RFP Invitation Letter (Rev. 3, 8/8/07) RFP Invitation Letter Acquisition Services Management (ASM) Division Subcontracts, ASM-SUB P.O. Box 1663, Mail Stop * Los Alamos, New Mexico 87545 505-667-* / Fax 505-665-* E-mail: * * * Attention: * * Subject: * Request For Proposal (RFP) No. * Greetings: You are invited to submit a proposal for * for the above referenced project in accordance with the below listed and enclosed proposal documents: Instructions to Offerors Subcontract Form of Agreement SFA-1 Government Clauses and DOE Directives Incorporated By Reference Exhibit "A" – General Conditions Exhibit "B" – Special Conditions Exhibit "C" – Quantities, Pricing and Data Exhibit "D" – Scope of Work and Technical Specifications Exhibit "E" – Drawings Exhibit “F” – ES&H Requirements Exhibit “G” – Security Requirements Exhibit “H” – Quality Assurance Requirements Proposals are solicited only from Small Business Concerns. Proposals received from concerns that are not Small Business Concerns shall be considered non-responsive and will be rejected. For more information, see section titled “Notice Of Total Small Business Set-Aside” in the Instructions to Offerors. A portion of this requirement, identified elsewhere in this solicitation, has been set-aside for award to one or more Small Business Concerns. For more information, see section titled “Notice Of Partial Small Business Set-Aside” in the Instructions to Offerors. A mandatory pre-proposal meeting and site visit will be held on * for all prospective Offerors. For more information, see section titled “Pre-Proposal Meeting” in the Instructions to Offerors. Page 1 of 3
26
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: RFP Invitation Letter

RFP Invitation Letter (Rev. 3, 8/8/07)

RFP Invitation Letter

Acquisition Services Management (ASM) Division Subcontracts, ASM-SUB P.O. Box 1663, Mail Stop * Los Alamos, New Mexico 87545 505-667-* / Fax 505-665-* E-mail: * * * Attention: * * Subject: *

Request For Proposal (RFP) No. * Greetings: You are invited to submit a proposal for * for the above referenced project in accordance with the below listed and enclosed proposal documents:

Instructions to Offerors Subcontract Form of Agreement SFA-1 Government Clauses and DOE Directives Incorporated By Reference Exhibit "A" – General Conditions Exhibit "B" – Special Conditions Exhibit "C" – Quantities, Pricing and Data Exhibit "D" – Scope of Work and Technical Specifications Exhibit "E" – Drawings Exhibit “F” – ES&H Requirements Exhibit “G” – Security Requirements Exhibit “H” – Quality Assurance Requirements

Proposals are solicited only from Small Business Concerns. Proposals received from concerns that are not Small Business Concerns shall be considered non-responsive and will be rejected. For more information, see section titled “Notice Of Total Small Business Set-Aside” in the Instructions to Offerors. A portion of this requirement, identified elsewhere in this solicitation, has been set-aside for award to one or more Small Business Concerns. For more information, see section titled “Notice Of Partial Small Business Set-Aside” in the Instructions to Offerors. A mandatory pre-proposal meeting and site visit will be held on * for all prospective Offerors. For more information, see section titled “Pre-Proposal Meeting” in the Instructions to Offerors.

Page 1 of 3

Page 2: RFP Invitation Letter

RFP Invitation Letter (Rev. 3, 8/8/07)

Your proposal is to be submitted on the enclosed proposal forms in original and * copies, to the undersigned not later than * PM Mountain Time on *, 200*. Your proposal and each copy shall be identified in the upper right corner of the cover as "Original, Copy 1, Copy 2," etc. Partial or incomplete proposals will not be considered. Proposals on other than the proposal forms provided, or received later than the date and time listed above may be rejected. Proposal submissions sent via the U. S. Postal Service should be addressed as follows:

Los Alamos National Security, LLC Attn: * P.O. Box 1663, MS * Los Alamos, New Mexico 87545

Proposal submissions sent via other delivery services such as UPS, Federal Express, Airborne, etc. should be addressed as follows:

Los Alamos National Security, LLC Attn: *, MS * Bldg. SM-30 Bikini Atoll Road Los Alamos, New Mexico 87545

Proposals that are hand-carried should only be delivered to:

Los Alamos National Security, LLC Attn: * 125 Central Park Square (Across 15th Street from the YMCA) Los Alamos, New Mexico 87544

Offerors electing to hand-carry proposals are responsible for delivery to the undersigned by the proposal due date and time. Do not fax proposals. Modifications to proposal are subject to the same submission requirements stated above. Proposals received in response to this RFP will be evaluated as stated in the Basis of Award section in the Instructions to Offerors. If the offering entity is a joint venture, association, consortia or partnership, evidence of the authority of the person signing on behalf of the offering entity shall be attached to the proposal. The evidence of the signatory's authority shall be signed by all members of the joint venture, association, consortia or partnership. Proposal security is not required. Please advise us of your planned response to this RFP and designate your representative(s) to whom correspondence and addenda are to be sent by completing and returning within seven (7) calendar days the enclosed notification form. If you choose not to submit a proposal, please return all documents to the undersigned. Any and all questions you may have concerning this invitation should be directed to the undersigned Procurement Specialist (aka Contract Administrator) at email address or fax number shown at the top of this letter.

Page 2 of 3

Page 3: RFP Invitation Letter

RFP Invitation Letter (Rev. 3, 8/8/07)

Very truly yours, * xc: file Enclosures as stated

Page 3 of 3

Page 4: RFP Invitation Letter

NOTIFICATION OF INTENT TO SUBMIT PROPOSAL To: Los Alamos National Security, LLC

Attn: * P.O. Box 1663, Mail Stop * Los Alamos, New Mexico 87545

From: (Name of offeror) (Mailing address) Subject: *

Request For Proposal (RFP) No. * We are in receipt of the subject RFP. (Check appropriate box below and provide information requested.) [ ] We do not intend to submit a proposal because:

[ ] We will submit a proposal on or before the due date of *.

Our designated contact for this RFP is: `

Address for courier delivery:

Phone:

Fax:

E-mail Address: Date: (Signature) Title:

Page 5: RFP Invitation Letter

RFP Instruction to Offerors (Rev. 5, 8/30/07)

Los Alamos National Security, LLC (LANS) Los Alamos National Laboratory (LANL)

