RIVER BANK STABILIZATION USING ROCK RIPRAP FALLING APRONS DAVID C. FROEHLICH * 303 Frenchmans Bluff Drive, Cary, NC 27513, USA ABSTRACT A rational mathematical model is presented that provides a sensible and realistic description of the physical processes that take place as a horizontal rock riprap apron (generally known as a ‘falling apron’) launches in stages and then gradually covers and protects an eroding river bank. The model is a simplified kinematic description of complex riprap cover development that does not reference directly the forces that lead to stream bank erosion or apron deployment. The formulation accounts for the regularly repeated processes of slope erosion followed by rock settlement that take place along a receding stream bank. Ideas used to develop the model are based on published results of small-scale experiments of falling apron behaviour, and on experience that has influenced current design practices. The model is uncomplicated and can be applied without difficulty to evaluate the adequacy of apron thickness, the amount of stone lost during deployment, the effect of rock riprap properties, and the lateral extent of bank erosion before complete slope coverage is established. However, application is limited to river reaches that are not highly curved. Copyright # 2008 John Wiley & Sons, Ltd. key words: rock riprap; falling apron; bank stabilization; revetment; riprap Received 24 August 2008; Accepted 17 September 2008 INTRODUCTION Holding a river in place by protecting its bank against erosion with a continuous covering of loose stones or riprap is a common engineering practice that is used throughout the world (Task Committee on Channel Stabilization Works, 1965) When revetting a bank this way, the armour stone needs to extend below the lowest bed level expected at the toe of the underwater slope as the streambed scours. The facing can be installed in two general ways: (1) By excavating the bank so that armour material can be placed directly on a prepared slope, or (2) by placing a sufficient quantity of loose stone along the top of the bank so that it will fall gradually and cover the slope as the bank recedes and undermines the stockpile. The first approach might be preferable, but construction could be difficult or costly, especially when underwater excavation is needed. The second method has been used widely to stabilize the banks of both large and small alluvial streams by placing the rock supply on existing ground surfaces or in shallow excavations. Placing a supply of stone that will fall or launch down a slope when undermined is a technique that was used to resist erosion in India throughout the second half of the 19th century when the first railway bridges were being built across the Ganges River and its tributaries (Bell, 1890). Developed from many practical applications, broad guidelines on how to apply the approach are given by Spring (1903), and the concept is shown in Figure 1, which is nearly identical to Spring’s (1903) illustration, which has been reproduced in many references since. When installed around a structure, such as a bridge pier, or along the base of an embankment, the deposited stone resembles an apron, and, for this reason, is known as a falling or launching apron. As described concisely by Gales (1920), who relied upon the technique when building river training works to control the Ganges River at the Hardinge Bridge, ‘the design provides that, as the river cuts away the sand from under the outer edge of this apron, the stone falls in and automatically pitches a slope in continuation of the slope of the bank’. Current falling apron design practice [see, e.g. Brown and Clyde, 1989; U.S. Army Corps of Engineers (USACE), 1994; Przedwojski et al., 1995; Biedenharn et al., 1997; Garg, 2002; Richardson et al., 2001; Schiereck, RIVER RESEARCH AND APPLICATIONS River. Res. Applic. 25: 1036–1050 (2009) Published online 19 November 2008 in Wiley InterScience (www.interscience.wiley.com) DOI: 10.1002/rra.1211 *Correspondence to: David C. Froehlich, Consulting Engineer, 303 Frenchmans Bluff Drive, Cary, NC 27513, USA. E-mail: [email protected]Copyright # 2008 John Wiley & Sons, Ltd.
15
Embed
River bank stabilization using rock riprap falling aprons
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
RIVER RESEARCH AND APPLICATIONS
River. Res. Applic. 25: 1036–1050 (2009)
Published online 19 November 2008 in Wiley InterScience
RIVER BANK STABILIZATION USING ROCK RIPRAP FALLING APRONS
A rational mathematical model is presented that provides a sensible and realistic description of the physical processes that takeplace as a horizontal rock riprap apron (generally known as a ‘falling apron’) launches in stages and then gradually covers andprotects an eroding river bank. The model is a simplified kinematic description of complex riprap cover development that doesnot reference directly the forces that lead to stream bank erosion or apron deployment. The formulation accounts for theregularly repeated processes of slope erosion followed by rock settlement that take place along a receding stream bank. Ideasused to develop the model are based on published results of small-scale experiments of falling apron behaviour, and onexperience that has influenced current design practices. The model is uncomplicated and can be applied without difficulty toevaluate the adequacy of apron thickness, the amount of stone lost during deployment, the effect of rock riprap properties, andthe lateral extent of bank erosion before complete slope coverage is established. However, application is limited to river reachesthat are not highly curved. Copyright # 2008 John Wiley & Sons, Ltd.
