Federal Aviation Administration Rick Etter Airports Acquisition Specialist FAA, Office of Airport Planning and Programming International Right-of-Way International Right-of-Way Association Association Federal Agency Update Federal Agency Update Washington, DC Washington, DC March 21, 2012 March 21, 2012 FAA Airports Programs
22
Embed
Rick Etter Airports Acquisition Specialist FAA, Office of Airport Planning and Programming
FAA Airports Programs. International Right-of-Way Association Federal Agency Update Washington, DC March 21, 2012. Rick Etter Airports Acquisition Specialist FAA, Office of Airport Planning and Programming. FAA Airport Programs. FAA Airports Overview. Who we are. What we do. - PowerPoint PPT Presentation
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Federal AviationAdministration
Rick EtterAirports Acquisition SpecialistFAA, Office of Airport Planning and Programming
International Right-of-Way AssociationInternational Right-of-Way AssociationFederal Agency UpdateFederal Agency Update
IRWA Federal Agency UpdateMarch 21, 2012Washington, DC
4Federal AviationAdministration
Core Functions
Airport Planning and Programming Airport Engineering / Safety / Certification Airport Noise and Environmental
Assessments Airport Compliance
IRWA Federal Agency UpdateMarch 21, 2012Washington, DC
5Federal AviationAdministration
Airport owners and operators
Traveling public
Airlines and other aviation system users
Neighboring and impacted communities
State aeronautical agencies
Elected and appointed officials (Federal, state and local)
Other units within the FAA (e.g., Air Traffic Organization, Runway Safety Office, Flight Standards, Flight Procedures, Policy Office)
Other Federal agencies (e.g., FHWA, TSA, EPA, Corps of Engineers, etc.)
Federal oversight units (GAO, OIG, OMB)
Key Stakeholders
IRWA Federal Agency UpdateMarch 21, 2012Washington, DC
6Federal AviationAdministration
AIP Federal-aid Airport SystemNational Plan of an Integrated Airport System (NPIAS)
The NPIAS identifies, for Congress and the public, the composition of a national system of airports together with the airport development and costs necessary that will be needed over the next 10 years
Airport Improvement Program
IRWA Federal Agency UpdateMarch 21, 2012Washington, DC
7Federal AviationAdministration
How is an Airport Project defined?
One ODO for single or multi-phase project
Runway extension (ODO) may include: • Environmental Assessment• Project Design• Land Acquisition (Concurrent/Prior)• Relocating NAVAIDS• Parallel Taxiway• Hold Apron• Construction of Extension• Lighting, Marking, Signage, etc• Commissioned
• Includes all necessary components & tasks to provide required functional utility, satisfying the Overall Development Objective (ODO)
IRWA Federal Agency UpdateMarch 21, 2012Washington, DC
8Federal AviationAdministration
FAA Modernization and Reform Act of 2012
• Airport Improvement Program (AIP) Funding• 4 Year Authorization (2012 – 2015)
• Authorized AIP Funding at $13.4 billion over 4 years ($3.35 billion/yr)
• 2013 Budget Request @ $2.4 billion AIP
IRWA Federal Agency UpdateMarch 21, 2012Washington, DC
9Federal AviationAdministration
Land Acquisition & Relocation Assistance for Airport Development, 2012 -2016
$800 million AIP Funded
Airport Improvement Program – Planned Development
Development Work 2012 – 2016
Total Cost roughly $40 Billion
AIP Funded $14 Billion
IRWA Federal Agency UpdateMarch 21, 2012Washington, DC
10Federal AviationAdministration
New perspectives on “the system”
Updated priorities
Environmental issues
Economic and financial issues
Oversight, transparency and accountability
Changes and Trends in AIP
IRWA Federal Agency UpdateMarch 21, 2012Washington, DC
11Federal AviationAdministration
Areas of Continued Focus
Improving nonstandard Runway Safety Areas (RSAs)
Compliance with all planning, design and construction standards
Reducing runway incursions
Minimizing wildlife hazards
Airspace reviews of proposed development (on- and off-airport)
IRWA Federal Agency UpdateMarch 21, 2012Washington, DC
12Federal AviationAdministration
Airports will be better NeighborsNextGen Benefits to Airports
NextGen will help airports operate in an environmentally responsible manner as new approaches and procedures provide more precise routings near airports.
Optimized Profile Descents (OPDs), which allow aircraft to follow precise vertical and horizontal paths, can provide the following:• Reduced noise impact on residential
RNAV/RNP approaches can be designed to minimize noise impacts on residential areas surrounding airports.