INSTRUCTIONS TO OFFERORS

TABLE OF CONTENTS No. Title Page 1. GENERAL ........................................................................................Error! Bookmark not defined. 2. BASIS OF AWARD ..........................................................................Error! Bookmark not defined. 3. PREPARATION AND SUBMISSION OF PROPOSALS..................Error! Bookmark not defined. 4. EXAMINATION OF REQUEST FOR PROPOSAL DOCUMENTS..Error! Bookmark not defined. 5. SITE INSPECTION AND CONDITIONS..........................................Error! Bookmark not defined. 6. PRE-PROPOSAL MEETING ...........................................................Error! Bookmark not defined. 7. OFFEROR'S MODIFICATION AND WITHDRAWAL OF PROPOSALSError! Bookmark not defined. 8. PROPOSAL SECURITY ..................................................................Error! Bookmark not defined. 9. PENALTY FOR MAKING FALSE STATEMENT .............................Error! Bookmark not defined. 10. ADDENDA TO SOLICITATION .......................................................Error! Bookmark not defined. 11. UNNECESSARILY ELABORATE PROPOSALS.............................Error! Bookmark not defined. 12. DISCLOSURE OF PROPOSAL DATA ............................................Error! Bookmark not defined. 13. OFFEROR'S RETURN OF DOCUMENTS ......................................Error! Bookmark not defined. 14. NOTICE TO UNSUCCESSFUL OFFERORS..................................Error! Bookmark not defined. 15. PRE-AWARD SURVEY ...................................................................Error! Bookmark not defined. 16. OBJECTIONS TO SOLICITATION PROCEDURES .......................Error! Bookmark not defined. 17. RIGHT TO CANCEL ........................................................................Error! Bookmark not defined. 18. INSURANCE CERTIFICATES AND ENDORSEMENTS.................Error! Bookmark not defined. 19. SAFETY PERFORMANCE ELIGIBILITY REQUIREMENTS...........Error! Bookmark not defined. 20. PERFORMANCE AND PAYMENT SECURITIES ...........................Error! Bookmark not defined. 21. NOTICE OF TOTAL SMALL BUSINESS SET-ASIDE.....................Error! Bookmark not defined. 22. NOTICE OF PARTIAL SMALL BUSINESS SET-ASIDE .................Error! Bookmark not defined. 23. REGIONAL PURCHASING PRICING PREFERENCE....................Error! Bookmark not defined. 24. SUBCONTRACTOR’S REGIONAL AND COMMUNITY DEVELOPMENT PLANError! Bookmark not defined. 25. REVERSE E-AUCTION ...................................................................Error! Bookmark not defined. 26. NOTICE CONCERNING NEW MEXICO GROSS RECEIPTS TAX Error! Bookmark not defined. 27. ATTACHMENTS ..............................................................................Error! Bookmark not defined.

Page 6: RFP Invitation Letter

RFP Offeror’s Proposal Letter (Rev. 1, 8/3/07)

RFP No. * Page 1 of 2

OFFEROR’S PROPOSAL LETTER In response to the Request for Proposal (RFP) No. * dated *, 200*, and in accordance with the accompanying "Instructions To Offerors", the Offeror designated below hereby proposes to furnish all plant, labor, technical and professional services, supervision, materials and equipment (other than materials and equipment specified as furnished by others) and to perform all operations necessary and required to * for the * at Los Alamos National Laboratory, in accordance with provisions of the Request for Proposal Documents and any addenda thereto, and at the prices stated opposite the respective items set forth in the Schedule of Quantities and Prices attached hereto (hereinafter referred to collectively as Proposal). The undersigned agrees that this Proposal constitutes a firm offer to Los Alamos National Security, LLC (LANS) which, if not withdrawn prior to the proposal due date, cannot be withdrawn for * calendar days after the proposal due date or until a subcontract for the Work is executed by the undersigned and LANS, whichever is earlier. The undersigned certifies that it has examined and is fully familiar with all of the provisions of the Request for Proposal Documents and any addenda thereto; that it has carefully checked all of the words and figures shown in its Schedule of Quantities and Prices; that it has carefully reviewed the accuracy of all statements in this Proposal and attachments hereto; and that it has, by careful examination of the Request for Proposal Documents and any addenda thereto, satisfied itself as to the nature and location of all Work required by the subcontract and all other matters which can in any way affect the Work or the cost thereof. The undersigned hereby agrees LANS shall not be responsible for any errors or omissions on the part of the undersigned in preparing this Proposal. If awarded a subcontract, the undersigned agrees to execute the subcontract and deliver it to LANS within ten (10) calendar days after subcontract award with the certificates of insurance, insurance endorsements, and performance and payment securities as required. Attached hereto and by this reference incorporated herein and made a part of this Proposal is the data listed in Exhibit "C", Quantities, Pricing and Data, Table of Contents. The undersigned hereby acknowledges that any subcontract resulting from this Proposal will represent the entire agreement and that any exceptions taken in this Proposal, if not expressly included in the subcontract, will be considered resolved and void and that all exceptions have been listed on the attached Exhibit "C" Form Q titled "Exceptions And Deviations". The undersigned also acknowledges receipt, understanding and full consideration of the following addenda to the Request for Proposal Documents: Addenda Numbered . Date of Proposal: OFFEROR: (Name of offeror)

By: (Signature)

(Printed name)

Page 7: RFP Invitation Letter

RFP Offeror’s Proposal Letter (Rev. 1, 8/3/07)

(Title)

State of incorporation: (If offeror is a corporation)

Business address:

Dun and Bradstreet No.:

NM Contractor License No.:

License Expiration Date:

If required, evidence of the authority of the person signing on behalf of the offering entity is attached hereto.

RFP No. * Page 2 of 2

Page 8: RFP Invitation Letter

LFS Subcontract (Rev. 1, 9/4/07) Long Form Services Subcontract Form of Agreement

Subcontract No. * Page 1 of 2

Subcontract Form of Agreement

Subcontractor: * Subcontract No.: * Address: * Contact: * Telephone: * Facsimile: * E-mail: * D-U-N-S No.: * NAICS Code: * This subcontract, effective on the date of signature by the last party to sign, is hereby made and entered into by and between Los Alamos National Security, LLC (CONTRACTOR), and the above named SUBCONTRACTOR who hereby agree that all Work specified below, which is a portion of the goods and services to be provided by CONTRACTOR for the United States Department of Energy National Nuclear Security Administration (OWNER), shall be performed by the SUBCONTRACTOR in accordance with all the provisions of this subcontract, consisting of the following Subcontract Documents:

Subcontract Form of Agreement Appendix SFA-1, Government Clauses and DOE Directives Incorporated By Reference Exhibit "A" General Conditions Exhibit "B" Special Conditions Exhibit "C" Quantities, Pricing and Data Exhibit "D" Scope of Work and Technical Specifications Exhibit "E" List of Drawings Exhibit “F” Environmental, Safety and Health Requirements Exhibit “G” Security Requirements Exhibit “H” Quality Assurance Requirements

1. WORK TO BE PERFORMED: In accordance with the subcontract documents,

SUBCONTRACTOR shall furnish all plant; labor; materials; tools; supplies; equipment; transportation; supervision; technical, professional and other services; and shall perform all operations necessary and required to satisfactorily:

*

2. SCHEDULE: The Work shall be performed in accordance with the dates set forth in the

Exhibit "B" clause titled "COMMENCEMENT, PROGRESS AND COMPLETION OF THE WORK."

3. COMPENSATION: As full consideration for the satisfactory performance by

SUBCONTRACTOR of this subcontract, CONTRACTOR shall pay to SUBCONTRACTOR the total sum of * ($*), in accordance with the prices set forth in Exhibit "C" and the payment provisions of this subcontract.

4. JOINT VENTURE: In signing this subcontract as a Joint Venture comprised of *, *, and

*, the parties agree that they shall be jointly and severally obligated to CONTRACTOR to fulfill all the SUBCONTRACTOR'S obligations and responsibilities set forth herein.

