Risk Management April 8 th , 2014
71

Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions “What must be done?” “When will it be done?” “Who will build it?”

Dec 29, 2015

Download

Documents

Theodore Adams
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Risk Management

April 8th, 2014

Page 2: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

…recap::WBS and Scheduling

Answer the questions “What must be done?” “When will it be done?” “Who will build it?”“How much will it cost?”

2

Page 3: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

…recap::WBS and Scheduling

PMBOKWBS is part of Project Scope ManagementSchedule is part of Time Management

Process

3

Page 4: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

...recap::WBS

Definition: A WBS is a hierarchy of elements that decomposes

the project plan into discrete work tasks.

WBS Elements Delineation of all significant work Clear task decomposition for assignment and

responsibilities Framework for scheduling, budgeting and expenditure

tracking

4

Page 5: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

...recap::WBS – The Project Plan Architecture WBS is the project’s plan “architecture”

It must encapsulate change It must evolve with the appropriate level of

detail through the project lifecycle It must cover ALL project tasks

WBS Deliverables must be SMART: Specific, Measurable, Attainable, Relevant, Time-limited

5

Page 6: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

...recap::Project Schedule

Estimating Once tasks have been identified, the time and

resources necessary to accomplish them must be determined.

6

Page 7: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

...recap::Schedule Estimating

Project Manager (and the management team) develop a characterization of overall size, process, environment, people and quality for the overall project

A macro-level estimation of the total effort and schedule is developed

A high-level WBS is developed Team leaders and developers estimate

individual tasks

7

Page 8: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

GANTT (MS Project)

8

Page 9: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Network Diagrams

9

Page 10: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Risk Management Topics

Risk Management Principles Process Indicators

References MCSD Self-Paced Training Kit: Analyzing Requirements and

Defining Microsoft .NET Solution Architectures, Microsoft Press Managing Iterative Software Development Projects, Kurt Bittner,

Ian Spence, Addison Wesley 2006 RUP

10

Page 11: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Primary SDP themes

Getting the design right by focusing on architecture first

Managing risk through iterative development Reducing complexity by using components and

services Making software progress and quality tangible

through instrumented change management Automating the overhead and bookkeeping by

using automation and round-trip engineering tools

11

Page 12: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Risk Management

Risk Management begins with Risk AwarenessSickness of a skilled resourceDelivery fail for a supplierPoor performance of a work package

12

Page 13: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Risk Management Process

Risk Identification Risk Assessment Risk Evaluation Risk Management

13

Page 14: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Risk Identification [1] Risk Identification determines which risks might

affect the project and documents their characteristics

Participants in risk identification activities can include the following : Project managerProject team membersRisk management teamCustomersEnd users

14

Page 15: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Risk Identification [2]

Risk Identification is an iterative process New risks may become known as the

project progresses through its life cycle

15

Page 16: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Risk Identification [3] Identify activities that may be affected by

unexpected events Risks can be identified in a number of ways

General Risks – can happen to any task, resource or project

Risk specific to the projectRisks applicable to one taskResource specific risks

16

Page 17: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Risk Identification [4]

Review the schedule with experienced peopleRefer to previous projects files and archivesBrainstorm likely events that may occur in

your projectPerform SWOT analysis (Strength,

Weaknesses, Opportunities, Threats)

17

Page 18: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Checklist [1]

Key member of staff on critical path Key skill on long-duration task Project Manager on critical path External dependencies without tight contract Reliance on leading-edge technologies Many internal dependencies with conflicting

priorities

18

Page 19: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Checklist [2]

Ramping up resources Assumptions about availability of people

and equipments Vacation time resource absences Site shutdown for maintenance Health and safety requirements and

certifications

19

Page 20: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Checklist [3]

Identify risks that translate to project slippage

Identify near critical path that could become critical

Identify slack for non critical path Identify risks on critical path that translate

to slippage

20

Page 21: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Risk Identification Output The outputs from Risk Identification are

typically contained in a document that can be called a risk register and contains :List of identified risks The identified risks, including their root causes and

uncertain project assumptions, are describedList of potential responsesRoot causes of riskUpdated risk categories

21

Page 22: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Risk Register

22

Page 23: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

MSF Risk Register

Simple Risk Assessment.xls

23

Page 24: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Risk Assessment

Identify Probability and Impact of each risk Key question: what event will have an

influence on the project? Probability: How likely is it to happen? Impact: What will be the consequences?

24

Page 25: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Qualitative Risk Assessment Qualitative Risk Analysis includes methods

for prioritizing the identified risks for further action, such as :Quantitative Risk Analysis Risk Response Planning

Qualitative Risk Analysis determines the priority of identified risks using their probability of occurring and the corresponding impact on project objectives

25

Page 26: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Analyzing risks

Identify uncertainties surrounding project decisions and outcomes

Identify mitigation plans for risks that are inherent in a project

Risk concept is often associated with the potential for loss in value, control, functionality, quality, or timeliness of completion of a project.

failure to maximize gain in an opportunity and uncertainties in decision making that can lead to a missed business opportunity.