IRWA Federal Agency UpdateMarch 21, 2012Washington, DC
13Federal AviationAdministration
ATL
FTYPDK
RYY
CLT
UZA
JQF
PHL
ACYILG
PNELOM
EWRABEISP
JFK
LGA
SWF
HPNTEBCDW
MMUFRG
ORD
LOT GYYARR MDW
IGQ
DPARFDPWK
UGNENW
MKE
IAD
JYO
DCA
BWI
W66
MTN
HEF
FDKDMW
IAH
LVJSGR
AXH
CXODWH
IWS
EFDHOU
MSPSGSFCM
STP
LVN
ANE21DMIC
MIA
LNAFXE
TMB
PBI
FLLOPF
PHX FFZ
DVT
CHD
GEUIWA
SDL
SANSDM
MYF SEE
CRQ
LAX
ONT
CNOLGB
VNYBUR
POC
SNA
WHP
LAS
VGT
HND
SFOSQL HWD
SJC
LVKCCR
PAO
OAK
RHV
SEA
S50
RNT
S43
BFI
PAE
BOS
HNL
DTWCLE
PIT
DCA
CLT
TPA
MCO
FLL
MIA
MEM
STL
DFW
IAH
MSP
DEN
SLC
PDX
SEA
CVG
PHXSAN
LAX
LAS
ATL
IAD BWI
PHL
EWRJFK
LGAORD
MDW
SFO
NextGen Airport Development
IRWA Federal Agency UpdateMarch 21, 2012Washington, DC
14Federal AviationAdministration
FAA Modernization and Reform Act of 2012
New Policy / Changed Requirements •Changed Noise Land Disposal Requirements
• If there are no eligible noise compatibility projects or cost, now FAA allows use of proceeds from the sale of unneeded noise land on environmental mitigation or eligible airport development.
• Long term leasing is no longer considered a disposal
• Land may be retained for buffer/compatible land use
•Returns Federal share to 90% from 95% for described programs (details from your local FAA Airports District Office).
•Energy efficiency measures for Airport Buildings. Provision clearly spells out the Congressional intent to support energy efficiency and sustainability efforts in project designs.
IRWA Federal Agency UpdateMarch 21, 2012Washington, DC
15Federal AviationAdministration
New Policy / Changed Requirements
• Acquisition of Private Airports. Some appraisal criteria to be developed on Airport or Development Highest and Best Use.
• Restore Airport priority for BRAC surplus property disposals.
• Extends the AIP eligibility for compatible land use grants to local communities through September 30, 2015. (Extends prior pilot program).
• Runway Safety. Requires FAA to conduct a strategic study of runway safety.
• Requires appraisals of residences to disregard project influence. Although informed committee that this requirement existed under 49 CFR 24, the sponsor insisted on including the provision.
• Requires airports to complete Emergency Contingency Plans within 90 days addressing how they will handle passengers from diverted flights, and help prevent excessive tarmac delays. The plans are submitted to the Secretary.
IRWA Federal Agency UpdateMarch 21, 2012Washington, DC
16Federal AviationAdministration
New Policy / Changed Requirements
• Limited exception on revenue use for certain airports with excess revenues from mineral extraction.
• Within one year establish a pilot program on the redevelopment of acquired noise land. Guidance to be issued.
• Airport Cooperative Research Program (ACRP) made permanent and funded through 2015
• New rules for use of model aircraft at obligated airports.
IRWA Federal Agency UpdateMarch 21, 2012Washington, DC
17Federal AviationAdministration
Land Acquisition / Management
Typical Airport Land Acquisition Project• Airport Runway Standards
• Safety areas (on airport)• Runway Protection Zone (fee interest preferred)• Approaches (easements, local zoning/land use controls)
• Expansion• Extended or New Runway (PVD, FLL,PHL,ORD)
• Noise Compatibility/Mitigation• Buy-out of homes within moderate/high airport noise
contour
• New Airports
IRWA Federal Agency UpdateMarch 21, 2012Washington, DC
18Federal AviationAdministration
Land Acquisition / Management
Noise Land Inventory and Reuse Plans• Long Term Lease / Buffer Lands Added to Inventory• Allow disposal proceeds to be expended on eligible
airport projects.• Updated Guidance to be issued August 2012• Pilot Program to support redevelopment of
unneeded noise land
IRWA Federal Agency UpdateMarch 21, 2012Washington, DC
19Federal AviationAdministration
Land Acquisition / Management
On airport Gas and Oil development• Increased Solicitation of Airport Owners in Shale Gas Plays
IRWA Federal Agency UpdateMarch 21, 2012Washington, DC
20Federal AviationAdministration
Land Acquisition / Management “It’s an Airport not a Gas/oil Field”
• Any exploration or development on Airport Surface Land must be subordinated to FAA Safety and Operations Standards and Requirements.
• Gas and oil leases must restrict access and use of airport operational and aeronautical development land. (No drill zones defined)
• Airport Design and Construction Rules must be applied. (airspace, hazard elimination/prevention, environmental compliance, etc).
• FAA must Approve Changes to the Airport Layout Plan (ALP).• Lease is Contingent on ALP approval• NEPA Review for FAA Approval
• Gas and Oil leases terms and provisions must be at Fair Market Value (Signing bonus, royalty, surface land rents, terms and expiration provisions.)
• National Guidance to be Issued
IRWA Federal Agency UpdateMarch 21, 2012Washington, DC
21Federal AviationAdministration
FAA Airport Improvement Program Guidance
FAA Order 5100.38 – AIP Handbook• FAA Work Acceptance Rules
http://www.faa.gov/airports/aip/aip_handbook/
Land Acquisition and Relocation Assistance Guidancehttp://www.faa.gov/airports/environmental/relocation_assistance