Page 9: RFP Invitation Letter

LFS Subcontract (Rev. 1, 9/4/07) Long Form Services Subcontract Form of Agreement

This subcontract embodies the entire agreement between CONTRACTOR and SUBCONTRACTOR and supersedes all other writings. The parties shall not be bound by or be liable for any statement, representation, promise, inducement or understanding not set forth herein. For the CONTRACTOR: For the SUBCONTRACTOR: By: By: Name: Name: Title: Title: Date: Date:

Subcontract No. * Page 2 of 2

Page 10: RFP Invitation Letter

LFC SFA-1 (Rev. 2, 9/4/07) Long Form Construction Subcontract

Subcontract No. * Page 1 of 9

Appendix SFA-1 Government Clauses and DOE Directives Incorporated By Reference

(a) The Federal Acquisition Regulation (FAR) and the Department of Energy Acquisition

Regulation (DEAR) clauses which are incorporated by reference herein shall have the same force and effect as if printed in full text.

(b) Full text of the referenced clauses may be accessed electronically at website address:

http://www.arnet.gov/far/ or http://professionals.pr.doe.gov/ma5/MA-5Web.nsf/Procurement/Acquisition+Regulation?OpenDocument

(c) The following alterations apply only to FAR and DEAR clauses, and do not apply to DOE

Directives. Wherever necessary to make the context of the unmodified FAR and DEAR clauses applicable to this subcontract, the terms shown below shall have the meaning as stated:

(1) The term "Contractor" shall mean "SUBCONTRACTOR;"

(2) The term "Contract" shall mean this subcontract; and

(3) The term “DOE”, "Government," "Contracting Officer" and equivalent phrases

shall mean CONTRACTOR and/or CONTRACTOR’S representative, except the terms "Government" and "Contracting Officer" do not change:

(i) In the phrases “Government Property,” “Government-Furnished Property,”

and “Government-Owned Property;”

(ii) In any patent clauses incorporated herein;

(iii) When a right, act, authorization or obligation can be granted or performed only by the Government or the prime contract Contracting Officer or his duly authorized representative;

(iv) When title to property is to be transferred directly to the Government;

(v) When access to proprietary financial information or other proprietary data

is required except for authorized audit rights; and

(vi) Where specifically modified herein.

(4) For authorized audit rights, the term “Contracting Officer or an authorized representative of the Contracting Officer” shall also include “CONTRACTOR, or an authorized representative of CONTRACTOR.”

(d) DOE Directives referenced herein may be found at

http://www.directives.doe.gov/directives/read.html

Page 11: RFP Invitation Letter

LFC SFA-1 (Rev. 2, 9/4/07) Long Form Construction Subcontract

THE FOLLOWING CLAUSES APPLY TO THIS SUBCONTRACT REGARDLESS OF THE AMOUNT OF THE SUBCONTRACT PRICE, UNLESS OTHERWISE NOTED: Clause Number Title and Date Instructions

FAR 52.223-3 Hazardous Material Identification and Material Safety Data (Jan 1997) Alternate I (Jul 1995)

As used in this clause, the “Government” means “CONTRACTOR and the Government.”

FAR 52.223-5 Pollution Prevention And Right-To-Know Information (Aug 2003) Alternate I (Aug 2003)

FAR 52.223-10 Waste Reduction Program (Aug 2000)

FAR 52.223-12 Refrigeration Equipment and Air Conditioners (May 1995)

FAR 52.225-13 Restrictions on Certain Foreign Purchases (Mar 2005)

FAR 52.227-3 Patent Indemnity (Apr 1984)

FAR 52.227-23 Rights to Proposal Data (Technical) (Jun 1987)

FAR 52.230-2 Cost Accounting Standards (Apr 1998) Applies unless the subcontract is exempted from CAS (see 48 CFR 9903.201-1 (FAR Appendix)), or the subcontract is subject to modified CAS coverage (see 48 CFR 9903.201-2 (FAR Appendix)). When applicable, paragraph (b) is deleted.

FAR 52.230-6 Administration of Cost Accounting Standards (Apr 2005) Applies if FAR 52.230-2 or FAR 52.230-3 applies.

FAR 52.244-6 Subcontracts for Commercial Items (Dec 2004)

FAR 52.245-2 Government Property (Fixed-Price Contracts) (May 2004) Alternate I (Apr 1984)

Modified by DEAR 952.245-2.

FAR 52.247-64 Preference for Privately Owned U.S.-Flag Commercial Vessels (Apr 2003)

DEAR 952.203-70 Whistleblower Protection For Contractor Employees (Dec 2000)

DEAR 952.250-70 Nuclear Hazards Indemnity Agreement (Jun 1996)

DEAR 970.5223-1 Integration Of Environment, Safety, And Health Into Work Planning And Execution (Dec 2000)

DEAR 970.5229-1 State and Local Taxes (Dec 2000) Paragraph (b) is deleted.

THE FOLLOWING CLAUSES APPLY ONLY IF THE SUBCONTRACT PRICE EXCEEDS $2,500:

Clause Number Title and Date Instructions FAR 52.222-3 Convict Labor (Jun 2003)

FAR 52.222-41 Service Contract Act of 1965 as Amended (Jul 2005) Applies if subcontract is subject to the Service Contract Act of 1965, as amended. See FAR Subpart 22.10.

FAR 52.222-43 Fair Labor Standards Act and Service Contract Act – Price Adjustment (Multiple Year and Option Contracts) (Nov 2006)

Applies if FAR 52.222-41 applies, and subcontract is a multiple year contract or is a contract with options to renew.

FAR 52.222-44 Fair Labor Standards Act and Service Contract Act – Price Adjustment (Feb 2002)

Applies if FAR 52.222-41 applies, and subcontract is not a multiple year contract or is not a contract with options to renew.

FAR 52.225-1 Buy American Act – Supplies (Jun 2003)

FAR 52.232-23 Assignment of Claims (Jan 1986) Alternate I (Apr 1984)

Subcontract No. * Page 2 of 9

Page 12: RFP Invitation Letter

LFC SFA-1 (Rev. 2, 9/4/07) Long Form Construction Subcontract

THE FOLLOWING CLAUSES APPLY ONLY IF THE SUBCONTRACT PRICE EXCEEDS $10,000:

Clause Number Title and Date Instructions FAR 52.222-21 Prohibition of Segregated Facilities (Feb 1999)

FAR 52.222-26 Equal Opportunity (Apr 2002) Only paragraphs (b)(1) through (b)(11) are applicable.

FAR 52.222-36 Affirmative Action for Workers with Disabilities (Jun 1998)

THE FOLLOWING CLAUSES APPLY ONLY IF THE SUBCONTRACT PRICE IS $25,000 OR MORE:

Clause Number Title and Date Instructions FAR 52.222-35 Equal Opportunity for Special Disabled Veterans, Veterans of the

Vietnam Era, and Other Eligible Veterans (Dec 2001)

FAR 52.222-37 Employment Reports on Special Disabled Veterans, Veterans of the Vietnam Era, and Other Eligible Veterans (Dec 2001)

DEAR 970.5223-3 Agreement Regarding Workplace Substance Abuse Programs At DOE Sites (Dec 2000)

Solicitation provision applicable if performance of subcontract involves: (i) access to or handling of classified information or special nuclear materials; (ii) high risk of danger to life, the environment, public health and safety, or national security; or (iii) transportation of hazardous materials to or from a DOE site.

