NATURAL RESOURCE TECHNOLOGY EPA I^egion 5 Records Ctr. 360633 Wisconsin Public Service River Operable Unit Technical Letter Report Campmarina Former Manufactured Gas Plant Sheboygan, Wisconsin WIN000510058 MarclT 22, 2007 Project No: 1665
NATURAL RESOURCE TECHNOLOGY
EPA I^egion 5 Records Ctr.
360633
Wisconsin Public Service
River Operable Unit Technical Letter Report
Campmarina Former Manufactured Gas Plant Sheboygan, Wisconsin WIN000510058
MarclT 22, 2007
Project No: 1665
NATURAL
RESOURCE
TECHNOLOGY
RIVER OPERABLE UNIT TECHNICAL LETTER REPORT CAMPMARINA FORMER MANUFACTURED GAS PLANT
WISCONSIN PUBLIC SERVICE CORPORATION SHEBOYGAN, WISCONSIN USEPA ID: WIN000510058
Project No: 1665
Prepared For:
Wisconsin Public Service Corporation 700 N. Adams Street Green Bay, WI 54307
Prepared By:
Natural Resource Technology, Inc. 23713 W. Paul Road, Suite D
Pewaukee, WI 53072
March 22, 2007
'•(J^^MfA^ Richard H. Weber, PE Managing Engineer
23713 W. Paul Rd., Ste. D • Pewaukee, Wl 53072 • Phone: 262.523.9000 Pewaukee • Madison
Fax: 262.523.9001 • www.naturalrt.com
TABLE OF CONTENTS
1 INTRODUCTION 1 1.1 General Site Information 2 1.2 Site History 3
1.3 Current Site Conditions 5 1.4 Overview of Previously Performed Activities 6
1.4.1 Overview of Remediation Work Performed 6 1.4.2 Status of Site Conditions & Monitoring 7
1.5 Sheboygan River Characteristics 8
1.6 Dredging History 10
2 SHEBOYGAN RIVER AND HARBOR SUPERFUND SITE 12
2.1 Location and Description 12 2.2 Remedial Investigation 13 2.3 Risk Assessments 14 2.4 Sediment Transport Study 14
2.5 Feasibility Study 15 2.6 Record of Decision 15 2.7 Schedule 16
3 PREVIOUSLY PERFORMED RIVER OU INVESTIGATIONS AND RESULTS 17
3.1 BBL-1990 17
3.2 W D O T - 1 9 9 3 17
3.3 W D N R - 1 9 9 5 18
3.4 N R T - 1 9 9 8 18
3.4.1 October 1995 Investigation Activities 19 3.4.2 November 1995/June 1996 Investigation Activities 19
3.5 Chemical Constituents in Sediment 20
3.5.1 BTEX and PAH Results 21
3.5.2 Metals Results 22 3.5.3 PCB Results 22 3.5.4 Cyanide and Phenol Results 22
3.6 Chemical Constituents in Surface Water 23
4 REMEDIAL ACTIONS PERFORMED 24
5 IDENTIFIED RIVER OU PATHWAYS AND CONCLUSIONS 26
5.1 River OU Potential Exposure Scenarios and Receptors 26 5.1.1 Recreational Land Use Scenario - Visitor/Trespasser 26 5.1.2 Benthic Invertebrates-Aquatic Ecological Receptor 26 5.1.3 Other Ecological Receptors 27
1665 river ou tech Itr rev 0 final NATURAL i RESOURCE
TECHNOLOGY
TABLE OF CONTENTS
5.2 Additional Data Needs Summary 27
6 REFERENCES (RECORD FILE) 28
FIGURES
Figure 1 Figure 2
Site Location (1665-AOI.DWG)
Historical Site Layout (1665-3-BOI.DWG)
APPENDICES
Appendix A: Remedial Investigation/Feasibility Study Work Plan, Campmarina Former MGP Site, NRT July 2004 Sheet 1 Site Plan (I665\2-SED\I665-2-DOI.DWG)
Sheet 2 Former MGP Structure Locations (I665\2-SED\I665-2-DO2.DWG)
Sheet 3 Previous Sampling Locations, Distribution, of BTEX and Total PAH and Visual Observations (I665\2-SED\I665-2-DO3.DWG)
Appendix B: Sediment Investigation Report, Campmarina Former MGP Site, NRT February 1998 Table 1 through Table 4 Plate 2 Geologic Cross Section A-A' through J-J' (II83M.3II83-DO2)
Plate 3 Depth to Tar Contour (1183/4.3 II83-DO3)
Appendix C: BBL Sediment Sample Locations Appendix D: Construction Documentation Report, Campmarina Former MGP Site, NRT
February 2003 Table 2 Figure 5 (1313/3.8/AB/1313-B33)
Sheet C040 (1313/3.8/AB/1313DC040AB)
1665 river ou tech Itr rev 0 final NATURAL
RESOURCE
TECHNOLOGY
ACROYNMS
BBL Blasland, Bouck, & Lee, Inc. BTEX benzene, toluene, ethybenzene, xylene CITY City of Sheboygan CERCLA Comprehensive Environmental Response Compensation, and Liability Act COPCs constituents of potential concern cfs cubic feet per second cy cubic yard Garton Garton Toy Company HEC Hydrologic Engineering Center Heileman Heileman Brewing Company msl mean sea level MGP manufactured gas plant NCP National Contingency Plan ND non-detectable NRT Natural Resource Technology, Inc. OUs operable units ppm parts per million PVOCs petroleum volatile organic compounds PCB polychlorinated biphenyl PAHs polynuclear aromatic hydrocarbons RCRA Resource Conservation and Recovery Act RAP Remedial Action Plan ROD record of decision ARARs applicable or relevant and appropriate requirements RI/FS remedial investigation / feasibility study mi square miles Site site SGLC Sheboygan Gas Light Company SWAC surface-weighted average concentration TBCs To Be Considered TOC Total Organic Carbon USAGE U. S. Army Corps of Engineers USEPA United States Environmental Protection Agency USGS United States Geologic Survey WWSF warm water sport fish community WDNR Wisconsin Department of Natural Resources WDOT Wisconsin Department of Transportation WPSC Wisconsin Public Service Corporation
1665 river ou tech Itr rev 0 final ACR- 1
NATURAL
RESOURCE
TECHNOLOGY
River OU-Technical Letter Report - Campmarina Former MGP Revision 0 3/22/2007
Section 1 - Introduction Page 1 of 30
1 INTRODUCTION
The fonner Campmarina Manufactured Gas Plant (MGP) Site (Site), located in Sheboygan, Wisconsin
(Figure 1), is divided into two operable units (OUs) - the Upland OU and the River OU. Pursuant to the
Administrative Settlement Agreement and Order on Consent (Settlement Agreement) dated January 26,
2007, a Technical Letter Report is to be prepared for each OU to summarize environmental investigation
and remediation activities undertaken at the Site. Natural Resource Technology, Inc. (NRT), on behalf of
WPSC, prepared this Technical Letter Report to address the River OU. The Upland OU is addressed in a
separate Technical Letter Report.
In the early 1990s, the City of Sheboygan (City) installed a dock along the Sheboygan River as part of its
Campmarina Park project. The excavation of footings for the dock uncovered coal tar contamination
associated with the form MGP operations, hi order to address the contamination, on March 24, 1992,
WPSC and the City entered into an environmental investigation/remedial agreement (Contract Number
SF-91-04) in accordance with Section 144.442, Wis. Stats. The Contract required a Remedial
Investigation/Feasibility Study (Rl/FS) be completed consistent with the requirements of the
Comprehensive Environmental Response Compensation, and Liability Act (CERCLA), 42. U.S.C.
§§ 9601 et seq., as amended, and the National Contingency Plan (NCP). WPSC completed an RI/FS for
the upland portion of the Site, which lead to the Wisconsin Upland Record of Decision on January 11,
2001 (2001 ROD). The remedy in the 2001 ROD was constructed in 2001 and is in the operation,
monitoring, and maintenance phase. (The ongoing work is more fully described in the Upland Technical
Letter Report.)
The Campmarina Site is physically related to the larger Sheboygan River and Harbor Site. However, the
Campmarina work is related to releases from the historic MGP operations (which ceased in the 1920s),
while the Sheboygan River and Harbor Site addresses PCB contamination associated with former diecast
operations that occurred up until the early 1970s.
The River OU Technical Letter Report summarizes the previous work undertaken to investigate the River
sediments near the Campmarina Site and discusses the current conditions of the River in the vicinity of
the fonner Campmarina MGP site. In general, the purpose of this Report is to:
1665 river ou tech Itr rev 0 final NATURAL
RESOURCE
TECHNOLOGY
River OU-Technical Letter Report - Campmarina Former MGP Revision 0 3/22/2007
Section 1 - Introduction Page 2 of 30
Briefly describe areas and/or media previously addressed with the Upland OU response actions completed under the State Issued ROD;
Summarize the results and status of the Sheboygan River and Harbor Superfund Site, as it relates to WPSC's Campmarina MGP Site;
Summarize the results of WPSC's preliminary investigations of the River OU;
Summarize remedial actions performed within the River OU;
Identify areas/media within the River OU that may warrant remedial measures and/or response actions; and
• Describe the additional work that will be incorporated into the Site-sp)ecific RI/FS Planning documents.
The report is divided into the following sections:
Section 1: Introduction
Section 2: Sheboygan River and Harbor Superfund Site
Section 3: MGP Related River Investigations and Results
Section 4: Campmarina Remedial Actions Performed
Section 5: River OU Pathways and Conclusions
Section 6: References
1.1 General Site Information
Property Owner:
Former MGP Operator:
City of Sheboygan Contact: Mr. Tom Holtan (920-459-3366) 807 Center Avenue Sheboygan, WI 53081
Wisconsin Public Service Corporation Contact: Mr. Brian Bartoszek (920.433.2643) 700 North Adams Street, P.O. Box 19002 Green Bay, WI 54307-9002
] 665 river ou tech Itr rev 0 final NATURAL
RESOURCE
TECHNOLOGY
River OU-Technical Letter Report - Campmarina Former MGP Revision 0 3/22/2007
Section 1 - Introduction Page 3 of 30
Property Location: NWl/4 of the SW 1/4T15N, R23E, Section 23 732 North Water Street Sheboygan, Wisconsin Sheboygan County
USEPA ID: WIN000510058
WDNR BRRTS #: 02060000095
The Upland OU encompasses an area of approximately 2.3 acres and is bounded by a private boat club
facility on the north, former North Water Street on the east, a vacant lot on the south, and the Sheboygan
River on the west (Appendix A, Sheet 1).
Based on preliminary findings of MGP residuals within sediments, the River OU is approximately 3.4 acres,
adjacent to the Upland OU. This area extends about 80 feet upstream of the former Campmarina northern
property line, as much as 120 feet outward from the shoreline, and about 900 feet downstream of the
fonner Campmarina southern property line, a short distance south of the Pennsylvania Avenue bridge
(Appendix A, Sheet 3).
1.2 Site History
Two methods of coal gas production were used at the Campmarina MGP. The coal gas production
method, used from 1872 to 1886, involved heating the coal in an airtight chamber (retort) which produced
coke and gases containing a variety of volatilized organic constituents. The process also produced tar
which was sold for roofing, wood treatment, and paving roads. The gas was passed through purifiers to
remove impurities such as sulfur, carbon dioxide, cyanide, and ammonia. Dry purifiers contained lime or
hydrated iron oxide mixed with wood chips. The gas was then stored in large holders on the property
prior to distribution for lighting and heating.
The carburetted water gas process, used from 1886 to 1929, involved passing air and steam over the
incandescent coal in a brick-filled vessel to form a combustible gas which was then enriched by injecting
a fme mist of oil over the bricks. The gas was then purified and stored in holders prior to distribution.
The Campmarina MGP operations ceased in 1929. Former aboveground MGP related structures (Figure
2 and Appendix A, Sheet 2) included the following:
1665 river ou tech Itr rev 0 final NATURAL RESOURCE
TECHNOLOGY
River OU-Technical Letter Report - Campmarina Fonner MGP Revision 0 3/22/2007
Section 1 - Introduction Page 4 of 30
Three gas holders ranging in diameter from approximately 35 feet to 70 feet, the larger two with capacities of 70,000 cubic feet and 200,000 cubic feet;
One gas oil tank approximately 15 feet in diameter;
Three tar tanks; two approximately 30 feet by 8 feet and one approximately 20 feet by 5 feet;
One purifier approximately 25 feet in diameter; and
Gas manufacturing buildings including a garage, a gas meter shop, and a boiler room.
Based on review of Sanbom maps, the gas holders were removed between 1950 and 1955. Review of the
1955 Sanbom map indicates that many of the MGP buildings were still present in the Upland OU.
Sometime between 1955 and 1966, the remaining facility structures were razed and removed.
Numerous companies, which eventually became part of the Sheboygan Gas Light Company (SGLC),
owned the fonner Sheboygan MGP. In 1922, SGLC merged with other utilities to form WPSC. In 1966,
WPSC sold the prof)erty to Heileman Brewing Company (Heileman) for use as a parking lot. Heileman
sold the property in 1977, and it was then under ownership of three other non-manufacturing companies
until the City of Sheboygan purchased the property in 1985 when it became known as Campmarina.
Campmarina was equippied with gravel parking areas, electrical power and potable water for recreational
vehicle (RV) use. A docking area was also provided for recreational boat use on the Sheboygan River. In
2001 after WPSC completed upland remediation work, the City redeveloped Campmarina, North Water
Street adjacent to the property, and the property to the south (Center Avenue right-of-way) into a
neighborhood park called Worker's Water Street Park (Appendix A, Sheet 1).
Sanbom maps show the shorelines for the Sheboygan River at the former MGP property. Between 1891
and 1903, the channel appears to have been straightened by fill that extended approximately 60 feet into
the river. Subsequent Sanbom maps show that the shoreline did not change substantially from its present
location indicated on Figure 2.
During the Upland OU remediation (summarized in Section 1.4.1), a sheet pile banier wall was installed
along the Sheboygan River shoreline and the river bank was excavated and restored with filter gravel,
structural fill, and riprap. Details of the remedial action are provided in the Documentation Report (2(X)3,
NRT) and summarized in Section 4.
1665 river ou tech Itr rev 0 final NATURAL RESOURCE
TECHNOLOGY
River OU-Technical Letter Report - Campmarina Former MGP Revision 0 3/22/2007
Section 1 - Introduction Page 5 of 30
Based on review of the Sanbom maps. Boat Island is a man-made land mass located approximately 150
feet from the Site shoreline. The island is approximately 375 feet long by 105 feet wide (at its widest
point) and has several buildings which are used to store materials and supplies for the adjacent marina, the
Outboard Motor Club, located to the north of the Upland OU. The City of Sheboygan owns Boat Island .
The island has seasonal docking for boats.
Historical development activities adjacent (upstream) to the Upland OU included a property formerly
used as a tannery and a toy factory. Tannery operations terminated sometime between 1903 and 1940 and
the property was sold to Garton Toy Company (Garton). The 1950 Sanbom map indicates Garton used a
portion of the property adjacent to the river, directly across New York Avenue, for paint and lacquer
spraying.
1.3 Current Site Conditions
The Upland OU is now within Worker's Water Street Park with landscaped lawn, recreational areas,
seating, and sidewalks. The Park generally extends from the river on the west to 10* Street/North Water
Street on the east, and from the extension of Center Avenue on the south to Wisconsin Avenue on the
north. The Park footprint includes the former MGP property and abandoned right-of-ways for North
Water Street, Center Street, and New York Avenue.
An asphalt parking lot is located on the north side of the Park, with access from Wisconsin Avenue. A
small building constructed adjacent to this parking lot is shared by the Outboard Motor Club and WPSC. '
WPSC's use is related to the remediation work in the Upland OU, while the Outboard Motor Club uses it
to store equipment. The adjacent parking lot provides access to shoreline boat docks as well as additional
docks on Boat Island. North of the Park adjacent to the river is the former tannery and toy factory
building, which has been rehabilitated into multi-tenant housing.