26

Page 27: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Qualitative Assessment Tools Probability and Impact Matrix

Ratings are assigned to risks based on their assessed probability and impact

Evaluation of each risk’s importance is conducted using a probability and impact matrix, which is used to rating the risks as low, moderate, or high priority

The organization should determine which combinations of probability and impact result in a classification of high, moderate and low risk

27

Page 28: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Risk matrix example

Low Medium High Critical

Cost Insignificant <5% <10% >10%

Time Insignificant <10 days <25 days >25 days

Scope Insignificant No business impact

Some business impact

Definite business impact

Quality Insignificant No anticipated problems

Potential for problems

Definite problems

28

Page 29: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Risk Exposure

29

Page 30: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Evaluation example

Critical > 70 Medium > 50 Low < 50

30

Page 31: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Quantitative Risk Assessment [1] Is performed on risks that have been

prioritized as High-Risks by the Qualitative Risk Analysis process

Analyzes the effect of those risk events and assigns a numerical rating to those risks

31

Page 32: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Quantitative Risk Assessment [2]

Uses techniques such as Monte Carlo simulation and decision tree analysis to:Quantify the possible outcomes for the project

and their probabilities Identify risks requiring the most attention by

quantifying their relative contribution to overall project risk

32

Page 33: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Example – Inadequate training

33

Low Medium High Critical

Cost Insignificant <5% 6 <10% >10%

Time Insignificant <10 days <25 days >25 days 27

Scope Insignificant 5 No business impact

Some business impact

Definite business impact

Quality Insignificant No anticipated problems

Potential for problems

14 Definite problems

6+27+5+14 = 52 => Medium exposure

Page 34: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Exercise

Prototyping is worthwhile on the project?

34

Page 35: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Answer

35

Page 36: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Another exercise

36

Page 37: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Risk Assessment Document Risk statements, which capture the nature of each risk Risk probability, which describes the likelihood of the

occurrence of the risk Risk severity, which specifies the impact of the risk Risk exposure, which specifies the overall threat of the

risk Mitigation plans, which describe the efforts for preventing

or minimizing the risk Contingency plans and triggers, which specify the steps

that you need to take when a risk occurs and when to take those steps

Risk ownership, which specifies the name of the team member who is responsible for monitoring the risk on a regular basis

37

Page 38: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Risk Assessment Metrics

Probability and impact can be weighted in many ways:High/medium/low0-100%Banded: 0-10%, 11-30%...

38

Page 39: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Risk Evaluation [1]

Risks can be placed on a graph according to probability and impact

Decide the zone on the graph that contains unacceptable risks:Depends on organizationDepends on domainDepends on project

39

Page 40: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Risk Evaluation [2]

To move each risk out of that zone:Reduce the probabilityReduce the impact

=> Reduce exposure These actions are recorded in the risk register:

Mitigation (what will be done to prevent?)Triggers (when will it be done?)Responsible (who will do it?)

40

Page 41: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Risk Management Chart

41

Page 42: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Another Example

High Risk : dark gray (largest numbers)Moderate risk : light gray (in-between numbers)Low risk : medium gray (smallest numbers)

42

Page 43: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Principles of Risk Management

Proactive Continuous

MonitoringAssessmentDecision making

Expected result: Continuous risk reduction

43

Page 44: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Risk management approach

The team continuously assesses, monitors, and actively manages risks until they are:either resolved or turned into problems to be handled as such.

44

Page 45: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Continuous Risk Reduction For a successful iterative project the risk

evolution vs. implemented functionality should look like the diagram below.

45

Page 46: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Risk Metrics

MeasurementsEP - Total Project Exposure

Ei – Exposure for Risk i

Ii – Impact for Risk i

Pi – Probability for Risk i

46

Page 47: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Risk Metrics Trend

47

Risk Exposure Metric (should → 0)

Risk Exposure Metric Trend (should <0)

i

n

ii

n

iiP IPEE

11

*

dt

dEE pP

Page 48: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Risk management process (MSF example) The risk management process in MSF

defines six logical steps through which the team manages current risks, plans and executes risk management strategies, and documents knowledge for the enterprise

48

Page 49: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Risk Management Steps [1]

Risk identification – allows individuals to identify risks so that the team becomes aware of any potential problems.

Risk analysis – transforms the estimates or data about specific project risks that emerges during risk identification into a form the team can use to make decisions about prioritization.

Risk planning – uses the information obtained from risk analysis to formulate strategies, plans, and actions.

49

Page 50: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Risk Management Steps [2]

Risk tracking – monitors the status of specific risks and documents the progress in their respective action plans.

Risk control – is the process of executing risk action plans and their associated status reporting.

Risk learning – formalizes the lessons learned and relevant project documents and tools, and records that knowledge in reusable form for use within the team and by the enterprise.

50

Page 51: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Risk Management Process

51

Page 52: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Risk Management Plan Development Define risk management procedures and tools Create initial risk list Assign risk management team Decide strategies for managing top 10 risks Define risk indicators for top 10 risks Set schedule for risk reporting and review

52

Page 53: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Risk Response Planning

Develop options and determine actions to enhance opportunities and minimize threats to project objectives

Assign responsibility to individuals or parties for each risk response.

