Task_Table1NameDurationSummaryMEDUPI LPS CIVILS Rev14495.13
daysYes PROJECT MANAGEMENT405.06 daysYesMedupi Project Admin
Requirements405.06 daysNoMedupi Civils Site Project Plant405.06
daysNoMedupi Civils Site Project Offices302.81 daysNoMedupi Project
Site Staff Offices302.81 daysNoMedupi Civils Site Project
Stores302.81 daysNoMedupi Site Project Management Cleaners405.06
daysNo Medupi Civils Site Project Management405.06 daysNo
MILESTONES495.13 daysYes Start0 daysNo Finish0 daysNo ACCESS
MILESTONES284.44 daysYes Access to Valve Pit 'CC1'0 daysNo Access
to Valve Pit 'CC2'0 daysNo Access to Valve Pit 'CC3'0 daysNo Access
to Valve Pit 'CC4'0 daysNo Access to Valve Pit 'CC5'0 daysNo Access
to Valve Pit 'CC6'0 daysNo Access to Valve Pit BB10 daysNo Access
to Valve Pit 'V1' to Valve Pits 'LL1/MM1/NN1 & CSY)0 daysNo
Access to Ash Dump Make-up Routing from FWS Pipe Installation0
daysNo Access to Compressor house North0 daysNo ACCESS to DIESEL
STORAGE & OFFLOADING AREA0 daysNo ACCESS to COAL STOCK YARD0
daysNo ACCESS to ASH DUMP IRRIGATION PUMP STATION0 daysNoValve Pit
"01" Auxbay Unit 10 daysNo COMPLETION MILESTONES462.44 daysYes FIRE
WATER OVERLAND PIPE TRENCHING411 daysYes Valve Pit "CC1" to Unit 6
ACC0 daysNo Valve Pit "CC2" to Unit 5 ACC0 daysNo Valve Pit "CC3"
to Unit 4 ACC0 daysNo Valve Pit "CC4" to Unit 3 ACC0 daysNo Valve
Pit "CC5" to Unit 2 ACC0 daysNo Valve Pit "CC6" to Unit 1 ACC0
daysNo Valve Pit "R" to Substation West0 daysNo Valve Pit "BB1' to
Fire Pump House0 daysNo Valve Pit "K" to Valve Pit "L2" to TH30
daysNo Valve Pit "Q" to Incline Coal Conveyor0 daysNo Valve Pit "K"
to 10 000 ton Silo (EXXARO)0 daysNo Valve Pit "V1" to "LL1" to
"MM1" to "NN1" to CSY South0 daysNo Valve Pit "V1" to "LL1" to
"MM1" to "NN1" to CSY South MANHOLE COVERS INSTALLED0 daysNo
Routing from Valley Pit "V" to TH8 & TH9 + Ash Dam to Silo0
daysNo Fire Pump House Completion Date0 daysNoValve Pit "01" Auxbay
Unit 10 daysNo CLEAN DIRTY DRAIN SYSTEM20.25 daysYes Clean &
Dirty Drains Overland Pipe Trenching Completion Date0 daysNo Clean
& Dirty Drains Pump House Completion Date0 daysNo RAW WATER
SYSTEM0 daysYes Raw Water Phase 20 daysNo WATER TREATMENT
PLANT213.19 daysYes Base Type P08 Complete0 daysNo Pipe Support to
Calrifier Complete0 daysNo COMPRESSED AIR87.63 daysYes COMPRESSOR
HOUSE ( NORTH )0 daysNo 88M BRIDGE / CAS BRIDGE ( NORTH)0 daysNo
DIESEL STORAGE & OFFLOADING AREA234.69 daysYes DESIGN,
PROCUREMENT AND SETTING OUT ( Complete )0 daysNo CONSTRUCTION (
Complete )0 daysNo COAL STOCK YARD0 daysYes DESIGN, PROCUREMENT AND
SETTING OUT ( Complete )0 daysNo CONSTRUCTION ( Complete )0 daysNo
ASH DUMP IRRIGATION PUMP STATION393.25 daysYes DESIGN, PROCUREMENT
AND SETTING OUT ( Complete )0 daysNo CONSTRUCTION ( Complete )0
daysNo ASH DUMP IRRIGATION ( Complete )0 daysNo LP GAS PIPELINE
COMPLETE0 daysNo RING FEED HYDRANDTS COMPLETE0 daysNo DELAYS25.31
daysYesNUMSA Strike0 daysNoNation Wide strike by Metal Industry
Members ref letter:C222-1.2-730 daysNoNUMSA Strike ref
letter:PSE-LNS-550-P04-PM0 daysNoWaiting for Steel,Rebar & Cast
in Items10.31 daysNo CONSTRUCTION495.13 daysYes FIRE WATER
SYSTEM477.44 daysYes FIRE PUMP HOUSE & DIESEL BUND178.93
daysYesRe Compact Fire Pumphouse GROUND WORKS5 daysNo Aprons10
daysNo Fit pipes, valve9.5 daysNo Handrailing to sump2 daysNoPlinth
type P1 & P2 (2NO)9.63 daysYesScabbling4.5 daysNoDowelling1
dayNoRebar1 dayNoFormwork1 dayNoConcrete1 dayNoStrip Formwork1
dayNoFIRE WATER PUMP HOUSE(DIESEL BUND AREA)141.86 daysYesAFC
Drawings0 daysNoWap Submition2 daysNoWap Aproval15
daysNoProcurement of Material(rebar & cast in items)2 wksNoShop
Detail drawings Preparation1 wkNoShop Drawing approval4
wksNoFabrication of Structural steel4 wksNoSetting out1
dayNoBASE,PLINTHS (4no) & BEAMS(2no)6.63 daysYesScabble
Surface1 dayNoDowelling1 dayNoRebar1 dayNoFormwork1 dayNoConcrete1
dayNoStrip1 dayNoCOLUMNS(4no)4.38 daysYesRebar1 dayNoFormwork1
dayNoConcrete1 dayNoStrip1 dayNoBEAMS37.13 daysYesFormwork4
daysNoRebar2 daysNoTQ 110 Raised (TOC Descrepency)9 daysNoConcrete1
dayNoCuring21 daysNoStrip3.38 daysNoStructural Steel13.3
daysYesInstallation10 daysNoPunch List3 daysNo QC Documentation3
daysNo Handover0 daysNo FIRE WATER OVERLAND PIPE TRENCHING477.44
daysYes VALVE PIT "CC1" to Unit 6 ACC6.13 daysYes 110 OD MPVC 24M
LONG6.13 daysYes Denso Wrapping by ( SVK )0 daysNo SVK Over
Wrapped0 daysNo Backfill3 daysNo Install Fire Hydrant Pedastals1
dayNoFloor washer Repairs3.13 daysYesDenso Wrapping by SVK0
daysNoBackfill2 daysNo Handover1 dayNo VALVE PIT "CC2" to Unit 5
ACC89.19 daysYesDelay Access50 daysNo 160 OD MPVC 135M LONG9.81
daysYesLaying of Pipes1 dayNoPipe fitting1 dayNo Thrust Block3
daysNo Thrust Block Concrete Curing7 daysNo Blanket backfill7
daysNo 110 OD MPVC 24M LONG17.5 daysYes Hydro Testing2 daysNo Denso
Wrapping by ( SVK )0 daysNo Backfill2 daysNo Install Fire Hydrant
Pedastals1 dayNoSoilcrete1 dayNo Handover1 dayNoHandover
Certificate ref letter:PSE-LNS-595-P04-PM0 daysNo VALVE PIT "CC3"
to Unit 4 ACC212.18 daysYesPhase 3, Wind wall to Rack, ACC 4212.18
daysYesAccess Delay ref letter:PSE-LNS-640-P04-PM84.31
daysNoLNS-PSE-722-P04-PM/PSE-SS-SI-037 Change in Programme Sequence
for installation.101 daysNo 160 OD MPVC 24M LONG26.86 daysYes
Setting out1 dayNo Excavation3 daysNo Bedding1.19 daysNo Laying of
pipes2.59 daysNoFH and fittings1 dayNoThrust Blocks Casting3.69
daysNoThrust block curing3 daysNoSoilcrete backfill1 dayNoBlanket
backfilling2 daysNo Hydro Testing2 daysNoDenso Wrapping0 daysNo
Backfill2 daysNo Install Fire Hydrant Pedestals1 dayNo Handover1
dayNoQC - Documentation2 daysNoPhase 2, VP to Wind wall, ACC
4186.31 daysYes 200 OD MPVC 135M LONG186.31 daysYesDelay Access as
per PSE-LNS-638-P04-PM/LNS-PSE-722-P04-PM/PSE-SS-SI-03793
daysNoLNS-PSE-722-P04-PM/PSE-SS-SI-037 Change in Programme Sequence
for installation.73 daysNo Setting out1 dayNo Excavation4 daysNo
Bedding3 daysNo Laying of pipes2 daysNo FH and Fittings2 daysNo
Thrust Block Casting1 dayNo Thrust Block Curing4 daysNo Blanket
Backfill3 daysNo Denso Wrapping0 daysNo Hydro Testing3 daysNo
Backfill3 daysNo Install fire Hydrant Pedestals1 dayNo Handover1
dayNo VALVE PIT "CC4" to Unit 3 ACC117.5 daysYesPhase 1, Wind wall
to Rack, ACC 3108.25 daysYesAccess Delay ref
letter:PSE-LNS-638-P04-PM52.5
daysNoLNS-PSE-722-P04-PM/PSE-SS-SI-037 Change in Programme Sequence
for installation.1.88 daysNo 160 OD MPVC 24M LONG41.25 daysYes
Setting out1 dayNo Excavation3 daysNo Bedding1 dayNo Laying of
pipes1 dayNoFH and fittings1 dayNoThrust Blocks Casting3.13
daysNoSoilcrete backfill1 dayNoLPS-C222-TQ 54 - Incorrect position