South of the Park is a nanow parcel with a condominium unit at the northwest comer of Water Street and
Pennsylania Avenue. The Pennsylvania Avenue Bridge crosses the river just downstream of the Park and
former MGP. North Commerce Street parallels the river on its west side, with industrial/commercial
buildings located between the street and river.
1665 river ou tech Itr rev 0 final NATURAL RESOLHRCE
TECHNOLOGY
River OU-Technical Letter Report - Campmarina Former MGP Revision 0 3/22/2007
Section 1 - Introduction Page 6 of 30
Based on the United States Geologic Survey (USGS) Sheboygan North Quadrangle, photo revised 1973,
relief within one mile of the Site is approximately 95 feet, ranging from approximately 580 feet mean sea
level (msl) at Lake Michigan to approximately 675 feet msl northwest of the Site in the City of
Sheboygan. The ground surface elevation for the majority of existing Site groundwater monitoring wells
ranges between 588 and 591 feet msl; the Site slopes from Water Street to the Sheboygan River. The
elevation of the Sheboygan River ranges from about 578 feet msl (September 2(X)6) to 579 feet (August
2004), def)endent on the general elevation of Lake Michigan.
1.4 Overview of Previously Performed Activities
A summary of cunent Site conditions was provided to the United States Environmental Protection
Agency (USEPA) in October 2005. The Site status summary included information pertaining to the
upland remediation work performed and the status of Site conditions and monitoring, as well as a listing
of documents pertaining to the Site. A summary of the information included in the report is presented
below.
1.4.1 Overview of Remediation Work Performed
• Upland OU remediation work included soil excavation and thermal treatment (10,500 tons), installation of a containment system (sheet pile barrier around the perimeter of the Site and an engineered geosynthetic cover over the surface) and a biosparge system within the containment area (Appendix A, Sheet 1).
• Mass removal through soil excavation and thennal treatment followed by installation of the containment system is the primary remedy for the Upland OU. The biosparge system is currently in operation and is a secondary remedial measure. The biosparge system is undergoing performance monitoring to evaluate the effectiveness of longer term operation.
H Groundwater monitoring is conducted to demonstrate containment system performance. An Annual Operation, Maintenance, and Monitoring Report was submitted to USEPA and WDNR on November 28, 2005. The 2006 Annual Operation, Maintenance, and Monitoring Report will be incorporated into the Upland OU Technical Letter Report.
• Initial river sediment quality assessments were performed in 1995 and 1996.
1665 river ou tech Itr rev 0 final NATURAL RESOURCE
TECHNOLOGY
River OU-Technical Letter Report - Campmarina Former MGP Revision 0 3/22/2007
Section 1 - Introduction Page 7 of 30
1.4.2 Status of Site Conditions & Monitoring
• Groundwater depth ranges from approximately 5 lo 8 feet below ground surface. Flow is to the south-southeast toward Sheboygan River.
• Soils beneath the former MGP area include sand and gravel fill, and general fill with cinders over the entire former MGP to about 4 to 14 feet below ground surface, underlain by silty/clayey sand and clays to bedrock, at an estimated depth of 35 to 40 feet below ground surface. Thermally treated soils were replaced in the remedial excavations.
• Post-remediation residual concentrations of petroleum volatile organic compounds (PVOCs), polynuclear aromatic hydrocarbons (PAHs), and cyanide are present in soil and/or groundwater in the Upland OU. (^o i^c «-r\ ^a>J-ic>\s To^t, 7
u Shallow groundwater quality is close to or below Wisconsin Administrative Code, -Vupitcl Chapter NR140 standards at perimeter wells MW-705, 708 and 709R (outside of the ^ o P containment system. Appendix A, Sheet 1). Groundwater quality in deeper piezometers ^^•r«4vck'^'' (screened in clay at depth) exceeds standards at one location, PZ-703, and only for benzene.
• Groundwater elevation data demonstrates the containment of MGP-impacted groundwater. (Compare the groundwater elevations in MW-708 located outside the containment barrier with the groundwater elevations in MW-706 located within the containment banier.) ( CA-c.(v3 w^ap V\ou37 ^
• The secondary measure of containment performance -contaminant concentration trends in monitoring wells - confirms containment. See monitoring wells MW-705, MW-708 and MW-709 and piezometers PZ-701, PZ-702 and PZ-703. The only exception is \ PZ-703 which indicates fluctuating groundwater concentrations. ( v-t^c«^^cd +« w* "-
• Biosparge system performance was measured based on contaminant concentration and geochemistry trends at shallow groundwater monitoring wells MW-701R, MW-706 and ^ i do MW-707R within the containment system. The trends indicate fluctuating to decreasing ( % y*f"'^J^'>'j, benzene and naphthalene concentrations and continued biologic activity within the *°'i x biosparge system's zone of influence. (7|A(xP •5V\0U5*» a ^«ospo . r^ t •2<3KC o f ' >- l*^«»^e^)
• Water depths in the Sheboygan River vary from about 2 feet to greater than 10 feet. 1995-1996 poling data identified a sediment area of approximately 3.4 acres with visible coal tar, sheen, and/or odor (Appendix A, Sheet 3). This area extends about 80 feet upstream of the former upstream (northem) MGP Site property line, as much as 120 feet outward from the shoreline, and about 900 feet downstream of the fonner downstream (southem) propierty line, a short distance past the Pennsylvania Avenue bridge. Tar was evident in sample cores ranging in depth from about 1.5 feet to 9.5 feet.
1665 river ou tech ICr rev 0 final NATURAL RESOURCE
TECHNOLOGY
River OU-Technical Letter Report - Campmarina Former MGP Revision 0 3/22/2007
Section 1 - Introduction Page 8 of 30
• Based on the limited 1995-1996 sediment core sampling, the highest total PAH concentrations in the tar/sheen area was 9,294 mg/kg. In two areas without tar observations, PAH concentrations for two samples ranged from essentially non-detectable (ND), 0.09 mg/kg, to 8.1 mg/kg. In nearby areas, both upstream and downstream of the tar/sheen/odor, PAH concentrations ranged from 0.44 mg/kg to 2.17 mg/kg.
1.5 Sheboygan River Characteristics
The Sheboygan River is classified a Class C surface water by the WDNR. Class C surface waters are not
suitable as drinking water sources; however, they are suitable for fishing and fish propagation. Class C
waters are also designated for primary (e.g., swimming) and secondary (e.g., boating) contact recreation.
The River OU is within a portion of the Sheboygan River classified as a warm water sport fish
community (WWSF). (A WWSF community includes surface waters capable of supporting a community
of warm water sport fish or serving as a spawning area for warm water sport fish.)
The Sheboygan River drains 427 square miles (mi^), with its headwaters located in Fond du Lac County.
Near Lake Michigan, the Sheboygan River is a gaining stream that receives groundwater and surface
water from the Sheboygan area and discharges into Lake Michigan. Near the Site, the river varies from
approximately 130 feet (on either the east or west side of Boat Island) to 300 feet wide (just upstream of
Boat Island). Boat Island is in the approximate center of the river resulting in an east and a west channel
adjacent to the Upland OU. A gauging station active from October 1993 through September 1995
recorded an average flow rate of 177 cubic feet per second (cfs) at the mouth of the river (approximately
one mile downstream from the Upland OU).
During 1995 and 1996 sediment investigations (described in Section 3.2.2), an assumed river water
elevation of 582 feet msl was used as a datum for sediment poling activities. This elevation was based on
the USGS topographic quadrangle which indicates the water level in Lake Michigan outside of the
Sheboygan Harbor is approximately 580 feet msl. The river bed elevation within the River OU ranges
from approximately 571.7 to 580.0 feet msl based on the poling data. Water depths within the River OU
ranged from approximately 2 feet to greater than 10 feet.
Flow of the Sheboygan River is generally easterly, toward the lake, but southerly past the Site and is
controlled by upstream dams located at Sheboygan Falls and Kohler. The USGS operated two automated
stream gauging stations: one near Interstate Highway 1-43 (cunently operational) and the other near the
1665 river ou tech Itr rev 0 final NATURAL RESOURCE
TECHNOLOGY
River OU-Technical Letter Report - Campmarina Former MGP Revision 0 3/22/2007
Section 1 - Introduction Page 9 of 30
river mouth (no longer in operation). The stream flow data discussed below was collected from
Hydrologic Station # 040860041, located at "Sheboygan River al Mouth at Sheboygan, Wl." The station
was located over one mile downstream of the WPSC Site, with conditions similar to those of the river at
the Site.
Daily mean discharge data between October 1993 and September 1995 are summarized below:
Summary of Flow Conditions
Daily Average for 2 year Record
Daily Maximum for 2 year Record
Daily Minimum for 2 year Record
Flow (cfs)
177
1,440
32
Date
—
Mar. 23, 1994
Sept. 15, 1995
In addition, the monthly average stream flow for this two-year period is set forth below:
i
,- ' Month
January
Febmary
March
April
May
June
? . - J - . — • • • 1 = ^ 1 —
Mean Daily Discharge
(in cfs)
81
212
581
409
206
81
Month
July
August
September
October
November
December
Mean Daily, Discharge
(in cfs)
63
74
50
113
131
120
1665 river ou tech Itr rev 0 final NATURAL
RESOURCE
TECHNOLOGY
River OU-Technical Letter Report - Campmarina Former MGP Revision 0 3/22/2007
Section 1 - Introduction Page 10 of 30
During 1993 to 1995, highest average daily flow rate (581 cfs) occuned in March. The lowest average
daily flow rate (50 cfs) occuned in September. The variability in water levels and stream flow in the
Sheboygan River is the result of both snowfall accumulation (and the resulting spring mn off) and
precipitation during late spring/eariy summer.
The 1991 FEMA map indicates the 100 year floodplain is at Elevation 584 msl.
1.6 Dredging History
The U. S. Army Corps of Engineers (USAGE) Detroit District is responsible for maintaining a navigation
channel and tuming basin within the river downstream of the MGP Site. The upstream limit of the
USAGE navigation channel is located approximately 500 feet downstream of the MGP Site, just below
the Pennsylvania Avenue Bridge. From the Pennsylvania Avenue Bridge and extending approximately
2,300 feet downstream to near the Eighth Street Bridge, the channel has a project depth of 15 feet. The
remainder of the navigation channel (4,200 feet) downstream to the harbor has a project channel depth of
21 feet.
The Sheboygan Harbor was constructed at the mouth of the Sheboygan River in the early 1920s. In 1954,
part of the lower Sheboygan River (the channel upstream of the Eighth Street Bridge) was added to the
Sheboygan Harbor. The channel above Eighth Street (over 3,000 feet downstream of the MGP Site) was
dredged in 1956. No further dredging occuned. Between 1956 and 1969, a total of 404,000 cubic yards
of sediment were dredged downstream of the Eighth Street Bridge.
Maintenance dredging of the Sheboygan harbor last occuned in 1991 (1995, WDNR, Sheboygan River
RAP). Dredged materials were disposed of south of the harbor as part of a beach nourishment project.
According to the USAGE Detroit District web site, no dredging is planned in the Sheboygan River in
2007.
According to a June 2005 USAGE bathymetric survey of the Sheboygan River, water depths are much
shallower than the USAGE project depths. In this June 2005 survey, observed water depths within the 21
foot project depth portion of the channel were between 5 and 15 feet, while observed water depths within
the 15 foot project depth portion of the channel were between 4 and 7 feet.
1665 river ou tech Itr rev 0 final NATURAL RESOURCE
TECHNOLOGY
River OU-Technical Letter Report - Campmarina Former MGP Revision 0 3/22/2007
Section 1 - Introduction Page 11 of 30
NRT is unaware of any historic public or private dredging activities or bathymetric surveys upstream of
the Pennsylvania Avenue Bridge in the area of the River OU.
1665 river ou tech Itr rev 0 final NATURAL RESOURCE
TECHNOLOGY
River OU-Technical Letter Report - Campmarina Former MGP Revision 0 3/22/2007
Seciion 2 - Sheboygan River and Harbor Superfund Site Page 12 of 30
2 SHEBOYGAN RIVER AND HARBOR SUPERFUND SITE
2.1 Location and Description
The Sheboygan River and Harbor Site includes the lower 14 miles of the Sheboygan River from the '
Sheboygan Falls Dam, downstream lo, and including the Inner Harbor. The Sheboygan River is divided
inlo three sections based on physical characteristics (e.g., average depth, width), the Upper River, Middle
River and Lower River and Harbor. The lower River and Harbor was subdivided into the Lower River,
Inner Harbor and Outer Harbor. The following table summarizes the three river sections and the Inner
and Outer Harbor.
: . ' • : • . . *
Boundaries
Length
Upper River
Sheboygan Falls Dam downstream to Waelderhaus Dam
4 miles
Middle River
Waelderhaus Dam downstream to the former Chicago & Northwestern Railroad Bridge
7 miles
Lower River
The Fonner Chicago & Northwestem Railroad Bridge downstream to the Pennsylvania Avenue Bridge
3 miles
Inner Harbor
Pennsylvania Avenue Bridge downstream to the Rivers' ouflet to the Outer Harbor
Less than 1 mile
; : Outer Harbor
Breakwall immediately south of the River's mouth to approximately 2,000 feet north of the River's mouth
2,000 feet
1665 river ou tech Itr rev 0 final NATURAL
RESOURCE
TECHNOLOGY
River OU-Technical Letter Report - Campmarina Former MGP Revision 0 3/22/2007
Section 2 - Sheboygan River and Harbor Superfund Site Page 13 of 30
Nature of Sediment
Approx. River Width
Water Depth Range
Upper River
Discrete soft sediment deposits and non-soft sediment areas including a mixture of soft sediment. rocks, cobbles and bare river bottom
100 to 120 feet
Ranges from 0.1 to 9.5 feet (behind the dams)
Typically ranges from 2 to 4 feet
Middle River
Soft and non-soft sediment areas, soft sediment is shallower than the Upper River, and more widely scattered
100 feet
Less than 6 inches to 1 to 2 feet
Lower River
A more continuous layer of soft sediment exists (compared to Upper and Middle River). Generally where upstream soft sedimeni is deposited
150 feel to 300 feel as it approaches the
Harbor
Much of the Lower River is less than 5 feet
Inner Harbor
Similar lo the Lower River. Between Pennsylvania Avenue and S' Street Bridge there is relatively little deposition in recent years and evidence of scour. Net deposition occurs primarily between the 8* Street Bridge and the harbor mouth
250 feel
1 fool (along shore) to 20 feel, typically averaging 6 to 12 feet
Outer Harbor
Recently dredged by the USAGE in 1991 and 1992
Nol applicable
1 fool to 28 feel. typically averaging 12 lo 23 feel
The Campmarina River OU is located within the Lower River.
2.2 Remedial Investigation
An extensive remedial investigation (RI) was conducted on the Sheboygan River and Harbor. The initial
focus was on sediment and fish tissue sampling within the Sheboygan Harbor. In 1977, WDNR's routine
fish tissue sampling results reported elevated polychlorinated biphenyl (PCB) concentrations which
prompted USEPA and USAGE sediment sampling efforts. Sedimeni sample results reported elevated
concentrations of arsenic, lead, zinc, chromium, and PCBs. Beginning in 1987, Blasland, Bouck, & Lee,
1665 river ou tech Itr rev 0 final NATURAL
RESOURCE
TECHNOLOGY
River OU-Technical Letter Report - Campmarina Former MGP Revision 0 3/22/2007
Section 2 - Sheboygan River and Harbor Superfund Site Page 14 of 30
Inc. (BBL), on behalf of Tecumseh Products Company, initiated sediment sampling within the Sheboygan
River to evaluate PCB concentrations.
