the City of

Sheboygan. The ground surface elevation for the majority of existing Site groundwater monitoring wells

ranges between 588 and 591 feet msl; the Site slopes from Water Street to the Sheboygan River. The

elevation of the Sheboygan River ranges from about 578 feet msl (September 2(X)6) to 579 feet (August

2004), def)endent on the general elevation of Lake Michigan.

1.4 Overview of Previously Performed Activities

A summary of cunent Site conditions was provided to the United States Environmental Protection

Agency (USEPA) in October 2005. The Site status summary included information pertaining to the

upland remediation work performed and the status of Site conditions and monitoring, as well as a listing

of documents pertaining to the Site. A summary of the information included in the report is presented

below.

1.4.1 Overview of Remediation Work Performed

• Upland OU remediation work included soil excavation and thermal treatment (10,500 tons), installation of a containment system (sheet pile barrier around the perimeter of the Site and an engineered geosynthetic cover over the surface) and a biosparge system within the containment area (Appendix A, Sheet 1).

• Mass removal through soil excavation and thennal treatment followed by installation of the containment system is the primary remedy for the Upland OU. The biosparge system is currently in operation and is a secondary remedial measure. The biosparge system is undergoing performance monitoring to evaluate the effectiveness of longer term operation.

H Groundwater monitoring is conducted to demonstrate containment system performance. An Annual Operation, Maintenance, and Monitoring Report was submitted to USEPA and WDNR on November 28, 2005. The 2006 Annual Operation, Maintenance, and Monitoring Report will be incorporated into the Upland OU Technical Letter Report.

• Initial river sediment quality assessments were performed in 1995 and 1996.

1665 river ou tech Itr rev 0 final NATURAL RESOURCE

TECHNOLOGY

Page 12: River Operable Unit Technical Letter Report · RAP Remedial Action Plan ROD record of decision ... wood treatment, and paving roads. The gas was passed through purifiers to remove

River OU-Technical Letter Report - Campmarina Former MGP Revision 0 3/22/2007

Section 1 - Introduction Page 7 of 30

1.4.2 Status of Site Conditions & Monitoring

• Groundwater depth ranges from approximately 5 lo 8 feet below ground surface. Flow is to the south-southeast toward Sheboygan River.

• Soils beneath the former MGP area include sand and gravel fill, and general fill with cinders over the entire former MGP to about 4 to 14 feet below ground surface, underlain by silty/clayey sand and clays to bedrock, at an estimated depth of 35 to 40 feet below ground surface. Thermally treated soils were replaced in the remedial excavations.

• Post-remediation residual concentrations of petroleum volatile organic compounds (PVOCs), polynuclear aromatic hydrocarbons (PAHs), and cyanide are present in soil and/or groundwater in the Upland OU. (^o i^c «-r\ ^a>J-ic>\s To^t, 7

u Shallow groundwater quality is close to or below Wisconsin Administrative Code, -Vupitcl Chapter NR140 standards at perimeter wells MW-705, 708 and 709R (outside of the ^ o P containment system. Appendix A, Sheet 1). Groundwater quality in deeper piezometers ^^•r«4vck'^'' (screened in clay at depth) exceeds standards at one location, PZ-703, and only for benzene.

• Groundwater elevation data demonstrates the containment of MGP-impacted groundwater. (Compare the groundwater elevations in MW-708 located outside the containment barrier with the groundwater elevations in MW-706 located within the containment banier.) ( CA-c.(v3 w^ap V\ou37 ^

• The secondary measure of containment performance -contaminant concentration trends in monitoring wells - confirms containment. See monitoring wells MW-705, MW-708 and MW-709 and piezometers PZ-701, PZ-702 and PZ-703. The only exception is \ PZ-703 which indicates fluctuating groundwater concentrations. ( v-t^c«^^cd +« w* "-

• Biosparge system performance was measured based on contaminant concentration and geochemistry trends at shallow groundwater monitoring wells MW-701R, MW-706 and ^ i do MW-707R within the containment system. The trends indicate fluctuating to decreasing ( % y*f"'^J^'>'j, benzene and naphthalene concentrations and continued biologic activity within the *°'i x biosparge system's zone of influence. (7|A(xP •5V\0U5*» a ^«ospo . r^ t •2<3KC o f ' >- l*^«»^e^)

• Water depths in the Sheboygan River vary from about 2 feet to greater than 10 feet. 1995-1996 poling data identified a sediment area of approximately 3.4 acres with visible coal tar, sheen, and/or odor (Appendix A, Sheet 3). This area extends about 80 feet upstream of the former upstream (northem) MGP Site property line, as much as 120 feet outward from the shoreline, and about 900 feet downstream of the fonner downstream (southem) propierty line, a short distance past the Pennsylvania Avenue bridge. Tar was evident in sample cores ranging in depth from about 1.5 feet to 9.5 feet.

1665 river ou tech ICr rev 0 final NATURAL RESOURCE

TECHNOLOGY

Page 13: River Operable Unit Technical Letter Report · RAP Remedial Action Plan ROD record of decision ... wood treatment, and paving roads. The gas was passed through purifiers to remove

River OU-Technical Letter Report - Campmarina Former MGP Revision 0 3/22/2007

Section 1 - Introduction Page 8 of 30

• Based on the limited 1995-1996 sediment core sampling, the highest total PAH concentrations in the tar/sheen area was 9,294 mg/kg. In two areas without tar observations, PAH concentrations for two samples ranged from essentially non-detectable (ND), 0.09 mg/kg, to 8.1 mg/kg. In nearby areas, both upstream and downstream of the tar/sheen/odor, PAH concentrations ranged from 0.44 mg/kg to 2.17 mg/kg.

1.5 Sheboygan River Characteristics

The Sheboygan River is classified a Class C surface water by the WDNR. Class C surface waters are not

suitable as drinking water sources; however, they are suitable for fishing and fish propagation. Class C

waters are also designated for primary (e.g., swimming) and secondary (e.g., boating) contact recreation.

The River OU is within a portion of the Sheboygan River classified as a warm water sport fish

community (WWSF). (A WWSF community includes surface waters capable of supporting a community

of warm water sport fish or serving as a spawning area for warm water sport fish.)

The Sheboygan River drains 427 square miles (mi^), with its headwaters located in Fond du Lac County.

Near Lake Michigan, the Sheboygan River is a gaining stream that receives groundwater and surface

water from the Sheboygan area and discharges into Lake Michigan. Near the Site, the river varies from

approximately 130 feet (on either the east or west side of Boat Island) to 300 feet wide (just upstream of

Boat Island). Boat Island is in the approximate center of the river resulting in an east and a west channel

adjacent to the Upland OU. A gauging station active from October 1993 through September 1995

recorded an average flow rate of 177 cubic feet per second (cfs) at the mouth of the river (approximately

one mile downstream from the Upland OU).

During 1995 and 1996 sediment investigations (described in Section 3.2.2), an assumed river water

elevation of 582 feet msl was used as a datum for sediment poling activities. This elevation was based on

the USGS topographic quadrangle which indicates the water level in Lake Michigan outside of the

Sheboygan Harbor is approximately 580 feet msl. The river bed elevation within the River OU ranges

from approximately 571.7 to 580.0 feet msl based on the poling data. Water depths within the River OU

ranged from approximately 2 feet to greater than 10 feet.

Flow of the Sheboygan River is generally easterly, toward the lake, but southerly past the Site and is

controlled by upstream dams located at Sheboygan Falls and Kohler. The USGS operated two automated

stream gauging stations: one near Interstate Highway 1-43 (cunently operational) and the other near the

1665 river ou tech Itr rev 0 final NATURAL RESOURCE

TECHNOLOGY

Page 14: River Operable Unit Technical Letter Report · RAP Remedial Action Plan ROD record of decision ... wood treatment, and paving roads. The gas was passed through purifiers to remove

River OU-Technical Letter Report - Campmarina Former MGP Revision 0 3/22/2007

Section 1 - Introduction Page 9 of 30

river mouth (no longer in operation). The stream flow data discussed below was collected from

Hydrologic Station # 040860041, located at "Sheboygan River al Mouth at Sheboygan, Wl." The station

was located over one mile downstream of the WPSC Site, with conditions similar to those of the river at

the Site.

Daily mean discharge data between October 1993 and September 1995 are summarized below:

Summary of Flow Conditions

Daily Average for 2 year Record

Daily Maximum for 2 year Record

Daily Minimum for 2 year Record

Flow (cfs)

177

1,440

32

Date

Mar. 23, 1994

Sept. 15, 1995

In addition, the monthly average stream flow for this two-year period is set forth below:

i

,- ' Month

January

Febmary

March

April

May

June

? . - J - . — • • • 1 = ^ 1 —

Mean Daily Discharge

(in cfs)

81

212

581

409

206

81

Month

July

August

September

October

November

December

Mean Daily, Discharge

(in cfs)

63

74

50

113

131

120

1665 river ou tech Itr rev 0 final NATURAL

RESOURCE

TECHNOLOGY

Page 15: River Operable Unit Technical Letter Report · RAP Remedial Action Plan ROD record of decision ... wood treatment, and paving roads. The gas was passed through purifiers to remove

River OU-Technical Letter Report - Campmarina Former MGP Revision 0 3/22/2007

Section 1 - Introduction Page 10 of 30

During 1993 to 1995, highest average daily flow rate (581 cfs) occuned in March. The lowest average

daily flow rate (50 cfs) occuned in September. The variability in water levels and stream flow in the

Sheboygan River is the result of both snowfall accumulation (and the resulting spring mn off) and

precipitation during late spring/eariy summer.

The 1991 FEMA map indicates the 100 year floodplain is at Elevation 584 msl.

1.6 Dredging History

The U. S. Army Corps of Engineers (USAGE) Detroit District is responsible for maintaining a navigation

channel and tuming basin within the river downstream of the MGP Site. The upstream limit of the

USAGE navigation channel is located approximately 500 feet downstream of the MGP Site, just below

the Pennsylvania Avenue Bridge. From the Pennsylvania Avenue Bridge and extending approximately

2,300 feet downstream to near the Eighth Street Bridge, the channel has a project depth of 15 feet. The

remainder of the navigation channel (4,200 feet) downstream to the harbor has a project channel depth of

21 feet.

The Sheboygan Harbor was constructed at the mouth of the Sheboygan River in the early 1920s. In 1954,

part of the lower Sheboygan River (the channel upstream of the Eighth Street Bridge) was added to the

Sheboygan Harbor. The channel above Eighth Street (over 3,000 feet downstream of the MGP Site) was

dredged in 1956. No further dredging occuned. Between 1956 and 1969, a total of 404,000 cubic yards

of sediment were dredged downstream of the Eighth Street Bridge.

Maintenance dredging of the Sheboygan harbor last occuned in 1991 (1995, WDNR, Sheboygan River

RAP). Dredged materials were disposed of south of the harbor as part of a beach nourishment project.

According to the USAGE Detroit District web site, no dredging is planned in the Sheboygan River in

2007.

According to a June 2005 USAGE bathymetric survey of the Sheboygan River, water depths are much

shallower than the USAGE project depths. In this June 2005 survey, observed water depths within the 21

foot project depth portion of the channel were between 5 and 15 feet, while observed water depths within

the 15 foot project depth portion of the channel were between 4 and 7 feet.

1665 river ou tech Itr rev 0 final NATURAL RESOURCE

TECHNOLOGY

Page 16: River Operable Unit Technical Letter Report · RAP Remedial Action Plan ROD record of decision ... wood treatment, and paving roads. The gas was passed through purifiers to remove

River OU-Technical Letter Report - Campmarina Former MGP Revision 0 3/22/2007

Section 1 - Introduction Page 11 of 30

NRT is unaware of any historic public or private dredging activities or bathymetric surveys upstream of

the Pennsylvania Avenue Bridge in the area of the River OU.

1665 river ou tech Itr rev 0 final NATURAL RESOURCE

TECHNOLOGY

Page 17: River Operable Unit Technical Letter Report · RAP Remedial Action Plan ROD record of decision ... wood treatment, and paving roads. The gas was passed through purifiers to remove

River OU-Technical Letter Report - Campmarina Former MGP Revision 0 3/22/2007

Seciion 2 - Sheboygan River and Harbor Superfund Site Page 12 of 30

2 SHEBOYGAN RIVER AND HARBOR SUPERFUND SITE

2.1 Location and Description

The Sheboygan River and Harbor Site includes the lower 14 miles of the Sheboygan River from the '

Sheboygan Falls Dam, downstream lo, and including the Inner Harbor. The Sheboygan River is divided

inlo three sections based on physical characteristics (e.g., average depth, width), the Upper River, Middle

River and Lower River and Harbor. The lower River and Harbor was subdivided into the Lower River,

Inner Harbor and Outer Harbor. The following table summarizes the three river sections and the Inner

and Outer Harbor.

: . ' • : • . . *

Boundaries

Length

Upper River

Sheboygan Falls Dam downstream to Waelderhaus Dam

4 miles

Middle River

Waelderhaus Dam downstream to the former Chicago & Northwestern Railroad Bridge

7 miles

Lower River

The Fonner Chicago & Northwestem Railroad Bridge downstream to the Pennsylvania Avenue Bridge

3 miles

Inner Harbor

Pennsylvania Avenue Bridge downstream to the Rivers' ouflet to the Outer Harbor

Less than 1 mile

; : Outer Harbor

Breakwall immediately south of the River's mouth to approximately 2,000 feet north of the River's mouth

2,000 feet

1665 river ou tech Itr rev 0 final NATURAL

RESOURCE

TECHNOLOGY

Page 18: River Operable Unit Technical Letter Report · RAP Remedial Action Plan ROD record of decision ... wood treatment, and paving roads. The gas was passed through purifiers to remove

River OU-Technical Letter Report - Campmarina Former MGP Revision 0 3/22/2007

Section 2 - Sheboygan River and Harbor Superfund Site Page 13 of 30

Nature of Sediment

Approx. River Width

Water Depth Range

Upper River

Discrete soft sediment deposits and non-soft sediment areas including a mixture of soft sediment. rocks, cobbles and bare river bottom

100 to 120 feet

Ranges from 0.1 to 9.5 feet (behind the dams)

Typically ranges from 2 to 4 feet

Middle River

Soft and non-soft sediment areas, soft sediment is shallower than the Upper River, and more widely scattered

100 feet

Less than 6 inches to 1 to 2 feet

Lower River

A more continuous layer of soft sediment exists (compared to Upper and Middle River). Generally where upstream soft sedimeni is deposited

150 feel to 300 feel as it approaches the

Harbor

Much of the Lower River is less than 5 feet

Inner Harbor

Similar lo the Lower River. Between Pennsylvania Avenue and S' Street Bridge there is relatively little deposition in recent years and evidence of scour. Net deposition occurs primarily between the 8* Street Bridge and the harbor mouth

250 feel

1 fool (along shore) to 20 feel, typically averaging 6 to 12 feet

Outer Harbor

Recently dredged by the USAGE in 1991 and 1992

Nol applicable

1 fool to 28 feel. typically averaging 12 lo 23 feel

The Campmarina River OU is located within the Lower River.

