Top Banner
7 th Semester Thesis Bachelor of Architectural Technology and Construction Management Risk Management in Construction Projects Application of Risk Management in Construction Period HAND IN BY ZENGHUA KUANG Consultant : Ernest Vivian Müller VIA UNIVERSITY COLLEGE Horsens Campus Denmark November 2011
41
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Risk Management in Construction Projects

7th Semester Thesis

Bachelor of Architectural Technology and Construction Management

Risk Management in Construction Projects

Application of Risk Management in Construction Period

HAND IN BY ZENGHUA KUANG

Consultant : Ernest Vivian Müller

VIA UNIVERSITY COLLEGE Horsens Campus

Denmark November 2011

Page 2: Risk Management in Construction Projects

Risk Management in Construction Projects Application of Risk Management in Construction Period ©ZENGHUA KUANG Student No. 123859 VIA University College,Horsens Campus, Denmark Bachelor of Architectural Technology and Construction Management 7th semester Consultant : Ernest Vivian Müller 2 Hard copies of report and a PDF-file on a CD-rom – Font Verdana 12 November 2010 39 pages , 300 words per page All rights reserved — no part of this publication may be reproduced without the prior mission of the author. NOTE: This dissertation was completed as part of a Bachelor of Architectural Technology and Construction Management Degree course No responsibility is taken for any advice, instruction or conclusion given within!

Page 3: Risk Management in Construction Projects

School of technology and business

3

Acknowledgements

This dissertation was written as part of the final semester of the education as

bachelor of architectural technology and construction management.

Many people have contributed to this work. First of all, I want to express my

gratitude to my consultant Ernest, he really gives me great help and conduct

which makes my report orientation and study scope smoothly going. And then,

I would like to say thanks to Renger , my former semester consultant. He also

helps me a lot this time. He lends to me some reference books which are very

helpful to my report.

I am extremely grateful to Director of studies, Jan Uwe Wolff. He is nice and

supports me a lot, although he is very busy. He contacts CASA company for

me, which helps me to have the chance to meet with the site manager.

I want to thank Clæs Knudsen, the site manager too. Thanks for his accepting

my visit during the busy construction period. The visit is a golden experience

for me as a student.

Finally, I would like to thank my closest friends here. Many thanks go to my

family members and fiancée for their support and love. Zz, without you this

work would never have been possible.

Thank you! All my friends in Denmark, China and all over the world are

acknowledged just for the reason they exist.

ZENGHUA KUANG

26,11,2010

Page 4: Risk Management in Construction Projects

School of technology and business

4

Abstract

As the most common and typical project types, construction projects have

several characteristics such as specific objects、time limit、financial constraints

and economic requirements, special organizational and legal conditions,

complexity and systematic characteristics, For that each investment project

itself is a complex system. Especially for the construction projects, there are

many risk facets and complicated relations, which will influence it. The

complicated relations include direct, indirect, obvious, implicit or unpredictable,

What's more, the various risk factors will cause different severity of the

consequences. If you do not consider these risk factors, or ignore the major

factors, they all will cause damage because of decision-making errors.

Quality targets, time targets, cost targets are the three objectives of project

management. Especially in the construction project, the time objective is

closely and inseparably related to the cost objective. Therefore, risk

management of construction period is a key part in the risk management of

construction

The overall aim of this study report is to let everyone know what risk

management is, realize the procedure of risk management in construction

project and have a deeper study on the application of risk management in

construction period. The study-involved examples of construction projects what

I have experienced in different places.

The results of this study present the effect of common and major risks on

construction period. Meanwhile, put forward the corresponding

countermeasures

Keywords: risk, risk management, construction project, construction period

Page 5: Risk Management in Construction Projects

School of technology and business

5

CONTENTS

ACKNOWLEGEMENTS-------------------------------------------------------------- 3

ABSTRACT--------------------------------------------------------------------------4

CONTENTS------------------------------------------------------------------------- 5

1. INTRODUCTION------------------------------------------------------------------7

1.1 Background------------------------------------------------------------------7

1.1.1 Definition of risk------------------------------------------------------7

1.1.2 Definition of risk management-------------------------------------- 7

1.1.3 Principle of risk management----------------------------------------8

1.1.4 The process of construction projects--------------------------------8

1.2 Problem formulation-------------------------------------------------------- 9

1.3 Aim, Objective and research questions-----------------------------------11

1.4 Delimitation----------------------------------------------------------------12

1.5 Research methodology----------------------------------------------------13

1.6 Structure of study---------------------------------------------------------14

2. THEORETICAL OVERVIEW------------------------------------------------------15

2.1 Project Risk Management--------------------------------------------------15

2.1.1 Risk Environment----------------------------------------------------16

2.1.2 Risk Identification---------------------------------------------------16

2.1.3 Risk Assessment-----------------------------------------------------17

2.1.4 Risk Response Planning---------------------------------------------19

2.1.5 Risk Control----------------------------------------------------------20

2.2 Risks in construction projects---------------------------------------------20

Page 6: Risk Management in Construction Projects

School of technology and business

6

3. CASE OF STUDY----------------------------------------------------------------23

3.1 Case Ⅰ Public building in Denmark---------------------------------------23

3.2 Case Ⅱ The International project in Vietnam ---------------------------26

4. THE ANALYSIS AND DISCUSSION---------------------------------------------28

4.1 Results and Analysis of cases---------------------------------------------28

4.2 Discussion on the problems in project risk management----------------29

5. FOUNDS AND CONCLUSION---------------------------------------------------31

5.1 Answering the research questions-----------------------------------------31

5.1.1 Findings about risks be identified during construction period-----31

5.1.2 Findings about the impact of risks on the construction period----31

5.1.3 The countermeasures for risks in construction period-------------33

5.2 The main conclusion--------------------------------------------------------36

5.3 Further Research-----------------------------------------------------------37

REFERENCES-----------------------------------------------------------------------38

APPENDIX--------------------------------------------------------------------------39

Page 7: Risk Management in Construction Projects

School of technology and business

7

INTRODUCTION

This chapter presented the background to the research area and sets discuss

the problem formulation. The aim, objectives and research questions are

stated and delimitations are described. Finally, the structure of the dissertation

is outlined.