DEAR 970.5223-4 Workplace Substance Abuse Programs at DOE Sites (Dec 2000)

Applies if performance of subcontract involves: (i) access to or handling of classified information or special nuclear materials; (ii) high risk of danger to life, the environment, public health and safety, or national security; or (iii) transportation of hazardous materials to or from a DOE site.

THE FOLLOWING CLAUSES APPLY ONLY IF THE SUBCONTRACT PRICE EXCEEDS $100,000:

Clause Number Title and Date Instructions FAR 52.203-3 Gratuities (Apr 1984)

FAR 52.203-5 Covenant Against Contingent Fees (Apr 1984)

FAR 52.203-6 Restrictions on Subcontractor Sales to the Government (Jul 1995)

FAR 52.203-7 Anti-Kickback Procedures (Jul 1995) Paragraph (c) (1) is deleted.

FAR 52.203-8 Cancellation, Rescission, And Recovery Of Funds For Illegal Or Improper Activity (Jan 1997)

FAR 52.203-10 Price Or Fee Adjustment For Illegal Or Improper Activity (Jan 1997)

In paragraph (d) only of this clause, the term “Government” means “Government or CONTRACTOR.”

FAR 52.203-12 Limitation On Payments To Influence Certain Federal Transactions (Jun 2003)

FAR 52.204-4 Printed Or Copied Double-Sided On Recycled Paper (Aug 2000)

FAR 52.215-2 Audit and Records –Negotiation (June 1999)

FAR 52.219-8 Utilization of Small Business Concerns (May 2004)

FAR 52.219-14 Limitations on Subcontracting (Dec 1996) Applies if any portion of the requirement is to be set aside for small business.

FAR 52.222-39 Notification of Employee Rights Concerning Payment of Union Dues or Fees (Dec 2004)

FAR 52.223-13 Certification of Toxic Chemical Release Reporting (Aug 2003) Solicitation provision.

Subcontract No. * Page 3 of 9

Page 13: RFP Invitation Letter

LFC SFA-1 (Rev. 2, 9/4/07) Long Form Construction Subcontract

Subcontract No. * Page 4 of 9

THE FOLLOWING CLAUSES APPLY ONLY IF THE SUBCONTRACT PRICE EXCEEDS $100,000:

Clause Number Title and Date Instructions FAR 52.223-14 Toxic Chemical Release Reporting (Aug 2003) Paragraph (e) is deleted.

FAR 52.227-1 Authorization and Consent (Jul 1995)

FAR 52.232-17 Interest (Jun 1996) Applies unless one of the exemptions listed in FAR Subpart 32.617 (a) apply.

FAR 52.247-63 Preference for U.S.-Flag Air Carriers (Jun 2003)

DEAR 952.209-72 Organizational Conflicts of Interest (Jun 1997) with Alternate I Applies if subcontract is for advisory and assistance services, as defined in FAR Subpart 2.101.

DEAR 970.5227-5 Notice and Assistance Regarding Patent and Copyright Infringement (Aug 2002)

THE FOLLOWING CLAUSES APPLY ONLY IF THE SUBCONTRACT PRICE EXCEEDS $500,000: Clause Number Title and Date Instructions FAR 52.230-3 Disclosure And Consistency Of Cost Accounting Practices (Apr

1998) Applies if the subcontract amount is less than $50 million, and the offeror certifies it is eligible for and elects to use modified CAS coverage (see 48 CFR 9903.201-2 (FAR Appendix)).

DEAR 952.226-74 Displaced Employee Hiring Preference (Jun 1997)

DEAR 970.5226-2 Workforce Restructuring Under Section 3161 of the National Defense Authorization Act for Fiscal Year 1993 (Dec 2000)

THE FOLLOWING CLAUSES APPLY ONLY WHEN THE SUBCONTRACTOR IS REQUIRED TO SUBMIT COST OR PRICING DATA AS DEFINED IN FAR 2.101: Clause Number Title and Date Instructions FAR 52.215-10 Price Reduction for Defective Cost or Pricing Data (Oct 1997)

FAR 52.215-12 Subcontractor Cost or Pricing Data (Oct 1997)

THE FOLLOWING CLAUSES APPLY ONLY WHEN COST OR PRICING DATA WILL BE REQUIRED FOR THE PRICING OF CONTRACT MODIFICATIONS, AND FAR 52.215-10 HAS NOT BEEN INCLUDED: Clause Number Title and Date Instructions FAR 52.215-11 Price Reduction for Defective Cost or Pricing Data – Modifications

(Oct 1997)

FAR 52.215-13 Subcontractor Cost or Pricing Data – Modifications (Oct 1997)

THE FOLLOWING CLAUSES APPLY ONLY IF THE SUBCONTRACT PRICE EXCEEDS $650,000 AND THE SUBCONTRACTOR IS REQUIRED TO SUBMIT COST OR PRICING DATA, OR WHERE PREAWARD OR POSTAWARD COST DETERMINATIONS WILL BE SUBJECT TO FAR PART 31, CONTRACT COST PRINCIPLES AND PROCEDURES: Clause Number Title and Date Instructions FAR 52.215-15 Pension Adjustments and Asset Reversions (Oct 2004)

FAR 52.215-18 Reversion or Adjustment of Plans for Postretirement Benefits (PRB) Other Than Pensions (Jul 2005)

Page 14: RFP Invitation Letter

LFC SFA-1 (Rev. 2, 9/4/07) Long Form Construction Subcontract

THE FOLLOWING CLAUSES APPLY ONLY IF THE SUBCONTRACT PRICE EXCEEDS $500,000, THE SUBCONTRACTOR IS A LARGE BUSINESS, AND FAR 52.219-8 IS APPLICABLE: Clause Number Title and Date Instructions FAR 52.219-9 Small Business Subcontracting Plan (Jan 2002), Alternate II (Oct

2001)

FAR 52.219-16 Liquidated Damages – Subcontracting Plan (Jan 1999)

THE FOLLOWING CLAUSE APPLIES ONLY IF THE SUBCONTRACT PRICE EXCEEDS $100,000, IS FOR NON-COMMERCIAL ITEMS, AND MAY REQUIRE OR INVOLVE THE SUBSTANTIAL EMPLOYMENT OF LABORERS OR MECHANICS: Clause Number Title and Date Instructions FAR 52.222-4 Contract Work Hours and Safety Standards Act - Overtime

Compensation (Sept 2000)

THE FOLLOWING CLAUSES APPLY ONLY IF THE STATEMENT OF WORK REQUIRES THE DESIGN, DEVELOPMENT, OR OPERATION OF A SYSTEM OF RECORDS ON INDIVIDUALS: Clause Number Title and Date Instructions FAR 52.224-1 Privacy Act Notification (Apr 1984)

FAR 52.224-2 Privacy Act (Apr 1984)

THE FOLLOWING CLAUSES APPLY AS STATED IN THE INSTRUCTIONS: Clause Number Title and Date Instructions FAR 52.208-8 Required Sources For Helium And Helium Usage Data (Apr 2002) Applies where performance of

subcontract involves a major helium requirement.