of Concrete sleeve16.63 daysNoPSE-SS-SI-042 ( TQ 54 response)0
daysNo Hand Excavation3 daysNoFounding level0.88 daysNo Bedding1.13
daysNo Laying of pipes0.81 daysNoFormwork under wind wall0.88
daysNoSoilcrete backfill1.13 daysNoFH and fittings1.13
daysNoBlanket backfilling2 daysNo Hydro Testing2 daysNoDenso
Wrapping0 daysNo Backfill2 daysNo Install Fire Hydrant Pedestals1
dayNo Handover1 dayNoPhase 4, VP to Wind wall, ACC 3117.5 daysYes
200 OD MPVC 135M LONG117.5 daysYesDelay Access as per
PSE-LNS-638-P04-PM/LNS-PSE-722-P04-PM/PSE-SS-SI-03766
daysNoLNS-PSE-722-P04-PM/PSE-SS-SI-037 Change in Programme Sequence
for installation.22.94 daysNo Setting out, 75 %1 dayNo Excavation,
75%4 daysNo Bedding, 75%2 daysNo Laying of pipes, 75%3 daysNo FH
and Fittings, 75%3.63 daysNo Thrust Block Casting, 75%1.94 daysNo
Thrust Block Curing, 75%4 daysNo Blanket Backfill, 75%3 daysNo
Denso Wrapping, 75%0 daysNoDelay- C222-1.2-17639 daysNoSetting out,
25%1 dayNoExcavating, 25%2 daysNoBedding 25%2 daysNoLaying pipes,
25%2 daysNoFH and fittings, 25%1 dayNoThrust block casting. 25%1
dayNoThrust block curring, 25%4 daysNoBlanket backfilling, 25%2
daysNoDenso wrapping 25%0 daysNoHydro testing.3 daysNo Backfill3
daysNo Install fire Hydrant Pedestals1 dayNo Handover1 dayNoQC -
Documentation2 daysNo VALVE PIT "CC5" to Unit 2 ACC193.06
daysYesAccess delay, Ref C222-1-2-165/ PSE-LNS-676-P04-PM149 daysNo
160 OD MPVC 135M LONG23.88 daysYes Setting out1 dayNo Excavation5
daysNo Bedding4 daysNo Laying of pipes3.69 daysNo Pipe Finttings1
dayNo Thrust Block2 daysNo thrust Block Concrete Curing7 daysNo
Blanket backfill3 daysNo 110 OD MPVC 24M LONG24.19 daysYes Setting
out1.75 daysNo Excavation2.25 daysNo Bedding2.25 daysNo Laying of
pipes2.56 daysNo Blanket backfill4 daysNo Hydro Testing3.56 daysNo
Denso Wrapping by ( SVK )0 daysNo Backfill3.44 daysNo Install Fire
Hydrant Pedastals2.38 daysNo Handover1 dayNo VALVE PIT "CC6" to
Unit 1 ACC192.94 daysYesAccess delay, Ref
C222-1-2-165/PSE-LNS-676-P04-PM158 daysNo 160 OD MPVC 135M
LONG25.19 daysYes Setting out1 dayNo Excavation5 daysNo Bedding4
daysNo Laying of pipes3.38 daysNo Pipe Fittings1.81 daysNo Thrust
Block2 daysNo Thrust Block Concrete Curing7 daysNo Blanket
backfill3.44 daysNo 110 OD MPVC 24M LONG34.56 daysYes Setting out1
dayNo Excavation2.81 daysNo Bedding4 daysNo Laying of pipes2.31
daysNo Blanket backfill3.44 daysNo Hydro Testing2.63 daysNo Denso
Wrapping by ( SVK )0 daysNo Backfill3.25 daysNo Install Fire
Hydrant Pedastals2 daysNo Handover1 dayNo VALVE PIT "R" to
SUBSTATION WEST / 1000 TON SILO134.88 daysYes 355 OD MPVC 310M
LONG134.88 daysYesWork delay. Receive spools from wetback /
PSE-LNS-592-P04-PM18.88 daysNo Re-install the spool3.69 daysNo
Thrust Block6.13 daysNo Thrust Block Concrete Curing7.25 daysNo
Hydro Testing1.63 daysNo Denso Wrapping ( SVK )8 daysNo Backfill2
daysNoDelay receival of spool for Re route to DFO/
PSE-LNS-621-P04-PM25.88 daysNoSpool installation0.88 daysNo Blanket
backfill (re-route to DFO)3.13 daysNoIncorrect spool detailed on
Drawings & New DR to be issue by LNS49.5 daysNoRe- installation
of spool and thrust block & curing4 daysNo Hydro Testing1 dayNo
Denso Wrapping ( SVK )1.88 daysNo Backfill1.13 daysNoDelay Access
permit for FH Pedastals installation96 daysNo Install Fire Hydrandt
Pedastals2 daysNo Handover1 dayNo VALVE PIT "Q" to INCLINE COAL
CONVEYOR / 1000 TON SILO145.31 daysYes 355 OD MPVC 150M LONG145.31
daysYesDelay, receive spools form wetback-PSE-LNS-592-P04-PM87.31
daysNo Received Spools From WETBACK0 daysNoLetter ref:
C222-1.2-LNS-002 Suspend Works & re-allocate resources to
FWS/ADM until 1st available resources39 daysNo Re-install the
spool5 daysNo Thrust Block3 daysNo Thrust Block Concrete Curing7
daysNo Blanket Backfilling1 dayNo Hydro Testing1 dayNo Denso
Wrapping ( SVK )0 daysNo Backfill3 daysNo Install Fire Hydrandt
Pedastals2 daysNo Final Handover1 dayNo VALVE PIT "V1" to "LL1" to
"MM1" to "NN1" to CSY SOUTH104 daysYes 355 OD MPVC 600M LONG104
daysYes Piping Between MM1 & CSY South104 daysYes Thrust Block4
daysNo Thrust Block Concrete Curing7 daysNo Blanket backfill2
daysNoFixing CAT A item6 daysNoTemporal Thrust Block ref
letter:LNS-PSE-653-P04-PM0 daysNoTemporal Thrust Block4
daysNoInstallaton of temporal thrust block ref
letter:PSE-LNS-601-P04-PM0 daysNo Hydro Testing(Preparation)2
daysNo Delay: Rain 04-11-2014/ PSE-LNS-609-P04-PM5 daysNoFixing
Leak East side of LL13 daysNo Hydro Testing3 daysNoHandover to
others for wrapping0 daysNo Denso Wrapping ( SVK )0 daysNo
Backfill5.63 daysNoDamage by Fire hydrant ref
letter:LNS-PSE-644-P04-PM11.38 daysNoInstalling Hydrant2 daysNo
Handover1 dayNo Valve Pit "MM 1"21.81 daysYes Denso Wrapping ( SVK
)5.06 daysNo Backfill4.94 daysNoDecember Break & 2015
Inductions, etc23 daysNo Install manhole covers0.88 daysNo Valve
Pit "NN 1"22.94 daysYes Denso Wrapping ( SVK )10.19 daysNo
Backfill4.8 daysNo Install manhole covers0.88 daysNo VALVE PIT
"BB1' to FIRE PUMP HOUSE49.69 daysYes 355 OD MPVC 30M LONG49.69
daysYesDelay, Handover from piping Contractor /
PSE-LNS-592-P04-PM31.56 daysNo Pipe fittings ( Wetback )2 daysNo
Thrust Block3 daysNo Thrust block concrete curing7 daysNo Blanket
backfill3 daysNo Hydro Testing ( Wetback )2 daysNo Final Backfill1
dayNo VALVE PIT "K" TO 10 000 ton SILO (EXXARO)321.75 daysYes 250
OD MPVC 5000M LONG321.75 daysYesPumping Rain Water in Trenches0
wksNoFLASH POINT DETAIL 8 (DR-LNS-185)106.81 daysYesDR Date Issued0
daysNoProcurement of Material2 wksNoPipe Fitting3 daysNo
Instruction to re Open All Steel Spools for wrapping7.25 daysNo
Excavate for Denso Wrapping18 daysNoPumping of Rain Water ( 10 000
SILO )7 daysNo SVK DENSO9 daysNo Backfill5 daysNo Install Fire
Hydrandts Pedastals8 daysNoPumping rain water & cleaning mud at
VENT PIT K TO 10 000 SILO(16 &23 April 2014 rain)1
dayNoInstruction Re -Excavation (Rain Closed Trench) for Denso
Wrapping21 daysNoInstruction to
Re-Excavate(FH1,FH4,FH13,FH14,FH29)6 daysNo SVK DENSO0 daysNo
Backfill7 daysNo Install Fire Hydrandts Pedastals6 daysNoFailing
Hydro test VP K -10 000 SILO ref letter:PSE-LNS-516-P04-PM2
daysNoRe opening of Flange in Pit 20.56 daysNoRemoval of wrapping
& installing Spade1 dayNoRe-Hydro test1 dayNo Handover0
daysNoVP K to 10 000 ton Silo Flashing Pit128.94 daysYesDelay
Receival of clossure spools (Dwg 2955 Sheet 16, Spools 6,7 &
8126 daysNoInstall spools1 dayNoHydro test1 dayNoDenso Wrapping by
SVK1 dayNoHand over from SVK for backfill0 daysNoTQ 147 Concrete
Chamber Height-Response81 daysNoBlanket Backfill2 daysNoFinal
Backfill3.56 daysNo Handover0 daysNo VALVE PIT "K" to VALVE PIT