1.1 Background

1.1.1 Definition of risk

Definition of risk is a state of uncertainty where some possible outcomes have

an undesired effect or significant loss. Uncertainly is meaning that the lack of

certainly due to limited knowledge that it is impossible to state the outcome

exactly, perhaps, more than one possible outcome happens.

Risk concerns the deviation of one or more results of one or more future events from their expected value. Technically, the value of those results may be positive or negative. However, general usage tends to focus only on potential harm that may arise from a future event, which may accrue either from incurring a cost or by failing to attain some benefit. (http://en.wikipedia.org/wiki/Risk) 5. Nov.2010

1.1.2 Description of risk management

Risk management is the discipline of identifying, monitoring and limiting risks.

In some cases, the acceptable risk may be near zero. Risks can come from

accidents, natural causes and disasters as well as deliberate attacks from an

adversary.

Risk management applied in the field of construction currently, has been on

the agenda for about 25 years. It has focused in the main on large-scale

Page 8: Risk Management in Construction Projects

School of technology and business

8

projects with different kinds of complexity related to them, such as Technology,

international collaboration, geography or finance. (Hintze et al., 2004; Jaafari, 2001).

More recently, risk management has started to influence an increasing number

of companies and not only the largest projects. In spite of this, the small

projects in construction do not feature a great deal of systematic risk

management (Azinim & Edum-Fotwe, 2006; Simu, 2006)

1.1.3 Principle of risk management

The International Organization for Standardization identifies the following

principles of risk management:

Risk management should create value.

Risk management should be an integral part of organizational processes.

Risk management should be part of decision-making.

Risk management should explicitly address uncertainty.

Risk management should be systematic and structured.

Risk management should be based on the best available information.

Risk management should be tailor-made.

Risk management should take into account human factors.

Risk management should be transparent and inclusive.

Risk management should be dynamic, iterative and responsive to change.

Risk management should be capable of continual improvement and enhancement.

1.1.4 The process of construction projects

In general, Idea, Briefing, Design, Production and Maintenance management,

are five steps as the process of construction project. (Figure 1) Depending on

Page 9: Risk Management in Construction Projects

School of technology and business

9

the scope of the construction companies’ business concept, they enter this

process in different phases. The viewpoint in this study is that client has to

take charge of the phases of idea, briefing and maintenance. This description

of the construction process is a general one and several different descriptions

can be found in other literatures.

Figure 1: A general description of the construction process

In the construction process, it is still most common with competition using a

tender process to obtain the project and finish it. Such as commercial bid and

technical bid is used in popular. According to the client demands, each of the

competing companies submits a bid. The client will decide to choose the

company as a winner, which is offered by the most favorable price. The winner

is the one that continues with the project into the design and/or production

phase of the construction process. In some cases, the constructions companies

are exclusive and do not have to compete through bidding. As we know that

the many factors have influence on the outcome of the bidding process, such

as cost, quality, safety and sustainability determine the outcome of the bidding

process, the cost parameter has the greatest influence. Although others, they

do have a significant impact from time to time.

1.2 Problem Formulation

As the most common and typical project types, construction projects have

several characteristics such as specific objects: time restraints, cost restraints,

special organizational and legal conditions, complexity and systematic

characteristics. For that, each investment project, it is a complex system,

Page 10: Risk Management in Construction Projects

School of technology and business

10

especially for the construction project; there are many risk factors and

complicated relations, which will influence it. The complicated relations include

direct, indirect, obvious, implicit or unpredictable, what is more, the various

Risk factors will cause different severity of the consequences. If you do not

consider these risk factors at all, or ignore the main factors, they will cause

damage because of decision-making errors. Quality targets、time targets、cost

targets are the three major objectives of construction project management.

Especially in the construction project, the time objective is closely and

inseparably related to the cost objective. Therefore, we cannot ignore risk

management of the effect on time objective caused by risks during

construction phase.

According to the above description of the background in this thesis, we know

that risk management of construction period is the management on the time

limit in uncertain conditions. As the accordance to construction project

implementation, the technical and economic analysis is based on the prediction

and judgment analysts make of future events. The construction project

implementation process can be broken down into several specific parts, and

these parts are always affected by the political and economic environment、

sources condition、technical development, so there are uncertainty on their

future change, What is more, there are limitation on the predictable methods

and working conditions. Therefore, the assessment and predicting outcomes

will be erroneous results inevitably. This makes possible deviation between

actual value and predicting value, which bring about large risk to both the

owner and the construction companies. For example, investment or time limit

prolonged, productivity under design requirement, rising cost of raw materials,

increasing labor fee, fluctuating product prices, changing market demand, loan

interest rate and rate in foreign money, all these unpredictable effect even

damage to an investment project. The uncertainties, which can be considered

Page 11: Risk Management in Construction Projects

School of technology and business

11

as the reason for postponing time limit for a project in the construction project

contract, are the very point of studying time limit for a certain construction

project. Only by analyzing the influence, can we make a better predication and

control of the schedule and ensure the project complete successfully

1.3 Aim, objective and research questions

The overall aim of this study report is to let everyone know what risk

management is, realize the procedure of risk management in construction

project and have a deeper study on the application of risk management during

construction period, therefore, a better project output and better value for

both clients and constructors.