2.2 Remedial Investigation

An extensive remedial investigation (RI) was conducted on the Sheboygan River and Harbor. The initial

focus was on sediment and fish tissue sampling within the Sheboygan Harbor. In 1977, WDNR's routine

fish tissue sampling results reported elevated polychlorinated biphenyl (PCB) concentrations which

prompted USEPA and USAGE sediment sampling efforts. Sedimeni sample results reported elevated

concentrations of arsenic, lead, zinc, chromium, and PCBs. Beginning in 1987, Blasland, Bouck, & Lee,

1665 river ou tech Itr rev 0 final NATURAL

RESOURCE

TECHNOLOGY

Page 19: River Operable Unit Technical Letter Report · RAP Remedial Action Plan ROD record of decision ... wood treatment, and paving roads. The gas was passed through purifiers to remove

River OU-Technical Letter Report - Campmarina Former MGP Revision 0 3/22/2007

Section 2 - Sheboygan River and Harbor Superfund Site Page 14 of 30

Inc. (BBL), on behalf of Tecumseh Products Company, initiated sediment sampling within the Sheboygan

River to evaluate PCB concentrations.

Groundwater at the Tecumseh plant, floodplain surface soil, water column and water fowl were sampled.

RI sampling results showed the upstream sections of the Sheboygan River are the source of PCB

concentrations observed in downstream sediment and water column samples (May 1990, BBL).

2.3 Risk Assessments

Human health and ecological risk assessments (aquatic and tenestrial) were performed by USEPA,

WDNR, and Tecumseh. These assessments concluded the main contaminant of concem in the Sheboygan

River and Harbor is PCBs. Metals also present a risk, however these concentrations are co-located with

PCBs.

The potential pathways of exposure were considered to be dermal contact, ingestion of contaminated

surface water or sediment, and consumption of fish contaminated by sediment. Due lo PCBs, the human

health pathway presented the primary risk at the Sheboygan River and Harbor Site. This risk was based

on the consumption of contaminated fish and nol dermal contact.

2.4 Sediment Transport Study

A Sedimeni Transport Study of the Lower River and Inner Harbor was perfonned to evaluate potential

deposition in the Inner Harbor (November 1996, BBL). The study focused on natural processes burying

contaminated sediments and assessed the feasibility of natural capping/recovery in the Inner Harbor. The

model was not intended to be a comprehensive chemical fate and transport study.

The analytical data showed the maximum PCB concentrations were generally at depth. Near surface PCB

concentrations were generally low, due to the depositional effects in the Inner Harbor. Therefore, the

modeling effort was used to evaluate the natural sedimentation processes and compared that with the

potential for future high-flow events lo erode the deposited material.

1665 river ou tech Itr rev 0 final NATURAL RESOURCE

TECHNOLOGY

Page 20: River Operable Unit Technical Letter Report · RAP Remedial Action Plan ROD record of decision ... wood treatment, and paving roads. The gas was passed through purifiers to remove

River OU-Technical Letter Report - Campmarina Former MGP Revision 0 3/22/2007

Section 2 - Sheboygan River and Harbor Superfund Site Page 15 of 30

Extreme event simulations (i.e., 100-year flood) modeled with HEC-6 predicted the Inner Harbor is

expected to provide long-term stability and protectiveness. Relatively minor net scour (up to 1 foot) was

predicted in the vicinity of the Pennsylvania Avenue and against erosion. These scour events are nol

anticipated lo result in higher PCB exposures because the higher PCB concentrations are found at 4 feet

below the 1997 sediment surface level.

2.5 Feasibility Study

Three remediation objectives were listed for the Sheboygan River and Harbor (BBL, April 1998):

• Protect human health and the environment due to PCBs attributed to the Sheboygan River and Harbor Site;

• Mitigate potential PCB sources to the Shebogyan River and Harbor system and reduce PCB transport within the river system; and

• Remove and dispose of Confined Treatment Facility/Sediment Management Facility sediments and previously armored/capped PCB-contaminated soft sediment deposits.

To achieve these remediation objectives, the Feasibility Study contemplated the removal of PCB-

contaminated soft sediment so the average surface-weighted average concentration (SWAC) of PCBs in

the Sheboygan River is 0.5 parts per million (ppm).

Several remedial altematives were evaluated. Sediment altematives ranged from no action, monitored

natural recovery, sediment removal, and capping. Each altemative was compared to the nine criteria

described in 40 CFR Part 300.430.

2.6 Record of Decision

The Record of Decision (ROD) for the Sheboygan River and Harbor was issued by USEPA in May 2000.

Selected remedies include sediment removal in the Upper River, additional characterization and

monitoring in the Middle River, and additional characterization and potential removal subject to natural

and recreational disturbances in the Lower River and Inner Harbor.

1665 river ou tech Itr rev 0 final NATURAL RESOURCE

TECHNOLOGY

Page 21: River Operable Unit Technical Letter Report · RAP Remedial Action Plan ROD record of decision ... wood treatment, and paving roads. The gas was passed through purifiers to remove

River OU-Technical Letter Report - Campmarina Former MGP Revision 0 3/22/2007

Section 2 - Sheboygan River and Harbor Superfund Site Page 16 of 30

Long-term monitoring of the remedial actions includes fish and sediment sampling to ensure achievement

of the SWAC tliroughout all of the Sheboygan River. In addition, the Lower River and Inner Harbor will

have annual bathymelric surveys lo identify areas susceptible lo scour. The USAGE'S most recent

bathymetric survey was performed in June 2005 (Condition of Channel for the Sheboygan Harbor in June

2005).

Applicable or Relevant and Appropriate Requirements (ARARs) and requirements To Be Considered

(TBCs) are provided beginning on page 88 of the ROD.

2.7 Schedule

According to the Fact Sheet, updated February 2007, for the Sheboygan River and Harbor Site (EPA

Identification number WrD980996367), Phase 11 Upper River soft sediment dredging operations were

performed in June 2006 through November 2006. Additional dredging in Phase II is to be performed in

May 2007 and is anticipated to go through October 2007. A total of 21,000 cubic yards (CY) of PCB

contaminated sediment is planned for removal in the Upper River.

Additional sample collection and characterization of soft sediment deposits for the Middle River, Lower

River, and Inner Harbor also will be performed in the summer of 2007. A schedule for addressing

sediment in the Inner Harbor was not mentioned in the Fact Sheet. Depending on the findings of

additional characterization in the Middle River and Lower River, the soft sediment deposits within the

Lower River may also require removal. The River OU of the former Campmarina MGP Site is located at

the downstream end of the Lower River.

1665 river ou tech Itr rev 0 final NATURAL RESOURCE

TECHNOLOGY

Page 22: River Operable Unit Technical Letter Report · RAP Remedial Action Plan ROD record of decision ... wood treatment, and paving roads. The gas was passed through purifiers to remove

River OU-Technical Letter Report - Campmarina Former MGP Revision 0 3/22/2007

Section 3 - Previously Performed River OU Investigations and Results Page 17 of 30

3 PREVIOUSLY PERFORMED RIVER OU INVESTIGATIONS AND RESULTS

The following sections summarize known sediment investigations performed near or within the River

OU. Specific discussions regarding contaminant exposure pathways are included in Section 4.

3.1 BBL-1990

Beginning in 1987, BBL conducted sediment sampling for PCBs, VOCs, PAHs, and metals as part of the

Sheboygan River and Harbor Remedial Investigation. Sampling methodologies and results are detailed in

the Remedial Investigation/Enhanced Screening Report - Sheboygan River and Harbor (May 1990,

BBL). Fifteen (15) sediment samples were collected along the length of the river, with 10 samples being

collected above the Pennsylvania Avenue Bridge and 5 samples downstream of the bridge.

A number of sediment samples were collected near or just downstream of the MGP Site (sample locations

are provided in Appendix C). Three samples, R-98, R-lOO, and H-20, had oil or concentrations of PAHs.

Sample R-98 was collected near the downstream end of Boat Island and the sediment was described as

"oil saturated" from 2 to 6 feet below the sediment surface. Sediment samples R-lOO and H-20 were

collected immediately downstream of the Pennsylvania Avenue bridge. Sample R-lOO was described as

"oil saturated" from 4 to 6 feet below the sediment surface; however, neither sample R-98 nor R-lOO were

analyzed for PAHs. Sample H-20 was described as "oil saturated" from 4 to 16 feet below the sediment

surface and had a total PAHs concentration of 70 ppm in the 2 to 4 foot sediment sample. There was no

mention of elevated PAHs downstream of sample location H-20 and no mention of oil saturated

sediments was noted for samples R-99 andR-101, collected on the west side of Boat Island, opposite the

fonner MGP (May 1990, BBL).

3.2 WDOT-1993

In 1993, river sediment sampling was perfonned for the Wisconsin Department of Transportation

(WDOT) construction project on the Eighth Street Bridge. The bridge is located approximately 3,000 feet

1665 river ou tech In- rev 0 final NATURAL R E S O U R C E

T E C H N O L O G Y

Page 23: River Operable Unit Technical Letter Report · RAP Remedial Action Plan ROD record of decision ... wood treatment, and paving roads. The gas was passed through purifiers to remove

River OU-Technical Lener Report - Campmarina Former MGP

Revision 0 3/22/2007

Section 3 - Previously Perfonned River OU Investigations and Results Page 18 of 30

downstream of the MGP Site (1993, RMT). PAHs were found in the sediments around the Eighth Street

Bridge in concentrations ranging from 5 to 97 ppm in the top 0 to 2 feet of sediment.

3.3 WDNR-1995

In Febmary 1995, WDNR collected one sediment sample within the River OU, approximately 20 to 30

feet from the shoreline, close to the downstream end of Boat Island (October 1995, WDNR). This sample

contained apparent coal tar and was analyzed for PAHs.

3.4 NRT-1998

NRT performed preliminary sediment investigations for WPSC in 1995 and 1996. Results are detailed in

the Sediment Investigation Report dated Febmary 26, 1998. Sediment sampling focused on identifying

the preliminary nature and extent of MGP residuals in river sediments or natural soil (parent material)

underlying the Sheboygan River. Sediment/soil samples were collected from as deep as 10.5 feet below

the bottom of the river, although in some locations parent materials were encountered beneath the soft

sediments, and this material was also sampled.

Further details regarding the methods for locating, poling, and sediment sampling are included in the

Sediment Investigation Report. The analytical results from NRT sampling efforts are tabulated in

Appendix B of this Technical Letter Report on Table 1 (Field Observations at Sediment Sample

Locations), Table 2 (Sediment Analytical Results - PAHs), Table 3 (Sediment Analytical Results -

BTEX), and Table 4 (Sediment Analytical Results - Cyanide, Phenol, Oil & Grease, Resource

Conservation and Recovery Act (RCRA) Metals & PCBs). Appendix A, Sheet 3 provides a summary of

the distribution of these constituents and the visual observations made during preliminary investigation

activities. Appendix B, Plate 2 provides cross sectional details of river sediment investigations and

Appendix B, Plate 3 provides a contour map of the depth to tar found in river sediments. The following

sections summarize the results of the NRT 1995 and 1996 activities.

1665 river ou tech Itr rev 0 final NATURAL RESOURCE

TECHNOLOGY

Page 24: River Operable Unit Technical Letter Report · RAP Remedial Action Plan ROD record of decision ... wood treatment, and paving roads. The gas was passed through purifiers to remove

River OU-Technical Letter Report - Campmarina Former MGP

Revision 0 3/22/2007

Section 3 - Previously Performed River OU Investigations and Results Page 19 of 30

3.4.1 October 1995 Investigation Activities

During October 1995, NRT performed an initial sediment investigation to determine the absence/presence

of MGP residuals in the surficial soft sediments (unconsolidated non-parent material). The study

indicated the presence of benzene, toluene, ethylbenzene, and xylenes (BTEX) and PAHs in sediments

within the River OU, adjacent to, and downstream of, the Upland OU (November 1998, NRT).

The sample collection and screening methods are described in the Sediment Sampling Work Plan, Former

Sheboygan II Manufactured Gas Plant Site, Sheboygan, Wisconsin (August 1995, NRT). NRT conducted

the initial sediment sampling with a manually driven Ogeechee'' ' corer and a Ponar''"' grab dredge

sampler. The longest sediment core collected using the Ogeechee''''*^ corer was approximately 30 inches

long, while the Ponar^"^ grab dredge sampler typically collected the top six inches of sediment.

Six transects, consisting of 22 sample locations, were completed. These transects were identified as T701

through T706 and the sampling locations were labeled SD-701A through SD-706C (Appendix A, Sheet 3).

The following is a summary of field observations from the initial investigation:

• All six sediment sample transects showed indications of either odor or tar. Sediment samples SD-702A & B and SD-703A (Appendix A, Sheet 3) exhibited odors in sediments recovered in the hand-core samples. The samples were located within 25 feet of the shoreline.

• Sediment samples SD-701 A, SD-703B, SD-704A & B, SD-705A, B, & C, and SD-706B (Appendix A, Sheet 3) all exhibited coal tar in sediments recovered in the hand-core samples, or on the sounding pole (used to evaluate the depth of sediments present at a given location). These samples were within 20 feet of the shore at SD-701 and within 60 feet of the shore at SD-704 and SD-706. In transects T703 and T705, tar was noted 70 feet and 100 feet, respectively, out from shore.

3.4.2 November 1995/June 1996 Investigation Activities

Following the October 1995 study, NRT conducted a detailed field investigation in November 1995 and

June 1996 to evaluate the distribution of MGP constituents and sediment characteristics. A summary of

the field investigations, results, and recommendations is provided in the Sediment Investigation Report

(November 1998, NRT). A vibrocore sediment collection technique was used to collect the sediment

samples.

1665 river ou tech Itr rev 0 final NATURAL RESOURCE

TECHNOLOGY

Page 25: River Operable Unit Technical Letter Report · RAP Remedial Action Plan ROD record of decision ... wood treatment, and paving roads. The gas was passed through purifiers to remove

River OU-Technical Letter Report - Campmarina Former MGP

Revision 0 3/22/2007

Section 3 - Previously Performed River OU Investigations and Results Page 20 of 30

Twelve transects were selected at locations starting approximately 375 feet upstream to approximately

900 feet downstream of the former MGP (Appendix A, Sheet 3 and Appendix B, Plate 2). The October

1995 transects were overlapped and extended. The new transects were identified as T701 through T712

and the sampling locations were labeled SD-701BV through SD-712BV. The transects did not extend

west past Boat Island to the river channel opposite the former MGP.