FAR 52.211-15 Defense Priority And Allocation Requirements (Sep 1990) Applies in subcontracts that are rated orders as defined in FAR Subpart 11.601.

FAR 52.222-1 Notice To The Government Of Labor Disputes (Feb 1997) Applies if a potential labor dispute may delay the timely performance of the CONTRACTOR’S Prime Contract with DOE/NNSA.

FAR 52.223-7 Notice of Radioactive Materials (Jan 1997) Applies if items containing either radioactive material (requiring specific licensing under the regulations issued pursuant to the Atomic Energy Act of 1954, as amended) or other radioactive material (not requiring specific licensing in which the specific activity is greater than 0.002 microcuries per gram or the activity per item equals or exceeds 0.01 microcuries) are to be delivered or serviced under this subcontract.

FAR 52.227-14 Rights in Data - General (June 1987) as modified by DEAR 927.409(a) (Dec 2000), including Alternate V (Jun 1987)

Applies if technical data or computer software is expected to be produced or delivered.

FAR 52.227-16 Additional Data Requirements (Jun 1987) Applies if subcontract involves experimental, developmental, research or demonstration work.

DEAR 952.211-71 Priorities And Allocations (Atomic Energy) (Jun 1996) Applies in subcontracts that are placed in support of authorized DOE atomic energy programs.

Subcontract No. * Page 5 of 9

Page 15: RFP Invitation Letter

LFC SFA-1 (Rev. 2, 9/4/07) Long Form Construction Subcontract

Subcontract No. * Page 6 of 9

THE FOLLOWING CLAUSES APPLY AS STATED IN THE INSTRUCTIONS: Clause Number Title and Date Instructions DEAR 952.211-71 Priorities And Allocations (Domestic Energy Supplies) Alternate I

(Jun 1996) Applies in subcontracts that are placed in support of programs or projects the purpose of which is to maximize domestic energy supplies.

DEAR 952.217-70 Acquisition Of Real Property (Apr 1984) Applies where the subcontractor, in performance of the subcontract, acquires or proposes to acquire use of real property.

DEAR 952.224-70 Paperwork Reduction Act (Apr 1994) Applies if it is anticipated that information collection from 10 or more persons will be necessary under the subcontract.

DEAR 952.227-11 Patent Rights – Retention by the Contractor (Short Form) (Mar 1995)

Applies if subcontract for experimental, developmental, research or demonstration work, and subcontractor is a domestic small business or nonprofit organization, as defined at FAR Subpart 27.301.

DEAR 952.227-13 Patent Rights – Acquisition by the Government (Sept 1997) Applies if subcontract for experimental, developmental, research or demonstration work, and subcontractor is not a domestic small business or nonprofit organization, as defined at FAR Subpart 27.301.

DEAR 970.5208-1 Printing (Dec 2000) Applies when printing is required, as “printing” is defined in Title I, Definitions, of the U.S. Government Printing and Binding Regulations (http://jcp.senate.gov/jcpregs.pdf)

DEAR 970.5227-1 Rights in Data-Facilities (Dec 2000) Applies if subcontract involves the design or operation of any LANL plants or facilities or specially designed equipment for such LANL plants or facilities, or related support services for those plants or facilities.

DEAR 970.5227-7 Royalty Information (Dec 2000) Solicitation provision which applies if the amount of royalties reported during negotiation is >$250.

DEAR 970.5227-8 Refund Of Royalties (Aug 2002) Applies if the amount of royalties reported during negotiation is >$250.

DEAR 970.5232-5 Liability With Respect To Cost Accounting Standards (Dec 2000) Applies if any Cost Accounting Standards clauses are included.

SUBCONTRACTOR SHALL PROVIDE SUCH INFORMATION, ASSISTANCE AND SUPPORT AS NECESSARY TO ENSURE CONTRACTOR’S COMPLIANCE WITH THE FOLLOWING DOE DIRECTIVES. IN ADDITION, SUBCONTRACTOR SHALL COMPLY WITH THE REQUIREMENTS OF THE CONTRACTOR REQUIREMENT DOCUMENT (CRD) ATTACHED TO A DIRECTIVE WHEN REQUIRED BY SUCH CRD.

Directive Number Title Requirements include, but are not limited to, the following:

DOE M 140.1-1B Interface with the Defense Nuclear Facilities Safety Board

CONTRACTOR will follow the DOE process specified to interface with the Defense Nuclear Facilities Safety Board.

Page 16: RFP Invitation Letter

LFC SFA-1 (Rev. 2, 9/4/07) Long Form Construction Subcontract

Subcontract No. * Page 7 of 9

SUBCONTRACTOR SHALL PROVIDE SUCH INFORMATION, ASSISTANCE AND SUPPORT AS NECESSARY TO ENSURE CONTRACTOR’S COMPLIANCE WITH THE FOLLOWING DOE DIRECTIVES. IN ADDITION, SUBCONTRACTOR SHALL COMPLY WITH THE REQUIREMENTS OF THE CONTRACTOR REQUIREMENT DOCUMENT (CRD) ATTACHED TO A DIRECTIVE WHEN REQUIRED BY SUCH CRD.

Directive Number Title Requirements include, but are not limited to, the following:

DOE O 142.2 Safeguards Agreement and Protocol with the IAEA

CONTRACTOR shall assist DOE, as directed by DOE, in meeting DOE’s obligations under the “Agreement Between the United States of America and the International Atomic Energy Agency for the Application of Safeguards in the United States” (the Agreement), the Original Protocol to the Agreement, the subsidiary arrangements to the Agreement, and the Interagency Procedures for the Implementation of the U.S. – IAEA Safeguards Agreement.

DOE O 151.1C Comprehensive Emergency Management System

CONTRACTOR must develop and implement a Comprehensive Emergency Management System and an integrated Operational Emergency Base Program as specified in the CRD.

DOE N 153.2 Connectivity to National Atmospheric Release Advisory Center (NARAC)

CONTRACTOR must establish connectivity with NARAC as specified in the CRD.

DOE O 221.1 Reporting Fraud, Waste, and Abuse to the Office of Inspector General

CONTRACTOR and its employees who have information about actual or suspected violations of law, regulations, or policy including fraud, waste, abuse, misuse, corruption, criminal acts, or mismanagement relating to DOE programs, operations, facilities, contracts, or information technology systems shall immediately notify the appropriate authorities.

DOE O 221.2 Cooperation with the Office of Inspector General (OIG)

CONTRACTOR and its employees must cooperate fully and promptly with requests from the OIG for information and data relating to DOE programs and operations.

DOE M 231.1-1A, Chg. 1 Environment, Safety, and Health Reporting Manual

CONTRACTOR must develop site-wide and facility-wide procedures, protocols, or other methods to meet the reporting requirements of the CRD.

DOE M 231.1-2 Occurrence Reporting and Processing of Operations Information

CONTRACTOR must categorize reportable occurrences, notify DOE as required, and Prepare and submit Occurrence Reports in accordance with the CRD.

DOE O 241.1A, Chg. 1 Scientific and Technical Information Management

CONTRACTOR is required to manage scientific and technical information created or obtained under its contract with DOE as a direct and integral part of the work and ensure its broad availability.