There are two objectives of this study:

1. To assess the most major and common risks which cause bad effect on

construction period.

2. To figure out reasonable solutions.

On the basis of the aim and the objectives, research questions have been

formulated.

1. what is the process of risk management?

2. How to apply risk management in construction projects?

3. What risks are there in construction projects?

4. How risks can be indentified during construction period?

5. How risks can be assessed during construction period?

6. How risks can be controlled during construction period?

Page 12: Risk Management in Construction Projects

School of technology and business

12

Figure 2: research questions

(See figure 2)The first three questions as the basis to support last three ones.

1.4 Delimitation

According to the statement of related problems in this report, I try my best to

narrow down the scope of my study and make my report more pertinent.

The original Risk Management: Concepts and Guidance (Defense Systems

Management College 1986) classified risk into five facets:

Technical(performance related)

Programmatic(performance related)

Supportability(environment related)

Cost

Schedule

Figure 3: Relationships among the five risk facets

Page 13: Risk Management in Construction Projects

School of technology and business

13

(See figure 3)Considering that, cost and schedule risks frequently serve as

indicators of project status. They are treated somewhat differently from the

others. However, cost and schedule can become a major source of project risk.

Based on the above, I decide to start from schedule, and narrow down the

scope to the risk management in construction period phase which makes my

report more specific. Go through the case of study, different realistic

constructions have been presented and analyzed . last section of the report

lists the most common and major risks during construction period and some

countermeasures referred to these risks.

1.5 Research methodology

Literature study and analytical research are my major learning methods, which

play an important role in this report. Analytical research involves analyzing

existing facts and information. Today’s world is based on information

technology and huge amounts of information are available on all kinds of

subjects.

In addition, to speak of, the report is more persuasive and practical based on

the study of real case and visit of site manager. As a student lacking experience

working on building site, the visit definitely has a critical effect on the

conclusion of this report.

I also use Internet-searching engine, which is a fast approach to get wanted

answers of this time. It offers me much writing inspiration and scientific proof

from other related articles.

Page 14: Risk Management in Construction Projects

School of technology and business

14

1.6 Structure of study

Chapter one is introduction to the background of the research area and sets

discuss the problem formulation. The aim, objectives and research questions

are stated and delimitations can be found. The purpose of this chapter is to

help the reader understand why this report needed to be written.

Chapter two is the theoretical overview and the state the literatures which this

thesis focuses. This chapter gives the theoretical foundation for the thesis and

the aim of this chapter is to ensure the reader that this thesis is at the cutting

edge of the research in the chosen area.

Chapter three is the case of study, the different constructions have been built

in different place. This section tells the background of each project and

describes different type of risks occurred in construction projects.

Chapter four is the analysis and discussion, this section’s objective is to

combine results of both the case of study and analytical research in order to

identify the main findings and their relevance and implications to current risk

management practices

Chapter five contains the findings and conclusions of the study. This part

points out the main research contributions and thinking about the specific

direction what we can still doing further study in future.

Page 15: Risk Management in Construction Projects

School of technology and business

15

THEORETICAL OVERVIEW

Chapter two is the theoretical overview and the state the literatures which this

thesis focuses. This chapter gives the theoretical foundation for the thesis and

the aim of this chapter is to ensure the reader that this thesis is at the cutting

edge of the research in the chosen area.

2.1 Project Risk Management

This part focuses on defining and explaining the elements of risk management

and presents the recommended overall structure for implementing risk

management. (The Figure 4) reflects a structure that mirrors the perspective

of the Project Management Institute's PMBOOk (® Guide (2004) within the

organizational environmental context.

Figure 4. the structure of risk management

Page 16: Risk Management in Construction Projects

School of technology and business

16

2.1.1 Risk Environment

In every project, there is a risk environment. There are risks that must be

faced, and there is a host of different ways to deal with them. Risk

management planning is the effort, organizationally, to draw together the risk

policies, practices, and procedures of the organization into a whole that will

address the nature of risk peculiar to the project.

Managing construction projects involves making decisions relating to changes

in conditions associated with construction, the environment, geotechnical,

economic and legislative aspects and so on. In spite of this, risk management

has only been applied in the construction industry for a little more than two

decades (Flanagan & Norman, 1993, p. 1). Formal and traditional risk

management as used today is based on the logical structure of identification,

assessment, response and finally also control.(see figure 4).

2.1.2 Risk Identification

A critical step in the risk management process, risk identification is an

organized, thorough approach to finding real risks associated with a project. It

is not, however, a process of inventing highly improbable scenarios in an effort

to cover every conceivable possibility. After risks are identified and described,

then they can be assessed or managed.

Perhaps the key failing of project managers in risk identification is the actual

description of risk events. Many project managers attempt to identify risks

simply as "schedule" or "cost." (The schedule in and of itself is not a risk.) A

risk event is something that may happen to the benefit or bad effect of the

Page 17: Risk Management in Construction Projects

School of technology and business

17

project. Risk events are most effective when they are described clearly and in

depth. A high-quality risk event description will describe the potential

occurrence and how it would influence the project. On a construction project,

the risk that a "wall will collapse, causing a delay" is different from the risk

that a "wall will collapse, killing someone."

To carry out risk identification effectively, basic project documentation must be

in place. The project charter, scope statement, and project management plan

(including the WBS) need to be available to build a thorough list of risks.

Without these elements as a frame of reference, it is impossible to effectively

evaluate the risks on a project. The risk management plan and the

organizational environment also must be clearly understood to conduct risk

identification. These establish the environment in which the risks will be

evaluated. The risk management plan may also identify specific risk

identification practices which are either preferred or rejected by the

organization as part of their risk culture. All this information can spur thinking

about different risk issues and concerns when evaluated using the tools and

techniques of risk identification.