The following is a summary of findings from the November 1995 and June 1996 field investigations:

• Numerous sediment cores exhibited tar, sheen, or odors within 125 feet of the shoreline, as shown on Sheet 3 in Appendix A. Visual observations of tar, sheen, or odors extended approximately 1,300 to 1,600 feet along the shore beginning approximately 90 feet upstream of the former WPSC property boundary, along the former MGP (approximately 580 feet), and extending approximately 900 feet downstream of the former WPSC property boundary.

• Based on the depth at which tar and animal hair (the suspected source of animal hair is the former upstream tannery) were observed within the sediment, tar and animal hair were covered by natural sedimentation processes. Little river scour was observed through certain sections of this segment of the river. The depth to tar from field observations (Appendix B, Table 1) is shown on Appendix B, Plate 3. These field observations showed a thin layer where the tar is located within 1 foot of the sediment surface. Further downstream, past Center Avenue extended (i.e., approximately the southem property line of the former Campmarina MGP), tar was found more than 2 feet below the sediment surface.

• The sediment core logs showed approximately 2 lo 10 feet of soft river bottom sediments, including silt, sand, and organic material. No aquatic plants were found at any of the sample locations. The soft upper sediment layer is underlain by native glacial sediments, characterized by sands and red brown clay till.

3.5 Chemical Constituents in Sediment

The sediment sampling locations and PCB analysis conducted by BBL for the Sheboygan River and

Harbor RI, related to the Campmarina River OU, was summarized on a figure included in Appendix C.

A summary of the NRT analytical results from the 1995 and 1996 sediment sampling events are provided

in Appendix B, Table 2 (PAHs), Table 3 (BTEX), and Table 4 (metals, cyanide, PCBs, phenol, oil and

grease, and TOC). A distribution of BTEX and total PAH concentrations at each sample location is

1665 river ou tech Itr rev 0 final NATURAL RESOURCE

TECHNOLOGY

Page 26: River Operable Unit Technical Letter Report · RAP Remedial Action Plan ROD record of decision ... wood treatment, and paving roads. The gas was passed through purifiers to remove

River OU-Technical Letter Report - Campmarina Former MGP

Revision 0 3/22/2007

Section 3 - Previously Performed River OU Investigations and Results Page 21 of 30

provided in Appendix A, Sheet 3. Laboratory results from the 1995 and 1996 Site investigations show

low concentrations of PCBs, RCRA metals, cyanide, and phenol.

3.5.1 BTEX and PAH Results

Total BTEX ranged from ND to 710 ppm, while total PAHs ranged from ND to 9,294 ppm, in sedimeni

samples collected and analyzed by NRT. Generally, high concentrations of BTEX co-occuned with high

PAH concentrations.

Based on the BTEX and total PAH analytical laboratory results, the highest concentrations were found at

depth; as indicated by NRT cores SD-702BV, SD-702CV, SD-704BV, and SD-705BV (Appendix

A, Sheet 3 and Appendix B, Tables 2 and 3). These sediment cores are all located adjacent to, and just

downstream of, the former MGP Site. The depths at which these samples were collected ranged from

approximately 2 lo 10 feet below the sediment surface. The deepest occunences of tar were present in

transects T704 and T705.

As discussed in Section 3.1, BBL also collected a sediment sample for PAH analysis at location H-20

(Appendix C) (just downstream of the Pennsylvania Avenue Bridge). The sample collected 2 to 4 foot

below the sediment surface had a total PAH concentration of 70 mg/kg (May 1990, BBL).

Visual observations of (Appendix A, Sheet 3) lar, sheen, and odors were found to extend approximately

900 feet downstream of the former MGP; however, the analytical results from sediment sample

SD-71 lAV showed constituents of concem may have migrated only approximately 580 feet downstream.

BTEX and total PAH concentrations in samples downstream of transect T705 (approximately 450 feet

upstream of transect T7] 1) are significantly lower than the concentrations reported in samples from

transects T702, T704, and T705, which were immediately adjacent to the fonner MGP. Additionally, the

results showed that sediments with MGP residuals, especially downstream of transect T705, were buried

below other non-native sedimeni (Appendix B, Plate 2 and 3). Sedimeni samples collected upstream of

the former MGP (from SD-708AV & BV and SD-709AV), and approximately 900 feet downstream

(SD-712AV and BV) of the former MGP, did not exhibit elevated BTEX or total PAH concentrations.

1665 river ou tech Itr rev 0 final NATURAL RESOURCE

TECHNOLOGY

Page 27: River Operable Unit Technical Letter Report · RAP Remedial Action Plan ROD record of decision ... wood treatment, and paving roads. The gas was passed through purifiers to remove

River OU-Technical Letter Report - Campmarina Former MGP

Revision 0 3/22/2007

Section 3 - Previously Performed River OU Investigations and Results Page 22 of 30

3.5.2 Metals Results

NRT submitted three samples from its preliminary sedimeni investigations for laboratory analysis of

RCRA metals (Appendix B, Table 4) from locations where animal hair (suspected tannery waste) was

present. Sample results showed generally low levels of metal constituents (Appendix B, Table 4).

Chromium and lead contamination are common constituents associated with tannery wastes.

Concentrations of chromium and lead were detected ranging from 7.4 to 500 ppm and 28 to 140 ppm,

respectively. No other sedimeni samples were characterized for metals.

Table 1 of the ROD issued in May 2000 by USEPA for the Sheboygan River and Harbor Superfund

Project indicates that metals contamination ranges from non-detect to 300 ppm in the Upper, Middle, and

Lower river sections. Maximum concentrations of chromium and lead detected were 143 ppm and 293

ppm, respectively.

3.5.3 PCB Results

NRT submitted three samples for laboratory analysis of PCBs (Appendix B, Table 4). The PCB

concentrations detected in the sediment samples from the Site ranged from 0.42 ppm lo 2.3 ppm.

PCB concentrations found upstream of the former MGP, as part of the Sheboygan River and Harbor

Superfund Project (October 1995, WDNR), ranged between non-detect up lo 4,500 ppm. PCB

concentrations detected adjacent to the former MGP Site as part of the BBL 1987 investigation (samples

R95, R99, RlOl, and R98) ranged between non-detect up to 2.3 ppm (May 1990, BBL). PCB

concentrations detected downstream of the MGP Site as part of the BBL 1987 investigation (sample

RlOO) ranged between non-detect up to 67 ppm (May 1990, BBL) (Appendix C).

3.5.4 Cyanide and Phenol Results

Thirteen sediment samples were analyzed for total cyanide, weak acid dissociable cyanide, and phenol in

October and November 1995 (Appendix B, Table 4). There was no blue/black sheen and/or blue/black

wood chips were observed in the sediments. The total cyanide were detected in 5 of 13 sediment samples

at concentrations ranging from 0.59 to 8.7 ppm. Weak acid dissociable cyanide was detected in 3 of 13

1665 river ou tech Itr rev 0 final NATURAL R E S O U R C E

T E C H N O L O G Y

Page 28: River Operable Unit Technical Letter Report · RAP Remedial Action Plan ROD record of decision ... wood treatment, and paving roads. The gas was passed through purifiers to remove

River OU-Technical Letter Report - Campmarina Former MGP

Revision 0 3/22/2007

Section 3 - Previously Performed River OU Investigations and Results Page 23 of 30

sediment samples at concentrations ranging from 0.51 to 3 ppm. Phenol was present in only 4 of 13

sediment samples at concentrations ranging from 0.19 to 48 ppm.

Cyanide and phenols were not tested for as part of the Sheboygan River and Harbor Superfund site

investigations, as such no data is available for these contaminants.

3.6 Chemical Constituents in Surface Water

Surface water chemistry data for conventional pollutants (i.e., nutrients, solids, bacteria, etc.) are collected

on a nearly monthly basis in the Sheboygan River at the Esslingen Park sampling location by the WDNR.

Esslingen Park is located approximately 1.5 miles upstream of the Former MGP Site. PAHs, BTEX,

RCRA metals, PCBs, cyanide, and phenols are not routinely measured in the Sheboygan River.

Table 3 of the USEPA ROD for the Sheboygan River and Harbor Superiiind site (May 2000, USEPA)

showed PCB concentrations in surface water ranged from non-delecl (<0.05 parts per billion [ppb]) to

0.77 ppb during an interim PCB removal action conducted several miles upstream in 1989 and 1990.

1665 river ou tech Itr rev 0 final NATURAL RESOURCE

TECHNOLOGY

Page 29: River Operable Unit Technical Letter Report · RAP Remedial Action Plan ROD record of decision ... wood treatment, and paving roads. The gas was passed through purifiers to remove

River OU-Technical Letter Report - Campmarina Former MGP Revision 0 3/22/2007

Section 4 - Remedial Actions Performed Page 24 of 30

4 REMEDIAL ACTIONS PERFORMED

No remedial actions have been performed lo dale in the River OU.

During the 2001 Upland OU soil remediation activities (February 2003, NRT), approximately 670 feet of

river bank was excavated and reconstructed lo provide stmctural support for the geosynthetic cover and

future park stmctures. Excavation operations generally were limited to material above the groundwater

table and/or shoreline. The following activities were conducted to reconstruct the river bank:

• Existing riprap that with a visually clean surface was removed and segregated for reuse;

• An old 30-fool long, ten-inch diameter pipe, mnning parallel lo the river, that connected to a wooden crock, were both removed and properly disposed in a landfill. The pipe and crock exhibited MGP odors;

• The former retaining wall along the river was cut and removed at the approximate river elevation;

• Excavation operations extended lo the planned design 580 feet msl elevation with the exception of one area located midway along the river bank. MGP-related contamination and evidence of coal tar-like materials were observed in soils at approximately 8 to 10 feel bgs in the central portion of EZ-4 excavation. In order to address the area, an 88 feel by 10 feel area was excavated to elevation 578 feet msl. Excavation operations did not extend lower than the 578 feel msl elevation due to the close proximity of the river. The location of the deeper excavation zone is indicated on Sheet C040 in Appendix D;

• Excavation base samples (EZ-401 through EZ-405) were sampled al the 580 feet msl elevation with the exception of EZ-403, which was sampled at approximately the 578 feet msl elevation. The sampling documented the near shore sediment conditions outside the perimeter of the vertical banier wall; and

• The riverbank was restored with filter gravel, stmctural fill, and riprap. Approximately 2 feet of structural fill was placed in the over-excavaied area from elevation 578 feet msl to 580 feet msl. A non-woven geofabric and six inches of filter gravel were placed over the fill along the base of the riverbank (elevation 580 feet). A second layer of filter fabric was placed over the filter gravel followed by stmctural fill that was compacted to restore the river bank at a slope of approximately two feet horizontal to one fool vertical (2H: 1V). Riprap was then placed along the restored river bank as shown on Sheet C040 in Appendix D.

1665 river ou tech Itr rev 0 final NATURAL RESOURCE

TECHNOLOGY

Page 30: River Operable Unit Technical Letter Report · RAP Remedial Action Plan ROD record of decision ... wood treatment, and paving roads. The gas was passed through purifiers to remove

River OU-Technical Letter Report - Campmarina Former MGP

Revision 0 3/22/2007

Section 4 - Remedial Actions Performed Page 25 of 30

At EZ-4, the soil/sedimenl quality was analyzed for total BTEX/benzene, total PAHs/naphthaiene and

total cyanide/lead. The results are summarized in Appendix D, Table 2 and Figure 5 and indicate residual

concentrations of benzene, naphthalene, total lead, and total cyanide. These residual concentrations are

effectively capped with up to 6 feel of clean compacted stmctural fill. As stated in the Documentation

Report (Febmary 2003, NRT), the remaining material will be considered as part of future sediment

management work.

1665 river ou tech Itr rev 0 final NATURAL R E S O U R C E

T E C H N O L O G Y

Page 31: River Operable Unit Technical Letter Report · RAP Remedial Action Plan ROD record of decision ... wood treatment, and paving roads. The gas was passed through purifiers to remove

River OU-Technical Letter Report - Campmarina Former MGP Revision 0 3/22/2007

Section 5 - Identified River OU Pathways and Conclusions . Page 26 of 30

5 IDENTIFIED RIVER OU PATHWAYS AND CONCLUSIONS

As discussed in Seciion 1.1, remedial actions have been performed in the Upland OU and assessment of

the appropriate Upland OU exposure pathways are discussed in the Upland OU Technical Letter Report.

5.1 River OU Potential Exposure Scenarios and Receptors

A qualified risk assessor will perform a Site reconnaissance to assist in developing the Work Plan (WP)

for the River OU RI. As part of the Site reconnaissance, a biological habitat assessment will be

performed and the sunounding land use and access to the River OU will be noted. The results of the Site

reconnaissance will be used to refine the Campmarina River OU CSM.

Potential exposure scenarios and receptors to be evaluated in the River OU WP include:

5.1.1 Recreational Land Use Scenario - Visitor/Trespasser

A visitor may be potentially exposed to constituents of potential concem (COPCs) in surface water and

sediment while swimming, wading, fishing, or boating in the Sheboygan River, adjacent to the former

MGP facility. The potential exposure scenarios to be evaluated include incidental ingestion and dermal

contact with surface water and/or sediment from the Sheboygan River.

5.1.2 Benthic Invertebrates - Aquatic Ecological Receptor

Benthic invertebrates form the base of many food chains and spend most or all of their life-cycle

burtowed or feeding just at the interface between surface water and sediment. Benthic invertebrates may

be potentially exposed to COPCs in surface waler and sediment in the Sheboygan River, adjacent to the

former MGP facility. The potential exposure scenarios to be evaluated include ingestion and dermal

exposure with surface water and/or sedimeni from the Sheboygan River.

1665 river ou tech Itr rev 0 final NATURAL RESOURCE

TECHNOLOGY

Page 32: River Operable Unit Technical Letter Report · RAP Remedial Action Plan ROD record of decision ... wood treatment, and paving roads. The gas was passed through purifiers to remove

River OU-Technical Letter Report - Campmarina Former MGP

Revision 0 3/22/2007

Section 5 - Identified River OU Pathways and Conclusions Page 27 of 30

5.1.3 Other Ecological Receptors

Other species may be exposed to COPCs in sediment and/or surface water from the Sheboygan River.

The need to carry forward additional ecological receptors from higher trophic levels (e.g., fish) will be

evaluated based on the biological habitat assessment and the results from previously collected chemical

concentrations in surface water and/or sediment. If the biological habitat assessment indicates there is

limited habitat area within the Sheboygan River adjacent to the former MGP facility, additional

ecological receptors will not be canied forward.