Groundwater at the Tecumseh plant, floodplain surface soil, water column and water fowl were sampled.
RI sampling results showed the upstream sections of the Sheboygan River are the source of PCB
concentrations observed in downstream sediment and water column samples (May 1990, BBL).
2.3 Risk Assessments
Human health and ecological risk assessments (aquatic and tenestrial) were performed by USEPA,
WDNR, and Tecumseh. These assessments concluded the main contaminant of concem in the Sheboygan
River and Harbor is PCBs. Metals also present a risk, however these concentrations are co-located with
PCBs.
The potential pathways of exposure were considered to be dermal contact, ingestion of contaminated
surface water or sediment, and consumption of fish contaminated by sediment. Due lo PCBs, the human
health pathway presented the primary risk at the Sheboygan River and Harbor Site. This risk was based
on the consumption of contaminated fish and nol dermal contact.
2.4 Sediment Transport Study
A Sedimeni Transport Study of the Lower River and Inner Harbor was perfonned to evaluate potential
deposition in the Inner Harbor (November 1996, BBL). The study focused on natural processes burying
contaminated sediments and assessed the feasibility of natural capping/recovery in the Inner Harbor. The
model was not intended to be a comprehensive chemical fate and transport study.
The analytical data showed the maximum PCB concentrations were generally at depth. Near surface PCB
concentrations were generally low, due to the depositional effects in the Inner Harbor. Therefore, the
modeling effort was used to evaluate the natural sedimentation processes and compared that with the
potential for future high-flow events lo erode the deposited material.
1665 river ou tech Itr rev 0 final NATURAL RESOURCE
TECHNOLOGY
River OU-Technical Letter Report - Campmarina Former MGP Revision 0 3/22/2007
Section 2 - Sheboygan River and Harbor Superfund Site Page 15 of 30
Extreme event simulations (i.e., 100-year flood) modeled with HEC-6 predicted the Inner Harbor is
expected to provide long-term stability and protectiveness. Relatively minor net scour (up to 1 foot) was
predicted in the vicinity of the Pennsylvania Avenue and against erosion. These scour events are nol
anticipated lo result in higher PCB exposures because the higher PCB concentrations are found at 4 feet
below the 1997 sediment surface level.
2.5 Feasibility Study
Three remediation objectives were listed for the Sheboygan River and Harbor (BBL, April 1998):
• Protect human health and the environment due to PCBs attributed to the Sheboygan River and Harbor Site;
• Mitigate potential PCB sources to the Shebogyan River and Harbor system and reduce PCB transport within the river system; and
• Remove and dispose of Confined Treatment Facility/Sediment Management Facility sediments and previously armored/capped PCB-contaminated soft sediment deposits.
To achieve these remediation objectives, the Feasibility Study contemplated the removal of PCB-
contaminated soft sediment so the average surface-weighted average concentration (SWAC) of PCBs in
the Sheboygan River is 0.5 parts per million (ppm).
Several remedial altematives were evaluated. Sediment altematives ranged from no action, monitored
natural recovery, sediment removal, and capping. Each altemative was compared to the nine criteria
described in 40 CFR Part 300.430.
2.6 Record of Decision
The Record of Decision (ROD) for the Sheboygan River and Harbor was issued by USEPA in May 2000.
Selected remedies include sediment removal in the Upper River, additional characterization and
monitoring in the Middle River, and additional characterization and potential removal subject to natural
and recreational disturbances in the Lower River and Inner Harbor.
1665 river ou tech Itr rev 0 final NATURAL RESOURCE
TECHNOLOGY
River OU-Technical Letter Report - Campmarina Former MGP Revision 0 3/22/2007
Section 2 - Sheboygan River and Harbor Superfund Site Page 16 of 30
Long-term monitoring of the remedial actions includes fish and sediment sampling to ensure achievement
of the SWAC tliroughout all of the Sheboygan River. In addition, the Lower River and Inner Harbor will
have annual bathymelric surveys lo identify areas susceptible lo scour. The USAGE'S most recent
bathymetric survey was performed in June 2005 (Condition of Channel for the Sheboygan Harbor in June
2005).
Applicable or Relevant and Appropriate Requirements (ARARs) and requirements To Be Considered
(TBCs) are provided beginning on page 88 of the ROD.
2.7 Schedule
According to the Fact Sheet, updated February 2007, for the Sheboygan River and Harbor Site (EPA
Identification number WrD980996367), Phase 11 Upper River soft sediment dredging operations were
performed in June 2006 through November 2006. Additional dredging in Phase II is to be performed in
May 2007 and is anticipated to go through October 2007. A total of 21,000 cubic yards (CY) of PCB
contaminated sediment is planned for removal in the Upper River.
Additional sample collection and characterization of soft sediment deposits for the Middle River, Lower
River, and Inner Harbor also will be performed in the summer of 2007. A schedule for addressing
sediment in the Inner Harbor was not mentioned in the Fact Sheet. Depending on the findings of
additional characterization in the Middle River and Lower River, the soft sediment deposits within the
Lower River may also require removal. The River OU of the former Campmarina MGP Site is located at
the downstream end of the Lower River.
1665 river ou tech Itr rev 0 final NATURAL RESOURCE
TECHNOLOGY
River OU-Technical Letter Report - Campmarina Former MGP Revision 0 3/22/2007
Section 3 - Previously Performed River OU Investigations and Results Page 17 of 30
3 PREVIOUSLY PERFORMED RIVER OU INVESTIGATIONS AND RESULTS
The following sections summarize known sediment investigations performed near or within the River
OU. Specific discussions regarding contaminant exposure pathways are included in Section 4.
3.1 BBL-1990
Beginning in 1987, BBL conducted sediment sampling for PCBs, VOCs, PAHs, and metals as part of the
Sheboygan River and Harbor Remedial Investigation. Sampling methodologies and results are detailed in
the Remedial Investigation/Enhanced Screening Report - Sheboygan River and Harbor (May 1990,
BBL). Fifteen (15) sediment samples were collected along the length of the river, with 10 samples being
collected above the Pennsylvania Avenue Bridge and 5 samples downstream of the bridge.
A number of sediment samples were collected near or just downstream of the MGP Site (sample locations
are provided in Appendix C). Three samples, R-98, R-lOO, and H-20, had oil or concentrations of PAHs.
Sample R-98 was collected near the downstream end of Boat Island and the sediment was described as
"oil saturated" from 2 to 6 feet below the sediment surface. Sediment samples R-lOO and H-20 were
collected immediately downstream of the Pennsylvania Avenue bridge. Sample R-lOO was described as
"oil saturated" from 4 to 6 feet below the sediment surface; however, neither sample R-98 nor R-lOO were
analyzed for PAHs. Sample H-20 was described as "oil saturated" from 4 to 16 feet below the sediment
surface and had a total PAHs concentration of 70 ppm in the 2 to 4 foot sediment sample. There was no
mention of elevated PAHs downstream of sample location H-20 and no mention of oil saturated
sediments was noted for samples R-99 andR-101, collected on the west side of Boat Island, opposite the
fonner MGP (May 1990, BBL).
3.2 WDOT-1993
In 1993, river sediment sampling was perfonned for the Wisconsin Department of Transportation
(WDOT) construction project on the Eighth Street Bridge. The bridge is located approximately 3,000 feet
1665 river ou tech In- rev 0 final NATURAL R E S O U R C E
T E C H N O L O G Y
River OU-Technical Lener Report - Campmarina Former MGP
Revision 0 3/22/2007
Section 3 - Previously Perfonned River OU Investigations and Results Page 18 of 30
downstream of the MGP Site (1993, RMT). PAHs were found in the sediments around the Eighth Street
Bridge in concentrations ranging from 5 to 97 ppm in the top 0 to 2 feet of sediment.
3.3 WDNR-1995
In Febmary 1995, WDNR collected one sediment sample within the River OU, approximately 20 to 30
feet from the shoreline, close to the downstream end of Boat Island (October 1995, WDNR). This sample
contained apparent coal tar and was analyzed for PAHs.
3.4 NRT-1998
NRT performed preliminary sediment investigations for WPSC in 1995 and 1996. Results are detailed in
the Sediment Investigation Report dated Febmary 26, 1998. Sediment sampling focused on identifying
the preliminary nature and extent of MGP residuals in river sediments or natural soil (parent material)
underlying the Sheboygan River. Sediment/soil samples were collected from as deep as 10.5 feet below
the bottom of the river, although in some locations parent materials were encountered beneath the soft
sediments, and this material was also sampled.
Further details regarding the methods for locating, poling, and sediment sampling are included in the
Sediment Investigation Report. The analytical results from NRT sampling efforts are tabulated in
Appendix B of this Technical Letter Report on Table 1 (Field Observations at Sediment Sample
Locations), Table 2 (Sediment Analytical Results - PAHs), Table 3 (Sediment Analytical Results -
BTEX), and Table 4 (Sediment Analytical Results - Cyanide, Phenol, Oil & Grease, Resource
Conservation and Recovery Act (RCRA) Metals & PCBs). Appendix A, Sheet 3 provides a summary of
the distribution of these constituents and the visual observations made during preliminary investigation
activities. Appendix B, Plate 2 provides cross sectional details of river sediment investigations and
Appendix B, Plate 3 provides a contour map of the depth to tar found in river sediments. The following
sections summarize the results of the NRT 1995 and 1996 activities.
1665 river ou tech Itr rev 0 final NATURAL RESOURCE
TECHNOLOGY
River OU-Technical Letter Report - Campmarina Former MGP
Revision 0 3/22/2007
Section 3 - Previously Performed River OU Investigations and Results Page 19 of 30
3.4.1 October 1995 Investigation Activities
During October 1995, NRT performed an initial sediment investigation to determine the absence/presence
of MGP residuals in the surficial soft sediments (unconsolidated non-parent material). The study
indicated the presence of benzene, toluene, ethylbenzene, and xylenes (BTEX) and PAHs in sediments
within the River OU, adjacent to, and downstream of, the Upland OU (November 1998, NRT).
The sample collection and screening methods are described in the Sediment Sampling Work Plan, Former
Sheboygan II Manufactured Gas Plant Site, Sheboygan, Wisconsin (August 1995, NRT). NRT conducted
the initial sediment sampling with a manually driven Ogeechee'' ' corer and a Ponar''"' grab dredge
sampler. The longest sediment core collected using the Ogeechee''''*^ corer was approximately 30 inches
long, while the Ponar^"^ grab dredge sampler typically collected the top six inches of sediment.
Six transects, consisting of 22 sample locations, were completed. These transects were identified as T701
through T706 and the sampling locations were labeled SD-701A through SD-706C (Appendix A, Sheet 3).
The following is a summary of field observations from the initial investigation:
• All six sediment sample transects showed indications of either odor or tar. Sediment samples SD-702A & B and SD-703A (Appendix A, Sheet 3) exhibited odors in sediments recovered in the hand-core samples. The samples were located within 25 feet of the shoreline.
• Sediment samples SD-701 A, SD-703B, SD-704A & B, SD-705A, B, & C, and SD-706B (Appendix A, Sheet 3) all exhibited coal tar in sediments recovered in the hand-core samples, or on the sounding pole (used to evaluate the depth of sediments present at a given location). These samples were within 20 feet of the shore at SD-701 and within 60 feet of the shore at SD-704 and SD-706. In transects T703 and T705, tar was noted 70 feet and 100 feet, respectively, out from shore.
3.4.2 November 1995/June 1996 Investigation Activities
Following the October 1995 study, NRT conducted a detailed field investigation in November 1995 and
June 1996 to evaluate the distribution of MGP constituents and sediment characteristics. A summary of
the field investigations, results, and recommendations is provided in the Sediment Investigation Report
(November 1998, NRT). A vibrocore sediment collection technique was used to collect the sediment
samples.
1665 river ou tech Itr rev 0 final NATURAL RESOURCE
TECHNOLOGY
River OU-Technical Letter Report - Campmarina Former MGP
Revision 0 3/22/2007
Section 3 - Previously Performed River OU Investigations and Results Page 20 of 30
Twelve transects were selected at locations starting approximately 375 feet upstream to approximately
900 feet downstream of the former MGP (Appendix A, Sheet 3 and Appendix B, Plate 2). The October
1995 transects were overlapped and extended. The new transects were identified as T701 through T712
and the sampling locations were labeled SD-701BV through SD-712BV. The transects did not extend
west past Boat Island to the river channel opposite the former MGP.
The following is a summary of findings from the November 1995 and June 1996 field investigations:
• Numerous sediment cores exhibited tar, sheen, or odors within 125 feet of the shoreline, as shown on Sheet 3 in Appendix A. Visual observations of tar, sheen, or odors extended approximately 1,300 to 1,600 feet along the shore beginning approximately 90 feet upstream of the former WPSC property boundary, along the former MGP (approximately 580 feet), and extending approximately 900 feet downstream of the former WPSC property boundary.
• Based on the depth at which tar and animal hair (the suspected source of animal hair is the former upstream tannery) were observed within the sediment, tar and animal hair were covered by natural sedimentation processes. Little river scour was observed through certain sections of this segment of the river. The depth to tar from field observations (Appendix B, Table 1) is shown on Appendix B, Plate 3. These field observations showed a thin layer where the tar is located within 1 foot of the sediment surface. Further downstream, past Center Avenue extended (i.e., approximately the southem property line of the former Campmarina MGP), tar was found more than 2 feet below the sediment surface.
• The sediment core logs showed approximately 2 lo 10 feet of soft river bottom sediments, including silt, sand, and organic material. No aquatic plants were found at any of the sample locations. The soft upper sediment layer is underlain by native glacial sediments, characterized by sands and red brown clay till.
3.5 Chemical Constituents in Sediment
The sediment sampling locations and PCB analysis conducted by BBL for the Sheboygan River and
Harbor RI, related to the Campmarina River OU, was summarized on a figure included in Appendix C.
A summary of the NRT analytical results from the 1995 and 1996 sediment sampling events are provided
in Appendix B, Table 2 (PAHs), Table 3 (BTEX), and Table 4 (metals, cyanide, PCBs, phenol, oil and
grease, and TOC). A distribution of BTEX and total PAH concentrations at each sample location is
1665 river ou tech Itr rev 0 final NATURAL RESOURCE
TECHNOLOGY
River OU-Technical Letter Report - Campmarina Former MGP
Revision 0 3/22/2007
Section 3 - Previously Performed River OU Investigations and Results Page 21 of 30
provided in Appendix A, Sheet 3. Laboratory results from the 1995 and 1996 Site investigations show
low concentrations of PCBs, RCRA metals, cyanide, and phenol.
3.5.1 BTEX and PAH Results
Total BTEX ranged from ND to 710 ppm, while total PAHs ranged from ND to 9,294 ppm, in sedimeni
samples collected and analyzed by NRT. Generally, high concentrations of BTEX co-occuned with high
PAH concentrations.
Based on the BTEX and total PAH analytical laboratory results, the highest concentrations were found at
depth; as indicated by NRT cores SD-702BV, SD-702CV, SD-704BV, and SD-705BV (Appendix
A, Sheet 3 and Appendix B, Tables 2 and 3). These sediment cores are all located adjacent to, and just
downstream of, the former MGP Site. The depths at which these samples were collected ranged from
approximately 2 lo 10 feet below the sediment surface. The deepest occunences of tar were present in
transects T704 and T705.
As discussed in Section 3.1, BBL also collected a sediment sample for PAH analysis at location H-20
(Appendix C) (just downstream of the Pennsylvania Avenue Bridge). The sample collected 2 to 4 foot
below the sediment surface had a total PAH concentration of 70 mg/kg (May 1990, BBL).
Visual observations of (Appendix A, Sheet 3) lar, sheen, and odors were found to extend approximately
900 feet downstream of the former MGP; however, the analytical results from sediment sample
SD-71 lAV showed constituents of concem may have migrated only approximately 580 feet downstream.
