Top Banner
Review for Design I Exam CHEN 4253 Terry A. Ring
13
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Review for Design I Exam CHEN 4253 Terry A. Ring.

Review for Design I Exam

CHEN 4253

Terry A. Ring

Page 2: Review for Design I Exam CHEN 4253 Terry A. Ring.

Materials CoveredWeek 1-22 AugustChapt 1 (p.1 -25), Chapt 2, Chapt 3 Product Design-

Introduction to course – Product and Process DesignProduct Design-1 OverviewProduct Design-2 Property Estimation

Week 2-29 August Chapters 16 and 17

Product Design-3 Innovation MapsProduct Design-4 Six Sigma in Product DesignProduct Design-5 Engineering Ethics

Week 3–5 September (Holiday Monday)Chapt 1 (p25-31) Chapter 4 Process Creation-

Ethics in Chemical EngineeringProcess Safety

Process Design OverviewProcess Creation

Page 3: Review for Design I Exam CHEN 4253 Terry A. Ring.

Materials Covered-con’t

Week 4–12 September (Celanese in Class Monday)Chapt 4&5&6 Aspen for Process Creation–

Use of Aspen for Process Creation-1Use of Aspen for Process Creation-2Heuristics for Process Simulation

Week 5 – 19 September Chapt 4&5 Aspen Tutorials and Problems Solved in Class (Reserve the ICC) -Week 6 - 26 September (Away Wednesday and Friday)Chapt 5&6 ProMax Tutorials and Problems Solved in Class (Reserve the ICC) - Week 7–3 OctoberChapter 22-22 (p543-558) &23 Profitability Analyses -

Annual CostsEarningsProfitability Analysis

Week 8- 11 October FALL BREAK

Page 4: Review for Design I Exam CHEN 4253 Terry A. Ring.

What have we really covered?

• Product Design (Ethics) Chapt. 1,2&3

• Process Creation Chapt 4– Heuristics for Process Synthesis Chapt 6

• Process Simulators Chapt 5– Aspen– Promax

• Capital Cost Estimates Chapt 22

• Profitability Analyses Chapt 23

Page 5: Review for Design I Exam CHEN 4253 Terry A. Ring.

Chapters 1, 2,3 & 4• Chpt. 1 - The Design Process

– Ethics in Chemical Engineering– Product design

• Chpt. 2 – Product Development• Chpt. 3 - Molecular Structure Design

– Property estimation• Chpt. 4 – Process Creation

– Gross Profitability Analysis– Process Synthesis

• Start with the reactor (differences in molecular type)• Separation (differences in composition)• Heat transfer, pumping, compression, flash tanks

(differences in temperature, pressure, and phase)• Integraton

Page 6: Review for Design I Exam CHEN 4253 Terry A. Ring.

Chemical Product Design

Pyramid

Figure of Merit

Page 7: Review for Design I Exam CHEN 4253 Terry A. Ring.

Physical Property Estimation

• Hansen Solubility Parameters• Group Contribution Methods

– Polymer properties– Surface tension– HLB– Heat of Mixing

• Drago E and C

– Work of Adhesion• Wetting

• Bio-concentration factor• Oil-water distribution Coefficient• Lethal Dose

• Flash Point Temp.

Page 8: Review for Design I Exam CHEN 4253 Terry A. Ring.

Chapters 5 and 6

• Chapter 5 – Simulation to Assist in Process Creation– Steady-state flow sheet simulation

• Table 5.1 – Unit Subroutines• Recycle (tear streams)

– Recycle convergence

• Chapter 6 – Heuristics for Process Synthesis– Summary on page 174, Table 6.2– Using these as a start in design/simulation

Page 9: Review for Design I Exam CHEN 4253 Terry A. Ring.

Process Creation

• Process Economics – Gross Profitability Analysis

• Focus on Reactor– Equilibrium– Kinetics or Conversion

• Focus on Separation System

• Heuristics in Process Design

Page 10: Review for Design I Exam CHEN 4253 Terry A. Ring.

Chapter 22 - Costing

• Accounting – Debits/credits; annual report; balance sheet

• Cost Indexes• Capital investment costs (Table 22.9,pg. 547)

– Bare model costs– Total depreciable capital– Total permanent investment– Total capital investment

• Estimation of Total Capital Investment– Order-of-magnitude– Study estimate– Preliminary estimate– Definitive estimate

Page 11: Review for Design I Exam CHEN 4253 Terry A. Ring.

Investment Chapter 23 - Costing

• Estimation of total capital– Order-of-magnitude (method of Hill)

• See page 498• +/- 50%

– Study estimate (Method of Lang)• See page 500• +/- 35%

– Preliminary estimate (method of Guthrie)• See page 503• +/- 20%• Most likely used• Need fob equipment purchase cost

– More definitive• Aspen Icarus (but we do not have this license)

Page 12: Review for Design I Exam CHEN 4253 Terry A. Ring.

Process Economics

• Capital Cost Estimation– Cost Indexes– Three types

• Scaleup of Capital Investments - 6/10th rule• Order of Magnitude Estimate (±50%) - Hill• Study Estimate (±35%) - Lang

• Profitability Analysis– ROI, PBP, IRR, VP, Cash Flow Calcs.

• Accounting

Page 13: Review for Design I Exam CHEN 4253 Terry A. Ring.

Format for Exam

• Exam in 2 parts– Wednesday, 20 October 2009

• In class written exam• Open book, open notes• Last Year’s Exam

– Friday, 22 October 2009• In class, open book, open notes

– 1- Aspen Problem– 1- ProMax Problem

» Competency Test