5.2 Additional Data Needs Summary

Additional River OU RI activities will focus on the following objectives:

Evaluate the nature and extent of MGP residuals in near-shore sediment; i • ^ F ' "

Assess potential human health and ecological risk related to MGP residuals in sediment;

Evaluate the nature and extent of non-MGP related constituents;

Perform river water sampling lo evaluate if conditions exist that may pose a risk to human health and the environment;

Evaluate whether Boat Island wananls characterization;

Collect additional Site data to support a feasibility study; and

If a remedial action is necessary, establish acceptable remediation goals.

As described in Section FV, Task 1(B) and (C), the above work elements will be discussed in a Technical

Scoping Meeting to be held within seven to fourteen business days after submitting this River OU

Technical Letter Report. The River OU Work Plan will be submitted within 90 days of receipt of the

Technical Scoping Meeting summary. A River OU project specific schedule for RI/FS tasks will also be

included in the RI/FS Work Plan.

1665 river ou tech Itr rev 0 final NATURAL RESOURCE

TECHNOLOGY

Page 33: River Operable Unit Technical Letter Report · RAP Remedial Action Plan ROD record of decision ... wood treatment, and paving roads. The gas was passed through purifiers to remove

River OU-Technical Letter Report - Campmarina Former MGP Revision 0 3/22/2007

Section 6 - References Page 28 of 30

6 REFERENCES (RECORD FILE)

1990 May, Blasland, Bouck and Lee, Inc. Remedial Investigation/Enhanced Screening Report, Sheboygan River and Harbor, Sheboygan Wisconsin.

1991 April, Washington State Department of Ecology, Sediment Management Standards, Chapter 173-204 WAC.

1991 December, Wisconsin Department of Natural Resources, Conditional Approval of "Work Plan, Phase 1 Site Investigation, Manufactured Gas Plant Site, Sheboygan, Wisconsin".

] 992 February, Wisconsin Department of Natural Resources, Final Statement of Work for the Sheboygan Gas Plant Investigation.

1992 April, Wisconsin Department of Natural Resources, Campmarina, The Former Coal Gas Facility Operated by Wisconsin Public Service Corporation and Owned By the City of Sheboygan located in Sheboygan, Wl", Section 144.442, Wis. Stats. CONTRACT, Contract Number SF-91-04.

1992 June, Simon Hydro-Search, Phase I Environmental Investigation of Manufactured Gas Plant Site, Sheboygan, Wisconsin, Project No. 453114843.

1992 July, Blasland, Bouck and Lee, Inc. Alternatives Anay Document, Tecumseh Products Company, Sheboygan Falls, Wisconsin.

1992 November, Simon Hydro-Search, Phase 11 Work Plan - Environmental Investigation Manufactured Gas Plant Site, Sheboygan , Wisconsin, Project No. 304533034.

1993 RMT, Inc., Subsurface Investigation Summary Report and Work Plan, Wisconsin Department of Transportation ID No. 4996-00-40, 8* Street Bridge, Sheboygan, Wisconsin.

1994 June, Natural Resource Technology, Inc., Sediment Sampling Work Plan - Former Manufactured Gas Plant Site, Sheboygan II, Wisconsin, Project No. 1060.

1995 April, WPSC, Letter to Ms. Margaret Graefe (Wisconsin Departmenl of Natural Resources) Phase II Environmental Investigations Sheboygan I and II Former Manufactured Gas Plant Sites, Project No. 1033.

1995 August 31, Natural Resource Technology, Inc., Sediment Sampling Work Plan Former Manufactured Gas Plant Site, Sheboygan, Wisconsin, Project No. 1060.

1995 October, Wisconsin Departmenl of Natural Resources, Sheboygan River Remedial Action Plan, A Plan lo Clean Up Sheboygan Area Rivers and Harbor.

1665 river ou tech Itr rev 0 final NATURAL RESOURCE

TECHNOLOGY

Page 34: River Operable Unit Technical Letter Report · RAP Remedial Action Plan ROD record of decision ... wood treatment, and paving roads. The gas was passed through purifiers to remove

River OU-Technical Letter Report - Campmarina Former MGP

Revision 0 3/22/2007

Section 6 - References Page 29 of 30

1996 June 28, Natural Resource Technology, Inc., Phase II Environmental Investigation Report, Former Manufactured Gas Plant Site, North Water Street, Sheboygan, Wisconsin, Project No. 1060.

1996 November, Blasland, Bouck and Lee, Inc. Sediment Transport Study, Sheboygan River and Harbor, Sheboygan Wisconsin.

1997 July, United States Army Corps of Engineers, Condition of Channel for Inner and Outer Harbor.

1998 April, Blasland, Bouck and Lee, Inc. Feasibility Study Report, Sheboygan River and Harbor, Sheboygan Wisconsin.

1998 November, Natural Resource Technology, Inc., Sediment Investigation Report Former Manufactured Gas Plant Site, Sheboygan, Wl, Project No. 1183.

1998 December, Natural Resource Technology, Inc., Feasibility Study Work Plan Campmarina, Former Coal Gas Facility, Wisconsin Public Service Corporation, Sheboygan, WI, Project No. 1313.

1999 MacDonald, D.D. and M. MacFarlane. (Draft). Criteria for managing contaminated sediment in British Columbia, British Columbia Ministry of Environment, Lands, and Parks. Victoria, British Columbia. .

1999 May, Natural Resource Technology, Inc., Feasibility Study Campmarina, Former Coal Gas Facility, Wisconsin Public Service Corporation, Sheboygan, Wl, Project No. 1313.

1999 October, Wisconsin Department of Natural Resources, Campmarina - Former Coal Gas Facility, Sheboygan, Wisconsin, Feasibility Study for the Campmarina-Former Coal Gas Faciliry approval letter.

2000 February, Natural Resource Technology, Inc., Remedial Work Plan Phase I, Excavation and Grading Campmarina and Center Avenue Right-of-Way, Former Coal Gas Facility, Sheboygan, VV/Project No. 1313.

2000 March, Natural Resource Technology, Inc., Pilot Test Work Plan, Campmarina and the Center Avenue Right-of-Way, Sheboygan, WI, Project No. 1313.

2000 April, Natural Resource Technology, Inc., Phase II Remedial Work Plan, Campmarina and Center Avenue Right-of-Way, Former Coal Gas Facility, Sheboygan, Wisconsin, Project No. 1313.

2000 May, United States Environmental Protection Agency Superfund, Record of Decision, Sheboygan River and Harbor, Sheboygan, Wisconsin.

2000 June, United Stales Army Corps of Engineers, Sheboygan Harbor, Wisconsin, Condition of Channel.

1665 river ou tech Itr rev 0 final NATURAL R E S O U R C E

T E C H N O L O G Y

Page 35: River Operable Unit Technical Letter Report · RAP Remedial Action Plan ROD record of decision ... wood treatment, and paving roads. The gas was passed through purifiers to remove

River OU-Technical Letter Report - Campmarina Former MGP

Revision 0 3/22/2007

Section 6 - References Page 30 of 30

20(X) July, Wisconsin Public Service Corporation Letter to Susan Schumacher (Wisconsin Departmenl of Natural Resources) Affidavit for the "Notice of Proposed Grading" for Camp Marina Site in Sheboygan, Wl, Project No 1313.

2000 July, MacDonald, D.D., C.G. Ingersoll, and T.A. Berger. Development and evaluation of consensus-based sediment quality guidelines for freshwater ecosystems. Arch. Environ. Contam. Toxicol. 39:20-31.

2000 July, Wisconsin Departmenl of Natural Resources, Phase I and Phase 2 Remedial Work Plan Approval, Campmarina and Center Avenue Right of Way, Sheboygan, file reference FID #460134950 ERR-ERP, BRRTS #0260000095.

2001 January, Wisconsin Department of Natural Resources, Record of Decision, Campmarina, the Former Sheboygan Coal Gas Site, Remedial Action Operable Unit for Upland Area.

2003 Febmary, Natural Resource Technology, Inc., Phase 1 and II Remedy Documentation Report, Campmarina Former Coal Gas Facility, Sheboygan, Wisconsin, Project Number 1312.

2003 December, Natural Resource Technology, Inc., 2003 Annual Operation Maintenance, ami Monitoring Report Former Wisconsin Public Service Corporation Manufactured Gas Plant Site, Campmarina And Center Avenue Right-of-Way, Sheboygan, Wisconsin, FID #400134950, DNR Activity #02-60-000095.

2004 July, Natural Resource Technology, Inc., Remedial Investigation/Feasibility Study Work Plan, Campmarina Former MGP Site, Sheboygan, Wisconsin, Project Number 1665.

2004 August, Wisconsin Department of Natural Resources, Preliminary Comments of Remedial Investigation/Feasibility Study Work Plan, Campmarina Fonner MGP Site, Sheboygan, Wisconsin, FID #400134950, DNR Activity #02-60-000095.

2004 December, Natural Resource Technology, Inc., 2004 Annual Operation Mainteruince, and Monitoring Report Former Wisconsin Public Service Corporation Manufactured Gas Plant Site, Campmarina And Center Avenue Right-of-Way, Sheboygan, Wisconsin, FID #4(X)] 34950, DNR Activity #02-60-000095.

2005 November, Natural Resource Technology, Inc., 2005 Annual Operation, Maintenance, and Monitoring Report Former Wisconsin Public Service Corporation Manufactured Gas Plant Site Campmarina and Center Avenue Right-of-Way, Sheboygan, Wisconsin.

2007 January, United States Environmental Protection Agency, Administrative Settlement Agreement and Order on Consent for the Remedial Investigation and Feasibility Study for the WPSC Campmarina Site in Sheboygan, Wisconsin, Docket V-W-07-C-862.

1665 river ou tech Itr rev 0 final NATURAL RESOURCE

TECHNOLOGY

Page 36: River Operable Unit Technical Letter Report · RAP Remedial Action Plan ROD record of decision ... wood treatment, and paving roads. The gas was passed through purifiers to remove

0

Page 37: River Operable Unit Technical Letter Report · RAP Remedial Action Plan ROD record of decision ... wood treatment, and paving roads. The gas was passed through purifiers to remove

I N

SOURCE: USGS 7 .5 MINUTE QUADRANGLE, SHEBOYGAN NORTH AND SOUTH. DATED 1 9 5 4 . PHOTOREVISED 1 9 7 3 . OUADRANCLE LOCATION

0 2000 4000

SCALE IN FEET CONTOUR INTERVAL 10 FEET

N R

Natural Resource Technology

SITE LOCATION MAP CAMPMARINA FORMER COAL GAS FACILITY WISCONSIN PUBLIC SERVICE CORPORATION

SHEBOYGAN, WISCONSIN

DRAWN BY: TAS APPROVED BY: JMK DATE: 04 /23 /04

PROJECT NO. 1665

DRAWING NO. 1665-A01

FIGURE NO. 1

Page 38: River Operable Unit Technical Letter Report · RAP Remedial Action Plan ROD record of decision ... wood treatment, and paving roads. The gas was passed through purifiers to remove

NEW YORK A

CD -* — 2

z -• W I

- I VI £ lyi _. I/) n

^ X 3 to 2 r

•" L.J "" lO *"

O ? X O ^ u

> -J c

o m ^ m i£

OJ 31 -S -

»_ H- U

? =h M _ £ (/I CO 3

7 ]

^ ^

m

> o ^ H n > 33 Z

S

n 5

1 1

• " 3

=°S o 2 T I E m m

^1

1 1

1 1

X

w o :a

> !3 TO C

o - t

33

m

« 2: § t / i -< ^ O

X

> 5

o

CO O

in I X(/, O ^ H : o o

g o z >

> o

V

|— m CD m

o

o

NATURAL RESOURCE TECHNOLOGY

HISTORICAL SITE LAYOUT TECHNICAL LETTER REPORT-RIVER OU

CAMPMARINA FORMER MGP SITE WISCONSIN PUBLIC SERVICE CORPORATION

SHEBOYGAN, WISCONSIN

DRAWN BY: BJK

CHECKED BY: HMS

APPROVED BY: JMK

DATE: 03/12/07

DATE: 03/20/07 DATE; 03/22 /07

DRAWING NO: 1665-3-BOl REFERENCE:.

Page 39: River Operable Unit Technical Letter Report · RAP Remedial Action Plan ROD record of decision ... wood treatment, and paving roads. The gas was passed through purifiers to remove

APPENDIX A

MEDIAL INVESTIGATION/FEASIBILITY STUDY WORK PLAN, NMT JULY 2(1

H

Page 40: River Operable Unit Technical Letter Report · RAP Remedial Action Plan ROD record of decision ... wood treatment, and paving roads. The gas was passed through purifiers to remove

!

/ •

LEGEND « "w-'«

» PZ-70,

y ^ "

« o o o

O

MONITORING WELL

PIEZOMETER

STAFT GAUGE

TDEES

RIPRAP

UGHT POLE

FORMER CAMPUARINA PROPERTY BOUNDARY

BARRIER

RWERS EDGE

SOURCE NOTES: 1. PORTIONS OF THIS DRAWING SH WERE DEVaOPEO FROU DRAWING HLE

CAMPPLAN.DWG DATU) 1 /4 /00 OBTAINED FROU THE CITY OF SHEBOYGAN. 2. SURVEY OF CONTAINMENT B«?RRIER BT RETTirR CORPORATION. UARCH 2001,

DtGfTAL RLE TOPO022B01.DWG. 3. PORTIONS OF THIS DRAWING SET WERE DEVELOPED FTTOU DRAWING RLE

NRT-AERIALDWG E-WWLED 1/13/04 FROM THE CfTY OF SHEBOYGAN. 4. MONITORING WELLS SURVEYED BY ROBERT E. LEE & ASSOCUVTES SUFMMNG.

FEBUARY 2004. SHEBOYGAN COUNTY COORDINATE SYSTEM ANO (WVDSS VERTICAL MTUM.