BTEX and total PAH concentrations in samples downstream of transect T705 (approximately 450 feet
upstream of transect T7] 1) are significantly lower than the concentrations reported in samples from
transects T702, T704, and T705, which were immediately adjacent to the fonner MGP. Additionally, the
results showed that sediments with MGP residuals, especially downstream of transect T705, were buried
below other non-native sedimeni (Appendix B, Plate 2 and 3). Sedimeni samples collected upstream of
the former MGP (from SD-708AV & BV and SD-709AV), and approximately 900 feet downstream
(SD-712AV and BV) of the former MGP, did not exhibit elevated BTEX or total PAH concentrations.
1665 river ou tech Itr rev 0 final NATURAL RESOURCE
TECHNOLOGY
River OU-Technical Letter Report - Campmarina Former MGP
Revision 0 3/22/2007
Section 3 - Previously Performed River OU Investigations and Results Page 22 of 30
3.5.2 Metals Results
NRT submitted three samples from its preliminary sedimeni investigations for laboratory analysis of
RCRA metals (Appendix B, Table 4) from locations where animal hair (suspected tannery waste) was
present. Sample results showed generally low levels of metal constituents (Appendix B, Table 4).
Chromium and lead contamination are common constituents associated with tannery wastes.
Concentrations of chromium and lead were detected ranging from 7.4 to 500 ppm and 28 to 140 ppm,
respectively. No other sedimeni samples were characterized for metals.
Table 1 of the ROD issued in May 2000 by USEPA for the Sheboygan River and Harbor Superfund
Project indicates that metals contamination ranges from non-detect to 300 ppm in the Upper, Middle, and
Lower river sections. Maximum concentrations of chromium and lead detected were 143 ppm and 293
ppm, respectively.
3.5.3 PCB Results
NRT submitted three samples for laboratory analysis of PCBs (Appendix B, Table 4). The PCB
concentrations detected in the sediment samples from the Site ranged from 0.42 ppm lo 2.3 ppm.
PCB concentrations found upstream of the former MGP, as part of the Sheboygan River and Harbor
Superfund Project (October 1995, WDNR), ranged between non-detect up lo 4,500 ppm. PCB
concentrations detected adjacent to the former MGP Site as part of the BBL 1987 investigation (samples
R95, R99, RlOl, and R98) ranged between non-detect up to 2.3 ppm (May 1990, BBL). PCB
concentrations detected downstream of the MGP Site as part of the BBL 1987 investigation (sample
RlOO) ranged between non-detect up to 67 ppm (May 1990, BBL) (Appendix C).
3.5.4 Cyanide and Phenol Results
Thirteen sediment samples were analyzed for total cyanide, weak acid dissociable cyanide, and phenol in
October and November 1995 (Appendix B, Table 4). There was no blue/black sheen and/or blue/black
wood chips were observed in the sediments. The total cyanide were detected in 5 of 13 sediment samples
at concentrations ranging from 0.59 to 8.7 ppm. Weak acid dissociable cyanide was detected in 3 of 13
1665 river ou tech Itr rev 0 final NATURAL R E S O U R C E
T E C H N O L O G Y
River OU-Technical Letter Report - Campmarina Former MGP
Revision 0 3/22/2007
Section 3 - Previously Performed River OU Investigations and Results Page 23 of 30
sediment samples at concentrations ranging from 0.51 to 3 ppm. Phenol was present in only 4 of 13
sediment samples at concentrations ranging from 0.19 to 48 ppm.
Cyanide and phenols were not tested for as part of the Sheboygan River and Harbor Superfund site
investigations, as such no data is available for these contaminants.
3.6 Chemical Constituents in Surface Water
Surface water chemistry data for conventional pollutants (i.e., nutrients, solids, bacteria, etc.) are collected
on a nearly monthly basis in the Sheboygan River at the Esslingen Park sampling location by the WDNR.
Esslingen Park is located approximately 1.5 miles upstream of the Former MGP Site. PAHs, BTEX,
RCRA metals, PCBs, cyanide, and phenols are not routinely measured in the Sheboygan River.
Table 3 of the USEPA ROD for the Sheboygan River and Harbor Superiiind site (May 2000, USEPA)
showed PCB concentrations in surface water ranged from non-delecl (<0.05 parts per billion [ppb]) to
0.77 ppb during an interim PCB removal action conducted several miles upstream in 1989 and 1990.
1665 river ou tech Itr rev 0 final NATURAL RESOURCE
TECHNOLOGY
River OU-Technical Letter Report - Campmarina Former MGP Revision 0 3/22/2007
Section 4 - Remedial Actions Performed Page 24 of 30
4 REMEDIAL ACTIONS PERFORMED
No remedial actions have been performed lo dale in the River OU.
During the 2001 Upland OU soil remediation activities (February 2003, NRT), approximately 670 feet of
river bank was excavated and reconstructed lo provide stmctural support for the geosynthetic cover and
future park stmctures. Excavation operations generally were limited to material above the groundwater
table and/or shoreline. The following activities were conducted to reconstruct the river bank:
• Existing riprap that with a visually clean surface was removed and segregated for reuse;
• An old 30-fool long, ten-inch diameter pipe, mnning parallel lo the river, that connected to a wooden crock, were both removed and properly disposed in a landfill. The pipe and crock exhibited MGP odors;
• The former retaining wall along the river was cut and removed at the approximate river elevation;
• Excavation operations extended lo the planned design 580 feet msl elevation with the exception of one area located midway along the river bank. MGP-related contamination and evidence of coal tar-like materials were observed in soils at approximately 8 to 10 feel bgs in the central portion of EZ-4 excavation. In order to address the area, an 88 feel by 10 feel area was excavated to elevation 578 feet msl. Excavation operations did not extend lower than the 578 feel msl elevation due to the close proximity of the river. The location of the deeper excavation zone is indicated on Sheet C040 in Appendix D;
• Excavation base samples (EZ-401 through EZ-405) were sampled al the 580 feet msl elevation with the exception of EZ-403, which was sampled at approximately the 578 feet msl elevation. The sampling documented the near shore sediment conditions outside the perimeter of the vertical banier wall; and
• The riverbank was restored with filter gravel, stmctural fill, and riprap. Approximately 2 feet of structural fill was placed in the over-excavaied area from elevation 578 feet msl to 580 feet msl. A non-woven geofabric and six inches of filter gravel were placed over the fill along the base of the riverbank (elevation 580 feet). A second layer of filter fabric was placed over the filter gravel followed by stmctural fill that was compacted to restore the river bank at a slope of approximately two feet horizontal to one fool vertical (2H: 1V). Riprap was then placed along the restored river bank as shown on Sheet C040 in Appendix D.
1665 river ou tech Itr rev 0 final NATURAL RESOURCE
TECHNOLOGY
River OU-Technical Letter Report - Campmarina Former MGP
Revision 0 3/22/2007
Section 4 - Remedial Actions Performed Page 25 of 30
At EZ-4, the soil/sedimenl quality was analyzed for total BTEX/benzene, total PAHs/naphthaiene and
total cyanide/lead. The results are summarized in Appendix D, Table 2 and Figure 5 and indicate residual
concentrations of benzene, naphthalene, total lead, and total cyanide. These residual concentrations are
effectively capped with up to 6 feel of clean compacted stmctural fill. As stated in the Documentation
Report (Febmary 2003, NRT), the remaining material will be considered as part of future sediment
management work.
1665 river ou tech Itr rev 0 final NATURAL R E S O U R C E
T E C H N O L O G Y
River OU-Technical Letter Report - Campmarina Former MGP Revision 0 3/22/2007
Section 5 - Identified River OU Pathways and Conclusions . Page 26 of 30
5 IDENTIFIED RIVER OU PATHWAYS AND CONCLUSIONS
As discussed in Seciion 1.1, remedial actions have been performed in the Upland OU and assessment of
the appropriate Upland OU exposure pathways are discussed in the Upland OU Technical Letter Report.
5.1 River OU Potential Exposure Scenarios and Receptors
A qualified risk assessor will perform a Site reconnaissance to assist in developing the Work Plan (WP)
for the River OU RI. As part of the Site reconnaissance, a biological habitat assessment will be
performed and the sunounding land use and access to the River OU will be noted. The results of the Site
reconnaissance will be used to refine the Campmarina River OU CSM.
Potential exposure scenarios and receptors to be evaluated in the River OU WP include:
5.1.1 Recreational Land Use Scenario - Visitor/Trespasser
A visitor may be potentially exposed to constituents of potential concem (COPCs) in surface water and
sediment while swimming, wading, fishing, or boating in the Sheboygan River, adjacent to the former
MGP facility. The potential exposure scenarios to be evaluated include incidental ingestion and dermal
contact with surface water and/or sediment from the Sheboygan River.
5.1.2 Benthic Invertebrates - Aquatic Ecological Receptor
Benthic invertebrates form the base of many food chains and spend most or all of their life-cycle
burtowed or feeding just at the interface between surface water and sediment. Benthic invertebrates may
be potentially exposed to COPCs in surface waler and sediment in the Sheboygan River, adjacent to the
former MGP facility. The potential exposure scenarios to be evaluated include ingestion and dermal
exposure with surface water and/or sedimeni from the Sheboygan River.
1665 river ou tech Itr rev 0 final NATURAL RESOURCE
TECHNOLOGY
River OU-Technical Letter Report - Campmarina Former MGP
Revision 0 3/22/2007
Section 5 - Identified River OU Pathways and Conclusions Page 27 of 30
5.1.3 Other Ecological Receptors
Other species may be exposed to COPCs in sediment and/or surface water from the Sheboygan River.
The need to carry forward additional ecological receptors from higher trophic levels (e.g., fish) will be
evaluated based on the biological habitat assessment and the results from previously collected chemical
concentrations in surface water and/or sediment. If the biological habitat assessment indicates there is
limited habitat area within the Sheboygan River adjacent to the former MGP facility, additional
ecological receptors will not be canied forward.
5.2 Additional Data Needs Summary
Additional River OU RI activities will focus on the following objectives:
Evaluate the nature and extent of MGP residuals in near-shore sediment; i • ^ F ' "
Assess potential human health and ecological risk related to MGP residuals in sediment;
Evaluate the nature and extent of non-MGP related constituents;
Perform river water sampling lo evaluate if conditions exist that may pose a risk to human health and the environment;
Evaluate whether Boat Island wananls characterization;
Collect additional Site data to support a feasibility study; and
If a remedial action is necessary, establish acceptable remediation goals.
As described in Section FV, Task 1(B) and (C), the above work elements will be discussed in a Technical
Scoping Meeting to be held within seven to fourteen business days after submitting this River OU
Technical Letter Report. The River OU Work Plan will be submitted within 90 days of receipt of the
Technical Scoping Meeting summary. A River OU project specific schedule for RI/FS tasks will also be
included in the RI/FS Work Plan.
1665 river ou tech Itr rev 0 final NATURAL RESOURCE
TECHNOLOGY
River OU-Technical Letter Report - Campmarina Former MGP Revision 0 3/22/2007
Section 6 - References Page 28 of 30
6 REFERENCES (RECORD FILE)
1990 May, Blasland, Bouck and Lee, Inc. Remedial Investigation/Enhanced Screening Report, Sheboygan River and Harbor, Sheboygan Wisconsin.
1991 April, Washington State Department of Ecology, Sediment Management Standards, Chapter 173-204 WAC.
1991 December, Wisconsin Department of Natural Resources, Conditional Approval of "Work Plan, Phase 1 Site Investigation, Manufactured Gas Plant Site, Sheboygan, Wisconsin".
] 992 February, Wisconsin Department of Natural Resources, Final Statement of Work for the Sheboygan Gas Plant Investigation.
1992 April, Wisconsin Department of Natural Resources, Campmarina, The Former Coal Gas Facility Operated by Wisconsin Public Service Corporation and Owned By the City of Sheboygan located in Sheboygan, Wl", Section 144.442, Wis. Stats. CONTRACT, Contract Number SF-91-04.
1992 June, Simon Hydro-Search, Phase I Environmental Investigation of Manufactured Gas Plant Site, Sheboygan, Wisconsin, Project No. 453114843.
1992 July, Blasland, Bouck and Lee, Inc. Alternatives Anay Document, Tecumseh Products Company, Sheboygan Falls, Wisconsin.
1992 November, Simon Hydro-Search, Phase 11 Work Plan - Environmental Investigation Manufactured Gas Plant Site, Sheboygan , Wisconsin, Project No. 304533034.
1993 RMT, Inc., Subsurface Investigation Summary Report and Work Plan, Wisconsin Department of Transportation ID No. 4996-00-40, 8* Street Bridge, Sheboygan, Wisconsin.
1994 June, Natural Resource Technology, Inc., Sediment Sampling Work Plan - Former Manufactured Gas Plant Site, Sheboygan II, Wisconsin, Project No. 1060.
1995 April, WPSC, Letter to Ms. Margaret Graefe (Wisconsin Departmenl of Natural Resources) Phase II Environmental Investigations Sheboygan I and II Former Manufactured Gas Plant Sites, Project No. 1033.
1995 August 31, Natural Resource Technology, Inc., Sediment Sampling Work Plan Former Manufactured Gas Plant Site, Sheboygan, Wisconsin, Project No. 1060.
1995 October, Wisconsin Departmenl of Natural Resources, Sheboygan River Remedial Action Plan, A Plan lo Clean Up Sheboygan Area Rivers and Harbor.
1665 river ou tech Itr rev 0 final NATURAL RESOURCE
TECHNOLOGY
River OU-Technical Letter Report - Campmarina Former MGP
Revision 0 3/22/2007
Section 6 - References Page 29 of 30
1996 June 28, Natural Resource Technology, Inc., Phase II Environmental Investigation Report, Former Manufactured Gas Plant Site, North Water Street, Sheboygan, Wisconsin, Project No. 1060.
1996 November, Blasland, Bouck and Lee, Inc. Sediment Transport Study, Sheboygan River and Harbor, Sheboygan Wisconsin.
1997 July, United States Army Corps of Engineers, Condition of Channel for Inner and Outer Harbor.
1998 April, Blasland, Bouck and Lee, Inc. Feasibility Study Report, Sheboygan River and Harbor, Sheboygan Wisconsin.
1998 November, Natural Resource Technology, Inc., Sediment Investigation Report Former Manufactured Gas Plant Site, Sheboygan, Wl, Project No. 1183.
1998 December, Natural Resource Technology, Inc., Feasibility Study Work Plan Campmarina, Former Coal Gas Facility, Wisconsin Public Service Corporation, Sheboygan, WI, Project No. 1313.
1999 MacDonald, D.D. and M. MacFarlane. (Draft). Criteria for managing contaminated sediment in British Columbia, British Columbia Ministry of Environment, Lands, and Parks. Victoria, British Columbia. .
1999 May, Natural Resource Technology, Inc., Feasibility Study Campmarina, Former Coal Gas Facility, Wisconsin Public Service Corporation, Sheboygan, Wl, Project No. 1313.
1999 October, Wisconsin Department of Natural Resources, Campmarina - Former Coal Gas Facility, Sheboygan, Wisconsin, Feasibility Study for the Campmarina-Former Coal Gas Faciliry approval letter.
2000 February, Natural Resource Technology, Inc., Remedial Work Plan Phase I, Excavation and Grading Campmarina and Center Avenue Right-of-Way, Former Coal Gas Facility, Sheboygan, VV/Project No. 1313.
2000 March, Natural Resource Technology, Inc., Pilot Test Work Plan, Campmarina and the Center Avenue Right-of-Way, Sheboygan, WI, Project No. 1313.
2000 April, Natural Resource Technology, Inc., Phase II Remedial Work Plan, Campmarina and Center Avenue Right-of-Way, Former Coal Gas Facility, Sheboygan, Wisconsin, Project No. 1313.