Page 17: RFP Invitation Letter

LFC SFA-1 (Rev. 2, 9/4/07) Long Form Construction Subcontract

Subcontract No. * Page 8 of 9

SUBCONTRACTOR SHALL PROVIDE SUCH INFORMATION, ASSISTANCE AND SUPPORT AS NECESSARY TO ENSURE CONTRACTOR’S COMPLIANCE WITH THE FOLLOWING DOE DIRECTIVES. IN ADDITION, SUBCONTRACTOR SHALL COMPLY WITH THE REQUIREMENTS OF THE CONTRACTOR REQUIREMENT DOCUMENT (CRD) ATTACHED TO A DIRECTIVE WHEN REQUIRED BY SUCH CRD.

Directive Number Title Requirements include, but are not limited to, the following:

DOE O 341.1 Federal Employee Health Services

CONTRACTOR must develop, participate in the development of, and/or maintain Occupational Medical Programs and Employee Assistance Programs that comply with the requirements of the CRD.

DOE O 414.1C Quality Assurance

CONTRACTOR must integrate multiple Quality Assurance program drivers imposed by QA regulations as specified in the CRD.

DOE O 420.1B Facility Safety

CRD establishes facility safety requirements. CONTRACTOR must ensure that any work done is consistent with applicable safety, design, or other analysis or requirements.

DOE O 420.2B Safety of Accelerator Facilities

CONTRACTOR must comply with accelerator-specific safety requirements specified in CRD.

DOE O 430.1B Real Property Asset Management

The CRD establishes the functional requirements for the acquisition, management, maintenance, disposition, or disposal of real property assets.

DOE O 430.2A Departmental Energy and Utilities Management

CONTRACTOR must have a documented energy management program and an energy management plan.

DOE O 433.1A Maintenance Management Program for DOE Nuclear Facilities

CONTRACTOR must have a nuclear facility maintenance management program that complies with CRD requirements.

DOE O 450.1, Chg.1 Environmental Protection Program

CONTRACTOR must integrate numerous environmentally related requirements through the use of an Environmental Management System incorporated into an Integrated Safety Management System.

DOE N 450.7 The Safe Handling, Transfer, and Receipt of Biological Etiologic Agents at Department of Energy Facilities

For work involving biological etiologic agents, CONTRACTOR must provide a reasonably safe and healthful workplace for workers while also protecting the public and the environment.

DOE O 452.1C Nuclear Explosive and Weapon Surety Program

CONTRACTOR must comply with the requirements of the CRD.

DOE O 452.2C Nuclear Explosive Safety CONTRACTOR must comply with the requirements of the CRD.

DOE O 460.1B Packaging and Transportation Safety

CONTRACTOR must comply with safety requirements for proper packaging and transportation of DOE/NNSA offsite shipments and onsite transfers of hazardous materials and for modal transport as specified in CRD.

Page 18: RFP Invitation Letter

LFC SFA-1 (Rev. 2, 9/4/07) Long Form Construction Subcontract

Subcontract No. * Page 9 of 9

SUBCONTRACTOR SHALL PROVIDE SUCH INFORMATION, ASSISTANCE AND SUPPORT AS NECESSARY TO ENSURE CONTRACTOR’S COMPLIANCE WITH THE FOLLOWING DOE DIRECTIVES. IN ADDITION, SUBCONTRACTOR SHALL COMPLY WITH THE REQUIREMENTS OF THE CONTRACTOR REQUIREMENT DOCUMENT (CRD) ATTACHED TO A DIRECTIVE WHEN REQUIRED BY SUCH CRD.

Directive Number Title Requirements include, but are not limited to, the following:

DOE M 460.2-1 Radioactive Material Transportation Practices

CONTRACTOR must comply with standard transportation practices specified in CRD to use in planning and executing offsite shipments of radioactive materials including radioactive waste.

DOE M 474.1-1B Manual for Control and Accountability of Nuclear Materials

CONTRACTOR must comply with the requirements specified in the CRD for nuclear material control and accountability.

DOE M 474.1-2A Manual for Nuclear Materials Management and Safeguards System Reporting and Data Submission

CONTRACTOR must comply with the requirements specified in the CRD for documenting and reporting data submissions for nuclear materials transactions, inventories, and material balances to the Nuclear Materials Management and Safeguards System.

DOE O 522.1 Pricing of Departmental Materials and Services

CONTRACTOR must comply with the requirements specified in the CRD for establishing prices and charges for materials and services sold or provided to external organizations, other Federal agencies, and the private sector.

DOE O 534.1B Accounting

CONTRACTOR must comply with the requirements specified in the CRD for recording and reporting all business transactions.

Page 19: RFP Invitation Letter

LFC Exhibit A General Conditions (Rev. 2, 9/14/07) Long Form Construction Subcontract

Subcontract No. * Page 1 of 2

EXHIBIT "A" GENERAL CONDITIONS

TABLE OF CONTENTS

GC Title Page GC-1 INDEPENDENT CONTRACTOR (May 2007) ...........................Error! Bookmark not defined. GC-2 AUTHORIZED REPRESENTATIVES (May 2007) ....................Error! Bookmark not defined. GC-3 NOTICES (May 2007) ...............................................................Error! Bookmark not defined. GC-4 SUBCONTRACT INTERPRETATION (May 2007) ...................Error! Bookmark not defined. GC-5 NOTICE TO PROCEED (May 2007).........................................Error! Bookmark not defined. GC-6 ORDER OF PRECEDENCE (Aug 2007)...................................Error! Bookmark not defined. GC-7 STANDARDS AND CODES (May 2007)...................................Error! Bookmark not defined. GC-8 LAWS AND REGULATIONS (May 2007)..................................Error! Bookmark not defined. GC-9 PERMITS (May 2007) ...............................................................Error! Bookmark not defined. GC-10 TAXES (May 2007)....................................................................Error! Bookmark not defined. GC-10B NEW MEXICO GROSS RECEIPTS TAX (May 2007)...............Error! Bookmark not defined. GC-11 LABOR, PERSONNEL AND WORK RULES (May 2007).........Error! Bookmark not defined. GC-12 COMMERCIAL ACTIVITIES (May 2007) ..................................Error! Bookmark not defined. GC-13 NONDISCLOSURE (June 2007)...............................................Error! Bookmark not defined. GC-14 PUBLICITY AND ADVERTISING (May 2007)...........................Error! Bookmark not defined. GC-15 SAFETY AND HEALTH (May 2007) .........................................Error! Bookmark not defined. GC-16 ENVIRONMENTAL REQUIREMENTS (May 2007) ..................Error! Bookmark not defined. GC-17 SITE CONDITIONS AND NATURAL RESOURCES (May 2007)Error! Bookmark not defined. GC-18 DIFFERING SITE CONDITIONS (May 2007) ...........................Error! Bookmark not defined. GC-19 TITLE TO MATERIALS FOUND (May 2007) ............................Error! Bookmark not defined. GC-20 SURVEY CONTROL POINTS AND LAYOUTS (May 2007).....Error! Bookmark not defined. GC-21 SUBCONTRACTOR'S WORK AREA (May 2007) ....................Error! Bookmark not defined. GC-22 CLEANING UP (May 2007) .......................................................Error! Bookmark not defined. GC-23 COOPERATION WITH OTHERS (May 2007) ..........................Error! Bookmark not defined. GC-24 SUPERINTENDENCE BY SUBCONTRACTOR (May 2007)....Error! Bookmark not defined. GC-25 RESPONSIBILITY FOR WORK, PHYSICAL SECURITY AND PROPERTY (May