5. SEDIMENT SAMPLES nELD MEASURED BY NRT. 1995.

DATUM (FT)

IGLD

5 7 9 . 8

USGS

581

CITY OF SHEBOYGAN

0 —a-2—

0 25 50 100

SCALE IN FEET

N R T

Natural Resource Technology

SITE PLAN Rl/FS WORK PLAN

CAMPMARINA V/ISCONSIN PUBUC SERVICE CORPORATION

SHEBOYGAN. WISCONSIN CAD Fl-E: 1665\2-SED\1665-2-D01.DWG

REFERENCE HLES:

PROJECT NO. 1665/2.0

DRAWN BY: RLH 05/10/04 CHECKED BY:

JTB

APPROVED BY: JMK 03/20/07

SHEET NO. 1

Page 41: River Operable Unit Technical Letter Report · RAP Remedial Action Plan ROD record of decision ... wood treatment, and paving roads. The gas was passed through purifiers to remove

H^

^

LEGEND

e c o o

o

— —

— . . . —

TREES

RIPRAP

UGHT POLE

FORMER MGP STFUCTURES

FORMER CAMPMARINA PROPERTY BOUNDARY

COHTAINMENT BARRIER

RWERS EDGE

/ r

SOURCE NOTES: 1. PORTIONS OF THIS DRAWING S O WERE DEVELOPED FTTOM DRAWING FILE

CAMPPLAN.DWG DATED l / 4 / O O OBTAINED FROU THE CFTY OF SHEBOYGAN. 2. SUTrV€t OF CONTAINMENT BfRRRIER BY RETTLER CORPORATION. MARCH 2 0 0 1 .

DIGITAL RLE TOP0022801.DWG. 3. PORTIONS OF THIS DRAWING S O WERE DEVELOPED FROM DRAWING RLE

NRT-AERlAL-DWG E-UAJLED 1 / 1 3 / 0 4 FROM THE CITY OF SHEBOYGAN. 4. UONITORINC WELLS SURVEYED BY ROBERT L LEE * ASSOCIATES SURVEYING.

FIBUARY 2004 . SHEBOYGAN COUNTY COORDINATE SYSTEM AND NAVD88 VERTICAL DATUM.

5. SEDIMENT SAMPLES RELD MEASURED B f NRT. 1996.

25 50

DATUM (FT)

IGLD

579.8

USGS

581

CITY OF SHEBOYGAN

0

100

SCALE IN FEET

N R T

Natural Resource Technology

FORMER MGP STRUCTURE LOCATIONS Rl/FS WORK PLAN

CAMPMARINA WISCONSIN PUBLIC SERVICE CORPORATION

SHEBOYGAN, WISCONSIN CAD FILE: 1665\2-SED\1665-2-D02.DWG REFERENCE FILES:

PROJECT NO. 1665/2.0

DRAWN BY: RLH 05/10/04 CHECKED BY:

JTB

APPROVED BY: JMK 03/20/07

SHEET NO.

Page 42: River Operable Unit Technical Letter Report · RAP Remedial Action Plan ROD record of decision ... wood treatment, and paving roads. The gas was passed through purifiers to remove

I aP-TUAV I DATT I DEfTH I BTEX I ID-7J1AV I t n t / } 9 H I 11.41 I ND

'•"••'•. V ' . ^ ^ ^ ^ i M ' v l l ; -,

i£C£HQ

B A M T U L0CAT10r< S A M I U m

DATE DATS SAMTLE COLLECTZD

DETTH IAMFUDET™

BTEX Teal BTEX

F A R S

ToilPAhl

T705 TRANSECT BASE

• S0-704C SEDIMENT SAMPLE (HAND CORED)

SD-702BV yrx SEDIMENT SAMPLE

' ° ' (VIBROCORE)

MW-70E MONITORING WELL

... PZ-701

<B PIEZOMETER

® TREES

O O O RIPRAP

•0- UGHT POLE

Q

APPROXIMATI LOCATION OF SHEEN

APPROXIMATE LOCATION OF SHEEN AND ODOR

APPROXIMATE LOCATION OF SHEEN, ODOR. AND TAR

FORMER CAMPMARINA PROPERTY BOUNCMRY

CONTAINMENT BARRIER

RIVERS EDGE

WTVJH (FO IGLD

579.8

USGS

561

CITY o r SHEBOYGAN

0

25 a-2— 50 100

SCALE IN FEET

Natural Resource Technology

PREVIOUS SAMPLING LOCATIONS, DISTRIBUTION OF BTEX AND TOTAL PAH AND VISUAL OBSERVATIONS

RI /FS WORK PLAN CAMPMARINA

WISCONSIN PUBLIC SERVICE CORPORATION SHEBOYGAN, WISCONSIN

CAD FILE: 1 6 6 5 \ 2 - S E D \ 1 6 6 5 - 2 - D 0 3 . D W G

REFERENCE RLES:

PROJECT NO. 1 6 6 5 / 2 . 0

DRAWN BY: RLH 0 5 / 1 0 / 0 4

CHECKED BY: JTB

APPROVED BY: JMK 0 3 / 2 0 / 0 7

SHEET NO.

Page 43: River Operable Unit Technical Letter Report · RAP Remedial Action Plan ROD record of decision ... wood treatment, and paving roads. The gas was passed through purifiers to remove

APPENDIX B

SEDIMENT INVESTIGATION REPORT, NRT FEBRUARY 1998

H

Page 44: River Operable Unit Technical Letter Report · RAP Remedial Action Plan ROD record of decision ... wood treatment, and paving roads. The gas was passed through purifiers to remove

Table 1. Field Observations at Sediment Sample Locations Former Sheboygan II MGP Site - WPSC

1 Sample Number**

1 BKG-700 SD-701 A SD-701 B SD-701 BV

SD-701 C SD-702A SD-702B SD-702BV SD-702C SD-702CV

SD-702DV

SD-703A SD-703B SD-703BV SD-703C SD-703CV

SD-703D SD-704A SD-704B SD-704BV

SD-704C SD-704CV

SD-704D SD-705A SD-705B SD-705BV

SD-705C SD-705CV

SD-705D SD-705DV

SD-705E

SD-706A

SD-706B SD-706BV

SD-706C SD-706CV

SD-707AV

Sample Date

10/16/95 10/17/95 10/17/95 06/11/96

10/17/95 10/16/95 10/16/95 11/05/95 10/16/95 06/11/96

06/13/96

10/17/95 10/17/95 06/13/96 10/17/95 06/18/96

10/20/95 10/17/95 10/17/95 06/11/96

10/17/95 06/17/96

10/20/95 10/18/95 10/18/95 11/05/95

10/18/95 06/17/96

10/18/95 06/11/96

10/20/95

10/18/95

10/18/95 06/17/96

10/18/95 06/18/96

11/04/95

Depth to Sediment / Water Interface

(inches)

nm 37 40 54

43 44 26 nm 67 61

62

40 47 63 58 78

68 37 51 70

64 74

57 46 67 nm

71 84

61 80

46

24

100 84

66 59

nm

Sedimeni Elevation above MSL

(feel)

nm 578.92 578.67 577.50

578.42 578.33 579.83

nm 576.42 576.92

576.83

578.67 578.08 576.75 577.17 575.50

576.33 578.92 577.75 576.17

576.67 575.83

577.25 578.17 576.42

nm

576.08 575.00

576.92 575.33

578.17

580.00

573.67 575.00

576.50 577.08

nm

Sample Interval

(inches)

0-15 0-31 0-10 0-26 26-34 34-44 44-45 45-47 47-49

0-8 0-16.75 0-15.25

0-86 0-3

0-27 27-64 64-89 0-17 17-43 43-57 57-61 61-67 67-75 75-82 82-91

91-100 0-19 0-14 0-95 0-23 0-43

43-68 68-80 0-10

0-17.5 0-23 0-17 17-28

28-102 102-108 108-116

0-21 0-49

49-67 67-76 76-86 86-93

0-3 0-14

0-18.8 0-15 15-21 21-26 26-45 45-47 47-50 50-53 53-58 4-12 0-50

50-112 112-117 117-126

0-10 0-24

24-36 36-54 0-9.5

0-3

0-11 0-13 13-31 31-36 0-11 0-4

4-11 11-19 19-24 24-32 32-44 44-46 46-59 59-81 0-15 15-23 23-35 35-48 48-60 60-74

PID Reading

4.6 22 0 na na na na na na 0

1667 0 na 1.2 na na na na na na na na na na na na

72.7 4.7 na 8.1 na na na

13.6 7.1

43.1 na na na na na 6.4 na na na na na na 4.7 23.9 207 18

13.1 56.1 81.6 40.1 36

14.5 18.5 na na na na 7.3 na na na 7.5

na 16.9 na na na

21.9 na na na na na na na na na

10.3 9.1 14.3 41 34

14.6

Assay Result

1.57 HI

2.37 na na na na na na 2.1 1.83 1.71 na

1.57 na na na na na na na na na na na na HI

1.95 na

0.93 na na na

1.77 29.95

HI na na na na na

1.37 na na na na na na HI HI na na na na na na na

na HI na na na na

2.13 na na na

1.91

na 2.7 na na na

ND na na na na na na na na na na na na na na na

Filed Observations

Hair Odor

... yes

...

... „ .

yes yes yes yes

yes

yes

.... yes yes yes yes

...

... yes yes

...

... yes yes

yes yes yes

yes

...

...

...

...

... yes

yes yes

yes yes yes yes

yes yes yes

yes yes yes

yes ... ...

yes ... ... ... ... ...

yes „ .

...

... yes

yes yes

... yes

yes yes

...

...

...

... - . ... ... ... ... ... ...

yes

...

... yes

...

...

...

...

...

...

...

...

... yes yes — ... ... ... ... ... ... ... — ... ... ... ... ... ... . . .

i Sheen

1

1 1 1 1 1

1 1

j yes I yes

yes

...

I

1 ... ...

1 -1 1

1 ...

...

... yes

...

...

...

...

...

...

...

...

...

...

...

...

...

...

...

... 1 —

... — ... ... ... ... ... ... ...

...

...

... yes yes

...

...

yes yes

...

... yes^-

___ yes yes yes

...

...

1 i 1 1 1

I ... ...

yes yes ...

yes ...

Tar

... yes

...

...

... yes yes yes yes

... —

yes

... .... yes yes

... yes yes yes yes

...

...

... yes

.__

...

...

...

...

...

yes

yes yes

...

.__ •

... yes yes yes yes yes

yes ... ... ...

yes yes

... yes

yes

.__

...

... yes

...

...

...

...

... yes

— ... ... ... ... ...

yes

...

...

...

...

...

yes

yes

1665 sediment tables compared to PEC.xIs Page lof 2 Table 1 - Field Observations

Page 45: River Operable Unit Technical Letter Report · RAP Remedial Action Plan ROD record of decision ... wood treatment, and paving roads. The gas was passed through purifiers to remove

Table 1. Field Observations, Continued

Sample Number**

SD-707BV

SD-707CV

SD-708AV

SD-708BV

SD-709AV

SD-71 OAV

SD-71 OB V

SD-71 OCV

SD-71 lAV

SD-71 IBV

SD-71 ICV

SD-712AV

SD-712BV

Sample Date

11/04/95

06/10/96

11/04/95

06/10/96

11/04/95

06/18/96

06/18/96

06/18/96

06/18/96

06/18/96

06/18/96

06/18/96

06/18/96

Depth lo Sediment / Water Interface

(inches)

nm

75

nm

82

nm

106

78

59

109

80

58

no

124

Sediment Elevation

above MSL

(feet)

nm

575.75

nm

575.17

nm

573.17

575.50

577.08

572.92

575.33

577.17

572.83

571.67

Sample Interval

(inches)

0-5 5-14 14-17 17-20 20-25 25-30 30-35 35-50 0-16 16-20 20-24 24-28 28-60 60-69 69-71 71-79 79-84 0-10 10-29 29-36 36-40 40-53 53-66 66-70 0-16 16-35 35-52 52-60 O-Il 11-24 24-36 0-23

23-34 34-44 44-50 50-52 52-54 54-64 0-34 34-38 38-44 44-52 0-42

42-52 52-64 0-24 24-28 28-36 36-48

0-7 7-13 13-18 18-22 22-29 29-34 34-48 48-50 50-58 58-68 68-78 78-87

87-100 0-21 21-36 36-48 48-55 55-60 60-69 0-38

38-48 48-67 67-73 0-42

42-48 48-77

PID Reading

4.7 4.5 5.3 5.3 8.4 5.2 7.9 3.7 na na na na na na na na na 8.3

20.5 20.7 9.6 14.8 6.1 14 na na na na

14.3 33.9 9.2 na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na

Assay Result

na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na

Filed Observations

Hair

...

...

...

...

...

... _-. ... --. - .

yes yes yes yes yes yes

...

...

...

... — . -—

yes yes

...

...

...

...

...

... yes yes yes

... —

...

...

...

...

...

yes

...

...

...

... yes ...

yes

yes yes

yes ... ... ... ...

... — ... ... ...

Odor

...

...

... -_-... ... ... ... ... _-.

...

.-.

...

...

...

...

...

...

...

...

...

... -.-... ... ... ... ... ... — ...

...

...

...

... __. ___ ... ... ... ...

... — ... ... ... ... ... ...

yes

...

...

...

... yes

yes yes

...

...

...

...

... ... ...

Sheen

... — ...

... - .

:;: ... ... ... — ... ... ... ... -._ ... ... ... _._ ... — — — ... ... ... ...

...

...

...

...

.... yes ...

::: — — ... — _-_ ... ... ...

...

...

...

... yes yes

...

...

... yes ... ... ... ... ...

Tar

...

...

...

... yes

... yes

...

...

...

... yes

...

...

...

...

... ___ ___ ... ___ ... -__ ... ... ... ... ... ... — ...

yes yes yes yes

...

yes yes

...

...

...

...

...

...

... yes yes

...

...

.-_ —.

yes

...

...

...

...

...

...

...