The tools and techniques that are applied in risk identification are as varied as

the projects they serve. However, some groups of tool and technique types are

most commonly applied. According to PMl BOOK, they include documentation

reviews, information-gathering techniques, checklists, assumptions analysis,

and diagramming techniques.

2.1.3 Risk Assessment

Risk assessment is performed in numerous ways. Tools and techniques have

been developed to consider probabilities and consequences, using historical

data, statistical data or estimated judgment translated into numerical

Page 18: Risk Management in Construction Projects

School of technology and business

18

information (Aven, 2003; Grey, 1995). There are also assessments grading

certainty in scales such as rare-almost certain and low-extreme. They share

estimates of probability and consequence and the use of software tools to

manage the data. Scoring techniques (Grey, 1995) are developed checklists

that include the evaluation of both probability and the consequence of a risk

breakdown and those are used to produce risk matrices. This is a common

technique for risk assessment in construction projects that is widely used due

to its simple approach. As with checklists, the disadvantage is that some

aspects are forgotten. The bias that also needs to be considered is that

different evaluations will appear depending on the individuals carrying out the

assessment. Using models or simulation to assess risks is another approach.

Models are simply a breakdown of a complex project into manageable bits and

pieces, often by using mathematics to show how these bits and pieces are

linked together. The disadvantage of any model using figures is that the user

could easily be blinded by exact figures, without having any more precise

information than a more qualitative answer. It is important to remember that,

with models and simulations, the saying “what goes in is what comes out” is

very applicable.

Figure 5 Probability- Impact Matrix

Page 19: Risk Management in Construction Projects

School of technology and business

19

2.1.4 Risk Response Planning

Risk response development is a critical element in the risk management

process that determines what action (if any) will be taken to address risks

evaluated in the identification, qualification, and quantification efforts. All

information generated to date becomes crucial in determining what the

organization will do that is in keeping with the risks, the organization's

tolerance, the project tolerances, and the customer culture.

To some measure, risk is a cultural phenomenon. Different countries, regions,

and organizations have different cultural tolerances for risk and risk responses.

Determining what limits exist early in the risk response planning process is

important to ensure that time is not wasted on approaches that are intolerable.

Risk thresholds frequently are as significant here as they are in establishing

basic probability and impact for the risks. These risk thresholds should become

a component of the risk management plan.

All risks have causes; sometimes multiple risks within a given project arise

from a common cause. In developing risk responses, the project team should

work to identify any common causes, as those causes may have common risk

responses. Generally, response strategies for threats fall into one of the

following categories:

• Avoidance

• Transference

• Mitigation

• Acceptance

Page 20: Risk Management in Construction Projects

School of technology and business

20

2.1.5 Risk Control

After risks have been identified, qualified, and quantified, and clear responses

have been developed, those findings must be put into action. Risk monitoring

and control involves implementing the risk plan, which should be an integral

part of the project plan. Two key challenges are associated with monitoring

and control. The first is putting the risk plans into action and ensuring that the

plans are still valid. The second is generating meaningful documentation to

support the process. The final step in the description of the risk management

flow chosen in this thesis involves ensuring the use of the prior steps. It is a

question of making sure that the identified risks, which are regarded as

important, are also controlled in the way that was planned in the response step.

In the control step, it is also possible to identify new risks that emerge and the

continuous process proceeds.

2.2 Risks in construction projects

Risks in construction projects may be classified in a number of ways. One form

of risks classification is as follows:

1. Socioeconomic factors

Environmental protection

Public safety regulation

Economic instability

Exchange rate fluctuation

2. Organizational relationships

Contractual relations

Attitudes of participants

Communication

Page 21: Risk Management in Construction Projects

School of technology and business

21

3. Technological problems

Design assumptions

Site conditions

Construction procedures

Construction occupational safety

The environmental protection movement has contributed to the uncertainty for

construction because of the inability to know what will be required and how

long it will take to obtain approval from the regulatory agencies. The

requirements of continued re-evaluation of problems and the lack of definitive

criteria which are practical have also resulted in added costs. Public safety

regulations have similar effects, which have been most noticeable in the

energy field involving nuclear power plants and coal mining. The situation has

created constantly shifting guidelines for engineers, constructors and owners

as projects move through the stages of planning to construction. These moving

targets add a significant new dimension of uncertainty which can make it

virtually impossible to schedule and complete work at budgeted cost. Economic

conditions of the past decade have further reinforced the climate of uncertainty

with high inflation and interest rates.

During periods of economic expansion, major capital expenditures are made by

industries and bid up the cost of construction. In order to control costs, some

owners attempt to use fixed price contracts so that the risks of unforeseen

contingencies related to an overheated economy are passed on to contractors.

However, contractors will raise their prices to compensate for the additional

risks.

The risks related to organizational relationships may appear to be unnecessary

but are quite real. Strained relationships may develop between various

organizations involved in the design/construct process. When problems occur,

discussions often center on responsibilities rather than project needs at a time

Page 22: Risk Management in Construction Projects

School of technology and business

22

when the focus should be on solving the problems. Cooperation and

communication between the parties are discouraged for fear of the effects of

impending litigation. This barrier to communication results from the ill-

conceived notion that uncertainties resulting from technological problems can

be eliminated by appropriate contract terms. The net result has been an

increase in the costs of constructed facilities.

