1 Right-of-Way Industry Forum SR 400 Express Lanes PI 0001757 Fulton/Forsyth Joe Carpenter, PE – P3 Director Tim Matthews, PE – MMIP Program Manager January 8, 2019
1
Right-of-WayIndustry ForumSR 400 Express Lanes PI 0001757 Fulton/Forsyth
Joe Carpenter, PE – P3 DirectorTim Matthews, PE – MMIP Program Manager
January 8, 2019
2
Disclaimer Statement
At this meeting the Department will provide information about the project’s delivery goals, anticipated scope, anticipated Design-Build procurement process, and potential risks. Participants will be encouraged to ask questions during this meeting; however, any information provided by the Department shall be considered as informational only and is subject to change.
3
We Will Cover
• Major Mobility Investment Program• SR 400 Express Lanes• Disadvantaged Business Enterprise (DBE) Program• Right-of-Way (ROW) Services for the Office of Innovative Delivery
(OID)• Open Discussion
4
Major Mobility Investment Program
5
11 MMIP Projects
3 Major Interchange
Projects
4 Major Express Lanes Projects
3 Major Interstate Widening Projects
1 Commercial Vehicle Lanes
Project
6
MMIP Project Locations
7
MMIP Schedule
8
Consultant Opportunities
9
Disadvantaged Business Enterprises
10
Program Delivery Model- PMC & GECs
11
DBE Goal and Mentoring Program
• 15% DBE Goal for GECs• GEC Mentoring Program
o RFQ may require Mentoring Program implementation plan
12
SR 400 Express Lanes
13
SR 400 Express Lanes Overview
• Anticipate Design-Build-Finance-Operate-Maintain (DBFOM) delivery method –Availability Payment Approach
• Two express lanes in each direction along SR 400 between I-285 and McGinnis Ferry Road
• One express lane in each direction from McGinnis Ferry Road to McFarland Parkway
• Will directly connect to I-285 Top End Express Lanes• Intermediate access points to be determined
• Estimated Cost: $1.8 Billion• Est. Construction Letting: Q4 2020
15
SR 400 Express Lanes
• I-285 to McGinnis Ferry Road • Two express lanes in each direction (illustrative example)
Express lanes
Bi-directional(Buffer Separated)
Express Lanes
16
SR 400 Express Lanes
• McGinnis Ferry Road to McFarland Parkway• One express lane in each direction (illustrative example)
Express lanes
Bi-directional(Buffer Separated)
Express Lanes
17
SR 400 Express Lanes Project Status
Scoping Phase• Traffic analysis• Access testing• Coordination with Stakeholders, SRTA, and MARTA• Environmental field work
GEC Pre-Let Status• Concept Approval Q1 2019• PIOH Q1 2019• Advance ROW Acquisitions • DBFOM Development and Technical Provisions• Issue NOIA/PNA Q2 2019• Issue RFQ Q3 2019• Issue Preliminary RFP Q1 2020• Costing Plans Set Complete & Draft RFP Q2 2020• Final NEPA Approval Q3 2020• Issue Final RFP Q3 2020• Letting/Proposer Selection Q4 2020
18
SR 400 Express Lanes Schedule
Project Phases 2017 2018 2019 2020
2021
2022
2023
2024
Environmental
Design-Build Procurement
Right-of-Way
Final Design
Construction Schedule subject to change
Early ROW acquisition
19
SR 400 Express Lanes Next Steps
• Environmental phase• Concept approval• Future conditions operational analysis• Opportunity for early ROW acquisition
20
Right-of-Way Services forOffice of Innovative DeliveryPhil CopelandPMC Right-of-Way Lead
21
Anticipated Right-of-Way ServiceClasses for the Prime
22
Anticipated Right-of-Way ServiceClasses for Sub-consultants
Number Right-of-Way Acquisition Services10.3.1 Appraisal Report10.3.3 Cost to Cure Report10.3.4 Trade Fixture Report10.3.5 Sign Report10.3.9 Detailed Cost Estimator10.4.1 ROW Project Manager10.4.2 Pre-Acquisition10.4.3 Acquisition10.4.4 Negotiation through Closing10.4.5 Relocation (Negotiations)10.1.2 Relocation (Benefits Package Preparation)
23
MMIP Right-of-Way Service ProviderRoles & Responsibilities
Pre-Let• Cost Estimates• Conceptual Plan Review and Coordination with GEC• Pre-Acquisition Activities• Status Meetings• Right-of-Way Plan Revisions• Offer Packages and Negotiations• Closing Preparation• Property Management• Relocation Activities• Detailed Record Keeping• e-Builder Utilization
24
MMIP ROW Keys to Success
• Experienced Project Manager• Qualified Key Team Agents• Appropriate Team Structure• Proven Responsiveness• Proactive Coordination• Committed to DBE Success• Schedule Expeditor• Innovative Delivery Approaches
25
RFP Overview
• Approximately 50 Parcels• Anticipated 18-24 Months Duration• GDOT will evaluate price and technical approach• DBE Goal• Conflict of Interest-Refer to GDOT Design-Build Manual for More Info
26
Team Requirements# of Agents Number Valuation/Acquisition Services
4 10.3.1 Appraisal Report2 10.3.3 Cost to Cure Report1 10.3.4 Trade Fixture Report1 10.3.5 Sign Report1 10.3.9 Detailed Cost Estimator1 10.4.1 ROW Project Manager1 10.4.2 Pre-Acquisition1 10.4.3 Acquisition Manager2 10.4.4 Negotiation through Closing2 10.4.5 Relocation (Negotiations)1 10.1.2 Relocation (Benefits Package Preparation)
27
Work From Conceptual Overlay to…
28
Anticipated Procurement Schedulea. GDOT issues Public Notice Advertisement (PNA) 12/18/2018 ----------
b. Industry Forum/Pre-Bid Meeting – GDOT 01/08/2019 9:00 AM
c. GDOT issues Request for Proposal (RFP) 01/15/2019 -----------
d. Proposal Due
e. Anticipated Award of ROW Service Provider
02/15/2019
April 2019
-----------
-----------
Tentative dates and subject to change. Refer to RFQ.
29www.dot.ga.gov/MMIP@GeorgiaDOT @GADeptofTrans @gadeptoftrans
THANKYOU
For Viewing