RIG & LIFTBOAT MOVE PLANNING & EXECUTION Name Title Company Name Presented by: Capt Bjarke Pedersen Deputy Director, Fleet Operations
22

RIG & LIFTBOAT MOVE PLANNING - energy.gov.bnenergy.gov.bn/Shared Documents/HSSE/Information Sharing... · RIG & LIFTBOAT MOVE PLANNING & EXECUTION Name Title Company Name Presented

Apr 24, 2018

Download

Documents

dinhtuong
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: RIG & LIFTBOAT MOVE PLANNING - energy.gov.bnenergy.gov.bn/Shared Documents/HSSE/Information Sharing... · RIG & LIFTBOAT MOVE PLANNING & EXECUTION Name Title Company Name Presented

RIG & LIFTBOAT MOVE PLANNING & EXECUTION

NameTitleCompany Name

Presented by: Capt Bjarke PedersenDeputy Director, Fleet Operations

Page 2: RIG & LIFTBOAT MOVE PLANNING - energy.gov.bnenergy.gov.bn/Shared Documents/HSSE/Information Sharing... · RIG & LIFTBOAT MOVE PLANNING & EXECUTION Name Title Company Name Presented

Lessons Learned from Incidents

Lessons Learned from other Jackup Incidents

Page 3: RIG & LIFTBOAT MOVE PLANNING - energy.gov.bnenergy.gov.bn/Shared Documents/HSSE/Information Sharing... · RIG & LIFTBOAT MOVE PLANNING & EXECUTION Name Title Company Name Presented

Key Assessment Criteria & Information

Teras Internal procedures in place for the Unit Specific Operations Manual

Key details including dimensions, number of legs, weigh,. Jacking system, pre-load details, wind areas etc.

Location Assessment / Site Specific AssessmentWater depth, Metocean conditions, airgap

seabed (topographic, debris, etc) and sub-seabed data (strength of soil)

Operations Time of year & duration of proposed operations, nature of operations.

Crane serviceable range, accommodation requirements

Verified by Marine Warranty Surveyor (MWS) with Certificate of Approval.

Page 4: RIG & LIFTBOAT MOVE PLANNING - energy.gov.bnenergy.gov.bn/Shared Documents/HSSE/Information Sharing... · RIG & LIFTBOAT MOVE PLANNING & EXECUTION Name Title Company Name Presented

Control Measures in place

Conduct of Geophysical & Geotechnical Survey

Suitability Checks Methods

Rig Strong Enough

- Based on site specific metocean & soils data- Within limited operating envelopes- Structural integrity checks

Legs Long Enough - Subject to the following- Rig stated operating water depth- Sufficient height for harsh metocean- Leg penetration

Location Hazards/ Position

- Avoid overlapping old footprint where possible- Avoid seabed debris- Hull is above extreme water level- Spudcan to platform / pile proximity - Hull / platform proximity afloat

Page 5: RIG & LIFTBOAT MOVE PLANNING - energy.gov.bnenergy.gov.bn/Shared Documents/HSSE/Information Sharing... · RIG & LIFTBOAT MOVE PLANNING & EXECUTION Name Title Company Name Presented

Rig Strong Enough

Bearing Capacity

Page 6: RIG & LIFTBOAT MOVE PLANNING - energy.gov.bnenergy.gov.bn/Shared Documents/HSSE/Information Sharing... · RIG & LIFTBOAT MOVE PLANNING & EXECUTION Name Title Company Name Presented

Reserve of leg above jack-house

Water depth

Leg penetration

Air gap

Legs Long Enough

Does it fit?Max predicted penetration

Water Depth

Air gap (min or per client)

Page 7: RIG & LIFTBOAT MOVE PLANNING - energy.gov.bnenergy.gov.bn/Shared Documents/HSSE/Information Sharing... · RIG & LIFTBOAT MOVE PLANNING & EXECUTION Name Title Company Name Presented

Location Hazards

Rapid spudcan penetration

Uneven seabed

Footprints

Debris

Pipelines & Cables

Boulders

Spudcan-pile interaction

Buried / infilled channels

Page 8: RIG & LIFTBOAT MOVE PLANNING - energy.gov.bnenergy.gov.bn/Shared Documents/HSSE/Information Sharing... · RIG & LIFTBOAT MOVE PLANNING & EXECUTION Name Title Company Name Presented

Location Hazards

Footprints

Uneven seabed

Pipelines & Cables

Page 9: RIG & LIFTBOAT MOVE PLANNING - energy.gov.bnenergy.gov.bn/Shared Documents/HSSE/Information Sharing... · RIG & LIFTBOAT MOVE PLANNING & EXECUTION Name Title Company Name Presented