"L2" to TH375.13 daysYes 355 OD MPVC 200M LONG (Outstanding)41.44
daysYesWorking on CAT A items6 daysNo Hydro Test2 daysNo Denso
Wrapping ( SVK )0 daysNo Backfill10 daysNo Valve Pit "MM"43.69
daysYes Walls43.69 daysYes Install manhole covers2 daysNo Denso
Wrapping ( SVK )0.88 daysNo Backfill10.19 daysNo Valve Pit
Complete0.88 daysNo Handover1.63 daysNo Valve Pit "NN"48.94
daysYesDCN-LNS-3215.69 daysYesREINSTATING OF APPRON SLAB5.69
daysYesFormwork1 dayNoMesh1 dayNoConcrete1 dayNoStrip1 dayNoJoint
Sealing1.25 daysNo Walls48.94 daysYes Install manhole covers2
daysNo Denso Wrapping ( SVK )0.88 daysNo Backfill9.13 daysNo Valve
Pit Complete0.88 daysNo Handover1.69 daysNo ROUTING FROM VALVE PIT
"V" to TH8 & TH9 + ASH DAM to SILO385.91 daysYesDELAYS &
DISRUPTIONS290.5 daysYes Receipt of AFC Drawings0 daysNoQuantify
& Procurement of Materials8 wksNoFree Issue material
confirmation51 daysNo Setting out6 daysNoDelay Cable cut during
excavation6 daysNoSuspension of excavation due to the danger on
site during Excavations at ADM Line ref
letter:PSE-LNS-503-P04-PM3.88 daysNoSetting out (remaining )5.63
daysNoObstruction of material ADM. TQ 105. ref letter
PSE-LNS-518-P04-PM56 daysNoConfirmation of Contractors's verbal
Instruction to De-Mobilise excavation Equipment ref
letter:PSE-LNS-521-P04-PM0 daysNoDelay in Construction ref
letter:PSE-LNS-554-P04-PM10.25 daysNoDelay:Distraction as Other
Contractors are working/ obstacles in the area ( FH9 - SOP12)74.81
daysNoDelay; TQ 137 Directionl Drilling (SOP 12)72
daysNoDelay:Distraction as Other Contractors are working/ obstacles
in the area (SOP12 - SOP 5 )156 daysNoTQ 144 Line clashes with
Stormwater Ressolved (TH7 - PJFF)51 daysNoTQ 109 Water
seepage-Ressolved (FH12 - FH13)90 daysNoEarly warning additional
works ref letter:LNS-PSE-651-P04-PM/PSE-LNS-600-P04-PM & SI
0458106 daysNoTQ 101 Clash with the Route-Response ( FH15 - AV 5
)74.25 daysNoTQ 104 Stormwater Pipe -Resolution ( FH15 - AV 5109
daysNoDelay in Construction ref letter:PSE-LNS-554-P04-PM ( FH15 -
AV 550 daysNoTQ 138 Clash with Channel ( Bridge 28 )50.69
daysNoDelay:Waiting for LNS to clear Fence Isues (FH19-FH20
DIRECTIONAL DRILLING)114 daysNoTQ 114 Outside Security Fence
(FH19-FH20 DIRECTIONAL DRILLING)105 daysNoDelay. Pumping water and
cleaning mud. Ref letter PSE-LNS-631-P04-PM. C222-1-2-13511
daysNoDelay in Construction ref TQ 114 and
letter:PSE-LNS-554-P04-PM ( AV5 - FH25)119.25 daysNoDelays at ADM
Ref letter:PSE-LNS-599-P04-PM ( AV5 - SOP52 )40 daysNoDrawing on
Hold ( AV5 - FH52)40 daysNoDelay of free issue material:
PSE-LNS-593-P04-PM2 daysNoTQ 123 Concrete Chamber Details ( Valve
Pit AV 1 )22.25 daysNoTQ 136 Water Seepage ( Scour Valve 2 &
Isolation Valve 1; 2 )4 daysNoTQ 143 Electric Cable clash ( Scour
Valve 3 )7 daysNoDelay: Rain 03-11-2014 ( Scour Valve 4 )5
daysNoDelay: Rain 03-11-2014 ( Isolation Valve 1)1 dayNoPumping
rain wate & cleaning mud ( Isolation Valve 1)1 dayNoPumping
Rain Water and cleaning mud ( Isolation Valve 3 )8 daysNoRain
damage ref letter :C222-1-2-135 ( Isolation Valve 3 )2 daysNoDelay
due to Rain ref letter:PSE-LNS-631-P04-PM ( Isolation Valve 3 )2
daysNoRain Delay ( Isolation Valve 4)4 daysNoCivil leave Rain0
daysNoPumping Rain water and cleaning mud ( Isolation Valve 4)8
daysNoRain damage ref letter :C222-1-2-1351 dayNoDelay due to Rain
ref letter:PSE-LNS-631-P04-PM2 daysNoMilestones165.04 daysYesStart0
daysNoFinish0 daysNoDelivery of Spools0 daysNoPHASE 1 & PHASE
II107.88 daysYesTeam 1119 daysYes TH 773 daysYesSetting Out42.88
daysNoExcavating Test Holes42.5 daysNoPiping60.63 daysYesAwaiting
for Design42.88 daysNoExcavation6.5 daysNoFounding level1
dayNoBedding2 daysNoPipe laying0 daysNoBlanket0.88 daysNoThrust
Block SHT 10 Det.1-21 dayNoInstall Spools SHT 10 Det.349.88
daysYesDimension0.94 daysNoWelding0.88 daysNoGalvanise0.94
daysNoReceive Spools0.88 daysNoFitting4.13 daysNoThrust Block SHT
10 Det. 031 dayNoHydro1.88 daysNoWrapping0 daysNoHoliday Test1.38
daysNoBackfill4 daysNoSOP 4-SOP12 (Piping)20.25 daysYesExcavation5
daysNoRe-routing from SOP7-SOP5 DR 2611 dayNoExcavation2
daysNoFounding level1 dayNoBedding4 daysNoPipe laying2.88
daysNoBlanket Backfill0 daysNoSOP 5(TB)20.63 daysYes Founding
level0 daysNoBlinding1 dayNoSpools2 daysNoRebar0.88
daysNoFormwork1.88 daysNoConrete0.13 daysNoStrip formwork0.88
daysNoSOP 6 (TB)15.38 daysYes Founding level1 dayNoBlinding1
dayNoSpools1.88 daysNoRebar1.88 daysNoFormwork2.88 daysNoConrete0
daysNoStrip formwork0 daysNoSOP 7 (TB)17.38 daysYes Founding level0
daysNoBlinding1 dayNoSpools1 dayNoRebar2.88 daysNoFormwork2.88
daysNoConrete0 daysNoStrip formwork0 daysNoThrust Block SOP 5915.5
daysYesExcavation & Founding Level2.88 daysNoFormwork5.38
daysNoConcrete1.88 daysNoSOP 10 Valve Chamber (IS1 TYPE 2)34.88
daysYesExcavation1 dayNoFounding level0.33 daysNoBlinding1
dayNoRain Delay0 daysNoPumping Water & Cleaning Mud5
daysNoRebar3 daysNoFormwork2 daysNoConcrete1 dayNoStripping0.88
daysNoROAD 3 (SOP12-SOP13)60.38 daysYesDelay - WAP Document
approval/ / PSE-LNS-608 & 679-P04-PM7 daysNoPermit to Close the
Road & Procurement of Plant ( Excavator)4.88 daysNo
Excavation0.88 daysNoScarify & Compact0.88 daysNoG6
Layerworks(1Layer)0.88 daysNo76mm Blinding0.88 daysNoInstall
Concrete Sleeves0 daysNoFormwork0 daysNo Mass Concrete0.88
daysNoConcrete Curing3 daysNoStripping Formwork0 daysNoCut &
Weld HDPE Pipe ( modifications)0.88 daysNoInstall HDPE Pipe0.88
daysNoDelay - Cracks Repairs10 daysNoG6 Layerworks (7Layers)3
daysNoC4 Subbase(1 Layer Stabilized)1 dayNoC4 Curing7 daysNoCBR/UCS
Tests1 dayNoC3 Subbase(1 Layer Stabilized)1 dayNoC3 Curing3
daysNoCBR/UCS Tests2 daysNoInstall Road Kerbs2 daysNoPrimer &
Premix2 daysNoRoad Reopen0 daysNo SOP 12 (TB)12 daysYesExcavation0
daysNoBlinding0.88 daysNoSpools3 daysNoRebar1.88 daysNoFormwork1
dayNoConrete1 dayNoStrip Formwork1 dayNoHydro3 daysNoWrapping9.13
daysNoHoliday Test1.38 daysNoBackfill6 daysNoTeam 2123.5 daysYes
SOP 13 (TB)16.88 daysYesFounding level1 dayNoBlinding1
dayNoInstallation of Spools1 dayNoRebar1 dayNoFormwork1 dayNoCast
Concrete1 dayNoCuring11.88 daysNoStrip1 dayNoSOP 14-15 (TB)16.88
daysYesFounding level1 dayNoBlinding1 dayNoInstallation of Spools1
dayNoRebar1 dayNoFormwork1 dayNoCast Concrete1 dayNoCuring11.88
daysNoStrip1 dayNoBlanket3 daysNo #17 Spool 1 &1A (T
Pieces)64.75 daysYesExcavation1 dayNoAwaiting for Spool10.88
daysNoCut PVC1 dayNoDelay - Receive Spool/ C222-1.2-LNS-00252
daysNoFinal installation os spools0.88 daysNoPipe to TP 04-33-020
(TH8)29 daysYesExcavation2.25 daysNoFounding Level5 daysNoBedding0
daysNoPipe laying1.38 daysNoDelays - Underground water &