53

Page 54: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Risk Response Planning

Risk response must be:Proportional to the severity of the riskCost effectiveTimelyRealisticAccepted by all parties involvedOwned by a person or a party

54

Page 55: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Risk Response Strategies (-)

Avoidance Reduction (Mitigate) Transfer Acceptance

55

Page 56: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Risk Response Strategies (+)

Exploit (opposite to Avoidance) Enhance (opposite to Reduce) Share (opposite to Transfer) Acceptance

56

Page 57: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

ExerciseDescription Strategy

Remove a work package from the project Avoid

Assign a team member to visit the suppliers’ facility Mitigate impact

Move a work package to a date when a more experienced resource is available

Exploit

Begin negotiation for an equipment early to insure a better price

Enhance impact

Notify management that there could be a cost increase due to a risk because no action was taken to

Accept

Provide a team member having limited experience with additional training

Mitigate probability

Outsource difficult work to a more experienced company Transfer

Prototype a risky piece of equipment Mitigate probability

Ask the client to handle some of the work Transfer

57

Page 58: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Risk Management Tool

Risk Template Tool.xls

58

Page 59: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Types of risks (from RUP)

Resource Risks Business Risks Technical Risks Schedule Risks

59

Page 60: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Resource Risks (1)

Organization Is there sufficient commitment to this project

(including management, testers, QA, and other external but involved parties)?

Is this the largest project this organization has ever attempted?

Is there a well-defined process for software engineering?

60

Page 61: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Resource Risks (2)

Funding Is the funding in place to complete project? Has funding been allocated for training and

mentoring? Are there budget limitations such that the

system must be delivered at a fixed cost or be subject to cancellation?

Are cost estimates accurate?

61

Page 62: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Resource Risks (3)

People Are enough people available? Do they have appropriate skills and experience? Have they worked together before? Do they believe the project can succeed? Are user representatives available for reviews? Are domain experts available?

62

Page 63: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Resource Risks (4)

Time Is the schedule realistic? Can functionality be scope-managed to meet

schedules? How critical is the delivery date? Is there time to "do it right"?

63

Page 64: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Business Risks

What if a competitor reaches the market first? What if project funding is jeopardized (the other

way to look at this is to ask "what can assure adequate funding")?

Is the projected value of the system greater than the projected cost? (be sure to account for the time-value of money and the cost of capital).

What if contracts cannot be made with key suppliers?

64

Page 65: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Technical Risks (1)

Scope risks Can success be measured? Is there agreement on how to measure success? Are the requirements fairly stable and well

understood? Is the project scope firm or does the scope keep

expanding? Are the project development time scales short and

inflexible?

65

Page 66: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Technical Risks (2) Technological risks

Has the technology been proven? Are reuse objectives reasonable?

An artifact must be used once before it can be re-used. It may take several releases of a component before it is stable enough to reuse without

significant changes. Are the transaction volumes in the requirements reasonable? Are the transaction rate estimates credible? Are they too optimistic? Are the data volumes reasonable? Can they be held on currently available mainframes, or, if

the requirements lead you to believe a workstation or departmental system will be part of the design, can the data reasonably be held there?

Are there unusual or challenging technical requirements that require the project team to tackle problems with which they are unfamiliar?

Is success dependent on new or untried products, services or technologies, new or unproven hardware, software, or techniques?

Are there external dependencies on interfaces to other systems, including those outside the enterprise?  Do the required interfaces exist or must they be created?

Are there availability and security requirements which are extremely inflexible (for example, "the system must never fail")?

Are the users of the system inexperienced with the type of system being developed? Is there increased risk due to the size or complexity of the application or the newness of the

technology? Is there a requirement for national language support? Is it possible to design, implement, and run this system? Some systems are just too huge or

complex to ever work properly. 66

Page 67: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Technical Risks (3)

External dependency risk Does the project depend on other (parallel)

development projects? Is success dependent on off the shelf products or

externally-developed components? Is success dependent on the successful integration of

development tools (design tools, compilers, and so on), implementation technologies (operating systems, databases, inter-process communication mechanisms, and so on). Do you have a back-up plan for delivering the project without these technologies?

67

Page 68: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Schedule risks

Are indicated by metrics complexityreal-time constraintsstorage constraints experience availability of good toolsschedule pressure

68

Page 69: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Risk indicators

Total impact of top ten risks Top ten risks mitigation costs Top ten risk variation Top ten risks impact variation

69

Page 70: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Risk management key points

One of the iterative development main benefits is improved risk management

Risks should be monitoredContinuouslyProactively

Risk management should be planned and the effort for it estimated (if the effort exceeds the risk, it is not risk)

70

Page 71: Risk Management April 8 th, 2014. …recap::WBS and Scheduling Answer the questions  “What must be done?”  “When will it be done?”  “Who will build it?”

Next time

Project Monitoring and Control