2000 May, United States Environmental Protection Agency Superfund, Record of Decision, Sheboygan River and Harbor, Sheboygan, Wisconsin.
2000 June, United Stales Army Corps of Engineers, Sheboygan Harbor, Wisconsin, Condition of Channel.
1665 river ou tech Itr rev 0 final NATURAL R E S O U R C E
T E C H N O L O G Y
River OU-Technical Letter Report - Campmarina Former MGP
Revision 0 3/22/2007
Section 6 - References Page 30 of 30
20(X) July, Wisconsin Public Service Corporation Letter to Susan Schumacher (Wisconsin Departmenl of Natural Resources) Affidavit for the "Notice of Proposed Grading" for Camp Marina Site in Sheboygan, Wl, Project No 1313.
2000 July, MacDonald, D.D., C.G. Ingersoll, and T.A. Berger. Development and evaluation of consensus-based sediment quality guidelines for freshwater ecosystems. Arch. Environ. Contam. Toxicol. 39:20-31.
2000 July, Wisconsin Departmenl of Natural Resources, Phase I and Phase 2 Remedial Work Plan Approval, Campmarina and Center Avenue Right of Way, Sheboygan, file reference FID #460134950 ERR-ERP, BRRTS #0260000095.
2001 January, Wisconsin Department of Natural Resources, Record of Decision, Campmarina, the Former Sheboygan Coal Gas Site, Remedial Action Operable Unit for Upland Area.
2003 Febmary, Natural Resource Technology, Inc., Phase 1 and II Remedy Documentation Report, Campmarina Former Coal Gas Facility, Sheboygan, Wisconsin, Project Number 1312.
2003 December, Natural Resource Technology, Inc., 2003 Annual Operation Maintenance, ami Monitoring Report Former Wisconsin Public Service Corporation Manufactured Gas Plant Site, Campmarina And Center Avenue Right-of-Way, Sheboygan, Wisconsin, FID #400134950, DNR Activity #02-60-000095.
2004 July, Natural Resource Technology, Inc., Remedial Investigation/Feasibility Study Work Plan, Campmarina Former MGP Site, Sheboygan, Wisconsin, Project Number 1665.
2004 August, Wisconsin Department of Natural Resources, Preliminary Comments of Remedial Investigation/Feasibility Study Work Plan, Campmarina Fonner MGP Site, Sheboygan, Wisconsin, FID #400134950, DNR Activity #02-60-000095.
2004 December, Natural Resource Technology, Inc., 2004 Annual Operation Mainteruince, and Monitoring Report Former Wisconsin Public Service Corporation Manufactured Gas Plant Site, Campmarina And Center Avenue Right-of-Way, Sheboygan, Wisconsin, FID #4(X)] 34950, DNR Activity #02-60-000095.
2005 November, Natural Resource Technology, Inc., 2005 Annual Operation, Maintenance, and Monitoring Report Former Wisconsin Public Service Corporation Manufactured Gas Plant Site Campmarina and Center Avenue Right-of-Way, Sheboygan, Wisconsin.
2007 January, United States Environmental Protection Agency, Administrative Settlement Agreement and Order on Consent for the Remedial Investigation and Feasibility Study for the WPSC Campmarina Site in Sheboygan, Wisconsin, Docket V-W-07-C-862.
1665 river ou tech Itr rev 0 final NATURAL RESOURCE
TECHNOLOGY
0
I N
SOURCE: USGS 7 .5 MINUTE QUADRANGLE, SHEBOYGAN NORTH AND SOUTH. DATED 1 9 5 4 . PHOTOREVISED 1 9 7 3 . OUADRANCLE LOCATION
0 2000 4000
SCALE IN FEET CONTOUR INTERVAL 10 FEET
N R
Natural Resource Technology
SITE LOCATION MAP CAMPMARINA FORMER COAL GAS FACILITY WISCONSIN PUBLIC SERVICE CORPORATION
SHEBOYGAN, WISCONSIN
DRAWN BY: TAS APPROVED BY: JMK DATE: 04 /23 /04
PROJECT NO. 1665
DRAWING NO. 1665-A01
FIGURE NO. 1
NEW YORK A
CD -* — 2
z -• W I
- I VI £ lyi _. I/) n
^ X 3 to 2 r
•" L.J "" lO *"
O ? X O ^ u
> -J c
o m ^ m i£
OJ 31 -S -
»_ H- U
? =h M _ £ (/I CO 3
7 ]
^ ^
m
> o ^ H n > 33 Z
S
n 5
1 1
• " 3
=°S o 2 T I E m m
^1
1 1
1 1
X
w o :a
> !3 TO C
o - t
33
m
« 2: § t / i -< ^ O
X
> 5
o
CO O
in I X(/, O ^ H : o o
g o z >
> o
V
|— m CD m
o
o
NATURAL RESOURCE TECHNOLOGY
HISTORICAL SITE LAYOUT TECHNICAL LETTER REPORT-RIVER OU
CAMPMARINA FORMER MGP SITE WISCONSIN PUBLIC SERVICE CORPORATION
SHEBOYGAN, WISCONSIN
DRAWN BY: BJK
CHECKED BY: HMS
APPROVED BY: JMK
DATE: 03/12/07
DATE: 03/20/07 DATE; 03/22 /07
DRAWING NO: 1665-3-BOl REFERENCE:.
APPENDIX A
MEDIAL INVESTIGATION/FEASIBILITY STUDY WORK PLAN, NMT JULY 2(1
H
!
/ •
LEGEND « "w-'«
» PZ-70,
y ^ "
« o o o
O
MONITORING WELL
PIEZOMETER
STAFT GAUGE
TDEES
RIPRAP
UGHT POLE
FORMER CAMPUARINA PROPERTY BOUNDARY
BARRIER
RWERS EDGE
SOURCE NOTES: 1. PORTIONS OF THIS DRAWING SH WERE DEVaOPEO FROU DRAWING HLE
CAMPPLAN.DWG DATU) 1 /4 /00 OBTAINED FROU THE CITY OF SHEBOYGAN. 2. SURVEY OF CONTAINMENT B«?RRIER BT RETTirR CORPORATION. UARCH 2001,
DtGfTAL RLE TOPO022B01.DWG. 3. PORTIONS OF THIS DRAWING SET WERE DEVELOPED FTTOU DRAWING RLE
NRT-AERIALDWG E-WWLED 1/13/04 FROM THE CfTY OF SHEBOYGAN. 4. MONITORING WELLS SURVEYED BY ROBERT E. LEE & ASSOCUVTES SUFMMNG.
FEBUARY 2004. SHEBOYGAN COUNTY COORDINATE SYSTEM ANO (WVDSS VERTICAL MTUM.
5. SEDIMENT SAMPLES nELD MEASURED BY NRT. 1995.
DATUM (FT)
IGLD
5 7 9 . 8
USGS
581
CITY OF SHEBOYGAN
0 —a-2—
0 25 50 100
SCALE IN FEET
N R T
Natural Resource Technology
SITE PLAN Rl/FS WORK PLAN
CAMPMARINA V/ISCONSIN PUBUC SERVICE CORPORATION
SHEBOYGAN. WISCONSIN CAD Fl-E: 1665\2-SED\1665-2-D01.DWG
REFERENCE HLES:
PROJECT NO. 1665/2.0
DRAWN BY: RLH 05/10/04 CHECKED BY:
JTB
APPROVED BY: JMK 03/20/07
SHEET NO. 1
H^
^
LEGEND
e c o o
o
— —
— . . . —
TREES
RIPRAP
UGHT POLE
FORMER MGP STFUCTURES
FORMER CAMPMARINA PROPERTY BOUNDARY
COHTAINMENT BARRIER
RWERS EDGE
/ r
SOURCE NOTES: 1. PORTIONS OF THIS DRAWING S O WERE DEVELOPED FTTOM DRAWING FILE
CAMPPLAN.DWG DATED l / 4 / O O OBTAINED FROU THE CFTY OF SHEBOYGAN. 2. SUTrV€t OF CONTAINMENT BfRRRIER BY RETTLER CORPORATION. MARCH 2 0 0 1 .
DIGITAL RLE TOP0022801.DWG. 3. PORTIONS OF THIS DRAWING S O WERE DEVELOPED FROM DRAWING RLE
NRT-AERlAL-DWG E-UAJLED 1 / 1 3 / 0 4 FROM THE CITY OF SHEBOYGAN. 4. UONITORINC WELLS SURVEYED BY ROBERT L LEE * ASSOCIATES SURVEYING.
FIBUARY 2004 . SHEBOYGAN COUNTY COORDINATE SYSTEM AND NAVD88 VERTICAL DATUM.
5. SEDIMENT SAMPLES RELD MEASURED B f NRT. 1996.
25 50
DATUM (FT)
IGLD
579.8
USGS
581
CITY OF SHEBOYGAN
0
100
SCALE IN FEET
N R T
Natural Resource Technology
FORMER MGP STRUCTURE LOCATIONS Rl/FS WORK PLAN
CAMPMARINA WISCONSIN PUBLIC SERVICE CORPORATION
SHEBOYGAN, WISCONSIN CAD FILE: 1665\2-SED\1665-2-D02.DWG REFERENCE FILES:
PROJECT NO. 1665/2.0
DRAWN BY: RLH 05/10/04 CHECKED BY:
JTB
APPROVED BY: JMK 03/20/07
SHEET NO.
I aP-TUAV I DATT I DEfTH I BTEX I ID-7J1AV I t n t / } 9 H I 11.41 I ND
'•"••'•. V ' . ^ ^ ^ ^ i M ' v l l ; -,
i£C£HQ
B A M T U L0CAT10r< S A M I U m
DATE DATS SAMTLE COLLECTZD
DETTH IAMFUDET™
BTEX Teal BTEX
F A R S
ToilPAhl
T705 TRANSECT BASE
• S0-704C SEDIMENT SAMPLE (HAND CORED)
SD-702BV yrx SEDIMENT SAMPLE
' ° ' (VIBROCORE)
MW-70E MONITORING WELL
... PZ-701
<B PIEZOMETER
® TREES
O O O RIPRAP
•0- UGHT POLE
Q
APPROXIMATI LOCATION OF SHEEN
APPROXIMATE LOCATION OF SHEEN AND ODOR
APPROXIMATE LOCATION OF SHEEN, ODOR. AND TAR
FORMER CAMPMARINA PROPERTY BOUNCMRY
CONTAINMENT BARRIER
RIVERS EDGE
WTVJH (FO IGLD
579.8
USGS
561
CITY o r SHEBOYGAN
0
25 a-2— 50 100
SCALE IN FEET
Natural Resource Technology
PREVIOUS SAMPLING LOCATIONS, DISTRIBUTION OF BTEX AND TOTAL PAH AND VISUAL OBSERVATIONS
RI /FS WORK PLAN CAMPMARINA
WISCONSIN PUBLIC SERVICE CORPORATION SHEBOYGAN, WISCONSIN
CAD FILE: 1 6 6 5 \ 2 - S E D \ 1 6 6 5 - 2 - D 0 3 . D W G
REFERENCE RLES:
PROJECT NO. 1 6 6 5 / 2 . 0
DRAWN BY: RLH 0 5 / 1 0 / 0 4
CHECKED BY: JTB
APPROVED BY: JMK 0 3 / 2 0 / 0 7
SHEET NO.
APPENDIX B
SEDIMENT INVESTIGATION REPORT, NRT FEBRUARY 1998
H
Table 1. Field Observations at Sediment Sample Locations Former Sheboygan II MGP Site - WPSC
1 Sample Number**
1 BKG-700 SD-701 A SD-701 B SD-701 BV
SD-701 C SD-702A SD-702B SD-702BV SD-702C SD-702CV
SD-702DV
SD-703A SD-703B SD-703BV SD-703C SD-703CV
SD-703D SD-704A SD-704B SD-704BV
SD-704C SD-704CV
SD-704D SD-705A SD-705B SD-705BV
SD-705C SD-705CV
SD-705D SD-705DV
SD-705E
SD-706A
SD-706B SD-706BV
SD-706C SD-706CV
SD-707AV
Sample Date
10/16/95 10/17/95 10/17/95 06/11/96
10/17/95 10/16/95 10/16/95 11/05/95 10/16/95 06/11/96
06/13/96
10/17/95 10/17/95 06/13/96 10/17/95 06/18/96
10/20/95 10/17/95 10/17/95 06/11/96
10/17/95 06/17/96
10/20/95 10/18/95 10/18/95 11/05/95
10/18/95 06/17/96
10/18/95 06/11/96
10/20/95
10/18/95
10/18/95 06/17/96
10/18/95 06/18/96
11/04/95
Depth to Sediment / Water Interface
(inches)
nm 37 40 54
43 44 26 nm 67 61
62
40 47 63 58 78
68 37 51 70
64 74
57 46 67 nm
71 84
61 80
46
24
100 84
66 59
nm
Sedimeni Elevation above MSL
(feel)
nm 578.92 578.67 577.50
578.42 578.33 579.83
nm 576.42 576.92
576.83
578.67 578.08 576.75 577.17 575.50
576.33 578.92 577.75 576.17
576.67 575.83
577.25 578.17 576.42
nm
576.08 575.00
576.92 575.33
578.17
580.00
573.67 575.00
576.50 577.08
nm
Sample Interval
(inches)
0-15 0-31 0-10 0-26 26-34 34-44 44-45 45-47 47-49
0-8 0-16.75 0-15.25
0-86 0-3
0-27 27-64 64-89 0-17 17-43 43-57 57-61 61-67 67-75 75-82 82-91
91-100 0-19 0-14 0-95 0-23 0-43
43-68 68-80 0-10
0-17.5 0-23 0-17 17-28
28-102 102-108 108-116
0-21 0-49
49-67 67-76 76-86 86-93
0-3 0-14
0-18.8 0-15 15-21 21-26 26-45 45-47 47-50 50-53 53-58 4-12 0-50
50-112 112-117 117-126
0-10 0-24
24-36 36-54 0-9.5
0-3
0-11 0-13 13-31 31-36 0-11 0-4
4-11 11-19 19-24 24-32 32-44 44-46 46-59 59-81 0-15 15-23 23-35 35-48 48-60 60-74
PID Reading
4.6 22 0 na na na na na na 0
1667 0 na 1.2 na na na na na na na na na na na na
72.7 4.7 na 8.1 na na na
13.6 7.1
43.1 na na na na na 6.4 na na na na na na 4.7 23.9 207 18
13.1 56.1 81.6 40.1 36
14.5 18.5 na na na na 7.3 na na na 7.5
na 16.9 na na na
21.9 na na na na na na na na na
10.3 9.1 14.3 41 34
14.6
Assay Result
1.57 HI
2.37 na na na na na na 2.1 1.83 1.71 na
1.57 na na na na na na na na na na na na HI
1.95 na
0.93 na na na
1.77 29.95
HI na na na na na
1.37 na na na na na na HI HI na na na na na na na
na HI na na na na
2.13 na na na
1.91
na 2.7 na na na
ND na na na na na na na na na na na na na na na
Filed Observations
Hair Odor
... yes
...
... „ .
yes yes yes yes
yes
yes
.... yes yes yes yes
...
... yes yes
...
... yes yes
yes yes yes
yes
...
...
...
...
... yes
yes yes
yes yes yes yes
yes yes yes
yes yes yes
yes ... ...
yes ... ... ... ... ...
yes „ .
...
... yes
yes yes
... yes
yes yes
...
...
...
... - . ... ... ... ... ... ...
yes
...
... yes
...
...
...
...
...
...
...
...
... yes yes — ... ... ... ... ... ... ... — ... ... ... ... ... ... . . .
i Sheen
1
1 1 1 1 1
1 1
j yes I yes
yes
...
I
1 ... ...
1 -1 1
1 ...
...
... yes
...
...
...
...
...
...
...
...
...