propose soilcrete backfill / LNS-PSE-651-P04-PM/PSE-LNS-600-P04-PM
& SI 045813.88 daysNoSoilcrete Backfill2 daysNoThrust Blocks 2
no2.5 daysNo SOP 57 Sleeper 1no (DR -266)69.75 daysYesProcurement
of Material2.8 wksNoBase2.25 daysYesFormwork2.25 daysNoRebar2.25
daysNoConcrete2.25 daysNoStrip Formwork2.25 daysNoPlinth53.88
daysYesRebar0.88 daysNoFormwork2.25 daysNoCast In item2.25
daysNoConcrete0.88 daysNoCuring3.63 daysNoStrip Formwork0.88
daysNoDelays to Spool modifications/C222-1.2-LNS-00224 daysNoInstal
Sleeper1 dayNoWrapping3 daysNoBackfill2 daysNo#19 Det.28 (Spool
9-10)62.13 daysYesExcavation1 dayNoCut PVC1 dayNoInstall Spools1
dayNoSpool removed & sent for Galvanising0.88 daysNoDelay -
Receival of Spool/C222-1.2-LNS-0026.38 daysNoInstal Spool2.25
daysNo#17 Det.21 (Spool 1 & 1A)99.25 daysYesExcavation1
dayNoCut PVC1 dayNoInstall Spools1 dayNoSpool removed & sent
for Galvanising0.88 daysNoDelay - Receival of
Spool/C222-1.2-LNS-0026.38 daysNoInstal Spool2.25 daysNoSite
decision to Excavate & Install spools ( 2, 2A, 3 & 3A)18.88
daysNoSite decision to remove spools & backfill as above info.2
daysNoSOP 183.38 daysYesBackfill Soilcrete1 dayNoAlign Pipes1
dayNoBlanket Backfill2 daysNoIS1 Valve Chamber15.75
daysYesStripping1 dayNoCleaning1 dayNoInstall Spool1 dayNoGrouting1
dayNoCuring3 daysNoSOP 26 (TB)16 daysYesThrust Block1 dayNoCuring7
daysNoT to Scour1 dayNoBlanket1 dayNoSOP 28 (TB)45.25
daysYesFounding level1 dayNoBlinding1 dayNoSpools1 dayNoRain Delay
civil Dec leave0 daysNoCleaning Mud & Pumping water10.88
daysNoRebar1.88 daysNoFormwork1.88 daysNoConcrete0 daysNoCuring5.13
daysNoStripping0.88 daysNoHydro2.88 daysNoWrapping2 daysNoHoliday
Test1 dayNoBackfill6 daysNoTeam 3121.5 daysYesIS370.5
daysYesconcrete0.88 daysNoStrip formwork1.88 daysNo Receive Spool
(SHT 23 Spool 2A &4A)0.88 daysNoSpools2.88 daysNoDelays from QC
Inspectors1 dayNoGrouting0.88 daysNoCuring2.75 daysNoFH12-FH139
daysYesBedding2 daysNoPipe laying2 daysNoBlanket3 daysNoAV2/AV3 Air
realese Chamber (SOP 31- 32)61.5 daysYesReceive Spool SHT 23 Det.
630.88 daysNoSpools0.88 daysNoFounding level1 dayNoMass concrete
for the base1 dayNoInstal precast Chamber2 daysNoFH15 -SOP
35(Piping)6.75 daysYesBedding1 dayNoPipe laying3.75 daysNoBlanket3
daysNoIS413.25 daysYesReceive Spools (SHT 23 Spool 2)0.88
daysNoSpools2.25 daysNoGrouting5 daysNoCuring0 daysNoSOP 35
(TB)46.25 daysYesInstall Spools1 dayNoRebar1 dayNoRain Delay civil
Dec leave0 daysNoCleaning Mud & Pumping water8.88
daysNoFormwork1.63 daysNoConcrete Casting0.88 daysNoCuring7.38
daysNoStripping1 dayNoSOP 36 (TB)18.75 daysYesInstall Spool
(WETBACK)0 daysNoHandover from Pipe fitting (WETBACK)0.88
daysNoFounding Level0 daysNoBlinding0 daysNoRebar2
daysNoFormwork1.88 daysNoConcrete Casting0.88 daysNoCuring8.25
daysNoStripping1.88 daysNoSOP 37 (TB)26 daysYesInstall Spool
(WETBACK)6.38 daysNoHandover from Pipe fitting (WETBACK)0.88
daysNoExcavation due changes in Z- value2 daysNoFounding Level0.88
daysNoBlinding1 dayNoRebar2 daysNoFormwork2 daysNoConcrete Casting1
dayNoCuring3 daysNoStripping1 dayNoSOP 37-SOP66 (Piping)31.13
daysYesReceive Spools ( FH 16 ) /C222-1.2-LNS-00219
daysNoRe-excavate due to Z- value changes2.88 daysNoFounding
Level1.88 daysNoBedding0.88 daysNoPipe laying2 daysNoBlanket
Backfill6 daysNoInstall FH1 dayNoSOP 38 (TB)13.25 daysYesFounding
Level1 dayNoInstall Spools1 dayNoBlinding1 dayNoRebar1
dayNoFormwork1 dayNoConcrete Casting1 dayNoCuring3 daysNoStripping1
dayNoSOP 65 (TB)23.13 daysYesReceive Spools/ C222-1.2-LNS-00213.25
daysNoFounding level0.88 daysNoInstall Spools0.88 daysNoRebar0.88
daysNoFormwork0.88 daysNoConcrete Casting0.88 daysNoCuring3
daysNoStripping1 dayNoSOP 66 (TB)23.13 daysYesReceive Spools /
C222-1.2-LNS-00213.25 daysNoFounding level0.88 daysNoInstall
Spools0.88 daysNoRebar0.88 daysNoFormwork0.88 daysNoConcrete
Casting0.88 daysNoCuring3 daysNoStripping1 dayNoSOP 66 - SOP
4424.88 daysYesReceive Spools ( FH 17, 18 & 19 ) /
C222-1.2-LNS-00223.88 daysNoInstall FH1 dayNoHydro2.88
daysNoWrapping2 daysNoHoliday Test1 dayNoBackfill4 daysNoTeam
4100.63 daysYesAV4 Air realese Chamber4.13 daysYesFounding level1
dayNoMass concrete for the base1 dayNoinstal precast Chamber1
dayNoSOP 44-SOP45 (Piping)52.63 daysYesExcavation4 daysNoRain Delay
civil Dec leave0 daysNoCleaning Mud & Pumping water5 daysNoRe
Excavation2 daysNoFounding Level1 dayNoBedding3 daysNoPipe laying6
daysNoBlanket Backfill6 daysNoSOP 44 (TB)7 daysYesInstall Spools1
dayNoRebar1 dayNoFormwork1 dayNoConcrete Casting1 dayNoCuring3
daysNoStripping1 dayNoSOP 45 (TB)54.88 daysYesInstall Spools1
dayNoRebar1 dayNoRain Delay civil Dec leave0 daysNoCleaning Mud
& Pumping water10.63 daysNoFormwork & rebar8.75
daysNoConcrete Casting1 dayNoCuring3 daysNoStripping1.33
daysNoHydro3 daysNoWrapping2.75 daysNoHoliday Test0
daysNoBackfill3.88 daysNoTeam 599 daysYesSOP 46- TB SHT 30 Det.53
(TH9)64.13 daysYesExcavation2.88 daysNoFounding Level2.88
daysNoBedding4.38 daysNoReceive Spools ( FH 20 )
/C222-1.2-LNS-00223.88 daysNoPipe laying32 daysNoBlanket Backfill31
daysNoInstall FH1 dayNoTP 04-28-020 ( TH 9 ) - Delays37.88
daysYesNotification TP co-ords not aligning as per AFC dwg1
dayNoProposal by LNS/ESKOM for Rula to modify TP5.88 daysNoFurther
investigation by LNS15.88 daysNoDecision made by LNS to modify
trench to suit exist. TP7.88 daysNoRedline drawings issue3.88
daysNoSetting out1.88 daysNoExcavation1 dayNoBlinding0.88
daysNoRebar & Formwork1.88 daysNoCast concrete1 dayNoStrip
formwork1 dayNoCuring of concrete1 dayNoTHRUST BLOCK ( GRID C4
ONLY) - ADDITIONAL/MODIFY5.88 daysYesLNS-PSE-PSE-766-P04 Site
Instruction0.88 daysNoExcavation1 dayNoBlinding1 dayNoRebar0
daysNoFormwork0 daysNoCast concrete0.88 daysNoCuring2 daysNoSOP 46
(TB)40.75 daysYesBench marks request23.88 daysNoCut & Weld
HDPE0.88 daysNoInstall Spools1 dayNoResources re-allocated to TB 58
to enable Wetback to complete fieldwork7 daysNoTQ 155 HDPE
Alignment0 daysNoRebar1 dayNoFormwork1 dayNoConcrete Casting1
dayNoCuring3 daysNoStripping1 dayNoSOP 47 (TB)60.88 daysYesReceive
Spools0 daysNoBench marks request23.88 daysNoFounding level1
dayNoInstall Spools1 dayNoRebar1 dayNoFormwork1 dayNoConcrete
Casting1 dayNoCuring3 daysNoStripping1 dayNoReceive Spools ( Spool
2 Detail 50, SHT 29)0 daysNoInstall Spools (Detail 50, spool 2, SHT
29)1 dayNoSOP 58 (TB) Team 557.25 daysYesReceive Spools0
daysNoBench marks request23.88 daysNoFounding level0.88
daysNoInstall Spools1.88 daysNoFieldweld by Wetback6.88
daysNoRebar1.88 daysNoFormwork1.88 daysNoConcrete Casting2
daysNoCuring7 daysNoStripping1 dayNoAV5 Air realese Chamber4
daysYesFounding level1 dayNoMass concrete for the base1 dayNoinstal