NOTES: na = Sample not analyzed for parameter. . . . = Not observed in sample, nm = not measured. SP = Indicates sheen was observed on the sounding pole even though no sample was collected. ** Sample locations are presented on Plate I. HI = Immunoassay results out of the calibrated instrument range (Sample value > 500 ppm total PAHs). SD-7XXV = indicates sample collected by Vibrocore methods - all other samples collected manually. No Sedimeni Borehole Log for BKG-700 & SD-702BV

1665 sediment tables compared to PEC.xIs Page 2of 2 Table 1 - Field Observations

Page 46: River Operable Unit Technical Letter Report · RAP Remedial Action Plan ROD record of decision ... wood treatment, and paving roads. The gas was passed through purifiers to remove

Table 2 - PAH Sediment Laboratory Analytical Results Former Sheboygan II MGP Site - WPSC

Sample Number

.S ' ^P ' f Sample

^ ' ^ r ' ^ Date (mches)

Method Detection Limit

BKG-700 SD-701B SD-702A SD-702B SD-703C SD-704B SD-706C

0-15 0-10

0-16.75 0-15.25

0-23 0-23 O-Il

10/16/1995 10/17/1995 10/16/1995 10/16/1995 10/17/1995 10/17/1995 10/18/1995

PAHs (^g/kg)

1 t ca c o

< 40

u c _u "?.

s g-<

80

c

S

a <

8

Ben

zo(a

)ant

hrac

ene

2

u c u .£ C E o

3

B 2

C

B

i 3

I E V

CO 2

B

a. 'a

B

oa

8

4 eo

a u

CD

4

U

4

1 1 S S s 1 5 4

u B

•s B

s 3

E 8

B

o 3

16

Inde

no( 1

,2,3

-cd)

pyre

ne

4

• a

t >>

1 25

1 u

1 •a •s

! -g. 1 fl

1 25

1 c

• o. ! o

Z

40

B

1 c CQ C

1 ID

16

B

8

Total PAHs' (mg/kg)

Hand Cored Samples ]

nd nd nd nd nd

26,000 nd

nd nd nd nd nd

12,000 nd

35 nd nd nd nd

15,000 38

380

8 18 89 nd

11,000 110

130 14

11 57

nd 2,400

39

69 nd 15 55 nd

3,100 47

260 nd 18 98 nd

7,700 82

160 17 36 150 nd

5,300 110

180 8 10 64

nd 70,000

82

nd nd 14 21 nd

1,300 nd

640 18

18 83 nd

56,000 300

nd nd nd nd nd

31,000 nd

94

9 23 94 nd

3,200 93

nd nd nd nd nd nd nd

nd nd nd

nd nd nd nd

nd nd nd nd nd

124,000 nd

62 nd nd nd nd

66,000 160

160 11 nd 120 nd

9,600 180

2.2

0.1 0.2 0.8 nd 444 1.2

Vibrocore Samples |

SD-701BV SD-702BV SD-702CV SD-702CV SD-702CV SD-703BV

SD-704BV SD-704BV SD-705BV SD-705BV SD-705DV SD-706CV SD-707BV SD-707CV SD-708AV SD-709AV SD-711AV SD-712AV SD-712BV

47-69 75-86 0-27 27-64

80-89 37-42

28-102 112-116 45-47 53-58 36-54 46-59 35-43 60-79 53-66 11-24 36-48 38-48 48-77

6/11/1996 11/5/1995 6/11/1996 6/11/1996 6/11/1996 6/13/1996 6/13/1996 6/13/1996 11/5/1995 11/5/1995 6/13/1996 6/18/1996 11/4/1995 6/11/1996 11/4/1995 11/4/1995 6/18/1996 6/18/1996 6/18/1996

nd 203,000

nd 33,000 114,000

nd 68,000

nd 1,030,000

nd nd nd

3,300 nd nd nd nd nd nd

nd nd nd nd nd nd nd nd nd nd nd nd nd nd nd nd

nd nd nd

3,900 106,000

nd 37,000 32,000

nd 22,000

510 359,000

75 2,500

30 1,800 250 110 39

1,700

610 18

3,500 67,000

6 29,000 29,000

13

24,000 380

345,000 50

1,500 60

3,300 310 120 110 930

430 50

610 22,000

nd 5,400

40,000 15

4,800 100

115,000 16

280 14

840 48 40 42 170 110 13

1,200 17,000

nd 4,500 8,200

4 8,200 150

66,000 11

470 14 120

95 28 24 150 130 22

2,200 50,000

5 14,000 15,000

11 17,000

360 263,000

38 1,100

51 1,400 210 97 70 540 300 42

1,100 37,000

nd 10,000 8,800

10 12,000

320 204,000

26 770 58

1,400 140 75 52

410 240 49

1,400 42,000

nd 11,000 10,000

7 9,700 230

228,000 2

720 38

2,900 120 74

56 410 210 23

nd nd

nd nd nd nd nd nd nd nd nd nd 120 nd nd nd nd nd nd

8,400 330,000

10 141,000 102,000

20 41,000 1,300

1,580,000 130

5,100 120

11,000 730 220 170

1,700 2,200 120

4,000 207,000

nd 66,000 71,000

nd 52,000

370 490,000

45 1,300

nd 650 97 97 51

1,300 340 nd

1,400 28,000

nd 7,500 5,700

5 8,000 210

156,000 23 530 23

1,000 110 53 33 nd 180 22

11,000 nd nd

157,000 206,000

nd 158,000

470 nd nd

2,700 nd nd 75 nd nd

3,400 nd nd

10,000 nd nd

145,000 188,000

nd 135,000

700 nd nd

2,300 nd nd 92 nd nd

1,800 nd nd

7,200 974,000

nd

297,000 358,000

nd 190,000 3,000

2,520,000 470

3,900 nd nd nd nd nd

790 nd nd

10,000 344,000

nd 134,000 119,000

nd 91,000 1,800

1,370,000 150

7,800 150

6,000 930

330 110

4,000 2,100

56

2,900 99,000

nd 23,000 20,000

8 25,000

570 568,000

75 1,800

59 8,500 630 200 140

1,300 1,300

26

69 2^26 0.0

1,114 1327 0.1

866 10

9,294 1.1 33 0.6

42.3 3.8 1.4 0.9 19 8.2 0.4

NOTES: 1) Sample Locations are presented on Plate L 2) nd = Parameter Not Detected

3) No sediment borehole logs for BKG-700 or SD-702BV. 4) PAHs analyzed by U.S. EPA Method 8310

5) Constituents that exceed the PEC are highlighted in yellow 6) Concentrations have not been normalized to 1% TOC

CBSQG

TEC PEC

Total PAHs' (mg/kg)

1.6 22.8

CBSQG = Consensus-Based Sediment Quality Guidelines

TEC = Threshold Effect Concentration

PEC = Probable Effect Concentration

Reference; 1: MacDonald, D.D., C.G. Ingersoll, and T.A. Berger. 2000. Development and evaluation of consensus-based sediment quality guidelines for freshwater ecosystems. Arch. Environ. Contam. Toxicol. 39:20-31.

1665sedimenttablescomparedtoPEC.xls - Table 2 - Sed PAHs Page 1 of 1 Pi-ep. by: DRJ/SLF

Checked by: JAG/DVP

Page 47: River Operable Unit Technical Letter Report · RAP Remedial Action Plan ROD record of decision ... wood treatment, and paving roads. The gas was passed through purifiers to remove

Table 3 - BTEX Sediment Laboratory Analytical Reuslts Former Sheboygan II MGP Site - WPSC

Sample Number

Interval _ , T» .. .. . , Sample Date (mches) *

Method Detection Limit

BTEX(ngA^)

Benzene

5

Toluene

5

Ethylbenzene

5

Xylenes, total

15 Hand Cored Samples

BKG-700 SD-701B SD-702A SD-702B SD-703C SD-704B SD-706C

0-15 0-10

0-16.75 0-15.25

0-23 0-23 0-11

10/16/1995 10/17/1995 10/16/1995 10/16/1995 10/17/1995 10/17/1995 10/18/1995

nd nd nd nd nd

6,300 nd

nd nd nd nd nd

9,500 nd

nd nd nd nd nd

24,000 nd

nd nd nd nd nd

31,000 nd

Total BTEX (mg/kg)

Total BTX^ (mg/kg)

1 nd nd nd nd nd 71 nd

nd nd nd nd nd 47 nd

Vibrocore Samples 1 SD-701BV SD-702BV SD-702CV SD-702CV SD-702CV SD-703BV SD-704BV SD-704BV SD-70SBV SD-705BV SD-705DV SD-706CV SD-707BV SD-707CV SD-708AV SD-709AV SD-711AV SD-712AV SD-712BV

47-69 75-86 0-27 27-64 80-89 37-42 28-102 112-116 45^7 53-58 36-54 46-59 35-43 60-79 53-66 11-24 36-48 38-48 48-77

6/11/1996 11/5/1995 6/11/1996 6/11/1996 6/11/1996 6/13/1996 6/13/1996 6/13/1996 11/5/1995 11/5/1995 6/13/1996 6/18/1996 11/4/1995 6/11/1996 11/4/1995 11/4/1995 6/18/1996 6/18/1996 6/18/1996

nd 110,000

nd 49,000 30,000

nd 11,000

400 1,400

nd 270 nd nd nd nd nd 18 nd nd

280 220,000

nd 100,000 110,000

nd 3,900

nd 1,200

nd 62 nd nd nd nd nd 25 nd nd

810 280,000

nd 120,000 210,000

nd 71,000 1,700 7,200

49 940 nd nd nd nd nd 36 nd nd

690 380,000

nd 170,000 240,000

nd 88,000 1,600 7,700

50 450 nd nd nd nd nd 71 nd nd

1.8 990 nd

439 590 nd 174 3.7 18 0.1 1.7 nd nd nd nd nd 0.2 nd nd

1.0 710 nd

319 380 nd 103 2.0 10 0.1 0.8 nd nd nd nd nd 0.1 nd nd

NOTES: 1) Sample locations are presented on Plate I. 2) nd = Parameter Not Detected 3) No sediment borehole logs for BKG-700 or SD-702BV.

4) BTEX analyzed by U.S. EPA Mediod 8260 5) Constituents that exceed the PEC are highlighted in yellow 6) Concentrations have not been normalized to 1% TOC

CBSQG

TEC PEC

BTEX (mg/kg)

NS NS

Total BTX^ (mg/kg)

0.97 1.96

Reference:

CBSQG = Consensus-Based Sediment Quality Guidelines TEC = Threshold Effect Concentration PEC = Probable Effect Concentration NS = No Standard EstabHshed for ethyl benzene

2: MacDonald, D.D. and M. MacFarlane. 1999. (Draft). Criteria for managing contaminated sediment in British Columbia. British Columbia Ministry of Environment, Lands, and Parks. Victoria, British Columbia.

1665 sediment tat)les compared to PEC.xIs ~ Table 3-Sed BTEX Page 1 of 1 Prep, by: DRJ/EPK

Checked by: JAG/EPK

Page 48: River Operable Unit Technical Letter Report · RAP Remedial Action Plan ROD record of decision ... wood treatment, and paving roads. The gas was passed through purifiers to remove

Table 4 - Sediment Laboratory Analytical Results Cyanide, Phenol, TOC, Oil & Grease, RCRA Metals & PCBs

Former Sheboygan II MGP SUe - WPSC

Sample Number

Sample Interval (inches)

Sample Date

Method Detection Limit

BKG-700 SD-701B SD-702A SD-702B SD-703C SD-704B SD-706C

0-15 0-10

0-16.75 0-15.25

0-23 0-23 0-11

10/16/1995 10/17/1995 10/16/1995 10/16/1995 10/17/1995 10/17/1995 10/18/1995

(mgfltg) 1

Total Cyanide

025

Weak Acid Dissociable

Cyanide 0.25

PbenoP

0.13

OiI& Grease

.500

TOC

-Hand Cored Samnles I

0.59 nd 0.3 nd nd

084 nd

nd nd nd nd nd

0.62 nd

nd nd nd nd nd 2

0.19

na na na na na na na

30,000 17,000 20,000 20,000 17,000 31,000 7.600

Vibrocore Samples | SD-701AV SD-702BV SD-702CV SD-702DV SD-705BV SD-70SBV SD-707BV SD-708AV SD-708BV SD-709AV SD-711AV SD-711AV SD-7I1BV SD-711BV

47-69 75-86 27-64 GB

45-47 53-58 35-43 53-66 52-60 11-24 24-28 36-48 50-58 78-87

6/11/1996 11/5/1995 6/11/1996 6/13/1996 11/5/1995 11/5/1995 11/4/1995 11/4/1995 6/11/1996 11/4/1995 6/18/1996 6/18/1996 6/18/1996 6/18/1996

na 0.98 na na 8.7 nd nd nd na nd na na na na

na 0.51 na na 3 nd nd nd na nd na na na na

na 48 na na 4.3 nd nd nd na nd na na na na

na na

43,400 na na na na na na na

31,400 na

2.570 na

na 27,900

>100,000 71,600 25,700 1,600 1,100 1,100

na 1,700

19,000 2,000 21,000 9,600

Sample Number

fnZa, «™P'* ,. . ^ Date (mches)

Mediod Detection Limit SD-701BV SD-702CV SD-708BV SD-711BV

47-69 6/11/1996 27-64 6/11/1996 52-60 6/11/1996 50-58 6/18/1996

RCRA Metals (mg/kg)

Arsenic

012 na 1.8 2.1 1.0

Barium

0 5 na 26 47 12

Cadmium

1 na 1.6 1.4

Chromium

1 na 43 500 7.4

Lead'

4 na 140 71 28

Mercury'

0.02 na 02 0.47 0.18

Selenium

0.12 na

<0.48 <0.48 <0.I2

Silver^

1 na

<1.0 <1.0 <1.0

Total PCBs' (mg/kg)

0.12 0.42

1.8-2.3 na

0.97

NOTES: 1) For Sample Locadons, please reSsr to Plate I 2) nd = Parameter Not Detected 3) na = Parameter Not Analyzed for in this sample 4) ppm = part per million = mg/kg 5) GB = Grab sanple from surface, no depth reading

6) No sediment borehole logs for BKG-700 & SD-702BV 7) Contituents not listed in the table below do not have established standards 8) Consdtuents that exceed tlie PEC are highlighted in yellow 9) Concentrations have not been normalized to 1 % TCXI

CBSQG TEC PEC

As' (mg/kg)

9.8 33.0

Cd' (mg/kg)

0.99 5.0

Cr' (mg/kg)

43.0 110

Pb' (mg/kg)

36.0 130

Hg' (mg/kg)

018 1.1

(mg*g) 018 1.1

Total

PCBs' (mgAg) 0060 0.676

Phenol' (mg/kg)

4.2 12.0

CBStJG = Consensus-Based Sediment (Quality Guidelines TEC = Threshold Effect Concentration PEC = Probable Effect Concentration

Refisrences: 1: MacDonald, D.D.. C.G. Ingersoll and T.A. Berger. 2000. Development and evahiation of consensus-based sediment quality guidelines for freshwater ecosystems. Arch. Environ. Contam Toxicol. 39:20-31.

2: MacDonald. D.D. and M. MacFarlane. 1999. (Draft). Criteria for managing contaminated sediment in British Columbia. British Columbia Ministry of Environment. Lands, and Parks. Victoria, British Columbia.

3: Sediment Management Standards, Chapter 173-204 WAC, Washington State Department of Ecology. April 1991. The Standards were developed using the Apparent Effects Threshold Approach. The TEC and PEC values for the comopunds are based on no effect and miniiTial effect standards, respectively, from the Washington Standards and are intended to apply to Puget Sound, and estuarine habitat. The values were calculated based on an assumed TOC content in sediment of 1 %.