The risks related to technological problems are familiar to the design/construct

professions which have some degree of control over this category. However,

because of rapid advances in new technologies which present new problems to

designers and constructors, technological risk has become greater in many

instances. Certain design assumptions which have served the professions well

in the past may become obsolete in dealing with new types of facilities which

may have greater complexity or scale or both. Site conditions, particularly

subsurface conditions which always present some degree of uncertainty, can

create an even greater degree of uncertainty for facilities with heretofore

unknown characteristics during operation. Because construction procedures

may not have been fully anticipated, the design may have to be modified after

construction has begun.

If each of the problems cited above can cause uncertainty, the combination of

such problems is often regarded by all parties as being out of control and

inherently risky. Thus, the issue of liability has taken on major proportions and

has influenced the practices of engineers and constructors, who in turn have

influenced the actions of the owners.

Page 23: Risk Management in Construction Projects

School of technology and business

23

CASE OF STUDY Chapter three is the case of study, the different constructions have been built

in different place. This section tells the background of each project and

describes different type of risks occurred in construction projects.

3.1 Case Ⅰ Public building in Denmark

Background of the Project

This realistic project case is new educational building and multi-hall of our

school. This project is under construction. The gross of constructed floor area

is about 7600m2 for educational building and 1600m2 for multi-hall. The

educational building has been started from August.2010 before the schedule of

multi-hall, it has to be finished at July.2011.construction period is nearly 10

months. The multi-hall will be started at May.2011 and finished at

December.2011, and construction period will be nearly 7 months.

As the project client, our school have chosen the total contracting form of

procurement and offer a set of specific detailed brief. CASA A/S will be

responsible for the total co-ordination of the design and the construction. The

bid of price for construction works is approximately 87 million.

In order to get more realistic data, I visited building site of this project, and

had a short talk with him, it was my great honor. Clæs is a senior site manager

from CASA a/s, he has a 20-year experience of site management. He is

responsible for former projects of our school too. His duty of being building site

is to manage the operation of the whole construction phase, especially on

project’s quality, cost and schedule he also takes charge of the communication

Page 24: Risk Management in Construction Projects

School of technology and business

24

with client , sub-contractor ,supplier. Besides, there are two or three

colleagues to help him with these work.

Construction Related Risk

During the meeting with him, my research questions have been mentioned

that How can risk be identified, assessed , control during construction period?

These risks means the risks which have a bad effect on construction?

From the site manager’s aspects, there are four main risks that would affect

the construction period.

1. Safety risk

The first one would be safety risk. According to his opinion, this is the most

important thing that should be paid attention to. Based on plans for safety and

health, all the works should have its own precautions. The site manager has to

make a safe working environment for labors. If any accident happens during

the process, not only the schedule will be delayed but also the other areas will

be affected. Therefore, enough money is supplied to make sure the labor

safety on building site. At the mean time, site manager has to make and

implement a safety and health plan to assure the safety of the working process.

Manually inspections and supervision are also important.

2. Material supply risk

The second one would be risk on material supply. Material supply is a

compulsory part of the construction project. Under the influences of global

economy crisis, many suppliers are facing bankruptcy. By choosing a supplier

without great reputation and funding, it may lead the construction to facing

delay on delivery. If it is during the critical process, it will surely delay the

whole construction. In construction industry, the delay on time always cost

more. It would be a better idea for the total contractor to choose a supplier

Page 25: Risk Management in Construction Projects

School of technology and business

25

company wisely to avoid short of material and delay on delivery. For site

manager, his responsibility would be contacting supplier and arrange the

material delivery and transfer.

3. Unforeseen extra work

Third of all, unforeseen extra work is also one of site manager’s concerns. Most

of the unforeseen extra works take place on soil work. It is because that

geological exploration datum cannot predict and analyze the exact condition of

geology. The rest extra work might happen in other construction work methods.

The site manager stated that during this project, the soil problem has caused a

delay for couples of weeks. However, there is nothing the site manager can do

about this situation.

4. Omissions of construction work

The last main risk would be omissions of construction work. Due to the

consideration of cost, clients all wish to finish the construction as soon as

possible. This will bring a lot of pressure to the total contractor. They are

trying to do their work faster. When rushing into doing things, more mistakes

might happen. As a result, the quality of the construction will highly be

reduced. This leads to the omissions during construction period. However, they

still want to balance the time and quality. Consequently, total contractor will

hire more skilled and experienced workers as compensation. They will pay

attention to the critical parts of the work while speeding up on the easy ones.

And it is known that the Germans are good with concrete element work, the

Italians are good with wet room surface work.

During the period of construction projects, site manager always identify,

assess and control risks based on their own experience. This is also considered

as the most practical and convenient risk management. There are also other

methods which cannot be ignored, such as risk breaking down system,

meetings planning and so on.

Page 26: Risk Management in Construction Projects

School of technology and business

26

3.2 Case II The International project in Vietnam

Background of the Project

This case study relates to the development of a factory to produce yeast in the

southern part of Vietnam. The client is a joint venture based on a 50:50 share

between a France company and a Vietnamese company. The site area is about

40,000m and the gross of constructed floor area about 6,200m2. The contract

sum for construction works is approximately US$10 million. The client informed

that a few consultants and project management firms were invited to submit

fee proposals. French architects, engineers and project managers were

selected as they came from the same country as the foreign client. Project

Planning and design started in late 2001. Due to some problems within the

joint venture and technical issues with the yeast manufacturing method and

process of operating the factory, construction only started in early 2005 and

was expected to be completed in late 2006. However, the project was only

completed in 2008.

through the above description of the background, it is obvious that the project

lasts two years more than the planned time. there must be several risks during

the construction phase such as political risk, legal Risk, financial and economic

risk, design risk, construction risk, etc, and these risks haven't been well under

control at last, thus, affecting project performance. The following part is the

main analysis of risks in construction phase.