precast Chamber1 dayNoSealing1 dayNoHydro3 daysNoWrapping2
daysNoHoliday Test1 dayNoBackfill8 daysNoPHASE 3 & PHASE
4130.04 daysYesTeam 2122.04 daysYesPipe to TP 04-35-130 & TP
04-35-029 ( TH8 Substation) PHASE3 &415.25 daysYesExcavation2
daysNoFounding Level2 daysNoBedding2 daysNoPipe laying3
daysNoBlanket Backfill3 daysNoSV2 Valve Chamber(Team 2)31.38
daysYesExcavation2 daysNoBlinding1 dayNoRebar8 daysNoFormwork4
daysNoConcrete1 dayNoStripping Formwork3 daysNoGrouting4
daysNoCuring3 daysNoSOP 26 TO FW4 (Piping) Team 2123.85
daysYesExcavation3 daysNoDump Rock3 daysNoBidim2 daysNoG5
Layerworks2 daysNoFounding Level2 daysNoBedding4 daysNoPipe laying4
daysNoBlanket Backfill5 daysNoExcavation15 daysNoDump Rock2
daysNoBidim1 dayNoG5 Layerworks16.89 daysNoFounding Level30.38
daysNoBedding2 daysNoPipe laying1 dayNoBlanket Backfill2
daysNoThrust Blocks 4no5.5 daysYesFounding level1 dayNoBlinding1
dayNoSpools1 dayNoRebar1 dayNoFormwork1 dayNoConrete1 dayNoStrip
Formwork1 dayNoIS2 Valve Chamber ( Team 2)31.94 daysYesExcavation2
daysNoDump Rock2 daysNoBidim1 dayNoG5 Layerworks2 daysNoBlinding1
dayNoRebar4 daysNoFormwork4 daysNoConcrete1 dayNoStrip Formwork2
daysNoGrouting3 daysNoCuring3 daysNoHydro3 daysNoWrapping2
daysNoHoliday Test1 dayNoBackfill3 daysNoTeam 592.5 daysYesTB SHT
30 Det.53 -SOP 48 (TH9)22.69 daysYesExcavation4 daysNoFounding
Level2 daysNoBedding5 daysNoPipe laying5 daysNoBlanket Backfill6
daysNoThrust Blocks 3no6.13 daysYesFounding level1 dayNoBlinding1
dayNoSpools1 dayNoRebar1 dayNoFormwork1 dayNoConrete1 dayNoStrip
Formwork1 dayNoFH22-FH25 (Team5)28.31 daysYesExcavation4
daysNoFounding Level3 daysNoBedding5 daysNoPipe laying4
daysNoBlanket Backfill5 daysNoIS5 Valve Chamber19.5
daysYesExcavation2 daysNoBlinding1 dayNoRebar4 daysNoFormwork4
daysNoConcrete1 dayNoStrip Formwork3 daysNoAV6 Air realese
Chamber4.75 daysYesFounding level1 dayNoMass concrete for the base1
dayNoinstal precast Chamber1 dayNoSealing1 dayNoHydro3
daysNoWrapping2 daysNoHoliday Test1 dayNoBackfill7 daysNoTeam
160.75 daysYesSOP 47-SOP52 (Team1)41.63 daysYesExcavation14
daysNoFounding Level0.88 daysNoBedding5 daysNoPipe laying4
daysNoBlanket Backfill5 daysNoThrust Block2 daysNoAV7 Air realese
Chamber2.38 daysYesFounding level1 dayNoMass concrete for the base1
dayNoinstal precast Chamber1 dayNoHydro3 daysNoWrapping2
daysNoHoliday Test1 dayNoBackfill9 daysNo VALVE PIT "01" to AUX BAY
Unit 1175.06 daysYesCONCRETE SLEEVES ( Additional works)12
daysYesSite Instruction: LNS-PSE-750-P04-PM1 dayNoProcure
materials5.88 daysNoSetting out1 dayNoExcavation2 daysNoInstall
sleeves1.88 daysNoSoilcrete backfill2 daysNo 355 OD MPVC 500M
LONG175.06 daysYesAccess Delays - Letter ref: C222-1.2-101/
PSE-LNS-592-P04-PM114 daysNo Setting out2.25 daysNo Excavation8
daysNo Bedding7.06 daysNo Laying of pipes9 daysNo Pipe fittings3
daysNo Blanket backfill10 daysNo Thrust Block2 daysNo Thrust Block
Concrete Curing7.44 daysNo Hydro Testing4 daysNo Denso Wrapping (
SVK )0 daysNo Backfill5 daysNo Install Fire Hydrandt Pedastals2.06
daysNo Handover1 dayNo CLEAN DIRTY DRAIN SYSTEM361.94 daysYes CLEAN
AND DIRTY WATER PUMP STATION239.38 daysYes WORKS239.38 daysYes All
Plinths100.81 daysYesDelay: WAP document for Patching Leaks/
PSE-LNS-591-P04-PM/PSE-LNS-607-P04-PM/PSE-LNS-613-P04-PM50
daysNoPatching of Leaks on Walls9 daysNo Scabble existing floor2.94
daysNoTQ 139 Height Discrepancy-Ressolved52 daysNoDelay: Rain
03-11-20144 daysNoPumping rain wate & cleaning mud2 daysNoTQ146
Plinths Dimension Response1 dayNo Drill & dowel9 daysNo Rebar10
daysNo Formwork9 daysNo Anchor Bolts2 daysNo Concrete1 dayNo Strip2
daysNoGive Access to Others as requested by LNS8 daysNo
Flooring51.31 daysYesScreed mix design24.06 daysNo Grano screed5.63
daysNo Curing of screed16 daysNo Epoxy Flooring5.63 daysNo Building
Works125.94 daysYes Erect Structural Steel11 daysNo Brickwork39
daysNo Hang Windows6 daysNo Hang Door6 daysNo Hang Roller Shutter
Door6 daysNo Handrailing15 daysNoTQ 122-Roof Sheeting
-Response12.38 daysNo Roof Sheeting11
daysNoLNS-PSE-734-P04-PM/C222-1.2-161 Excavate trench at CDD
P/station29 daysYes Excavate trench1 dayNoBedding1 dayNoHandover to
Others1 dayNoWetback Install pipes5 daysNoHandover from Others20
daysNoBlanket Backfill1 dayNoFinal Backfill1 dayNoCABLE CORE ENTRY
PENETRATIONS17
daysYesLNS-PSE-756-P04-PM/LNS-PSE-758-P04-PM/LNS-PSE-762-P04-PM6
daysNoCoring of holes4 daysNoExcavate trench outside1 dayNoInstall
sleeves1 dayNoHand over to Cable Contractor1 dayNoReceive Handover
back for backfilling & sealing1 dayNoSeal and backfill3 daysNo
Fencing11 daysNo Handover22 daysYes Punchlist11 daysNo QC
Documentation11 daysNo Handover0 daysNo CLEAN AND DIRTY WATER
PIPELINE341.69 daysYesWaiting for Wrapping of CDD Pipeline
R31,R130,R114272 daysNoWork by others-outstanding Wrapping ref
letter:PSE-LNS-507-P04-PM3 daysNo CROSSINGS & VALVE PITS328.81
daysYes R130 - Scour Pit321.19 daysYes Denso Wrapping ( SVK )308
daysNo Backfill6 daysNo Install Step Iron2 daysNo Install manhole
cover1 dayNo Valve Pit Complete0 daysNo Handover1 dayNo R114 - Air
Vent Pit133 daysYes Denso Wrapping ( SVK )120 daysNo Backfill to
Foundation Level1.63 daysNo Blinding1 dayNo Mesh to base1 dayNo
Cast concrete to base1.31 daysNo Install Pre Cast Units2 daysNo
Backfill3 daysNo Install manhole cover2.69 daysNo R5 - Scour
Pit316.75 daysYes Pre Cast Concrete Sleepers6 daysNo Excavation1
dayNo Install Concrete Sleeper (4no)2 daysNoObstruction of Pipe by
Others201 daysNoInstall Concrete Sleeper (1no)1 dayNo Backfill1
dayNo CCD PUMP HOUSE - R5 - R2 ( Spillway )225.63 daysYesConstant
water Seepage98 daysNo Install Rino matresses1 dayNoTQ 134 Spillway
Levels-Raised0 daysNoTQ 134 Spillway Levels-Response with SI102
daysNoUnanswered TQs ref letter:PSE-LNS-607-P04-PM105 daysNo
Install Rino matresses11 daysNo CCD PUMP HOUSE - R295.56 daysYes
Denso Wrapping ( SVK )88.31 daysNo Final Backfill5 daysNo
COMPLETION16 daysYes Handover8 daysNo Punchlist6 daysNo QC
Documentation2 daysNo Handover0 daysNo RAW WATER SYSTEM218.47
daysYesPHASE 1 Grouting85.13 daysYesDate SI Receive0 daysNoShutter
& Grout ref letter:LNS-PSE-673-P04/ PSE-LNS-631-P04-PM0
daysNoProcurement of material4 wksNoWAP document5.3 wksNoSubmission
of WAP document0 daysNoApproval of WAP document24 daysNoMatimba
Induction1 dayNoThrust Block 29.88 daysYesCut off Joint Seals &
Remove cover0.81 daysNoScabble & Dowel2 daysNo Formwork1
dayNoGrouting1 dayNoStripping1 dayNoPost Concrete1 dayNoReinstate
Cover & Joints1 dayNoCrossing 29.5 daysYesCut off Joint Seals
& Remove cover1 dayNoScabble & Dowel2 daysNo Formwork1