...
...
...
...
...
...
... 1 —
... — ... ... ... ... ... ... ...
...
...
... yes yes
...
...
yes yes
...
... yes^-
___ yes yes yes
...
...
1 i 1 1 1
I ... ...
yes yes ...
yes ...
Tar
... yes
...
...
... yes yes yes yes
... —
yes
... .... yes yes
... yes yes yes yes
...
...
... yes
.__
...
...
...
...
...
yes
yes yes
...
.__ •
... yes yes yes yes yes
yes ... ... ...
yes yes
... yes
yes
.__
...
... yes
...
...
...
...
... yes
— ... ... ... ... ...
yes
...
...
...
...
...
yes
yes
1665 sediment tables compared to PEC.xIs Page lof 2 Table 1 - Field Observations
Table 1. Field Observations, Continued
Sample Number**
SD-707BV
SD-707CV
SD-708AV
SD-708BV
SD-709AV
SD-71 OAV
SD-71 OB V
SD-71 OCV
SD-71 lAV
SD-71 IBV
SD-71 ICV
SD-712AV
SD-712BV
Sample Date
11/04/95
06/10/96
11/04/95
06/10/96
11/04/95
06/18/96
06/18/96
06/18/96
06/18/96
06/18/96
06/18/96
06/18/96
06/18/96
Depth lo Sediment / Water Interface
(inches)
nm
75
nm
82
nm
106
78
59
109
80
58
no
124
Sediment Elevation
above MSL
(feet)
nm
575.75
nm
575.17
nm
573.17
575.50
577.08
572.92
575.33
577.17
572.83
571.67
Sample Interval
(inches)
0-5 5-14 14-17 17-20 20-25 25-30 30-35 35-50 0-16 16-20 20-24 24-28 28-60 60-69 69-71 71-79 79-84 0-10 10-29 29-36 36-40 40-53 53-66 66-70 0-16 16-35 35-52 52-60 O-Il 11-24 24-36 0-23
23-34 34-44 44-50 50-52 52-54 54-64 0-34 34-38 38-44 44-52 0-42
42-52 52-64 0-24 24-28 28-36 36-48
0-7 7-13 13-18 18-22 22-29 29-34 34-48 48-50 50-58 58-68 68-78 78-87
87-100 0-21 21-36 36-48 48-55 55-60 60-69 0-38
38-48 48-67 67-73 0-42
42-48 48-77
PID Reading
4.7 4.5 5.3 5.3 8.4 5.2 7.9 3.7 na na na na na na na na na 8.3
20.5 20.7 9.6 14.8 6.1 14 na na na na
14.3 33.9 9.2 na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na
Assay Result
na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na na
Filed Observations
Hair
...
...
...
...
...
... _-. ... --. - .
yes yes yes yes yes yes
...
...
...
... — . -—
yes yes
...
...
...
...
...
... yes yes yes
... —
...
...
...
...
...
yes
...
...
...
... yes ...
yes
yes yes
yes ... ... ... ...
... — ... ... ...
Odor
...
...
... -_-... ... ... ... ... _-.
...
.-.
...
...
...
...
...
...
...
...
...
... -.-... ... ... ... ... ... — ...
...
...
...
... __. ___ ... ... ... ...
... — ... ... ... ... ... ...
yes
...
...
...
... yes
yes yes
...
...
...
...
... ... ...
Sheen
—
... — ...
... - .
:;: ... ... ... — ... ... ... ... -._ ... ... ... _._ ... — — — ... ... ... ...
•
...
...
...
...
.... yes ...
::: — — ... — _-_ ... ... ...
...
...
...
... yes yes
...
...
... yes ... ... ... ... ...
Tar
...
...
...
... yes
... yes
...
...
...
... yes
...
...
...
...
... ___ ___ ... ___ ... -__ ... ... ... ... ... ... — ...
yes yes yes yes
...
—
yes yes
...
...
...
...
...
...
... yes yes
...
...
.-_ —.
yes
...
...
...
...
...
...
...
NOTES: na = Sample not analyzed for parameter. . . . = Not observed in sample, nm = not measured. SP = Indicates sheen was observed on the sounding pole even though no sample was collected. ** Sample locations are presented on Plate I. HI = Immunoassay results out of the calibrated instrument range (Sample value > 500 ppm total PAHs). SD-7XXV = indicates sample collected by Vibrocore methods - all other samples collected manually. No Sedimeni Borehole Log for BKG-700 & SD-702BV
1665 sediment tables compared to PEC.xIs Page 2of 2 Table 1 - Field Observations
Table 2 - PAH Sediment Laboratory Analytical Results Former Sheboygan II MGP Site - WPSC
Sample Number
.S ' ^P ' f Sample
^ ' ^ r ' ^ Date (mches)
Method Detection Limit
BKG-700 SD-701B SD-702A SD-702B SD-703C SD-704B SD-706C
0-15 0-10
0-16.75 0-15.25
0-23 0-23 O-Il
10/16/1995 10/17/1995 10/16/1995 10/16/1995 10/17/1995 10/17/1995 10/18/1995
PAHs (^g/kg)
1 t ca c o
< 40
u c _u "?.
s g-<
80
c
S
a <
8
Ben
zo(a
)ant
hrac
ene
2
u c u .£ C E o
3
B 2
C
B
i 3
I E V
CO 2
B
a. 'a
B
oa
8
4 eo
a u
CD
4
U
4
1 1 S S s 1 5 4
u B
•s B
s 3
E 8
B
o 3
16
Inde
no( 1
,2,3
-cd)
pyre
ne
4
• a
t >>
1 25
1 u
1 •a •s
! -g. 1 fl
1 25
1 c
• o. ! o
Z
40
B
1 c CQ C
1 ID
16
B
8
Total PAHs' (mg/kg)
Hand Cored Samples ]
nd nd nd nd nd
26,000 nd
nd nd nd nd nd
12,000 nd
35 nd nd nd nd
15,000 38
380
8 18 89 nd
11,000 110
130 14
11 57
nd 2,400
39
69 nd 15 55 nd
3,100 47
260 nd 18 98 nd
7,700 82
160 17 36 150 nd
5,300 110
180 8 10 64
nd 70,000
82
nd nd 14 21 nd
1,300 nd
640 18
18 83 nd
56,000 300
nd nd nd nd nd
31,000 nd
94
9 23 94 nd
3,200 93
nd nd nd nd nd nd nd
nd nd nd
nd nd nd nd
nd nd nd nd nd
124,000 nd
62 nd nd nd nd
66,000 160
160 11 nd 120 nd
9,600 180
2.2
0.1 0.2 0.8 nd 444 1.2
Vibrocore Samples |
SD-701BV SD-702BV SD-702CV SD-702CV SD-702CV SD-703BV
SD-704BV SD-704BV SD-705BV SD-705BV SD-705DV SD-706CV SD-707BV SD-707CV SD-708AV SD-709AV SD-711AV SD-712AV SD-712BV
47-69 75-86 0-27 27-64
80-89 37-42
28-102 112-116 45-47 53-58 36-54 46-59 35-43 60-79 53-66 11-24 36-48 38-48 48-77
6/11/1996 11/5/1995 6/11/1996 6/11/1996 6/11/1996 6/13/1996 6/13/1996 6/13/1996 11/5/1995 11/5/1995 6/13/1996 6/18/1996 11/4/1995 6/11/1996 11/4/1995 11/4/1995 6/18/1996 6/18/1996 6/18/1996
nd 203,000
nd 33,000 114,000
nd 68,000
nd 1,030,000
nd nd nd
3,300 nd nd nd nd nd nd
nd nd nd nd nd nd nd nd nd nd nd nd nd nd nd nd
nd nd nd
3,900 106,000
nd 37,000 32,000
nd 22,000
510 359,000
75 2,500
30 1,800 250 110 39
1,700
610 18
3,500 67,000
6 29,000 29,000
13
24,000 380
345,000 50
1,500 60
3,300 310 120 110 930
430 50
610 22,000
nd 5,400
40,000 15
4,800 100
115,000 16
280 14
840 48 40 42 170 110 13
1,200 17,000
nd 4,500 8,200
4 8,200 150
66,000 11
470 14 120
95 28 24 150 130 22
2,200 50,000
5 14,000 15,000
11 17,000
360 263,000
38 1,100
51 1,400 210 97 70 540 300 42
1,100 37,000
nd 10,000 8,800
10 12,000
320 204,000
26 770 58
1,400 140 75 52
410 240 49
1,400 42,000
nd 11,000 10,000
7 9,700 230
228,000 2
720 38
2,900 120 74
56 410 210 23
nd nd
nd nd nd nd nd nd nd nd nd nd 120 nd nd nd nd nd nd
8,400 330,000
10 141,000 102,000
20 41,000 1,300
1,580,000 130
5,100 120
11,000 730 220 170
1,700 2,200 120
4,000 207,000
nd 66,000 71,000
nd 52,000
370 490,000
45 1,300
nd 650 97 97 51
1,300 340 nd
1,400 28,000
nd 7,500 5,700
5 8,000 210
156,000 23 530 23
1,000 110 53 33 nd 180 22
11,000 nd nd
157,000 206,000
nd 158,000
470 nd nd
2,700 nd nd 75 nd nd
3,400 nd nd
10,000 nd nd
145,000 188,000
nd 135,000
700 nd nd
2,300 nd nd 92 nd nd
1,800 nd nd
7,200 974,000
nd
297,000 358,000
nd 190,000 3,000
2,520,000 470
3,900 nd nd nd nd nd
790 nd nd
10,000 344,000
nd 134,000 119,000
nd 91,000 1,800
1,370,000 150
7,800 150
6,000 930
330 110
4,000 2,100
56
2,900 99,000
nd 23,000 20,000
8 25,000
570 568,000
75 1,800
59 8,500 630 200 140
1,300 1,300
26
69 2^26 0.0
1,114 1327 0.1
866 10
9,294 1.1 33 0.6
42.3 3.8 1.4 0.9 19 8.2 0.4
NOTES: 1) Sample Locations are presented on Plate L 2) nd = Parameter Not Detected
3) No sediment borehole logs for BKG-700 or SD-702BV. 4) PAHs analyzed by U.S. EPA Method 8310
5) Constituents that exceed the PEC are highlighted in yellow 6) Concentrations have not been normalized to 1% TOC
CBSQG
TEC PEC
Total PAHs' (mg/kg)
1.6 22.8
CBSQG = Consensus-Based Sediment Quality Guidelines
TEC = Threshold Effect Concentration
PEC = Probable Effect Concentration
Reference; 1: MacDonald, D.D., C.G. Ingersoll, and T.A. Berger. 2000. Development and evaluation of consensus-based sediment quality guidelines for freshwater ecosystems. Arch. Environ. Contam. Toxicol. 39:20-31.
1665sedimenttablescomparedtoPEC.xls - Table 2 - Sed PAHs Page 1 of 1 Pi-ep. by: DRJ/SLF
Checked by: JAG/DVP
Table 3 - BTEX Sediment Laboratory Analytical Reuslts Former Sheboygan II MGP Site - WPSC
Sample Number
Interval _ , T» .. .. . , Sample Date (mches) *
Method Detection Limit
BTEX(ngA^)
Benzene
5
Toluene
5
Ethylbenzene
5
Xylenes, total
15 Hand Cored Samples
BKG-700 SD-701B SD-702A SD-702B SD-703C SD-704B SD-706C
0-15 0-10
0-16.75 0-15.25
0-23 0-23 0-11
10/16/1995 10/17/1995 10/16/1995 10/16/1995 10/17/1995 10/17/1995 10/18/1995
nd nd nd nd nd
6,300 nd
nd nd nd nd nd
9,500 nd
nd nd nd nd nd
24,000 nd
nd nd nd nd nd
31,000 nd
Total BTEX (mg/kg)
Total BTX^ (mg/kg)
1 nd nd nd nd nd 71 nd
nd nd nd nd nd 47 nd
Vibrocore Samples 1 SD-701BV SD-702BV SD-702CV SD-702CV SD-702CV SD-703BV SD-704BV SD-704BV SD-70SBV SD-705BV SD-705DV SD-706CV SD-707BV SD-707CV SD-708AV SD-709AV SD-711AV SD-712AV SD-712BV
47-69 75-86 0-27 27-64 80-89 37-42 28-102 112-116 45^7 53-58 36-54 46-59 35-43 60-79 53-66 11-24 36-48 38-48 48-77
6/11/1996 11/5/1995 6/11/1996 6/11/1996 6/11/1996 6/13/1996 6/13/1996 6/13/1996 11/5/1995 11/5/1995 6/13/1996 6/18/1996 11/4/1995 6/11/1996 11/4/1995 11/4/1995 6/18/1996 6/18/1996 6/18/1996
nd 110,000
nd 49,000 30,000
nd 11,000
400 1,400
nd 270 nd nd nd nd nd 18 nd nd
280 220,000
nd 100,000 110,000
nd 3,900
nd 1,200
nd 62 nd nd nd nd nd 25 nd nd
810 280,000
nd 120,000 210,000
nd 71,000 1,700 7,200
49 940 nd nd nd nd nd 36 nd nd
690 380,000
nd 170,000 240,000
nd 88,000 1,600 7,700
50 450 nd nd nd nd nd 71 nd nd
1.8 990 nd
439 590 nd 174 3.7 18 0.1 1.7 nd nd nd nd nd 0.2 nd nd
1.0 710 nd
319 380 nd 103 2.0 10 0.1 0.8 nd nd nd nd nd 0.1 nd nd
NOTES: 1) Sample locations are presented on Plate I. 2) nd = Parameter Not Detected 3) No sediment borehole logs for BKG-700 or SD-702BV.
4) BTEX analyzed by U.S. EPA Mediod 8260 5) Constituents that exceed the PEC are highlighted in yellow 6) Concentrations have not been normalized to 1% TOC
CBSQG
TEC PEC
BTEX (mg/kg)
NS NS
Total BTX^ (mg/kg)
0.97 1.96
Reference:
CBSQG = Consensus-Based Sediment Quality Guidelines TEC = Threshold Effect Concentration PEC = Probable Effect Concentration NS = No Standard EstabHshed for ethyl benzene
2: MacDonald, D.D. and M. MacFarlane. 1999. (Draft). Criteria for managing contaminated sediment in British Columbia. British Columbia Ministry of Environment, Lands, and Parks. Victoria, British Columbia.