key words: rock riprap; falling apron; bank stabilization; revetment; riprap
Received 24 August 2008; Accepted 17 September 2008
INTRODUCTION
Holding a river in place by protecting its bank against erosion with a continuous covering of loose stones or riprap is
a common engineering practice that is used throughout the world (Task Committee on Channel Stabilization
Works, 1965) When revetting a bank this way, the armour stone needs to extend below the lowest bed level expected
at the toe of the underwater slope as the streambed scours. The facing can be installed in two general ways: (1) By
excavating the bank so that armour material can be placed directly on a prepared slope, or (2) by placing a sufficient
quantity of loose stone along the top of the bank so that it will fall gradually and cover the slope as the bank recedes
and undermines the stockpile. The first approach might be preferable, but construction could be difficult or costly,
especially when underwater excavation is needed. The second method has been used widely to stabilize the banks
of both large and small alluvial streams by placing the rock supply on existing ground surfaces or in shallow
excavations.
Placing a supply of stone that will fall or launch down a slope when undermined is a technique that was used to
resist erosion in India throughout the second half of the 19th century when the first railway bridges were being built
across the Ganges River and its tributaries (Bell, 1890). Developed from many practical applications, broad
guidelines on how to apply the approach are given by Spring (1903), and the concept is shown in Figure 1, which is
nearly identical to Spring’s (1903) illustration, which has been reproduced in many references since. When
installed around a structure, such as a bridge pier, or along the base of an embankment, the deposited stone
resembles an apron, and, for this reason, is known as a falling or launching apron. As described concisely by Gales
(1920), who relied upon the technique when building river training works to control the Ganges River at the
Hardinge Bridge, ‘the design provides that, as the river cuts away the sand from under the outer edge of this apron,
the stone falls in and automatically pitches a slope in continuation of the slope of the bank’.
Current falling apron design practice [see, e.g. Brown and Clyde, 1989; U.S. Army Corps of Engineers
(USACE), 1994; Przedwojski et al., 1995; Biedenharn et al., 1997; Garg, 2002; Richardson et al., 2001; Schiereck,
*Correspondence to: David C. Froehlich, Consulting Engineer, 303 Frenchmans Bluff Drive, Cary, NC 27513, USA.E-mail: [email protected]
Copyright # 2008 John Wiley & Sons, Ltd.
Figure 1. Typical design diagram of a falling apron placed along the toe of a revetted embankment based on guidelines presented by Spring(1903)
ROCK RIPRAP FALLING APRONS 1037
2001; CIRIA, CUR, CETMEF, 2007] scarcely differs from the general principles presented by Bell (1890) and
Spring (1903), and applied by Gales (1920, 1938). Quantities of stone needed to provide adequate protective covers
on eroding banks are calculated based on a volume conservation principal that implies at best an unclear
understanding of the physical processes that take place after stone is launched and moves down a slope. Amounts of
stone swept off the slope by river currents, or that are effectively lost by burial in underlying sands, are taken into
account indirectly by increasing the assumed thickness of the final protective layer, or by adding a margin of safety
to the computed volume of launched material. The minimum thickness of an apron that is required to cover a slope
completely also is obtained indirectly as either a multiple of the diameter of stone needed to resist movement by
river currents, or as a multiple of the bank height.
A rational mathematical model that provides a reasonable representation of the physical processes that take place
as a horizontal rock apron launches in stages and then progresses down an eroding slope is presented. The model is
based on the results of published scale-model experiments of falling apron behaviour, and on practical experience
that has influenced current falling apron design theory. Because the model includes only basic aspects involved in
stone deployment and revetment development, it is presented in an uncomplicated and understandable form that
can be applied without difficulty.
CURRENT FALLING APRON DESIGN PRACTICES
Design conventions currently used to decide on rock volume requirements and shapes of falling aprons, gradation
of the rock mixture, and other design factors are summarized. This guidance has developed largely from practical
experience over more than a century.
General considerations
The fundamental idea behind placing a volume of rock at the top of an eroding river bank is that it will be
launched or deployed by itself without direct human control when the edge of the rock supply is eroded at its base,
allowing the material to fall downward along the slope to form a continuous protective cover. The best performance
occurs when aprons are laid upon channel banks composed of cohesionless soils where deep scour is expected and
comparatively uniform rates of launching can be expected (Biedenharn et al., 1997, page 151).