dayNoGrouting1 dayNoStripping1 dayNoPost Concrete1 dayNoReinstate
Cover & Joints1 dayNoCrossing 310.25 daysYesCut off Joint Seals
& Remove cover1 dayNoScabble & Dowel2 daysNo Formwork1
dayNoGrouting1 dayNoStripping1 dayNoPost Concrete1 dayNoReinstate
Cover & Joints1 dayNoCrossing 411.19 daysYesCut off Joint Seals
& Remove cover1 dayNoScabble & Dowel1 dayNo Formwork2
daysNoGrouting1 dayNoStripping1 dayNoPost Concrete1 dayNoReinstate
Cover & Joints1 dayNoThrust Block 38.81 daysYesCut off Joint
Seals & Remove cover1 dayNoScabble & Dowel1 dayNo
Formwork1.81 daysNoGrouting2 daysNoStripping1 dayNoPost Concrete1
dayNoReinstate Cover & Joints1 dayNoHandover0 daysNoPHASE 1 -
BYPASS to CROSSING #5 SLEEVE141.75 daysYesSI Receive0 daysNoMix
Design Inquiry8 wksNoWAP document1.5 wksNoSubmission of WAP
document0 daysNoApproval of WAP document21 daysNoAccess from LNS to
commence59 daysNoBypass to Crossing #5 Sleeve13.38 daysYesExcavate
wells1 dayNoCut through concrete sleeve1 dayNo Formwork to seals
sleeve ends3 daysNoCast Superflow Concrete1 dayNoStripping1
dayNoPost Concrete1 dayNoBackfill wells2 daysNo RAW WATER PHASE
2243.31 daysYes CROSSING #8187.13 daysYes Crossing 8 - Rebar to
Stormwater Headwall Bases4 daysNo Crossing 8 - Cast Concrete2
daysNo Crossing 8 - Formwork to Stormwater Headwall Bases4 daysNo
Crossing 8 - Rebar to Headwalls4 daysNo Crossing 8 - Formwork to
Headwalls3 daysNo Crossing 8 - Cast Concrete2 daysNo Crossing 8 -
Strip Formwork4 daysNo Crossing 8 - Soilcrete Blanket Stormwater
Pipes2 daysNoTQ 129-Stormwater Pipe invert level Ressolved15
daysNoDelay Backfilling Around Crossing 8 /PSE-LNS-623, 632, 662,
672, 676-P04-PM90 daysNoBlanket & Final Backfill around
Flanges5 daysNo Crossing 8 - Install Reno Mattress &
Gabions14.38 daysNo SCOUR PIT #7166.97 daysYesUpon Flanges
backfilling completion around Structure28 daysNoSupply PVC Pipe ref
letter:LNS-PSE-680-P04-PM0 daysNoInstallation of PVC Pipe western
& Eastern side1 dayNo Scour Pit #7 - Backfill11 daysNoDelays -
Hydro test by Others/ PSE-LNS-623, 632, 662, 672, 676-P04-PM76
daysNo Scour Pit #7 - Misc. Works4 daysNo SCOUR118.75 daysYesRain
& Consequential Delays/ PSE-LNS-623-P04-PM/PSE-LNS-632-P04-PM32
daysNo Scour Pit #7 (Scour) - Setting out1 dayNoIssue of Redline
Dwg : L09257-810-003 Rev 2B0 daysNoProcure an Excavator6
daysNoAdditional Works as per Dwg : L09257-810-003 Rev 2B27 daysNo
Scour Pit #7 (Scour) - Blinding1 dayNo Scour Pit #7 (Scour) -
Reinforcing to Floorslab3 daysNo Scour Pit #7 (Scour) - Formwork to
Side of Slab1 dayNo Scour Pit #7 (Scour) - Cast Concrete to
Floorslab1 dayNo Scour Pit #7 (Scour) - Reinforcing to Walls4.94
daysNo Scour Pit #7 (Scour) - Install Fittings2 daysNo Scour Pit #7
(Scour) - Formwork to Walls24 daysNo Scour Pit #7 (Scour) - Cast
Concrete Wall1 dayNo Scour Pit #7 (Scour) - Strip formwork1.09
daysNo Scour Pit #7 (Scour) - Backfill4.44 daysNo Scour Pit #7
(Scour) - Misc. Works2 daysNo Scour Pit #7 (Scour) - Install
Covers1.59 daysNo AIR RELEASE PIT #6107.69 daysYesUpon Flanges
backfilling completion around Structure ( Delay Handover from
Others)/ PSE-LNS-623, 632, 662, 672, 676-P04-PM93.94 daysNo ARP #6
- Backfill8.94 daysNo ARP #6 - Misc. Works3 daysNo AIR RELEASE PIT
#7104.5 daysYesUpon Flanges backfilling completion around Structure
( Delay Handover from Others)/ PSE-LNS-623, 632, 662, 672,
676-P04-PM91.69 daysNo ARP #7 - Backfill11.38 daysNo VENT PIT
#8147.96 daysYesWaiting for Handover Certificate31 daysNoHandover
Delay ref letter:C222-1.2-10620 daysNoHandover Delay ref
letter:PSE-LNS-602-P04-PM1 dayNoTQ 145 Incorect position of Starter
Bars- Response7 daysNo Vent Pit 8 - Install fittings by others1
dayNoDoweling Rebar2 daysNoFixing Rebar7 daysNo Vent Pit 8 -
Formwork to wall7.91 daysNo Vent Pit 8 - Cast concrete wall2
daysNoCivil leave Rain0 daysNoPump raing Water and cleaning of mud4
daysNo Vent Pit 8 - Strip Formwork5 daysNoConcrete Repairs14
daysNoUpon Flanges backfilling completion around Structure ( Delay
Handover from Others)/ C222-1.2-136, 128, 157,163,16729.28 daysNo
Vent Pit 8 - Backfill6.13 daysNo Vent Pit 8 - Misc. Works13.6
daysNo RESERVOIR INLET120.75 daysYes RESERVOIR INLET THRUST
BLOCK114.03 daysYes THRUST BLOCK60.56 daysYesHandover Delay ref
letter:C222-1.2-1062 daysNoHandover Delay ref
letter:PSE-LNS-602-P04-PM2 daysNo Reservoir Inlet - Install
fittings by others1 dayNo Reservoir Inlet Thrust Block -
Reinforcement (17%)2 daysNo Reservoir Inlet Thrust Block -
Formwork6.19 daysNo Reservoir Inlet Thrust Block - Concrete1 dayNo
Reservoir Inlet Thrust Block - Strip4.63 daysNoRedline Drawing
Received0 daysNoSoilcrete1 dayNoHandover from Others after Hydro
test14 daysNoGrout Pipe penetration3 daysNoInstall concrete cover
& Catladder1 dayNo RESERVOIR INLET - VALVE STATION91.69 daysYes
Reservoir Inlet Valve Station - Pipe Installation by Wetback11
daysNoInstall Sleepers2 daysNoConcrete Support2 daysNoBundwall
& Base9 daysNoSlab7 daysNoCivil leave Rain0 daysNoPumping rain
water and cleaning mud4 daysNoSlab8 daysNoConcrete Repairs3
daysNoJoint Sealing3 daysNo Reservoir Inlet Valve Station - Install
Steel Structure3.6 daysNoDelay Supply of Roof sheeting33 daysNo
Reservoir Inlet Valve Station - Install Roof Sheeting4 daysNo
COMPLETION6.72 daysYes Reservoir Inlet - Punch List3 daysNo
Reservoir Inlet - QC Documentation2 daysNo Reservoir Inlet -
Handover0 daysNo TRENCHING216.56 daysYes VENT PIT 7 TO VENT PIT 6
(584m)98.88 daysYes Trenching Vent Pit 7 to Vent Pit 6 - Laying
Pipe (Wetback)3.66 daysNo Fox Holes Modification4.97 daysNo
Trenching Vent Pit 7 to Vent Pit 6 - Wrapping Pipe (Ace)9.97
daysNo1st Handover From Piping Contractor (100M)0 daysNo Trenching
Vent Pit 7 to Vent Pit 6 - Blanket Backfill2 daysNoDelay : Work
stoppped due to pipe damage during Blanket backfill3 daysNo2nd
Handover From Piping Contractor (236M)0 daysNo Trenching Vent Pit 7
to Vent Pit 6 - Blanket Backfill14.91 daysNoWaiting for Handover
for 284m7 daysNo 3rd Handover from piping Contractor (204m)0 daysNo
Trenching Vent Pit 7 to Vent Pit 6 - Blanket Backfill6.97
daysNoWaiting for Handover for 44m/ PSE-LNS-592-P04-PM81.88
daysNo4th Handover from piping Contractor (12m)0 daysNoInsufficient
work ref letter:C222-1-2-1360 daysNoInsufficient work ref
letter:PSE-LNS-632-P04-PM0 daysNo Trenching Vent Pit 7 to Vent Pit
6 - Blanket Backfill last 12m2.97 daysNo Trenching Vent Pit 7 to
Vent Pit 6 - Final Backfill14 daysNo Trenching Vent Pit 7 to Vent
Pit 6 - Topsoil9 daysNo VENT PIT 6 TO SCOUR PIT 7 (596m)151.03
daysYes Trenching Vent Pit 6 to Scour Pit 7 - Laying Pipe
(Wetback)12 daysNo Fox Holes Modification10 daysNo Trenching Vent