Construction Related Risk

The main construction related risk faced in this project was substandard quality

of materials and workmanship. The client's representative had to ensure that

the factory achieved similar quality as the client's other yeast production

Page 27: Risk Management in Construction Projects

School of technology and business

27

factories throughout the world. However, in this project, the client's

representative had to accept a lower quality standard because that was what

the Vietnamese contractors were capable of. The low quality workmanship was

because some of the main contractor's workers were unskilled. They also

had low productivity. The main contractor's excuse was that he needed the

skilled manpower for his other ongoing projects. The lesson learned is that

foreign firms should enter Vietnam knowing that their built facility would not

be of the quality and standard that they are used to in developed countries.

Hence, quality control must be enforced strictly.

The project manager recounted that the contractors changed their site

management staff frequently. In response to this risk, the consultants required

that any change of personnel in the main contracting, nominated and domestic

subcontracting firms would need the project manager's approval.

In this project ,the equipment and materials are easily found in Vietnam.

Specialized items however had to be imported. The local main contractor had

to contend with long delivery time, delay in customs clearance and payment of

tax. There was a long lead-time for equipment to arrive from overseas, and

the main contractor overcame this risk by placing orders early. The delay in,

customs clearance is something that foreign firms should be aware of and build

this into their schedule. Import tax is complicated, and the rate depends on

the type of material and equipment, and when the items arrive in Vietnam.

Firms should therefore build in a large contingency sum for paying import tax

on materials and equipment.

Another construction risk faced by the project was unsafe work practices. The

project manager found that most of the contractors did not have safety

management systems in place. To manage this risk, the main contractor was

Page 28: Risk Management in Construction Projects

School of technology and business

28

required to engage a safety specialist, who must ensure that safe work

practices were adopted, and the working condition on site was safe.

In addition , There is one of risks in construction risks that we should not be

ignored, which is nature risk. Construction work in Vietnam may be affected by

heavy rain. The construction manager explained that in southern Vietnam, the

wet season lasts from May to October. In central Vietnam, flooding may occur

from October to December. In northern Vietnam, the rainy months are August

to November, with February and March having persistent, light, drizzling rain.

The construction manager said that he would undertake construction work that

would be affected by bad weather condition outside of the rainy season. Apart

from planning work to avoid heavy rain, the project did not face any other

severe natural risk that affected construction progress.

THE ANALYSIS AND DISCUSSION

Chapter four is the analysis and discussion, this section’s objective is to

combine results of both the case of study and analytical research in order to

identify the main findings and their relevance and implications to current risk

management practices

4.1 Analysis of case study

Risks may exist throughout the project lifetime from inception to design,

bidding, construction and commission. From previous cases what we have

uncovered is that the main and critical the risks are occurring during

construction period. Actually, in the whole project process, there are other

risks such as political risk, legal risk, financial and economic risks, design risk,

cultural risk. Bureaucracy, inadequate legal framework, high inflation rate,

those issues are significant factors affecting both clients and contractors’

Page 29: Risk Management in Construction Projects

School of technology and business

29

venture. After we know those, effective risk response techniques must be

adopted to manage the risks, such as documentation reviews, checklists

assumptions analysis are used often.

Another effective risk response technique is to use negotiation to solve

problems. It is found to be the most practical and effective way to overcome

difficulties faced in Vietnam. The implication is that practitioners should be well

equipped with negotiation skills when undertaking projects in Vietnam

As the quality of work and safety could be compromised in projects, it is

recommended that contractors provide workers with some training so that they

can achieve certain skills level and safety awareness. Safety management

systems should also be implemented on site.

4.2 Discussion on the problems in project risk management

When the scale of a project is huge, the construction period is quite long. there

will be lots of uncertain factors facing the whole project. At the beginning of

the construction project, the contractor and the owner have already foreseen

that certain factors causing the implementation of the project will definitely

occur during the implementation process. In order to safeguard each interest,

both sides make some special regulations when signing a contract. After

confirming the following factors, the construction period can be delayed

without paying for any fine to the clients undertaking project as long as the

performing units put forward the apply to units in charge of construction. The

factors include:

1. Change of working amount and design

Page 30: Risk Management in Construction Projects

School of technology and business

30

2. Contractors will not be responsible for the damage brought by the work

stoppages because of blackout, short of water supply or gas supply that not

belong to.

3. Force majeure

4. There meet unpredictable obstacle or ancient tombs 、cultural relic、

quicksand which need to be dealt with during the foundation construction.

5. Supplier do not supply the materials in time, the clients do not pay

construction fund on time or any other conditions the client admits.

Then we can avoid direct damage caused by some uncertainties to the project.

In order to make sure that there is no effect on stake, the project manager

cared more about the cost of construction than the construction schedule. So

the study of construction period is still resting on the theory at present and

there is little strict estimate and control on the project period when practicing.

In fact, construction period affects construction expenses directly, delay of the

period lead to change of both direct expenses and indirect expenses and thus

affecting the overall expenses of a project. Therefore, we should evaluate

project construction period reasonably and estimate the construction period

within bounds for that it is quite important for the implementation and

completeness of the whole project.

FINDS AND CONCLUSION

Chapter five contains the findings and conclusions of the study. This part

points out the main research contributions and thinking about the specific

direction what we can still doing further study in future.

5.1 Answering the research questions

Page 31: Risk Management in Construction Projects

School of technology and business

31

5.1.1 Findings about risks be identified during construction period

For that the construction project itself is a complicated system, there are many

influencing factors and various uncertainties result in different consequences.

We can start from the viewpoint of system when identifying uncertainties.