Falling aprons do not function well when placed on cohesive soils where stream banks erode in the form of
slumps with steep slip faces (Richardson et al., 2001, page 6.32). Such conditions were found in February 2002
along the upstream portion of the revetment at Sara, located on the left bank of the Ganges River about 5 km
upstream from the Hardinge Bridge in Bangladesh (Figure 2). Blench (1969, page 124) notes that where cohesive
Figure 2. Horizontal falling aprons composed of rock riprap tend not to perform well when placed on cohesive banks where erosion occurs in theform of slumps with steep slip faces. These conditions were found in February 2002 along the upstream portion of the revetment at Sara, locatedon the left bank of the Ganges River about 5 km upstream from the Hardinge Bridge in Bangladesh This figure is available in colour online at
www.interscience.wiley.com/journal/rra
1038 D. C. FROEHLICH
soils are present, launched stone will not be able to come to rest on the eroded banks, thereby leaving the slopes
unprotected. He also points out that as scour deepens, cohesive banks may also fail by sliding, carrying all or part of
an apron with them to positions where the stone will likely be useless.
Apron volume
Falling aprons formed from rock riprap are often placed horizontally along the toes of embankments that are
themselves protected from erosion by a layer of rock riprap as shown in Figure 1. To estimate the rock volume
needed for the apron, the average thickness of bank coverage Tb is usually assumed to equal some multiple of the
thickness T of the loose rock facing placed on the upper embankment. If an upper embankment does not exist, or if
the upper revetment is made from a material other than what is used in the falling apron, then for design purposes T
equals the thickness of a protective cover that would be constructed on a prepared bank slope from the apron
material. Based on this notion, the volume of material that would be needed per unit length of an apron to cover an
Figure 3. Stages 1 and 2 of apron launching showing the four steps (erosion, settlement, erosion, settlement)
ROCK RIPRAP FALLING APRONS 1043
would never be able to be covered completely by stone deployed from the apron because of losses. Therefore, k
needs to exceed kmin by a sufficient margin to make certain that a protective cover can be attained.
As rock gradually settles down a bank after launching, more of the slope will be protected from erosion.
However, because of the cyclic pattern of cover and exposure upon which the kinematic model is based, the crest of
a bank will erode laterally twice as fast at the toe until the initial launch volume makes its way to the bottom of the
Figure 4. Final state of a falling apron considered by the kinematic model of stone settlement showing intermediate positions of the erodingstream bank at various stages of deployment
�The values a¼ 358 and b¼ 26.68 were used to calculate x for all experiments.yEstimated from Equation (7) based on values of x and Vd/Vb.zFrom Van der Hoeven (2002).xFrom Thiel (2002).
ROCK RIPRAP FALLING APRONS 1045
include curved underwater slopes will be covered in a following publication. This development will also provide a
means of designing falling aprons around bridge piers and abutments, as well as along the curved ends of guide
banks that lead flood flows safely through bridge openings.
Rock retainage fraction
Experimental studies on the behaviour of falling aprons carried out by Van der Hoeven (2002) and Thiel (2002)
provide some factual information that can be used to assess the amount of rock lost at each settlement step. Model
apron dimensions and stone deployment volumes determined from laboratory flume cross sections measured before
and after launching are summarized in Table II, along with the calculated value of k needed to reproduce the results
according to the kinematic model.
The retained fraction of stone after each deployment step was found to be nearly constant for Van der Hoeven’s
(2002) four experiments, which were carried out using well-sorted apron material, with k ranging from 0.80 to 0.92.
However, Thiel’s (2002) two following tests using poorly-sorted apron stone yield estimates of k of about 0.75,
which is significantly less than the values found from the previous results. Larger loss of widely graded material
found by Thiel (2002) might be due to greater erosion of exposed small particles from the surface of the deployed
stone mixture, or the inclination of comparatively small stones to become buried beneath larger ones, thereby
helping to prevent underlying sands from migrating through voids in the surface layer as intended. However, Thiel
(2002) does not address this aspect of protective cover development. While the ratios of scale-model fall heightH to
apron thickness Ta, and thus the ratios x, are small for both sets of experiments in comparison to those from typical
falling apron constructions, estimates of k based on the results are probably reasonable for larger values of x as well.
However, more experiments need to be carried out to quantity stone loss rates more precisely.
Additional insight on the amount of rock lost at each deployment step can be obtained from the margins of safety
implied in commonly used falling apron design procedures. From the ratios Tb/D that can be derived from the
various conventional design criteria described previously for D¼D50, Vd/Vb ranges from 2 to 3.15. To estimate k,
we assume that a¼ 408 and b¼ 26.68, and consider the ratio H/Ta to range from 2 to 8 based on our experience. For
Vd/Vb¼ 2, k¼ 0.80 when H/Ta¼ 2, and k¼ 0.94 when H/Ta¼ 8. For Vd/Vb¼ 3.15, k¼ 0.76 when H/Ta¼ 2, and
k¼ 0.92 when H/Ta¼ 8. Therefore, based on conventional design guidelines, k can reasonably range from 0.76 to
0.94.