Pit 6 to Scour Pit 7 - Wrapping Pipe (Ace)15 daysNo Trenching Vent
Pit 6 to Scour Pit 7 - Handover From Piping Contractor(rejected)0
daysNoObstruction on area removed4 daysNo Trenching Vent Pit 6 to
Scour Pit 7 - Handover From Piping Contractor(108m)0 daysNo
Trenching Vent Pit 6 to Scour Pit 7 - Blanket Backfill3 daysNo
Trenching Vent Pit 6 to Scour Pit 7 - Handover (252m)From Piping
Contractor0 daysNo Trenching Vent Pit 6 to Scour Pit 7 - Blanket
Backfill9 daysNoWaiting for Handover from piping Contractor (296m)6
daysNo Trenching Vent Pit 6 to Scour Pit 7 - Handover From Piping
Contractor(48m)0 daysNo Trenching Vent Pit 6 to Scour Pit 7 -
Blanket Backfill17 daysNo Trenching Vent Pit 6 to Scour Pit 7 -
Final Backfill9 daysNoLevelling excavated material10 daysNo
Trenching Vent Pit 6 to Scour Pit 7 - Topsoil5 daysNoInstruction to
Re open around Flanges ref letter:PSE-SS-SI-036/
LNS-PSE-727-P04-PM/ PSE-LNS-651-P04-PM0 daysNoProcure an Excavator1
dayNoRe opening of Flange Western side of Scour Pit 74
daysNoHandover from Others to Backfill/ PSE-LNS-676-P04-PM42
daysNoBlanket & Final Backfill around Flanges5 daysNo Trenching
Vent Pit 6 to Scour Pit 7 - Topsoil2 daysNo ROAD DEVIATION41.03
daysYes Trenching Vent Pit 6 to Vent Pit 7 - Temporary Road
Bypass2.81 daysNo Trenching Vent Pit 6 to Scour Pit 7 -
Excavation4.47 daysNo Trenching Vent Pit 6 to Scour Pit 7 -
Bedding4 daysNoHandover to Piping Contractor0 daysNo Trenching Vent
Pit 6 to Scour Pit 7 - Fox Holes2 daysNo Trenching Vent Pit 6 to
Scour Pit 7- Laying Pipe (WBK)2 daysNo Fox Holes Modification1
dayNo Trenching Vent Pit 6 to Scour Pit 7 - Wrapping (ACE)3 daysNo
Trenching Vent Pit 6 to Scour Pit 7 - Handover from Pipe
Contractor0 daysNo Trenching Vent Pit 6 to Scour Pit 7 - Blanket
Backfill4.13 daysNo Trenching Vent Pit 6 to Scour Pit 7 - Final
Backfill8 daysNo VENT PIT 7 TO RESERVOIR INLET PIT (654m)93.44
daysYes Trenching Vent Pit 7 to Reservoir Inlet Pit - Re-Work
Laying of Pipes Pipes (WBK) 54x600mm pipes18 daysNo Fox Holes
Modification8 daysNo Trenching Vent Pit 7 to Reservoir Inlet Pit -
Re-Work Wrapping (ACE)12 daysNo Trenching Vent Pit 7 to Reservoir
Inlet Pit - Handover From Piping Contractor0 daysNo Trenching Vent
Pit 7 to Reservoir Inlet Pit - Blanket Backfill16 daysNo Trenching
Vent Pit 7 to Reservoir Inlet Pit - Final Backfill12.88
daysNoLevelling excavated material2 daysNo Trenching Vent Pit 7 to
Reservoir Inlet Pit - Topsoil10 daysNo BYPASS TO CROSSING 8
(461m)114.03 daysYes Trenching Bypass to Crossing 8 - Dumping of
ROCKS13 daysNo Trenching Bypass to Crossing 8 - G5 LAYERS2 daysNoSI
For soilcrete4 daysNo Trenching Bypass to Crossing 8 - REWORK
Bedding2 daysNo Trenching Bypass to Crossing 8 - Handover to Piping
Contractor0 daysNo Trenching Bypass to Crossing 8 - REWORK Fox
Holes8 daysNo Trenching Bypass to Crossing 8 - Handover to Piping
Contractor0 daysNo Trenching Bypass to Crossing 8 - REWORK Laying
Pipe (Wetback) 444/492 Linear Meters.13 daysNo Fox Holes
Modification10 daysNo Trenching Bypass to Crossing 8 - REWORK
Wrapping Pipe (Ace)9.97 daysNoDelay: Rain 03-11-20141 dayNoPumping
rain wate & cleaning mud7 daysNo 1st Handover from piping
Contractor (48M)0 daysNo Trenching Bypass to Crossing 8 - Blanket
Backfill4 daysNo2nd Handover from piping Contractor (48M)0 daysNo
Trenching Bypass to Crossing 8 - Blanket Backfill5 daysNo3rd &
4th Handover from piping Contractor (104M)0 daysNo Trenching Bypass
to Crossing 8 - Blanket Backfill9 daysNoWaiting for Handover from
piping Contractor (281m)9 daysNoHandover from piping Contractor
(180M)0 daysNo Trenching Bypass to Crossing 8 - Blanket Backfill5
daysNoSI for soilcrete ref letter:LNS-PSE-672-P04-PM0
daysNoHandover from piping Contractor (72M)0 daysNo Trenching
Bypass to Crossing 8 - Blanket Backfill2.97 daysNoHandover from
piping Contractor (Around Flanges)0 daysNo Trenching Bypass to
Crossing 8 - Blanket Backfill3 daysNo Trenching Bypass to Crossing
8 - Final Backfill15.69 daysNoStockpilling and levelling material25
daysNo Trenching Bypass to Crossing 8 - Topsoil7.22 daysNo CROSSING
8 TO SCOUR PIT 7 (54m)145.38 daysYes Trenching Crossing 8 to Scour
Pit 7- Excavation2 daysNo Trenching Crossing 8 to Scour Pit 7-
BIDIM2 daysNo Trenching Crossing 8 to Scour Pit 7- Dumping of
ROCKS2 daysNo Trenching Crossing 8 to Scour Pit 7- G5 LAYERS3.97
daysNo Trenching Crossing 8 to Scour Pit 7- Bedding3.72 daysNo
Trenching Crossing 8 to Scour Pit 7- Fox Holes3.97 daysNoHandover
to Piping Contractor0 daysNo Trenching Crossing 8 to Scour Pit 7-
Laying Pipe (Wetback)1.81 daysNo Fox Holes Modification1.97 daysNo
Trenching Crossing 8 to Scour Pit 7- Wrapping Pipe (Ace)0 daysNo1st
Handover From Piping Contractor(48m)0 daysNo Trenching Crossing 8
to Scour Pit 7- Blanket Backfill4.25 daysNoDelay: Rain 03-11-20141
dayNoPumping rain wate & cleaning mud6 daysNo Trenching
Crossing 8 to Scour Pit 7- Final Backfill3 daysNo2nd Handover From
Piping Contractor(3m)0 daysNo Trenching Crossing 8 to Scour Pit 7-
Blanket Backfill3 daysNo Trenching Crossing 8 to Scour Pit 7- Final
Backfill1 dayNoBlanket & Final Backfill around Flanges (
LNS-PSE-666-P04-PM)6 daysNoStockpilling and levelling material12
daysNoSI additional work ref letter:C222-1.2-1180 daysNoInstruction
to Re open around Flanges ref letter:LNS-PSE-675-PO4-PM0 daysNoRe
opening of Flange Western side of Crossing 85 daysNoInstruction to
Re open around Flanges ref letter:PSE-SS-SI-031/LNS-PSE-675-PO4-PM0
daysNoRe opening of Flange Eastern side of Crossing 83
daysNoHandover from Others to Backfill/ PSE-LNS-676-P04-PM78
daysNoBlanket & Final Backfill around Flanges5 daysNo Trenching
Crossing 8 to Scour Pit 7- Topsoil4 daysNo VENT PIT 7 TO VENT PIT
8134.38 daysYes Trenching Vent Pit 7 to Vent Pit 8 - Re Work
Removal of Bedding2 daysNo Trenching Vent Pit 7 to Vent Pit 8 - Re
Work Founding Level2 daysNo Trenching Vent Pit 7 to Vent Pit 8 - Re
Work Bedding4.97 daysNoDelay:Waiting for Others to mark Fox holes1
dayNoVeryfying & Acceptance of Handover by LNS3 daysNo
Trenching Vent Pit 7 to Vent Pit 8 - Re Work Fox Holes &
widening the trench23.22 daysNo Trenching Vent Pit 7 to Vent Pit 8
- Handover to Piping Contractor0 daysNo Trenching Vent Pit 7 to
Vent Pit 8 - Laying Pipe (Wetback) 125X900mm pipe4.47 daysNo Fox
Holes Modification5.97 daysNo Trenching Vent Pit 7 to Vent Pit 8 -
Wrapping Pipe (Ace)7.97 daysNoHandover from Piping Contractor 60M0
daysNo Trenching Vent Pit 7 to Vent Pit 8 - Blanket Backfill5.78
daysNoHandover from Piping Contractor 180M0 daysNo Trenching Vent
Pit 7 to Vent Pit 8 - Blanket Backfill4.84 daysNoWaiting for
handover from piping Contractor6 daysNo Trenching Vent Pit 7 to