Risk identification is an organized, thorough approach to finding real risks

associated with a project. It is not, however, a process of inventing highly

improbable scenarios in an effort to cover every conceivable possibility. Risks

cannot be assessed or managed until they are identified and described in an

understandable way. We should grasp the major factors among multiple

factors and then analyze the severity of input-output caused by the

uncertainties. The common methods are: Expert interviews, which depend on

veteran like project manager or site manager. Documentation reviews,

Analogy comparisons, Brainstorming, Risk breakdown structure, and Delphi

technique.

In construction projects, the common uncertainties are: soil and geological

conditions、weather conditions、material and equipment deficiency、imperfect

design scope、equipment change、labor productivity、contractor’s neglect of

duty and so on.

5.1.2 Findings about the impact of risks on the construction period

Uncertainties include three facets, operation factor、industry factor and market

factor. These three facets together have an effect on the project construction

period. However, the influences of the three factors made on the construction

Page 32: Risk Management in Construction Projects

School of technology and business

32

period are quite different. Operational risk is on the top, it is the most

uncertainty during the implementation of a construction project.

The follows are the description of the major uncertain factors influencing the

construction period.

1. The Nature risk. Open air、upper air and the underground are the major

building operation field, so the weather plays an important role on the

construction period and safety. For example, flood、earthquake、rainstorm ect.

2. Innovation of design, like using new technique、change of work method

deficiency of design and so on.

3. Equipment failure.

(1) Uncertainty of construction technology: every building is unique and has its

own characteristic. Construction technology needs to be innovated

continuously because of the constant change of the design, and then the

construction technology will meet the risk of “first failure”.

(2) Equipment breakdown.(such as crane, Hydraulic jacks, hydraulic concrete

pumps, welding equipment, demolition devices)

4. Labor productivity.

(1) The quality of construction teams

(2) Mating between labor and equipment: there need many kinds of specialized

type of work cooperating in one project such as carpenter, mason, plumber ,

welder, and so on. Although the enterprises follow the regulations of local

building environment, when they employ workers, scale of project is still so

huge that it need large amounts of teams, therefore, it is hard to say if the job

mating with equipment is reasonable or not.

Page 33: Risk Management in Construction Projects

School of technology and business

33

(3) Employment dynamics: if service operations are according to construction

schedule, keep the working performance as planned, pull the job off up to

standard within the limited time, after hand over or check the completed

project and leave the construction site immediately or not.

5. Materials delay.

(1) Dissatisfactory material quality.

(2) Uncertainty of equipment supply: the major materials used in the

construction are steel、wood、concrete、sands and brick, etc. Although these

construction materials are rich in the domestic market, the big amount of

manufacturers, the different quality of the same material and misuse of

construction companies may affect the construction quality and cause direct

financial loss.

(3) Uncertain price of construction materials: the bid price of the contract in a

construction project includes material prices. The construction period is very

long and if the material prices increase, the income will decrease.

(4) Poor local transportation condition.

6. Soil situation, Geological exploration datum can’t give an overall and exact

explanation of the geology, so soil situation is an indispensable factor.

Uncertainties exist in all kinds of activities of whole construction process and

have an effect on the whole project implementation. The control planning and

traditional work methods when we done before for managing construction

project that do not work because of these uncertainties.

5.1.3 The countermeasures for risks in construction period

According to the above analysis , we can take actions to control those

uncertainties which have great influence on the process of construction so as

Page 34: Risk Management in Construction Projects

School of technology and business

34

to provide a most effective risk control and risk management of the project

period. Moreover, take the following relative measures if necessary:

1. Try to make sure that the project gets up to a high standard on processing

operation and organizational structure, more importantly on the qualifications

of contractor. including the human resource required by the total contractor,

the strong market competiveness, qualified design capacity, complete project

management system, powerful technical support, the ability to purchase

equipments and construction supplies , good communication skill of the

contracts, the ability to face risk, advanced enterprise culture, etc.

2. Raise legal consciousness. We must comply with the law when we sign

contracts, claim indemnity, protect rights, operate, withstand risks, financing

and settle accounts, etc.

3. Implement talent strategy, impart knowledge of construction project

management, risk management, contract management, economy, finance,

insurance, operation control, etc to employees so that the enterprise can own

experts and professional project managers absorbing skills, law, strategy,

operation, foreign language, management.

4. Set specification on construction management, prepare the manuals and

planning by total contractor, in addition, build up their own risk management

system.

5. Take active technical countermeasures, including risk avoidance, risk

reduction, risk prevention, risk transfer and risk retention

Measures to avoid risk

Page 35: Risk Management in Construction Projects

School of technology and business

35

If risks become big threats that the enterprise could hardly bear and control to

the project, we should give up the contract and the project definitely to avoid

greater losses. Moreover, laying down the regulation that certain project

should be prohibited and avoiding the actions which may cause damage are

also good measures to evade risk.

Measures to reduce risk

This kind of measures can reduce the incidence of risk or the damage when

risk occurs. For the known risk, we can use project resources to cut down, for

the predictable or unpredictable risk, we should change it to known risk

through assumption and limited conditions and then take measures to reduce

the possibilities risk happen to a level which risk can be accepted.

Measures to prevent risk

Implement technical supporting and effective control planning to prevent risk.

The aiming is to prevent new risk factors; reduce existing risk factors; reduce

the incidence of risk events

Measures to transfer project risk

Spread the risk to other objects, including owners, subcontractor, partners,

investors, suppliers, etc.

Measures to risk retention

If the damage caused by known risks is not serious, sustain it on one’s own.

And one should have the ability, have emergency measures, back-up actions

and financial reserve.

Page 36: Risk Management in Construction Projects

School of technology and business

36

5.2 The main conclusion

Finally, after resolving the research questions, I would like to make a

conclusion of my report.