2007)..........................................................................................Error! Bookmark not defined. GC-26 SUBCONTRACTOR'S PLANT, EQUIPMENT AND FACILITIES (May 2007)Error! Bookmark not defined. GC-27 ILLUMINATION (May 2007) ......................................................Error! Bookmark not defined. GC-28 USE OF COMPLETED PORTIONS OF WORK (May 2007) ....Error! Bookmark not defined. GC-29 USE OF CONTRACTOR'S CONSTRUCTION EQUIPMENT OR FACILITIES (May

2007)..........................................................................................Error! Bookmark not defined. GC-30 FIRST AID FACILITIES (May 2007)..........................................Error! Bookmark not defined. GC-31 INSPECTION, QUALITY SURVEILLANCE, REJECTION OF MATERIALS AND

WORKMANSHIP (May 2007)....................................................Error! Bookmark not defined. GC-32 TESTING (May 2007)................................................................Error! Bookmark not defined. GC-33 EXPEDITING (May 2007)..........................................................Error! Bookmark not defined. GC-34 EXCUSABLE DELAYS (May 2007) ..........................................Error! Bookmark not defined. GC-35 CHANGES (May 2007)..............................................................Error! Bookmark not defined. GC-36 DISPUTES (May 2007) .............................................................Error! Bookmark not defined.

Page 20: RFP Invitation Letter

LFC Exhibit A General Conditions (Rev. 2, 9/14/07) Long Form Construction Subcontract

GC-37 BANKRUPTCY (May 2007).......................................................Error! Bookmark not defined. GC-38 RECORDS AND AUDIT (May 2007).........................................Error! Bookmark not defined. GC-39 WARRANTY (May 2007)...........................................................Error! Bookmark not defined. GC-40 BACKCHARGES (May 2007)....................................................Error! Bookmark not defined. GC-41 INDEMNITY (May 2007)............................................................Error! Bookmark not defined. GC-42 PATENT AND INTELLECTUAL PROPERTY INDEMNITY (May 2007)Error! Bookmark not defined. GC-43 ASSIGNMENTS AND SUBCONTRACTS (May 2007)..............Error! Bookmark not defined. GC-44 SUSPENSION (May 2007)........................................................Error! Bookmark not defined. GC-45 EXPORT COMPLIANCE (May 2007)........................................Error! Bookmark not defined. GC-46 GOVERNMENT RESTRICTED PARTIES AND COMMODITIES (May 2007)Error! Bookmark not defined. GC-47 OPTIONAL TERMINATION (May 2007) ...................................Error! Bookmark not defined. GC-48 TERMINATION FOR DEFAULT (May 2007) ............................Error! Bookmark not defined. GC-49 FINAL INSPECTION AND ACCEPTANCE (May 2007)............Error! Bookmark not defined. GC-50 NON-WAIVER (May 2007) ........................................................Error! Bookmark not defined. GC-51 REPRESENTATIONS AND CERTIFICATIONS (May 2007) ....Error! Bookmark not defined. GC-52 ADMINISTRATIVE CLOSE-OUT PROCEDURES (May 2007) Error! Bookmark not defined. GC-53 GOVERNMENT PROPERTY (May 2007).................................Error! Bookmark not defined. GC-59 CERTIFICATION REGARDING FORMER UC OR CONTRACTOR EMPLOYEES

(July 2007) .................................................................................Error! Bookmark not defined. APPENDICES A-1 REPRESENTATIONS AND CERTIFICATIONS *

Subcontract No. * Page 2 of 2

Page 21: RFP Invitation Letter

LFC Exhibit B Special Conditions (Rev. 4, 9/14/07) Long Form Construction Subcontract

Subcontract No. * Page 1 of 2

EXHIBIT "B" SPECIAL CONDITIONS TABLE OF CONTENTS

SC Title Page SC-3 AUTHORITY OF PERSONNEL (Aug 2007)..............................Error! Bookmark not defined. SC-5 COMMENCEMENT, PROGRESS AND COMPLETION OF THE WORK (May 2007)Error! Bookmark not defiSC-7 COMPONENT WARRANTIES (May 2007)...............................Error! Bookmark not defined. SC-9 CONSTRUCTION SUBCONTRACT SPECIAL TAX PROVISION (May 2007)Error! Bookmark not defined. SC-11 CONTRACTOR-FURNISHED DRAWINGS AND SPECIFICATIONS (May 2007)Error! Bookmark not definedSC-13 CONTRACTOR-FURNISHED GOVERNMENT-OWNED MATERIALS AND

EQUIPMENT (May 2007) ..........................................................Error! Bookmark not defined. SC-15 CONTRACTOR-FURNISHED PERMITS (May 2007)...............Error! Bookmark not defined. SC-19 CONTRACTOR-FURNISHED UTILITIES AND FACILITIES (May 2007)Error! Bookmark not defined. SC-25 DAVIS-BACON WAGE DETERMINATION (May 2007)............Error! Bookmark not defined. SC-27 DECONTAMINATION OF EQUIPMENT AND MATERIALS (May 2007)Error! Bookmark not defined. SC-29 DEFINITIONS (May 2007).........................................................Error! Bookmark not defined. SC-31 FINES AND PENALTIES (May 2007) .......................................Error! Bookmark not defined. SC-35 INSURANCE REQUIREMENTS (Aug 2007) ............................Error! Bookmark not defined. SC-37 INVOICING AND PAYMENT (Aug 2007)..................................Error! Bookmark not defined. SC-37A INVOICING AND PAYMENT (Aug 2007)..................................Error! Bookmark not defined. SC-39 LANL WORK DAYS AND AVERAGE ADVERSE WEATHER DAYS (May 2007)Error! Bookmark not definedSC-41 MEASUREMENT FOR PAYMENT (May 2007) ........................Error! Bookmark not defined. SC-41A MEASUREMENT FOR PAYMENT (May 2007) ........................Error! Bookmark not defined. SC-43 MODIFICATIONS TO EXHIBIT "A" GENERAL CONDITIONS (May 2007)Error! Bookmark not defined. SC-45 NUCLEAR HAZARDS INDEMNITY AND PRICE ANDERSON ACT (July 2007)Error! Bookmark not defined.SC-47 ON-SITE USE OF RADIOACTIVE DEVICES (May 2007)........Error! Bookmark not defined. SC-49 PERFORMANCE AND PAYMENT SECURITIES (May 2007) .Error! Bookmark not defined. SC-51 POSSIBILITY OF CONTAMINATION OF SUBCONTRACTOR-OWNED MATERIALS