From the published results of experimental studies, and from common design practice, we hypothesize that
k ranges from 0.75 to 0.95. Smaller values of k apply to conditions that give rise to greater rock loss, such as uneven
launching of stone due to the presence of cohesive soils beneath the apron, rapid erosion of the bank, the tendency
for bank slides to occur, or the use of poorly sorted apron stone. Larger values of k apply where bank erosion takes
place gradually, bank slides are not likely to occur, and well-sorted stone is used in the apron.
Additional experiments are needed to establish more precise estimates of k, taking into account the
hydrodynamic factors and soil properties that control the speed of bank erosion and the rapidity of stone launching.
Also, the notion of a varying degree of rock retainage (i.e. a non-constant value of k) as an apron deploys needs to be
investigated. Rock that becomes buried in underlying soils along the upper portion of an eroding slope will likely
Figure 6. Flowchart of horizontal rock riprap falling apron design procedure
ROCK RIPRAP FALLING APRONS 1047
throughout two monsoon floods, during which the apron had been covered by swiftly flowing water more than 4 m
deep. Stone had deployed uniformly from the apron, with only a few minor irregularities.
Example application
An uncomplicated example is presented to illustrate how the model might be used to evaluate the suitability of a
proposed falling apron. Using previously calculated values of water velocities and depths, bank shear stresses, and
channel scour depths, a river bank of height H¼ 10 m will need to be protected by rock riprap deployed from a
horizontal apron. The bank angle b¼ 26.68 is assumed based on previous experience and general rules currently in
practice. Riprap sizing relations applied to rock having a mass angle of repose a¼ 408 give D¼ 0.3 m. Because
bank erosion will take place gradually, the assumed rock retainage fraction k¼ 0.9. Additionally, the horizontal
distance from the top of the existing bank that can be used to provide space for the falling apron cannot exceed 15 m
at the site.
Alternative A. An initial apron thickness Ta¼ 1.5 m is considered, giving x¼ (10� sin 408)/(1.5�sin 26.68)¼ 9.58. The smallest feasible value of k is then kmin¼ 9.58/(1 + 9.58)¼ 0.905. Because k< kmin, a
protective rock riprap cover will never extend completely to the toe of the bank because of losses. Consequently, the
apron design would not be satisfactory. To improve performance, we need to decrease kmin either by reducing the
height of the bank that requires protection from erosion, or by increasing the volume of rock launched at each stage.
Alternative B. By increasing the apron thickness to Ta¼ 1.8 m, we obtain x¼ (10� sin 408)/(1.8�sin 26.68)¼ 7.99 and kmin¼ 7.99/(1 + 7.99)¼ 0.889. Because k> kmin, launched riprap can spread all the way
Figure 7. Sara revetment near the downstream end in April 2004 showing excellent performance of the falling apron since being rebuilt in 2002.Rock has deployed uniformly throughout two annual monsoon floods during which depth of water flowing over the apron had exceeded 5 m This
figure is available in colour online at www.interscience.wiley.com/journal/rra
1048 D. C. FROEHLICH
down to the toe of the bank before the cover disintegrates due to losses. From Equation (3), the number of launch
stages needed to cover the slope completely is found as
n ¼log 1 � 1�k
k
� �x
log k
¼log 1 � 1�0:9
0:9
� �7:99
log 0:9
¼ 20:8 (9)
and the maximum allowable value of n is
nmax ¼ 2H
D
� �sina
tan b� cosa
� �¼ 2
10
0:3
� �sin 40�
tan 26:6� � cos 40�� �
¼ 34:7 (10)
which far exceeds n, so the likelihood of the bank becoming too steep as it erodes is small. The total volume of stone
deployed per unit length Vd¼ nDTa/sin a¼ 20.8� 0.3 m� 1.8 m/sin 408¼ 17.5 m3 m–1, and the lateral extent of
erosion xe¼ nD/sina¼ 20.8� 0.3/sin 408¼ 9.71 m, which is less than the 15 m available. The apron could be
extended at the same thickness to provide rock volume amounting to about 55% of the quantity that is expected to
be deployed, which provides a volume safety factor fs¼ 1.55.
Alternative C. With Ta¼ 1.5 m as in Alternative A, the bank is excavated so that the apron can be placed 2 m
lower, giving H¼ 8 m, x¼ (8� sin 408)/(1.5� sin 26.68)¼ 7.67, and kmin¼ 7.67/(1 + 7.67)¼ 0.885. The
maximum allowable number of stages nmax¼ 27.7. From Equation (3), n¼ 18.1, which is substantially less