1665 S8d<ment tables compared to PEC.xIs - Table 4-Sed Various Rase 1 of i Prep, by: SLF/EPK

Checked by: DVP/EPK

Page 49: River Operable Unit Technical Letter Report · RAP Remedial Action Plan ROD record of decision ... wood treatment, and paving roads. The gas was passed through purifiers to remove

A 592-

590-

5 8 8 -

M 6 -

A

5 7 B -

5 7 6 -

SLT w m TAM

D D'

UJ 5 7 6 -

B B C c

578-

576-

582-1

560

5 7 8 -

I B 576-

572-

570-

..• '

582-1

5 8 0 -

578-

576-

574-

572-

570

568'

5 6 6 -

564-

^ 52.77. l^lZt

SMDS AW SLn

E 578-

g 576-

I 3 574-

572-

570-

5 5 8 -

566-

564-

FEET

n x n C U OACCMIUTIDN ' 4.00

Lis sMo

m , fcld SWDY SILT

0..,

l l J ORGMDC

0 c.. ^ SWOT CLAY

Sr . .

b 2 j SAND WITH CRAVa

• 1 TAR

S ^

SCREWED IMTIRVAl.

WATER LEVEL ELEVATIOM ON

18.6

JL IS

PAH»

BTEX

TOTAL PAHa (mg/kg)

?

BENZENE. TOLUCNL ETHTLBEMZENE. JfYIENE

570-

568-

Natural Resource Technology

GEOLOGIC CROSS SECTION A - A ' THROUGH J - J '

FORMER SHEBOYGAN SHEBOYGAN

DRAWN BY: T/iS

DATE:. 2 / 1 9 / 9 8

II MGP SITE , WISCONSIN

CHECKED BY: EPK

2/19/96

WPSC

APPROVED BY: RJK

2/19/98

PROJECT NO. 1183/4.3

DRAWING NO. 1183-D02

PLME 2

Page 50: River Operable Unit Technical Letter Report · RAP Remedial Action Plan ROD record of decision ... wood treatment, and paving roads. The gas was passed through purifiers to remove

r

SOUPCI HOIt:

I. potmoHs or THS M P N D S DC^VLOFCD FDOW A kUP smVFlID BY HMZE * ASSOCWIE^ HC. SMBtm^N. WBOMSm. REB&IEmX LAND SUVi^AS. JOB HD. D-2M1, CWTES SCFItUBOl 4. IMS.

2.F>0frTKMS or THE UAP WERE DfMli3PO FRoy MinAL ntOTO BT AOto-unmc ENOINQSMC BC. DATID APRL IB. I»90. TOWN or sxaoiTMN. SHEBtrrcw cDum.

3.SHEBCnUN RWn SHORELME DCMNSTKAU OF PtMNSnwMA WDtUC GRIOCE M^fU)PCD nwM UiP Vr BUSLAHD k BU3UCX ENCMEZRS. P.C. 1T6.D1DI SIM, i o n .

a p o n o e or TMS UW> WERE KVCLOPCI) FROU WP Bf SAKM »mWO-Sf>RCH. MTED Ct»/25/»3- PWUECl SOUUOM.

25 50

SCALE IN FEET

Natural Resource Technology

LEGEND

_ r 7 0 5

^ D - 7 0 4 C

^ S D - 7 0 2 B V

^ SG-7C1

0

OE

W/E

1 1

1 1

TT?ANSECT BASE

SEDIMENT SAMPLE (HAND CORED)

SEDIMENT SAMPLE (VIBROCORE)

STAFF GAUGE

UGHT POLE

OVERHEAD ELECTRIC

BURIED ELECTRIC

REU^TED STRUCTURE

DEPTH THAT TAR IS BURIED

BENEATH TOP OF SEDIMENT

24 ' -36 "

36--48"

48" OR MORE

DEPTH TO TAR CONTOUR FORMER SHEBOYGAN II MGP SITE - WPSC

SHEBOYGAN, WISCONSIN DRAWN BY: TAS

DATE: 2/24/98

CHECKED BY: EPK APPROVED BY: 2/24/98 2/24/98

PROJECT NO. 1183/4.3

DRAWING NO. 1183-D03

PLATE 3

Page 51: River Operable Unit Technical Letter Report · RAP Remedial Action Plan ROD record of decision ... wood treatment, and paving roads. The gas was passed through purifiers to remove

I

APPENDIX C

BBL SEDIMENT SAMPLE LOCATIONS

B

Page 52: River Operable Unit Technical Letter Report · RAP Remedial Action Plan ROD record of decision ... wood treatment, and paving roads. The gas was passed through purifiers to remove

\ j i

• • ^ i " • ; ; •

'yzP

: * i ^ 1 •••• b • -^ \ . ; . r : : : : ^ ; y :.::•:••• j i ; ; V

LEGEND

SAMPLE LOCATION CHOSEN FOR PARTICLE SIZE ANALYSIS

PCB Concentration (ppm, dry weigtit;

i ui

'ix-'l^-^lB...

v.'. . v: -- •••^OUTH OF INNER HARBOR-

r • • • -fp..

Vi

* * i k . * " ^ ' ' ^ .^ • • ' ^ '

1 •••• ? * " i ;

••"-"5r^-"™"'"-||---" •

.. ...JL il • • K I I " • • ! •

^'S il H}^ .-..il - -

lE.- T

:.-.::.i '• ^ " //III -...41

\ . . . . - / • •>•• i a l A aft.; • i ••^ f

i|j * - i ^ jl..5IJ.-i| i~ij"~—rii''~~. I$0.. ..il-

APPROX. SCALE: I = lOOO'

n il v., //:... JI..*.fth..JUl^..,:M.^H^

1«0791Rt1W07N6iX»R '•;: i iKoWer

\ i l x j : S ^ i _ j l '2ii 4..Ji-^l;:~::::{£»^/^vv£™:::;::::;v.dfe

/ - ^ ' i l n « ' / • •'4 ;1 ^ = i \ - ^ Mi' i i t ' ; Oil

L™J!. \JL«<i—s'.. L I I i,.5jiJ _....Jk£-«j Ji

BLASLAND, iOt tCK &.L1E, INC.

SHEBOYBAN RiVlR S MiAR&OP! SITE

SEDIMENT TRANSPORT -INVESTIGATION

SEDIMENT SAMPLING LOCATfONS

wmammmnki

Page 53: River Operable Unit Technical Letter Report · RAP Remedial Action Plan ROD record of decision ... wood treatment, and paving roads. The gas was passed through purifiers to remove

I

I I

DOCUMENTATION REPORT, NMT FEBRUARY 2M3

B

Page 54: River Operable Unit Technical Letter Report · RAP Remedial Action Plan ROD record of decision ... wood treatment, and paving roads. The gas was passed through purifiers to remove

Table 2 - Excavation Sidewall and Base Analytical Results Phase I and II Remedy Documentation Report Campmarina and Center Avenue Right of Way

Sam

ple

ID

Dat

e

EZ-101 12/15/2000

EZ-102 12/15/2000

EZ-103 12/15/2000

EZ-104 12/15/2000

EZ-105 12/15/2000

EZ-201 11/27/2000

EZ-202 11/27/2000

EZ-203 11/27/2000

EZ-204 4/2/2001

EZ-205 4/2/2001

EZ-206 4/2/2001

EZ.207 6/26/2001

EZ-208 6/26/2001

EZ-301 12/5/2000

EZ-302 12/5/2000

EZ-401 11/30/2000

EZ-402 11/30/2000

EZr403 11/30/2000

EZ-404 11/30/2000

EZ-405 11/30/2000

Volat i le O r g a

c

c ea

0.012*

0.3

0.577

0.045

0 .015*

0 .066

0 .028*

0.068

<0.009

<0.009

<0.009

<0.018

<0.009

<0.009

<0.009

0.284

5.49

0.579

0 .225*

0.371

at c 3

s2

0.024

0.084

0.083

0.049

0.023

0.045

0.083

0.072

<0.0042

<0.0042

<0.0042

<0.0084

<0.0042

<0.0042

<0.0042

0.578

3.57

0.394

0.092

0.476

nic C o m p o u n d s (mg/kg)

c

c

JZ

0.0065*

0.257

0.056

0.023

0.021

<0.0045

<0.0045

<0.0O45

<0.0O45

<0.0045

<0.0045

<0.009

<0.0045

<0.0045

<0.0045

0.082

0.613

0.12*

0.116*

0.107*

c

>-> X

1 <0.019

0.165

0.155

0.074

0 .057*

0 .061*

<0.019

0.121

<0.019

<0.019

<0.019

<0.O38

<0.019

<0.019

<0.019

0.265

2.72

<0.19

<0.19

<0.19

X

CQ

"rt

i2

0.043

0.806

0.871

0.191

0.116

0.172

0.111

0.261

nd

nd

nd

nd

nd

nd

nd

1.209

12.393

1,089

0.433

0.954

Po lynuc lea r A r o m a t i c H y d r o c a r b o n s ( P A H ' s ) m g / k g |

c

H JZ

a

• > >

<0.019

0.289

1.66

0.028*

0 .031*

na

na

na

<0.088

<0.102

0.804

<0.019

<0.018

0.364

0.387

0.399*

7.12

0.808

2.86

2.43

c

JC a a c ">,

^

<0.019

0.163

1.9

0.037*

<0.019

na

na

na

<0.088

<0.102

1.19

<0.019

<0.018

0.378

0.421

0.5*

5.77

0.908

0.494*

2.46

c CJ

£ a. cs c u

< <0.017

0.142

0.999

0 .023*

0.018*

na

na

na

<0.08

<0.094

0 .301*

<0.018

<0.017

1.45

0.222*

<0.199

14.2

0.26*

5.08

1.35

OJ

c

J= a. es c

<

0.03*

1.38

7.52

0.416

0 .023*

na

na

na

<0.095

0 .173*

0.228*

<0.021

<0.020

0.535

1.76

0.464*

39.3

5.65

0.829

12.7

c a a u

J :

<

0.019*

0.593

15.5

0.479

0 .021*

na

na

na

<0.079

0.112*

1.06

<0.017

0.017*

2.9

1.29

0.399*

118

2.54

3.11

6.98

c <u u n u

J= c es n

g c oa

<0.022

1.5

40.5

2.33

0.023*

na

na

na

0.135*

0.663

1.73

<0.022

0.051*

4.85

6.73

1.17

173

9.62

3.9

18.7

U

c <u u >-> a , n

c

p a

<0.017

3.27

41.4

2.32

0.036*

na

na

na

0.102*

0.742

1.79

<0.017

0 .033*

4.17

4.37

1.29

157

12.3

3.61

18.2

c (U

JZ

'c 2 o 3

N C

<0.0I7

2.92

50.5

3.08

<0.017

na

na

na

0.180*

1.0

1.99

<0.017

0.049*

4.445

7.67

1.32

168

14.5

3.4

25.9

Ol

c

L.

a.

OX)

I c oa

<0.033

1.68

21.6

1.4

<0.033

na

na

na

<0.154

0 .431*

0.611

<0.034

0.036*

2.72

3.29

1.31

83.4

6.65

1.76

7.46

tu c

c a u o 3

C

2 c

aa

<0.03

1.89

31.4

2.19

<0.03

na

na

na

0.177*

1.220

2.7

<0.030

0 .062*

4.3

5.61

1.29

105

8.14

2.95

14.6

2 c

i: J : U

<0.02

1.76

39.4

2.3

0.026*

na

na

na

0.162*

0.786

1.96

<0.020

0.056*

5.22

7.68

1.47

153

9.97

3.97

19.4

U c u CQ

u "c a

- - C 5 -

N C

5

<0.O43

0.563

8.32

0.556

<0.042

na

na

na

<0.196

<0.229

0.230*

<0.043

<0.041

0.98

1.19

<0.486

25.6

2.25

0 . 5 6 1 *

3.4

u c

JZ e CO u o 3

0.024*

1.83

63.2

4.04

0 .035*

na

na

na

0.338

0.592

4 .09

<0.013

0.148

11.2

10.6

2.85

431

15.2

8.87

21.6

c u o 3

<0.022

0.211

31.5

0.052*

<0.022

na

na

na

<0.1

<0.116

0.285*

<0.022

<0.021

1.19

0.248*

<0.248

48.4

0.544*

2.04

1.65

2 c CJ u >, a. '5' u

' \

"o" c CJ •a c

<0.046

1.42

20

1.42

<0.046

na

na

na

<0.214

0.388*

0.688*

<0.047

<0.045

2.59

3.29

1.08*

86

7.01

1.65

8.07

CJ c Oi

z

<0 .0 I6

0.527

4.65

0.141

0 .021*

na

na

na

<0.073

<0.0S5

<0.083

<0.016

<0.015

0.645

0.591

0.949

10.9

2.5

0.886

3.23

<u c CJ

£ C

c CJ £ 0.

0.032*

1.27

29.9

1.78

0.062

na

na

na

0 .133*

0.220*

0.841

<0.018

0.081

10.3

4.61

1.78

310

5.17

10.6

11.2

0) e

0.04*

2.6

65.4

3.74

0 .05*

na

na

na

0.319

0.906

3.77

<0.016

0.107

10.6

11.4

2.62

358

16.9

9.86

29.3

<

"a 'o

0.145

24.0

475.3

26.3

0.365

na

na

na

1.5

7.2

24.3

nd

0.6

68.8

71.4

18.9

2293.7

120.9

66.4

208.6

< Cu

o H

nd

13.3

231.5

14.2

0.085

na

na

na

0.8

4.8

11.1

nd

0.3

26.6

36.5

7.6

867.6

63.8

20.0

108.3

%

v: ."2

"c5 o

H

91

71

63

86

89

87

88

85

94

87

91

85

93

85

83

82

82

87

84

82

mg/kg l l

•a a

2.9*

29

363

25

2.6*

423

192

510

na

na

na

3.6*

7.5

346

230

1,010

60

168

62

229

CJ .•a ' c a

U "a

23

33

579

19

5.5

6.7

250

411

7.7

81

31

<0.024

5.3

93

241

3.2

25

42

2.7

113

I N T E R I M A N D P R E L I M I N A R Y G U I D A N C E L E V E L S (me/Ice)

G r o u n d w a t e r P a t h w a y

R C L Direct C o n t a c t

P a t h w a y - N o n -

indus t r i a l R C L Direct Con tac t

P a t h w a y - I n d u s t r i a l

R C L US EPA Res ident ia l

P R G s

US E P A Indus t r i a l

P R G s

5 .5E-03

ns

ns

0.65

1.5

1.5

ns

ns

520

520

2.9

ns

ns

230

230

4.1

ns

ns

210

210

ns

ns

n s

ns

ns

23

1,100

7.E-I-04

ns

ns

20

600

4.E-I-04

ns

ns

38

900

6.E+04

3,700

3.8E-1-04

0.7

18

360

ns

ns

3,000

5,000

3.E-I-05

2.2E-H04

l.OE-i-OS

17

0.088

3.9

0.62

2.9

48

8.8E-03

0.39

0.062

0.29

360

0.088

3.9

0.620

2.9

6,800

1.8

39

ns

n s

870

0.88

39

6.2

29

37

8.8

390

62

290

3 8

8.8E-03

0.39

0.062

0.29

500

600

4.E-I-04

2 3 0 0

3.0E-f04

100

600

4.E-H04

2600

3.3E-1-04

680

0.088

3.9

0.62

2.9

0.4

20

110

56

190

1.8

18

390

ns

ns

8,700

500

3.E-(-04

2,300

5.4E-4-04

ns

ns

ns

ns

ns

ns

ns

ns

ns

ns

-

"

-

- •

-

ns

50

500

400

750

ns

ns

ns

ns

ns

Notes: 1. na = not analyzed 2. nd = not detected 3. * = The reported result is less than the practical quantitation limit 4. [c]= carcinogenic PAH, classified as B2 probable human carcinogen 5. cPAHs=carcinogenic PAHs 6. RCL = WDNR generic Residual Contaminant Level 7. PRO = US EPA Region 9 Preliminary Remediation Goals for direct contact 8. Delected values bolded

lO.AA&'HMS/rTBAX}! | [ H M S J G R L 7 / 2 3 « 1 ] | R J C 0 6 ^ 4 ^ 2 )

1313/Doc.Report/Soil and Waier Analytical Tables/Tbl 2 Excavation Result Summary 1 ofl Natural Resource Technology, Inc.