1665 sediment tat)les compared to PEC.xIs ~ Table 3-Sed BTEX Page 1 of 1 Prep, by: DRJ/EPK
Checked by: JAG/EPK
Table 4 - Sediment Laboratory Analytical Results Cyanide, Phenol, TOC, Oil & Grease, RCRA Metals & PCBs
Former Sheboygan II MGP SUe - WPSC
Sample Number
Sample Interval (inches)
Sample Date
Method Detection Limit
BKG-700 SD-701B SD-702A SD-702B SD-703C SD-704B SD-706C
0-15 0-10
0-16.75 0-15.25
0-23 0-23 0-11
10/16/1995 10/17/1995 10/16/1995 10/16/1995 10/17/1995 10/17/1995 10/18/1995
(mgfltg) 1
Total Cyanide
025
Weak Acid Dissociable
Cyanide 0.25
PbenoP
0.13
OiI& Grease
.500
TOC
-Hand Cored Samnles I
0.59 nd 0.3 nd nd
084 nd
nd nd nd nd nd
0.62 nd
nd nd nd nd nd 2
0.19
na na na na na na na
30,000 17,000 20,000 20,000 17,000 31,000 7.600
Vibrocore Samples | SD-701AV SD-702BV SD-702CV SD-702DV SD-705BV SD-70SBV SD-707BV SD-708AV SD-708BV SD-709AV SD-711AV SD-711AV SD-7I1BV SD-711BV
47-69 75-86 27-64 GB
45-47 53-58 35-43 53-66 52-60 11-24 24-28 36-48 50-58 78-87
6/11/1996 11/5/1995 6/11/1996 6/13/1996 11/5/1995 11/5/1995 11/4/1995 11/4/1995 6/11/1996 11/4/1995 6/18/1996 6/18/1996 6/18/1996 6/18/1996
na 0.98 na na 8.7 nd nd nd na nd na na na na
na 0.51 na na 3 nd nd nd na nd na na na na
na 48 na na 4.3 nd nd nd na nd na na na na
na na
43,400 na na na na na na na
31,400 na
2.570 na
na 27,900
>100,000 71,600 25,700 1,600 1,100 1,100
na 1,700
19,000 2,000 21,000 9,600
Sample Number
fnZa, «™P'* ,. . ^ Date (mches)
Mediod Detection Limit SD-701BV SD-702CV SD-708BV SD-711BV
47-69 6/11/1996 27-64 6/11/1996 52-60 6/11/1996 50-58 6/18/1996
RCRA Metals (mg/kg)
Arsenic
012 na 1.8 2.1 1.0
Barium
0 5 na 26 47 12
Cadmium
1 na 1.6 1.4
Chromium
1 na 43 500 7.4
Lead'
4 na 140 71 28
Mercury'
0.02 na 02 0.47 0.18
Selenium
0.12 na
<0.48 <0.48 <0.I2
Silver^
1 na
<1.0 <1.0 <1.0
Total PCBs' (mg/kg)
0.12 0.42
1.8-2.3 na
0.97
NOTES: 1) For Sample Locadons, please reSsr to Plate I 2) nd = Parameter Not Detected 3) na = Parameter Not Analyzed for in this sample 4) ppm = part per million = mg/kg 5) GB = Grab sanple from surface, no depth reading
6) No sediment borehole logs for BKG-700 & SD-702BV 7) Contituents not listed in the table below do not have established standards 8) Consdtuents that exceed tlie PEC are highlighted in yellow 9) Concentrations have not been normalized to 1 % TCXI
CBSQG TEC PEC
As' (mg/kg)
9.8 33.0
Cd' (mg/kg)
0.99 5.0
Cr' (mg/kg)
43.0 110
Pb' (mg/kg)
36.0 130
Hg' (mg/kg)
018 1.1
(mg*g) 018 1.1
Total
PCBs' (mgAg) 0060 0.676
Phenol' (mg/kg)
4.2 12.0
CBStJG = Consensus-Based Sediment (Quality Guidelines TEC = Threshold Effect Concentration PEC = Probable Effect Concentration
Refisrences: 1: MacDonald, D.D.. C.G. Ingersoll and T.A. Berger. 2000. Development and evahiation of consensus-based sediment quality guidelines for freshwater ecosystems. Arch. Environ. Contam Toxicol. 39:20-31.
2: MacDonald. D.D. and M. MacFarlane. 1999. (Draft). Criteria for managing contaminated sediment in British Columbia. British Columbia Ministry of Environment. Lands, and Parks. Victoria, British Columbia.
3: Sediment Management Standards, Chapter 173-204 WAC, Washington State Department of Ecology. April 1991. The Standards were developed using the Apparent Effects Threshold Approach. The TEC and PEC values for the comopunds are based on no effect and miniiTial effect standards, respectively, from the Washington Standards and are intended to apply to Puget Sound, and estuarine habitat. The values were calculated based on an assumed TOC content in sediment of 1 %.
1665 S8d<ment tables compared to PEC.xIs - Table 4-Sed Various Rase 1 of i Prep, by: SLF/EPK
Checked by: DVP/EPK
A 592-
590-
5 8 8 -
M 6 -
A
5 7 B -
5 7 6 -
SLT w m TAM
D D'
UJ 5 7 6 -
B B C c
578-
576-
582-1
560
5 7 8 -
I B 576-
572-
570-
..• '
582-1
5 8 0 -
578-
576-
574-
572-
570
568'
5 6 6 -
564-
^ 52.77. l^lZt
SMDS AW SLn
E 578-
g 576-
I 3 574-
572-
570-
5 5 8 -
566-
564-
FEET
n x n C U OACCMIUTIDN ' 4.00
Lis sMo
m , fcld SWDY SILT
0..,
l l J ORGMDC
0 c.. ^ SWOT CLAY
Sr . .
b 2 j SAND WITH CRAVa
• 1 TAR
S ^
SCREWED IMTIRVAl.
WATER LEVEL ELEVATIOM ON
18.6
JL IS
PAH»
BTEX
TOTAL PAHa (mg/kg)
?
BENZENE. TOLUCNL ETHTLBEMZENE. JfYIENE
570-
568-
Natural Resource Technology
GEOLOGIC CROSS SECTION A - A ' THROUGH J - J '
FORMER SHEBOYGAN SHEBOYGAN
DRAWN BY: T/iS
DATE:. 2 / 1 9 / 9 8
II MGP SITE , WISCONSIN
CHECKED BY: EPK
2/19/96
WPSC
APPROVED BY: RJK
2/19/98
PROJECT NO. 1183/4.3
DRAWING NO. 1183-D02
PLME 2
r
SOUPCI HOIt:
I. potmoHs or THS M P N D S DC^VLOFCD FDOW A kUP smVFlID BY HMZE * ASSOCWIE^ HC. SMBtm^N. WBOMSm. REB&IEmX LAND SUVi^AS. JOB HD. D-2M1, CWTES SCFItUBOl 4. IMS.
2.F>0frTKMS or THE UAP WERE DfMli3PO FRoy MinAL ntOTO BT AOto-unmc ENOINQSMC BC. DATID APRL IB. I»90. TOWN or sxaoiTMN. SHEBtrrcw cDum.
3.SHEBCnUN RWn SHORELME DCMNSTKAU OF PtMNSnwMA WDtUC GRIOCE M^fU)PCD nwM UiP Vr BUSLAHD k BU3UCX ENCMEZRS. P.C. 1T6.D1DI SIM, i o n .
a p o n o e or TMS UW> WERE KVCLOPCI) FROU WP Bf SAKM »mWO-Sf>RCH. MTED Ct»/25/»3- PWUECl SOUUOM.
25 50
SCALE IN FEET
Natural Resource Technology
LEGEND
_ r 7 0 5
^ D - 7 0 4 C
^ S D - 7 0 2 B V
^ SG-7C1
0
OE
W/E
1 1
1 1
TT?ANSECT BASE
SEDIMENT SAMPLE (HAND CORED)
SEDIMENT SAMPLE (VIBROCORE)
STAFF GAUGE
UGHT POLE
OVERHEAD ELECTRIC
BURIED ELECTRIC
REU^TED STRUCTURE
DEPTH THAT TAR IS BURIED
BENEATH TOP OF SEDIMENT
24 ' -36 "
36--48"
48" OR MORE
DEPTH TO TAR CONTOUR FORMER SHEBOYGAN II MGP SITE - WPSC
SHEBOYGAN, WISCONSIN DRAWN BY: TAS
DATE: 2/24/98
CHECKED BY: EPK APPROVED BY: 2/24/98 2/24/98
PROJECT NO. 1183/4.3
DRAWING NO. 1183-D03
PLATE 3
I
•
APPENDIX C
BBL SEDIMENT SAMPLE LOCATIONS
B
\ j i
• • ^ i " • ; ; •
'yzP
: * i ^ 1 •••• b • -^ \ . ; . r : : : : ^ ; y :.::•:••• j i ; ; V
LEGEND
SAMPLE LOCATION CHOSEN FOR PARTICLE SIZE ANALYSIS
PCB Concentration (ppm, dry weigtit;
i ui
'ix-'l^-^lB...
v.'. . v: -- •••^OUTH OF INNER HARBOR-
r • • • -fp..
Vi
* * i k . * " ^ ' ' ^ .^ • • ' ^ '
1 •••• ? * " i ;
••"-"5r^-"™"'"-||---" •
.. ...JL il • • K I I " • • ! •
^'S il H}^ .-..il - -
lE.- T
:.-.::.i '• ^ " //III -...41
\ . . . . - / • •>•• i a l A aft.; • i ••^ f
i|j * - i ^ jl..5IJ.-i| i~ij"~—rii''~~. I$0.. ..il-
APPROX. SCALE: I = lOOO'
n il v., //:... JI..*.fth..JUl^..,:M.^H^
1«0791Rt1W07N6iX»R '•;: i iKoWer
\ i l x j : S ^ i _ j l '2ii 4..Ji-^l;:~::::{£»^/^vv£™:::;::::;v.dfe
/ - ^ ' i l n « ' / • •'4 ;1 ^ = i \ - ^ Mi' i i t ' ; Oil
L™J!. \JL«<i—s'.. L I I i,.5jiJ _....Jk£-«j Ji
BLASLAND, iOt tCK &.L1E, INC.
SHEBOYBAN RiVlR S MiAR&OP! SITE
SEDIMENT TRANSPORT -INVESTIGATION
SEDIMENT SAMPLING LOCATfONS
wmammmnki
I
I I
DOCUMENTATION REPORT, NMT FEBRUARY 2M3
B
Table 2 - Excavation Sidewall and Base Analytical Results Phase I and II Remedy Documentation Report Campmarina and Center Avenue Right of Way
Sam
ple
ID
Dat
e
EZ-101 12/15/2000
EZ-102 12/15/2000
EZ-103 12/15/2000
EZ-104 12/15/2000
EZ-105 12/15/2000
EZ-201 11/27/2000
EZ-202 11/27/2000
EZ-203 11/27/2000
EZ-204 4/2/2001
EZ-205 4/2/2001
EZ-206 4/2/2001
EZ.207 6/26/2001
EZ-208 6/26/2001
EZ-301 12/5/2000
EZ-302 12/5/2000
EZ-401 11/30/2000
EZ-402 11/30/2000
EZr403 11/30/2000
EZ-404 11/30/2000
EZ-405 11/30/2000
Volat i le O r g a
c
c ea
0.012*
0.3
0.577
0.045
0 .015*
0 .066
0 .028*
0.068
<0.009
<0.009
<0.009
<0.018
<0.009
<0.009
<0.009
0.284
5.49
0.579
0 .225*
0.371
at c 3
s2
0.024
0.084
0.083
0.049
0.023
0.045
0.083
0.072
<0.0042
<0.0042
<0.0042
<0.0084
<0.0042
<0.0042
<0.0042
0.578
3.57
0.394
0.092
0.476
nic C o m p o u n d s (mg/kg)
c
c
JZ
0.0065*
0.257
0.056
0.023
0.021
<0.0045
<0.0045
<0.0O45
<0.0O45
<0.0045
<0.0045
<0.009
<0.0045
<0.0045
<0.0045
0.082
0.613
0.12*
0.116*
0.107*
c
>-> X
1 <0.019
0.165
0.155
0.074
0 .057*
0 .061*
<0.019
0.121
<0.019
<0.019
<0.019
<0.O38
<0.019
<0.019
<0.019
0.265
2.72
<0.19
<0.19
<0.19
X
CQ
"rt
i2
0.043
0.806
0.871
0.191
0.116
0.172
0.111
0.261
nd
nd
nd
nd
nd
nd
nd
1.209
12.393
1,089
0.433
0.954
Po lynuc lea r A r o m a t i c H y d r o c a r b o n s ( P A H ' s ) m g / k g |
c
H JZ
a
• > >
<0.019
0.289
1.66
0.028*
0 .031*
na
na
na
<0.088
<0.102
0.804
<0.019
<0.018
0.364
0.387
0.399*
7.12
0.808
2.86
2.43
c
JC a a c ">,
^
<0.019
0.163
1.9
0.037*
<0.019
na
na
na
<0.088
<0.102
1.19
<0.019
<0.018
0.378
0.421
0.5*
5.77
0.908
0.494*
2.46
c CJ
£ a. cs c u
< <0.017
0.142
0.999
0 .023*
0.018*
na
na
na
<0.08
<0.094
0 .301*
<0.018
<0.017
1.45
0.222*
<0.199
14.2
0.26*
5.08
1.35
OJ
c
J= a. es c
<
0.03*
1.38
7.52
0.416
0 .023*
na
na
na
<0.095
0 .173*
0.228*
<0.021
<0.020
0.535
1.76
0.464*
39.3
5.65
0.829
12.7
c a a u
J :
<
0.019*
0.593
15.5
0.479
0 .021*
na
na
na
<0.079
0.112*
1.06
<0.017
0.017*
2.9
1.29
0.399*
118
2.54
3.11
6.98
c <u u n u
J= c es n
g c oa
<0.022
1.5
40.5
2.33
0.023*
na
na
na
0.135*
0.663
1.73
<0.022
0.051*
4.85
6.73
1.17
173
9.62
3.9
18.7
U
c <u u >-> a , n
c
p a
<0.017
3.27
41.4
2.32
0.036*
na
na
na
0.102*
0.742
1.79
<0.017
0 .033*
4.17
4.37
1.29
157
12.3
3.61
18.2
c (U
JZ
'c 2 o 3
N C
<0.0I7
2.92
50.5
3.08
<0.017
na
na
na
0.180*
1.0
1.99
<0.017
0.049*
4.445
7.67
1.32
168
14.5
3.4
25.9
Ol
c
L.
a.
OX)
I c oa
<0.033
1.68
21.6
1.4
<0.033
na
na
na
<0.154
0 .431*
0.611
<0.034
0.036*
2.72
3.29
1.31
83.4
6.65
1.76
7.46
tu c
c a u o 3
C
2 c
aa
<0.03
1.89
31.4
2.19
<0.03
na
na
na
0.177*
1.220
2.7
<0.030
0 .062*
4.3
5.61
1.29
105
8.14
2.95
14.6
2 c
i: J : U
<0.02
1.76
39.4
2.3
0.026*
na
na
na
0.162*
0.786
1.96
<0.020
0.056*
5.22
7.68
1.47
153
9.97
3.97
19.4
U c u CQ
u "c a
- - C 5 -
N C
5
<0.O43
0.563
8.32
0.556
<0.042
na
na
na
<0.196
<0.229
0.230*
<0.043
<0.041
0.98
1.19
<0.486
25.6
2.25
0 . 5 6 1 *
3.4
u c
JZ e CO u o 3
0.024*
1.83
63.2
4.04
0 .035*
na
na
na
0.338
0.592
4 .09
<0.013
0.148
11.2
10.6
2.85
431
15.2
8.87
21.6
c u o 3
<0.022
0.211
31.5
0.052*
<0.022
na
na
na
<0.1
<0.116
0.285*
<0.022
<0.021
1.19
0.248*
<0.248
48.4
0.544*
2.04
1.65
2 c CJ u >, a. '5' u
' \
"o" c CJ •a c
<0.046
1.42
20
1.42
<0.046
na
na
na
<0.214
0.388*
0.688*
<0.047
<0.045
2.59
3.29
1.08*
86
7.01
1.65
8.07
CJ c Oi
-«
z
<0 .0 I6
0.527
4.65
0.141
0 .021*
na
na
na
<0.073
<0.0S5
<0.083
<0.016
<0.015
0.645
0.591
0.949
10.9
2.5
0.886
3.23
<u c CJ
£ C
c CJ £ 0.