At the beginning of this report, I made up my mind the orientation of my study

through learning about the background related to my study aim such as what

is risk, what is risk management. The orientation of my study is the application

of risk management in construction projects. Then I start my study by finding

out literature references via borrowing related books and surfing the Internet.

Next, I list realistic construction projects, each project has its own

characteristic and building sites, so it will meet with various risks. In addition, I

make specific analysis based on what I learn from the document literature. At

last, I provide the resolving methods after theoretical study and case study.

This report tells us what risks will occur during construction period for that

risks have an effect on the cost and schedule of construction projects. I make

my study and description mainly on the schedule. Then presenting what are

the major and common risks influencing construction period that I choose from

numerous factors. In the end, I got the answers like how to ensure as soon as

possible、 how to make reasonable analysis and how to have a good control of

these risks.

As part of the final semester work, I get down to my report and graduation

project at the same time. Considering the writing time and writing depth , it is

a challenge for me. Nevertheless, I still try my best to search literature and

references and have profound study. I treat a better final report as my pursuit.

Page 37: Risk Management in Construction Projects

School of technology and business

37

5.3 Future research

I have learnt a lot what I did not know before through finishing this report,

which enrich my learning experience and broaden my horizon of project

management.

As is known to all, there are still many risks, which need us to solve. Risk

management has a wide usage, for example, we can apply risk management

to the analysis and management of the existing and possible risks from the

design phase to the construction phase.

Regarding writing time and writing scope, I narrow my report to a specific

aspect, which describes what risks are there during construction period and

what are the common risks affecting construction schedule. This is just a small

part of risk management application in construction projects. Moreover, there

is no more deep study of other aspects in this report.

Based on the report, we can make further analysis and study about the risks,

which affect construction cost for the further study to ensure budget balance of

construction projects, and maximum value of clients such as the study of what

factors may cause cost change except extension of construction time. There is

one of aspects of risk management is worth doing it.

Page 38: Risk Management in Construction Projects

School of technology and business

38

References

Jaafari, A. (2001). Management of risks, uncertainties and opportunities on

projects: time for a fundamental shift. International Journal of Project

Management, 19(2), 89-101.

Azinim, M. & Edum-Fotwe, F. T. (2006, 18-20 October). Risk management

practices of construction project staff: Preliminary lessons. Paper presented at

the Construction in the XXI Century- Local and global

challenges, Rome.

L.P. Gragg and J.M. Cassell, Progress in Management Engineering,pp. 173 -

197.2009 Nova Science Publishers, Inc.

CarL.Pritchard, risk management ,concepts and guidance pp28-54,2005 third

edition. printed in the United states of America

R.max wideman fellow,PMI, risk management - a guide to managing project

risks and opportunities, 1992,project management insitiute .inc.

Kajsa Simu, The Construction Site Manager’s Impact on Risk Management

Performance, doctoral thesis, 2009,Lulea, Sweden

http://civilengineerblog.com/risks-construction-projects/

Page 39: Risk Management in Construction Projects

Appendices

Appendix A

EXAMPLE OF RISK ASSESSMENT PLANING

Appendix B

EXAMPLE OF RISK ASSESSMENT PLANING 2

Page 40: Risk Management in Construction Projects

RISK ASSESSMENT

CLIENT

Who is he?

Esbjerg KommuneTorvegade 746700 Esbjerg

Liquidity

In all domain, the financial situation is not the bestright now but Esbjerg Kommune is the state andthey will have the money to finance the project

Experience

NO - DD Contractors has no experience withEsbjerg Kommune

Architect

Årstiderne ArkitektDalgasgade 117400 Herning

Experience Big experience with all kind of projects

Reputation

DD contractors havealready work withÅrstiderne Arkitekt

Engineer

RambøllDokken 106700 Esbjerg

Experience Big experience with all kind of projects

Reputation

DD contractors havealready work with Rambøll

PROJECT

Is the tender materials okay?

NO- Missing some of the tender documents

Specifications Okay

Have we tried this type of work before?

Yes, we have beenworking with this type ofwork before

Is it the time schedule realistic? Yes but of course some surprises can appear

Is the plan for safety and health okay?

No - DD contractors haven'treceived any basic plan for safetyand health

Is it new technology? Normal technology but more difficult than normalRESOURCES

Do we have time?Yes

Do we have the materialWe have

Can we have the necessarymachinery?Yes

Do we have the manpower/staff

Our trade (Ground, Soil, concreteand mounting element work

Other tradeNo

Do we need subcontractors

Yes but some risk due to thefinancial crisis (bankruptcy)

No, so need to ask for othersubcontractors

SURROUNDING

Weather (summer/Winter)Winter (1.11.09 to 31.03.10)Need some winter precautions

Winter (1.11.10 - 15.12.10Summer (1.04.10. to 01.07.10)

Delivery conditionsEasy access to the building site

Geographical conditionsOkay but of course not perfect

Competitors (other contractors)

Who are there?Unknown

Well working??

Expensive??

Position of the site

Idræts Alle 10,6740 Bramming

Flat plot

No big vegetation

Good accessibility (main road,...)

Big space

NeighboursResidential area

Green area

TransportGood access for big trucks

Only 3.5 km from the Motorway

PropertyPlaced on a big plot

Page 41: Risk Management in Construction Projects

Risk Assessments 

 

 

Small risk = Level 1 & 2  

Medium risk = Level 3 & 4 

High risk = Level 5 

  

Level 1  Level 2  Level 3 Level 4  Level 51 x  14 x  7 x 6 x 6 x1  28  21 24 30

 

→ 1 + 28 + 21 + 24 + 30 = 104             ↘ 104 : 34 = 3    

    → Risk for the project is 3