Page 55: River Operable Unit Technical Letter Report · RAP Remedial Action Plan ROD record of decision ... wood treatment, and paving roads. The gas was passed through purifiers to remove

EZ-405

B

BTEX

NAPH

PAHS

LEAD

CYAN

1 1 / 3 0 / 0 0

0.371

0.954

3.23

208.6

229

113

EZ-403

B

BTEX

NAPH

PAHS

LEAD

CYAN

1 1 / 3 0 / 0 0

0.579

1.089

2.5

120.9

168

42

EZ-404

B

8TEX

NAPH

PAHS

LEAD

CYAN

1 1 / 3 0 / 0 0

0.225*

0.433

0.886

66.4

62

2.7

c.^^' ^ , 0 ^ ^

^ N ^ ' 1^^

LEGEND

SAMPLE I.D.

B

BTEX

NAPH

PAHS

LEAD

CYAN

DATE

BENZENE ( m g / k g )

TOTAL BENZENE, TOLUENE, ETHYLBENZENE, XYLENES ( m g / k g )

NAPHTHALENE ( m g / k g )

TOTAL POLYNUCLEAR AROMATIC HYDROCARBONS ( m g / k g )

TOTAL LEAD ( m g / k g )

TOTAL CYANIDE ( m g / k g )

REPORTED RESULT IS LESS THAN THE PRACTICAL OUANTITATION LIMIT

m g / k g

EZ

GZ

NS

RCL

MILUGRAMS PER KILOGRAM

EXCAVATION ZONE

GRADING ZONE

NO STANDARD

RESIDUAL CONTAMINANT LEVEL

E Z - 4 0 1

' — • '—^ C 3 £ = ^

EXTENDED EXCAVATION AREA TO - 3 FT. ELEVATION

10 20

SCALE IN FEET

DATUM (FT)

IGLD

579.8

USGS

581

CITY OF SHEBOYGAN

0

GENERAL NOTES". 1 . ALL SAMPLE LOCATIONS ARE LOCATED OUTSIDE

THE PERIMETER OF THE VERTICAL BARRIER WALL. 2. EXCAVATION DEPTH WAS EXTENDED TO AN

ELEVATION OF APPROXIMATELY - 1 R . (CITY OF SHEBOYGAN DATUM) WITH EXCEPTION OF THE SHADED AREA THAT WAS EXTENDED TO APPROXIMATELY - 3 FT. TO REMOVE ADDITONAL MGP AFFECTED SOIL AND DEBRIS.

SOURCE NOTES: 1. PORTIONS OF THIS DRAWING SET WERE DEVELOPED FROM A

SURVEY PERFORMED BY WPS ON 8 / 1 1 / 9 6 . A SURVEY PERFORMED BY HINZE 4 ASSOCIATES INC.. SHEBOYGAN, WISCONSIN. JOB NO. D-3752. DRAWING D3752B.DWG AND LftNG.DWG AND A SURVEY FROM WPS SURVEY "SHEBOYGAN GAS MANUFACTURING PLANT TOPOGRAPHY SURVEY DATED 0 1 / 0 7 / 9 9 ' .

2 PORTIONS OF THIS DRAWING SET WERE MODIFIED FROM A MAP SURVEYED BY HINZE Ic ASSOCIATES. INC.. SHEBOYGAN. WISCONSIN. REGISTERED LAND SURVEYORS, JOB NO. D-2091. DATED SEPTEMBER 4. 1995.

3. PORTIONS OF "IHIS DRAWING SET WERE DEVELOPED FROM DRAWING HLES CAMPCONT.DWG DATED 12/20/99 AND CAMPPLAN.DWG DATED 1/4 /00 OBTAINED FROM THE CITY OF SHEBOYGAN.

4 MW-701 THROUGH MW-709 AND PZ-701 THROUGH PZ-703 WERE RELOCATED TO REFLECT CITY OF SHEBOYGAN SURVEY DATUM.

5. MONITORING WELLS (MW-701 THROUGH MW-707 AND PZ-7Q1), AND STAFF GAUGE (SC-701) COMPLETED BY NATURAL RESOURCE TECHNOLOGY. INC. (NRT). REFERENCE "PHASE II ENVIRONMENTAL INVESTIGATION REPORT" DATED JUNE 28. 1996.

6. MONITORING WELLS (MW-708. MW-709. PZ-702. PZ-703) AND STAFF GAUGE (50-702) COMPLETED BY NRT IN DECEMBER. 1998.

7. EXISTING SITE FEATURES FROM A SURVEY BY RETTLER CORPORATION. STEVENS POINT. WISCONSIN, DOCUMENT NO: 00.651, DATED 10/31/00.

8. BASE AND WAa SAMPLES FROM HELD NOTES BY NRT 9. MANHOLE (UH) FROM RETOER CORPORATION. STEVENS POINT.

WISCONSIN. SURVEY DATED 2 / 1 9 / 0 1 .

EXCAVATION BASE SAMPLE

EXCAVATED AREA AT - 3 R . ELEVATION (CnY OF SHEBOYGAN DATUM)

PERIMETER OF VERTICAL BARRIER

LIMIT OF WORK EXCAVATION AND GRADING ZONES

RIVERS EDGE

CHAIN LINK SECURITY FENCE

RIVERS EDGE RLTER FABRIC FENCE

EXISTING RIGHT-OF-WAY

RCL'S ( m g / k g )

PARAMETER

BENZENE

TOLUENE

ETHYLBENZENE

TOTAL XYLENES

NAPHTHALENE

TOTAL LEAD

TOTAL CYANIDE

GROUNDWATER

0.055

1.5

2.9

4.1

0.4

NS

NS*

DIRECT CONTACT

NON-INDUSTRIAL

NS

NS

NS

NS

20

50

50*«

DIRECT CONTACT

INDUSTRIAL

NS

NS

NS

NS

390

500

NS

• • RISK BASED DIRECT CONTACT RESIDENTIAL

Natural Resource Technology

REMAINING SOIL QUALITY RIVER BANK

PHASE I AND II REMEDY DOCUMENTATION REPORT CAMPMARINA AND CENTER AVENUE RIGHT-OF-WAY

WISCONSIN PUBLIC SERVICE CORPORATION CITY OF SHEBOYGAN, WISCONSIN

DRAWN BY: TAS/RLH

DATE: 0 4 / 0 4 / 0 2

CHECKED BY: HMS

DATE: 0 4 / 0 4 / 0 2

APPROVED BY: REW

DATE: 0 4 / 0 4 / 0 2

P R O J E C T N O .

1 3 1 3 / 3 . 8 / A B

DRAWING NO. 1 3 1 3 - B 3 3

FIGURE NO. 5

Page 56: River Operable Unit Technical Letter Report · RAP Remedial Action Plan ROD record of decision ... wood treatment, and paving roads. The gas was passed through purifiers to remove

US Bun Ncno: O 1. TM I M IH1DWL FtMO AT - I FT. DJWTOL

DCAwmi AREA TO -3 n . OfVATKM (OTY OF shCBcnvM [MTU14 TO rotcMi M^tc ia UATEWL

2. tZ-3 tXCAUATED TD TWO riZI KUW GKOUfC SUWACE (KS).

3 Q-1 tXCAVATID TO - I n . tUVAIDM . 4 d - l DrCMUTCD TWO F in BBS ON ll/ 'S/DO

ON 04/01/01. THt ttD nvmcN or i z - i EXCWATIS AN WOirOM FNE FEET BO. FMV. EXCWATXM WAS PERmOUCD CN JUKE U. 2002.

9 s a m r a : 3 T>«WU(» • cr Rocrr DOOJlCMTAnM KPO«T FOI SUVIMC AM) ANALYTCM. I»ESU.T5.

\

CAMPMARINA AND LOCATION OF FORMER COAL GAS FACILITY

/ /

/

EXCAVATION PLAN

-12 OZ. NON-WWEN

I 600 PS CCOFAaRC w o r n ceoFABRC FDR SCDMENT STABUZATCH

6" FI.TDI GRAVEL ( 1 " TO 1.5' CLEAN/WASHED S7DMC)

PHASE I RIVER BANK RESTORATION, CAMPMARINA

>< " HORIZONTAL

SCALE IN FEET

V B m C A L EXJLGGSUnON - 1

LEGENP

^

^

m s m m

=—=

— .

EZ

GZ

OHWU

UGP

HSL

I IDPE

pa

UNEXCAVATCD/NATIrt WATERLAL

CRUSHED AGGREGATE BASE COURSE

ACGREGATE/CEMEMT SLURRT aoWABLE RLL

THERUAU.Y TREATED bUTERIAL

STRUCTURAL F i l l

FILTER GRAVEL ( T TO l .S" CLEAN/WASHED SFOHq

12 OZ. N O N - W I M X GEOFABRIC

900 X 600 PSI WCWEN GEOrABRIC

20 UlL LLDPE UEUBRANE UNER

EXBTINC GROUND SURFACE

EXCAVATION UUFTS

TEUPORART WORKING SURFACE. PHASE 1 COUPLETION

EXCAVATION ZONE

GRADING ZONE

ORDINARY HIGH WATER UARK (ESTIU»TEO)

UANUFACTURED GAS PLANT

UEAN SEA LEVEL

U N D « LOW DENSmr POLYETHYLENE

POUNDS PER SQUARE INCH

PHASE I EXCAVATION RESTORATION, CENTER AVENUE RIGHT-OF-WAY

*^ HORIZONTAL SCALE IN FEET

viatnuL EUGGKRAHON - i

- K B T K C CWXJWD SURFAd

POO I 000 PS WOVEN CEOFABRC rOR SCDftCHT STABUZATKM

6' FLTER GRAKl ( ! ' TD U * CUMl/^ASHCD STOHQ

GENERAL COHTKACTOR NOTES: 1. CROSS SECnON A ANO B ARE TYPICAL CROSS

SECnOHS OF EXCAVATION AND BACKRU. ALONG THE SKEB0T(W4 RNER. PHASE I B^CKFTU ELEVATX)NS TO BE REUI VERIFIED.

2. EXCAVATION UU/TS TO REMAIN SEVERAL INCh<ES ABOVE THE RIVER LEVEL TO U1N1UIZE SEDIMENT DISTURBWCE. NO CONTRACTOR EOLiPUENT OR PERSONNEL ALLOWED OIRECTI.Y IN THE RfVER.

3. STHUCTURAL R U AND THERMALLY TREATED MA'iERlAL APPROVED EOR RE-USE TO BE COUPACTED TD 95X STANDARD PROCTOR DENSfTY.

• . ELEVATIONS ARE REJTROTCED TD CfTY OF SHEBOTGAN DATUM.

5. PROPOSED SHEET PILE WAU TO BE WSTALIED AS PART OF THE PHASE 11 ACTTVmES.

6. SEE SKEH NO. COSO FOR PH<«SE I GRADING REQUIREMENTS.

7. E Z - 2 AND E Z - J INDICATE SHUIDW EXCAVATWN ZONES TO REMOVE SURFACE UGP IMPACTS. EXCAVATIONS SHALL BE NO UORE THAN ONE FOOT DEEP UNLESS OTHERWISE INDICATED Bf ENCINEER.

8. CONTRACTOR TO FIELD VERIPT UMfT OF SHEET Pa£ WAU AUGHMENT FOLLOWING Rr/EP BANK RESTDRATXW CURRENTLY S n AT 10* FTTOM RfiCRS EDGE.

9. UUnS FOR PLACEMENT OF FLOWABLE H U AND LLDPE UEUBRANE IN CENTER AVENUE RCHT-OF-WAY TO BE HELD VERIFIED.

10. EXCAVATKM LIMITS ALONG Rr/ER BANK ARE BKSED ON SHEBOYGAN RVER UVEL OF - 1 (CITY OF SHEBOTGAN DATUM) AND A MINIMUM SIDPZ REOUIREMENT OF 1.5' HORIZONTAL TO 1" VEFTICAL CONTRACTOR TO HELD VERIFY RH/ER ELEVATIDMS AND RVER BANK RESTORATION SLOPES.

11. HLTER FABRIC BARRIER ALONG RIVERS EDGE TO REMAIN IN-PLACE THROUGH COMPLETION OF RWER E W « EXCAVATION AND PLACEMENT OF RIPRAP.

1 \ PHASE I RIVER BANK RESTORATION, CENTER AVENUE RIGHT-OF-WAY

" HORIZONTAL SCALE IN FEFT

VERTICAL EXAGGERATION •

Natural Resource Technology

ISSUED TO WDNR (NOT FOR CONSTRUCTION)

ISSUED FOR BID (NOT FOR CONSTRUCTION)

ISSUED FOR CONSTRUCTION

ISSUED FOR AS BUILT

DATE:

06/14/00 09/01/00 10/12/00 03/12/02

EXCAVATION PLAN AND CROSS SECTIONS PHASE I AND II REMEDY AS-BUILT

CAMPMARINA AND CENTER AVENUE RIGHT-OF-WAY WISCONSIN PUBLIC SERVICE CORPORATION

CITY OF SHEBOYGAN, WISCONSIN DRAWN BY: TAS

DATE: 0 8 / 1 1 / 0 0

CHECKED BY: SLF

0 8 / U / O O

APPROVED BY: REW

06/14/00

PROJECT NO. 1313/3.8/AB

DRAWING NO. 1313DC040AB

SHEET NO. C040