AND EQUIPMENT (May 2007) .................................................Error! Bookmark not defined. SC-53 PREFERENCE FOR LOCAL FIRMS IN SUBCONTRACTING (May 2007)Error! Bookmark not defined. SC-55 PRICING OF ADJUSTMENTS (May 2007)...............................Error! Bookmark not defined. SC-57 PHYSICAL SECURITY (May 2007) ..........................................Error! Bookmark not defined. SC-59 REPORTS (May 2007) ..............................................................Error! Bookmark not defined. SC-63 SECURITY INTEREST (May 2007) ..........................................Error! Bookmark not defined. SC-65 SUBCONTRACTOR-FURNISHED DRAWINGS, DATA AND SAMPLES (May 2007)Error! Bookmark not defSC-69 SUBCONTRACT SCHEDULE (July 2007)................................Error! Bookmark not defined. SC-69A SUBCONTRACT SCHEDULE (May 2007) ...............................Error! Bookmark not defined. SC-71 SUBCONTRACTS WITH CONTRACTOR’S TEAM MEMBERS AND TEAM

MEMBER AFFILIATES (June 2007) .........................................Error! Bookmark not defined. SC-75 TEMPORARY ACCESS AND HAUL ROADS (May 2007) .......Error! Bookmark not defined. SC-77 TITLE AND RISK OF LOSS (May 2007)...................................Error! Bookmark not defined. SC-79 WORK-SITE BULLETIN BOARD (May 2007)...........................Error! Bookmark not defined. SC-104 CONTRACT ADMINISTRATOR’S PROPERTY REPRESENTATIVE (May 2007)Error! Bookmark not definedSC-106 CONTRACTOR-FURNISHED GOVERNMENT-OWNED RECORDS (May 2007)Error! Bookmark not definedSC-108 COST ACCOUNTING STANDARDS LIABILITY (May 2007) ...Error! Bookmark not defined.

Page 22: RFP Invitation Letter

LFC Exhibit B Special Conditions (Rev. 4, 9/14/07) Long Form Construction Subcontract

SC-112 KEY PERSONNEL (Aug 2007) .................................................Error! Bookmark not defined. SC-114 LABORATORY ANALYSES (May 2007)...................................Error! Bookmark not defined. SC-116 LIMITATION OF FUNDS (June 2007).......................................Error! Bookmark not defined. SC-118 LIQUIDATED DAMAGES (May 2007).......................................Error! Bookmark not defined. SC-120 LOWER-TIER SUBCONTRACTORS (May 2007) ....................Error! Bookmark not defined. SC-122 MEASUREMENT SYSTEM (May 2007) ...................................Error! Bookmark not defined. SC-126 ON-SITE HANDLING AND DISPOSAL OF HAZARDOUS MATERIAL (May 2007)Error! Bookmark not defineSC-128 OFF-SITE TRANSPORTATION AND DISPOSAL OF HAZARDOUS MATERIAL (May

2007)..........................................................................................Error! Bookmark not defined. SC-134 REGIONAL PURCHASING PRICING PREFERENCE (July 2007)Error! Bookmark not defined. SC-141 SUBCONTRACTOR’S REGIONAL AND COMMUNITY DEVELOPMENT PLAN (July

2007)..........................................................................................Error! Bookmark not defined. SC-142 SUBCONTRACTOR’S SMALL BUSINESS SUBCONTRACTING PLAN (May 2007)Error! Bookmark not defi Appendices B-1 DAVIS-BACON WAGE DETERMINATION B-2 SMALL BUSINESS SUBCONTRACTING PLAN B-3 *

Subcontract No. * Page 2 of 2

Page 23: RFP Invitation Letter

LFC Exhibit C (Rev. 0, May 2007) Long Form Construction Subcontract

EXHIBIT “C” – QUANTITIES, PRICING AND DATA Subcontract No. * Table of Contents Page 1 of 1

EXHIBIT “C” QUANTITIES, PRICING AND DATA

TABLE OF CONTENTS

Form Title A Schedule of Quantities and Prices

Example 1 Lump Sum Form A Schedule of Quantities and Prices Form A-1 Schedule of Lump Sum Prices Form A-2 Schedule of Craft Rates for Changes Form A-3 Schedule of Rates for Design Work Changes Example 2 Lump Sum Milestones with Price Adjustment Provisions Form A Schedule of Quantities and Prices Form A-1 Schedule of Lump Sum Milestone Payments Example 3 Unit Price Form A Schedule of Quantities and Prices Form A-1 Schedule of Unit Prices Form A-2 Measurement For Payment Table

B Construction Plant and Equipment List C Subcontractor and Vendor List C-1 Lower-tier Experience Statement D Subcontract Schedule E Personnel Tabulation F Project Organization and Work Plan G Safety Program H Resumes of Key Personnel I Summary of QA/QC Program J Technical Data K Miscellaneous Information L Jobsite Requirements M Work in Progress N Experience Statement O [Reserved] P Estimated Payment Schedule Q Exceptions and Deviations R Alternative Material and Equipment S Shipping Schedule T Rigging Plans U Environmental Compliance V Alternative Bids

Page 24: RFP Invitation Letter

LFC Exhibit D (Rev. 0, May 2007) Long Form Construction Subcontract

EXHIBIT "D" SCOPE OF WORK AND TECHNICAL SPECIFICATIONS

1.0 PROJECT/PROGRAM GOALS AND OBJECTIVES: The goals and objectives of the *

project are as follows: *

SUBCONTRACTOR is expected to contribute to the foregoing goals and objectives in the following manner: *

2.0 SCOPE OF WORK: SUBCONTRACTOR shall furnish qualified personnel, equipment,

materials and facilities to perform, as detailed in this Exhibit “D”, all work necessary to *, and required by or reasonably inferable from the Subcontract Documents. SUBCONTRACTOR shall not be relieved of performing the details of any work manifestly or customarily performed to carry out the intent of this subcontract. All work shall be performed as if fully and correctly set forth and described in the subcontract.

2.1 Work Included

2.1.1 *

2.2 Work Excluded

2.2.1 *

3.0 TECHNICAL REQUIREMENTS

3.1 Technical Specifications: The following specifications and technical documents are incorporated by reference herein and shall have the same force and effect as if printed in full text.

Specification or Document No.

Rev.

Date Title

* * * *

3.2 Codes and Standards: The following codes and standards are incorporated by reference herein and shall have the same force and effect as if printed in full text.

Code or Standard No.

Rev. Date Title

* * * *

Notes:

2.2.1 *

3.3 Technical Approach: The following technical approach or methodology shall be followed in the performance of SUBCONTRACTOR’S work.

Subcontract No. * Page 1 of 2

Page 25: RFP Invitation Letter

LFC Exhibit D (Rev. 0, May 2007) Long Form Construction Subcontract

3.3.1 *

3.4 Technical Performance Requirements

3.4.1 *

3.5 Other Requirements

3.5.1 *

3.6 CONTRACTOR’S Policies and Procedures: SUBCONTRACTOR shall comply with the following LANL policies and procedures, or parts thereof, applicable to any person who performs work at Los Alamos National Laboratory.

Policy or Procedure Number Title and Date Instructions * * *

4.0 APPENDICES

D-1 Drawing and Data Requirements D-2 *

Subcontract No. * Page 2 of 2

Page 26: RFP Invitation Letter

LFC Exhibit E (Rev. 0, May 2007) Long Form Construction Subcontract

Subcontract No. * Page 1 of 1

EXHIBIT "E" LIST OF DRAWINGS

The following drawings form a part of this subcontract: Drawing No. Rev.

No. Date Title

* * * *