Location Hazards

Uneven Seabed Debris

Page 10: RIG & LIFTBOAT MOVE PLANNING - energy.gov.bnenergy.gov.bn/Shared Documents/HSSE/Information Sharing... · RIG & LIFTBOAT MOVE PLANNING & EXECUTION Name Title Company Name Presented

Location Hazards

Boulders

Visible in bathymetry / debris survey

Boulders

Page 11: RIG & LIFTBOAT MOVE PLANNING - energy.gov.bnenergy.gov.bn/Shared Documents/HSSE/Information Sharing... · RIG & LIFTBOAT MOVE PLANNING & EXECUTION Name Title Company Name Presented

Location Hazards

Spudcan-pile Interaction

Safe distance from the existing leg structure

Piled foundation structural integrity interaction

Page 12: RIG & LIFTBOAT MOVE PLANNING - energy.gov.bnenergy.gov.bn/Shared Documents/HSSE/Information Sharing... · RIG & LIFTBOAT MOVE PLANNING & EXECUTION Name Title Company Name Presented

Location Hazards

Buried / Infilled ChannelsDifferent penetration response

Excessive penetration

Eccentric loading

Page 13: RIG & LIFTBOAT MOVE PLANNING - energy.gov.bnenergy.gov.bn/Shared Documents/HSSE/Information Sharing... · RIG & LIFTBOAT MOVE PLANNING & EXECUTION Name Title Company Name Presented

Rig Strong Enough

Spudcan Penetration Responses

Page 14: RIG & LIFTBOAT MOVE PLANNING - energy.gov.bnenergy.gov.bn/Shared Documents/HSSE/Information Sharing... · RIG & LIFTBOAT MOVE PLANNING & EXECUTION Name Title Company Name Presented

Rig Move Procedure

Page 15: RIG & LIFTBOAT MOVE PLANNING - energy.gov.bnenergy.gov.bn/Shared Documents/HSSE/Information Sharing... · RIG & LIFTBOAT MOVE PLANNING & EXECUTION Name Title Company Name Presented

Approach Plan

Page 16: RIG & LIFTBOAT MOVE PLANNING - energy.gov.bnenergy.gov.bn/Shared Documents/HSSE/Information Sharing... · RIG & LIFTBOAT MOVE PLANNING & EXECUTION Name Title Company Name Presented

Final Position

Page 17: RIG & LIFTBOAT MOVE PLANNING - energy.gov.bnenergy.gov.bn/Shared Documents/HSSE/Information Sharing... · RIG & LIFTBOAT MOVE PLANNING & EXECUTION Name Title Company Name Presented

Side Profile

Page 18: RIG & LIFTBOAT MOVE PLANNING - energy.gov.bnenergy.gov.bn/Shared Documents/HSSE/Information Sharing... · RIG & LIFTBOAT MOVE PLANNING & EXECUTION Name Title Company Name Presented

Teras OffshoreLiftboat Simulation Training

Manoeuvring & Bridge Resource Management Training

Page 19: RIG & LIFTBOAT MOVE PLANNING - energy.gov.bnenergy.gov.bn/Shared Documents/HSSE/Information Sharing... · RIG & LIFTBOAT MOVE PLANNING & EXECUTION Name Title Company Name Presented

Lift Boat Simulation Training Centre (LSTC)

19 of 23

Page 20: RIG & LIFTBOAT MOVE PLANNING - energy.gov.bnenergy.gov.bn/Shared Documents/HSSE/Information Sharing... · RIG & LIFTBOAT MOVE PLANNING & EXECUTION Name Title Company Name Presented

Lift Boat Simulation Training Centre (LSTC)

Simulator assessment of candidates supported by feedback from other departments, e.g. Technical, Crewing, Operations and HSE.

20 of 23

Page 21: RIG & LIFTBOAT MOVE PLANNING - energy.gov.bnenergy.gov.bn/Shared Documents/HSSE/Information Sharing... · RIG & LIFTBOAT MOVE PLANNING & EXECUTION Name Title Company Name Presented

Lift Boat Simulation Training Centre (LSTC)

Scenarios designed based on Competency Requirements.

Scenarios include environmental factors, i.e. wind, current, swell height.

21 of 23

Page 22: RIG & LIFTBOAT MOVE PLANNING - energy.gov.bnenergy.gov.bn/Shared Documents/HSSE/Information Sharing... · RIG & LIFTBOAT MOVE PLANNING & EXECUTION Name Title Company Name Presented

Lift Boat Simulation Training Centre (LSTC)

Visual aids to facilitate trainee’s learning.

Trainer’s feedback and comments during and immediately after trainee’s session.