0.032*
1.27
29.9
1.78
0.062
na
na
na
0 .133*
0.220*
0.841
<0.018
0.081
10.3
4.61
1.78
310
5.17
10.6
11.2
0) e
0.04*
2.6
65.4
3.74
0 .05*
na
na
na
0.319
0.906
3.77
<0.016
0.107
10.6
11.4
2.62
358
16.9
9.86
29.3
<
"a 'o
0.145
24.0
475.3
26.3
0.365
na
na
na
1.5
7.2
24.3
nd
0.6
68.8
71.4
18.9
2293.7
120.9
66.4
208.6
< Cu
o H
nd
13.3
231.5
14.2
0.085
na
na
na
0.8
4.8
11.1
nd
0.3
26.6
36.5
7.6
867.6
63.8
20.0
108.3
%
v: ."2
"c5 o
H
91
71
63
86
89
87
88
85
94
87
91
85
93
85
83
82
82
87
84
82
mg/kg l l
•a a
2.9*
29
363
25
2.6*
423
192
510
na
na
na
3.6*
7.5
346
230
1,010
60
168
62
229
CJ .•a ' c a
U "a
23
33
579
19
5.5
6.7
250
411
7.7
81
31
<0.024
5.3
93
241
3.2
25
42
2.7
113
I N T E R I M A N D P R E L I M I N A R Y G U I D A N C E L E V E L S (me/Ice)
G r o u n d w a t e r P a t h w a y
R C L Direct C o n t a c t
P a t h w a y - N o n -
indus t r i a l R C L Direct Con tac t
P a t h w a y - I n d u s t r i a l
R C L US EPA Res ident ia l
P R G s
US E P A Indus t r i a l
P R G s
5 .5E-03
ns
ns
0.65
1.5
1.5
ns
ns
520
520
2.9
ns
ns
230
230
4.1
ns
ns
210
210
ns
ns
n s
ns
ns
23
1,100
7.E-I-04
ns
ns
20
600
4.E-I-04
ns
ns
38
900
6.E+04
3,700
3.8E-1-04
0.7
18
360
ns
ns
3,000
5,000
3.E-I-05
2.2E-H04
l.OE-i-OS
17
0.088
3.9
0.62
2.9
48
8.8E-03
0.39
0.062
0.29
360
0.088
3.9
0.620
2.9
6,800
1.8
39
ns
n s
870
0.88
39
6.2
29
37
8.8
390
62
290
3 8
8.8E-03
0.39
0.062
0.29
500
600
4.E-I-04
2 3 0 0
3.0E-f04
100
600
4.E-H04
2600
3.3E-1-04
680
0.088
3.9
0.62
2.9
0.4
20
110
56
190
1.8
18
390
ns
ns
8,700
500
3.E-(-04
2,300
5.4E-4-04
ns
ns
ns
ns
ns
ns
ns
ns
ns
ns
-
"
-
- •
-
ns
50
500
400
750
ns
ns
ns
ns
ns
Notes: 1. na = not analyzed 2. nd = not detected 3. * = The reported result is less than the practical quantitation limit 4. [c]= carcinogenic PAH, classified as B2 probable human carcinogen 5. cPAHs=carcinogenic PAHs 6. RCL = WDNR generic Residual Contaminant Level 7. PRO = US EPA Region 9 Preliminary Remediation Goals for direct contact 8. Delected values bolded
lO.AA&'HMS/rTBAX}! | [ H M S J G R L 7 / 2 3 « 1 ] | R J C 0 6 ^ 4 ^ 2 )
1313/Doc.Report/Soil and Waier Analytical Tables/Tbl 2 Excavation Result Summary 1 ofl Natural Resource Technology, Inc.
EZ-405
B
BTEX
NAPH
PAHS
LEAD
CYAN
1 1 / 3 0 / 0 0
0.371
0.954
3.23
208.6
229
113
EZ-403
B
BTEX
NAPH
PAHS
LEAD
CYAN
1 1 / 3 0 / 0 0
0.579
1.089
2.5
120.9
168
42
EZ-404
B
8TEX
NAPH
PAHS
LEAD
CYAN
1 1 / 3 0 / 0 0
0.225*
0.433
0.886
66.4
62
2.7
c.^^' ^ , 0 ^ ^
^ N ^ ' 1^^
LEGEND
SAMPLE I.D.
B
BTEX
NAPH
PAHS
LEAD
CYAN
DATE
BENZENE ( m g / k g )
TOTAL BENZENE, TOLUENE, ETHYLBENZENE, XYLENES ( m g / k g )
NAPHTHALENE ( m g / k g )
TOTAL POLYNUCLEAR AROMATIC HYDROCARBONS ( m g / k g )
TOTAL LEAD ( m g / k g )
TOTAL CYANIDE ( m g / k g )
REPORTED RESULT IS LESS THAN THE PRACTICAL OUANTITATION LIMIT
m g / k g
EZ
GZ
NS
RCL
MILUGRAMS PER KILOGRAM
EXCAVATION ZONE
GRADING ZONE
NO STANDARD
RESIDUAL CONTAMINANT LEVEL
E Z - 4 0 1
' — • '—^ C 3 £ = ^
EXTENDED EXCAVATION AREA TO - 3 FT. ELEVATION
10 20
SCALE IN FEET
DATUM (FT)
IGLD
579.8
USGS
581
CITY OF SHEBOYGAN
0
GENERAL NOTES". 1 . ALL SAMPLE LOCATIONS ARE LOCATED OUTSIDE
THE PERIMETER OF THE VERTICAL BARRIER WALL. 2. EXCAVATION DEPTH WAS EXTENDED TO AN
ELEVATION OF APPROXIMATELY - 1 R . (CITY OF SHEBOYGAN DATUM) WITH EXCEPTION OF THE SHADED AREA THAT WAS EXTENDED TO APPROXIMATELY - 3 FT. TO REMOVE ADDITONAL MGP AFFECTED SOIL AND DEBRIS.
SOURCE NOTES: 1. PORTIONS OF THIS DRAWING SET WERE DEVELOPED FROM A
SURVEY PERFORMED BY WPS ON 8 / 1 1 / 9 6 . A SURVEY PERFORMED BY HINZE 4 ASSOCIATES INC.. SHEBOYGAN, WISCONSIN. JOB NO. D-3752. DRAWING D3752B.DWG AND LftNG.DWG AND A SURVEY FROM WPS SURVEY "SHEBOYGAN GAS MANUFACTURING PLANT TOPOGRAPHY SURVEY DATED 0 1 / 0 7 / 9 9 ' .
2 PORTIONS OF THIS DRAWING SET WERE MODIFIED FROM A MAP SURVEYED BY HINZE Ic ASSOCIATES. INC.. SHEBOYGAN. WISCONSIN. REGISTERED LAND SURVEYORS, JOB NO. D-2091. DATED SEPTEMBER 4. 1995.
3. PORTIONS OF "IHIS DRAWING SET WERE DEVELOPED FROM DRAWING HLES CAMPCONT.DWG DATED 12/20/99 AND CAMPPLAN.DWG DATED 1/4 /00 OBTAINED FROM THE CITY OF SHEBOYGAN.
4 MW-701 THROUGH MW-709 AND PZ-701 THROUGH PZ-703 WERE RELOCATED TO REFLECT CITY OF SHEBOYGAN SURVEY DATUM.
5. MONITORING WELLS (MW-701 THROUGH MW-707 AND PZ-7Q1), AND STAFF GAUGE (SC-701) COMPLETED BY NATURAL RESOURCE TECHNOLOGY. INC. (NRT). REFERENCE "PHASE II ENVIRONMENTAL INVESTIGATION REPORT" DATED JUNE 28. 1996.
6. MONITORING WELLS (MW-708. MW-709. PZ-702. PZ-703) AND STAFF GAUGE (50-702) COMPLETED BY NRT IN DECEMBER. 1998.
7. EXISTING SITE FEATURES FROM A SURVEY BY RETTLER CORPORATION. STEVENS POINT. WISCONSIN, DOCUMENT NO: 00.651, DATED 10/31/00.
8. BASE AND WAa SAMPLES FROM HELD NOTES BY NRT 9. MANHOLE (UH) FROM RETOER CORPORATION. STEVENS POINT.
WISCONSIN. SURVEY DATED 2 / 1 9 / 0 1 .
EXCAVATION BASE SAMPLE
EXCAVATED AREA AT - 3 R . ELEVATION (CnY OF SHEBOYGAN DATUM)
PERIMETER OF VERTICAL BARRIER
LIMIT OF WORK EXCAVATION AND GRADING ZONES
RIVERS EDGE
CHAIN LINK SECURITY FENCE
RIVERS EDGE RLTER FABRIC FENCE
EXISTING RIGHT-OF-WAY
RCL'S ( m g / k g )
PARAMETER
BENZENE
TOLUENE
ETHYLBENZENE
TOTAL XYLENES
NAPHTHALENE
TOTAL LEAD
TOTAL CYANIDE
GROUNDWATER
0.055
1.5
2.9
4.1
0.4
NS
NS*
DIRECT CONTACT
NON-INDUSTRIAL
NS
NS
NS
NS
20
50
50*«
DIRECT CONTACT
INDUSTRIAL
NS
NS
NS
NS
390
500
NS
• • RISK BASED DIRECT CONTACT RESIDENTIAL
Natural Resource Technology
REMAINING SOIL QUALITY RIVER BANK
PHASE I AND II REMEDY DOCUMENTATION REPORT CAMPMARINA AND CENTER AVENUE RIGHT-OF-WAY
WISCONSIN PUBLIC SERVICE CORPORATION CITY OF SHEBOYGAN, WISCONSIN
DRAWN BY: TAS/RLH
DATE: 0 4 / 0 4 / 0 2
CHECKED BY: HMS
DATE: 0 4 / 0 4 / 0 2
APPROVED BY: REW
DATE: 0 4 / 0 4 / 0 2
P R O J E C T N O .
1 3 1 3 / 3 . 8 / A B
DRAWING NO. 1 3 1 3 - B 3 3
FIGURE NO. 5
US Bun Ncno: O 1. TM I M IH1DWL FtMO AT - I FT. DJWTOL
DCAwmi AREA TO -3 n . OfVATKM (OTY OF shCBcnvM [MTU14 TO rotcMi M^tc ia UATEWL
2. tZ-3 tXCAUATED TD TWO riZI KUW GKOUfC SUWACE (KS).
3 Q-1 tXCAVATID TO - I n . tUVAIDM . 4 d - l DrCMUTCD TWO F in BBS ON ll/ 'S/DO
ON 04/01/01. THt ttD nvmcN or i z - i EXCWATIS AN WOirOM FNE FEET BO. FMV. EXCWATXM WAS PERmOUCD CN JUKE U. 2002.
9 s a m r a : 3 T>«WU(» • cr Rocrr DOOJlCMTAnM KPO«T FOI SUVIMC AM) ANALYTCM. I»ESU.T5.
\
CAMPMARINA AND LOCATION OF FORMER COAL GAS FACILITY
/ /
/
EXCAVATION PLAN
-12 OZ. NON-WWEN
I 600 PS CCOFAaRC w o r n ceoFABRC FDR SCDMENT STABUZATCH
6" FI.TDI GRAVEL ( 1 " TO 1.5' CLEAN/WASHED S7DMC)
PHASE I RIVER BANK RESTORATION, CAMPMARINA
>< " HORIZONTAL
SCALE IN FEET
V B m C A L EXJLGGSUnON - 1
LEGENP
^
^
m s m m
=—=
— .
EZ
GZ
OHWU
UGP
HSL
I IDPE
pa
UNEXCAVATCD/NATIrt WATERLAL
CRUSHED AGGREGATE BASE COURSE
ACGREGATE/CEMEMT SLURRT aoWABLE RLL
THERUAU.Y TREATED bUTERIAL
STRUCTURAL F i l l
FILTER GRAVEL ( T TO l .S" CLEAN/WASHED SFOHq
12 OZ. N O N - W I M X GEOFABRIC
900 X 600 PSI WCWEN GEOrABRIC
20 UlL LLDPE UEUBRANE UNER
EXBTINC GROUND SURFACE
EXCAVATION UUFTS
TEUPORART WORKING SURFACE. PHASE 1 COUPLETION
EXCAVATION ZONE
GRADING ZONE
ORDINARY HIGH WATER UARK (ESTIU»TEO)
UANUFACTURED GAS PLANT
UEAN SEA LEVEL
U N D « LOW DENSmr POLYETHYLENE
POUNDS PER SQUARE INCH
PHASE I EXCAVATION RESTORATION, CENTER AVENUE RIGHT-OF-WAY
*^ HORIZONTAL SCALE IN FEET
viatnuL EUGGKRAHON - i
- K B T K C CWXJWD SURFAd
POO I 000 PS WOVEN CEOFABRC rOR SCDftCHT STABUZATKM
6' FLTER GRAKl ( ! ' TD U * CUMl/^ASHCD STOHQ
GENERAL COHTKACTOR NOTES: 1. CROSS SECnON A ANO B ARE TYPICAL CROSS
SECnOHS OF EXCAVATION AND BACKRU. ALONG THE SKEB0T(W4 RNER. PHASE I B^CKFTU ELEVATX)NS TO BE REUI VERIFIED.
2. EXCAVATION UU/TS TO REMAIN SEVERAL INCh<ES ABOVE THE RIVER LEVEL TO U1N1UIZE SEDIMENT DISTURBWCE. NO CONTRACTOR EOLiPUENT OR PERSONNEL ALLOWED OIRECTI.Y IN THE RfVER.
3. STHUCTURAL R U AND THERMALLY TREATED MA'iERlAL APPROVED EOR RE-USE TO BE COUPACTED TD 95X STANDARD PROCTOR DENSfTY.
• . ELEVATIONS ARE REJTROTCED TD CfTY OF SHEBOTGAN DATUM.
5. PROPOSED SHEET PILE WAU TO BE WSTALIED AS PART OF THE PHASE 11 ACTTVmES.
6. SEE SKEH NO. COSO FOR PH<«SE I GRADING REQUIREMENTS.
7. E Z - 2 AND E Z - J INDICATE SHUIDW EXCAVATWN ZONES TO REMOVE SURFACE UGP IMPACTS. EXCAVATIONS SHALL BE NO UORE THAN ONE FOOT DEEP UNLESS OTHERWISE INDICATED Bf ENCINEER.
8. CONTRACTOR TO FIELD VERIPT UMfT OF SHEET Pa£ WAU AUGHMENT FOLLOWING Rr/EP BANK RESTDRATXW CURRENTLY S n AT 10* FTTOM RfiCRS EDGE.
9. UUnS FOR PLACEMENT OF FLOWABLE H U AND LLDPE UEUBRANE IN CENTER AVENUE RCHT-OF-WAY TO BE HELD VERIFIED.
10. EXCAVATKM LIMITS ALONG Rr/ER BANK ARE BKSED ON SHEBOYGAN RVER UVEL OF - 1 (CITY OF SHEBOTGAN DATUM) AND A MINIMUM SIDPZ REOUIREMENT OF 1.5' HORIZONTAL TO 1" VEFTICAL CONTRACTOR TO HELD VERIFY RH/ER ELEVATIDMS AND RVER BANK RESTORATION SLOPES.
11. HLTER FABRIC BARRIER ALONG RIVERS EDGE TO REMAIN IN-PLACE THROUGH COMPLETION OF RWER E W « EXCAVATION AND PLACEMENT OF RIPRAP.
1 \ PHASE I RIVER BANK RESTORATION, CENTER AVENUE RIGHT-OF-WAY
" HORIZONTAL SCALE IN FEFT
VERTICAL EXAGGERATION •
Natural Resource Technology
ISSUED TO WDNR (NOT FOR CONSTRUCTION)
ISSUED FOR BID (NOT FOR CONSTRUCTION)
ISSUED FOR CONSTRUCTION
ISSUED FOR AS BUILT
DATE:
06/14/00 09/01/00 10/12/00 03/12/02
EXCAVATION PLAN AND CROSS SECTIONS PHASE I AND II REMEDY AS-BUILT
CAMPMARINA AND CENTER AVENUE RIGHT-OF-WAY WISCONSIN PUBLIC SERVICE CORPORATION
CITY OF SHEBOYGAN, WISCONSIN DRAWN BY: TAS
DATE: 0 8 / 1 1 / 0 0
CHECKED BY: SLF
0 8 / U / O O
APPROVED BY: REW
06/14/00
PROJECT NO. 1313/3.8/AB
DRAWING NO. 1313DC040AB
SHEET NO. C040