Vent Pit 8 - Blanket Backfill7 daysNo Trenching Vent Pit 7 to Vent
Pit 8 - Final Backfill8 daysNoStockpilling and levelling material4
daysNo Trenching Vent Pit 7 to Vent Pit 8 -Top Soil5.97 daysNoDelay
Completion Vent #7 to Vent #8 / PSE-LNS-676-P04-PM36.63
daysYesDelay Handover from Others to Backfill13 daysNoSite
Instruction: LNS-PSE-733-P04-PM0 daysNoExcavation & Expose
900NB pipe2 daysNoBackfill & secure against possible rain
damages1 dayNoDelay Hand over from Others14.84 daysNoBlanket
Backfill3.91 daysNoFinal Backfill7.28 daysNoTopsoil2 daysNo
COMPLETION144.97 daysYesService Test 600mm line for Operation3
daysNoPressuren Test & Flush 600mm Line10 daysNoPressure Test
& Flush 900mm10 daysNo Final Punch Lists23 daysNo QC
Documentation1.84 daysNo Final Handover2 daysNo RAW WATER PHASE II
SLEEPERS TEMPORAL SYSTEM176.84 daysYes Procurement of Material30
daysNo OVERLAND SLEEPERS (28nos)37.28 daysYes Overland Sleepers-
Bedding6 daysNo Overland Sleepers- Install Precast Sleepers7.94
daysNo Overland Sleepers- Backfill17.88 daysNo PF26 SLEEPER80.72
daysYesSleepers on Hold / DR-LNS-241/PSE-SS-TN-310/PSE-SS-TN-34948
daysNo PF26 Sleeper- Setting Out1.94 daysNo PF26 Sleeper- Cut Reno
Matress0.84 daysNo PF26 Sleeper- Construction of Base5 daysNo PF26
Sleeper- Construction of Plinth10 daysNo PF27 SLEEPER72.94
daysYesSleepers on Hold/ DR-LNS-241/PSE-SS-TN-310/PSE-SS-TN-34948
daysNo PF26 Sleeper- Setting Out1 dayNo PF26 Sleeper- Cut Reno
Matress1 dayNo PF26 Sleeper- Construction of Base4.09 daysNo PF26
Sleeper- Construction of Plinth6 daysNo GRAVEL ROAD CROSSING6
daysYes Gravel Road Crossing - Demolish Drift2.97 daysNo Gravel
Road Crossing - Clean Rubble3 daysNo CULVERT130.34 daysYes Culvert
- Setting Out1 dayNo Culvert - Excavation0.97 daysNo Culvert - G5
Layerwork2.06 daysNo Culvert - Bedding1 dayNo Culvert - Install
Precast Base3 daysNo Culvert - Install Precast Culverts8 daysNo
Culvert - Joint Sealing2 daysNo Culvert - Formwork for Mass
Foundation1 dayNo Culvert - Mass Concrete Foundation1.91 daysNo
Culvert - Strip Formwork to Mass foundation0.13 daysNo Culvert -
Brickwork5.38 daysNo Culvert - Plastering3.13 daysNo Culvert -
Brickwork/Plastering Curing7.63 daysNo Culvert - Backfilling8
daysNo ROAD60.78 daysYes Road - G5 Layerwork25.72 daysNo Road -
Chevron Signs (4no)2 daysNo Road - Gravel Wearing Course0 daysNo
Road - Trimming3.38 daysNo Road - Handover1 dayNoAdditional Works (
LNS-PSE-732-P04-PM & LNS-PSE-736-P04-PM) C222-1.2-16327.66
daysYesEarthpikes5.38 daysYesProcure Equipment2 daysNoArea
preparation1 dayNoDrilling2 daysNoElectrical Trench Excavation31.56
daysYesExcavation4 daysNoBedding3 daysNoHandover to Cable
Contractor0 daysNoDelay Handover from Cable Contractor21 daysNo
PIPE SUPPORTS258.31 daysYes WATER TREATMENT PLANT255.38 daysYes
BASE TYPE P0842.06 daysYes Waiting for Access0 daysNo BASE10
daysYes Excavation2 daysNo Blinding1 dayNo Reinforcing2 daysNo
Formwork1 dayNo Inspection1 dayNo Concrete1 dayNo Strip formwork1
dayNo PLINTHS15.94 daysYes Reinforcing2 daysNo Formwork2 daysNo
Inspection1 dayNo Concrete1 dayNo Strip formwork1 dayNo Backfill3
daysNo COMPLETION2.88 daysYes Punchlist2 daysNo Handover1
dayNoWATER TREATMENT PLANT (SUNCTION POINT)98.94 daysYesHandover to
Piping Contractor0 daysNoPiping by others92.56 daysNoHandover from
Piping Contractor1 dayNoHydro Testing1 dayNoBlanket1.63 daysNoFinal
Backfilling1.13 daysNoPunch List0.88 daysNoHandover0 daysNo PIPE
SUPPORT TO CLARIFIER ( 8 Concrete Supports )213.19 daysYesStanding
Time6 daysNoC222-1.2-100 Claims Settlement Agreement30.88 daysNo
Access from LNS123 daysNo BASE26.31 daysYes Survey/ Setting out3
daysNo Excavation5 daysNo Blinding2 daysNo Reinforcing9 daysNo
Formwork6 daysNo Inspection2 daysNo Concrete2 daysNo Strip
formwork3.31 daysNo PLINTHS20.69 daysYes Reinforcing6 daysNo
Formwork6 daysNo Inspection2 daysNo Concrete2.63 daysNo Strip
formwork2.25 daysNo Backfill7.5 daysNo COMPLETION5 daysYes
Punchlist4 daysNo Handover1 dayNo COMPRESSED AIR220.25 daysYes
COMPRESSOR HOUSE ( NORTH )178.06 daysYes NORTH SIDE69.56 daysYes
PREPERATION33.75 daysYesStanding time Delay Access ref
letter:PSE-LNS-559-P04-PM2 daysNoDelay-Waiting for obstacles to be
removed2 daysNo Setting out2 daysNo Saw cut existing slab2
daysNoWaiting for go ahead to do dowelling from PSE/LNS2.38 daysNo
Saw cut existing slab1 dayNo Excavation3 daysNo Blinding2 daysNoTQ
121-Dowelling18 daysNo BASE NORTH SIDE10.38 daysYes Reinforcement7
daysNo Formwork6 daysNoTQ 124 Clash with Existing Service1 dayNo
Concrete1 dayNo PLINTHS NORTH SIDE27.88 daysYes Reinforcement6
daysNo Formwork19 daysNo Cast-in items6 daysNo Concrete1 dayNo
Concrete1 dayNo BACKFILL3 daysNo EAST SIDE67.56 daysYes
PREPERATION32.13 daysYesDelay-Waiting for obstacles to be
removed22.5 daysNo Setting out2 daysNo Saw cut existing slab3
daysNo Excavation3 daysNo Blinding1 dayNo BASE EAST SIDE17 daysYes
Reinforcement16 daysNo Formwork12 daysNo Concrete1 dayNo PLINTHS
EAST SIDE5.13 daysYes Reinforcement2 daysNo Formwork2 daysNo
Cast-in items2 daysNo Concrete1 dayNo BACKFILL3 daysNo WEST
SIDE169.94 daysYes PREPERATION, GL E - B. (4no)151.56
daysYesDelay-Waiting for obstacles to be removed /
PSE-LNS-592-P04-PM48 daysNo Setting out2 daysNo Saw cut existing
slab3 daysNoDelay-Waiting for access / PSE-LNS-592-P04-PM94.56
daysNo Excavation3 daysNo Blinding1 dayNo BASE WEST SIDE, (4no)4.25
daysYes Reinforcement3.13 daysNo Formwork2 daysNo Concrete1.13
daysNo PLINTH WEST SIDE, (4no)3.88 daysYes Reinforcement2.75 daysNo
Formwork1.63 daysNo Cast-in items1.13 daysNo Concrete1.13 daysNo
BACKFILL3.19 daysNo PREPERATION, GL A, (1no)106.81
daysYesDelay-Waiting for access/ PSE-LNS-592-P04-PM103 daysNo
Setting out1.56 daysNo Excavation1.06 daysNo Blinding1 dayNo BASE
WEST SIDE, (1no)3 daysYes Reinforcement2 daysNo Formwork2 daysNo
Concrete1 dayNo PLINTH WEST SIDE, (1no)4 daysYes Reinforcement2
daysNo Formwork2 daysNo Cast-in items1 dayNo Concrete1 dayNo
BACKFILL3.13 daysNo SOUTH SIDE77.25 daysYes PREPERATION41.13
daysYesDelay-Waiting for obstacles to be removed28.13 daysNo Set
out5 daysNo Saw cut existing slab3 daysNo Excavation3 daysNo
Blinding2 daysNo BASE SOUTH SIDE14 daysYes Reinforcement11 daysNo
Formwork11 daysNo Concrete3 daysNo PLINTHS SOUTH SIDE19.13 daysYes
Reinforcement9 daysNo Formwork2 daysNoDelay:Rain 03-11-20141
dayNoPumping & Cleaning mud2 daysNo Formwork2 daysNo Cast-in
items3 daysNo Concrete2 daysNo BACKFILL3 daysNo COMPLETION4 daysYes
Punchlist3 daysNo Handover1 dayNo COMPRESSOR HOUSE PIPERACK, CAS
rack ( NORTH )216.13 daysYesConstruction, GL A-E; Ii-V.157.88
daysYes PREPERATION107.88 daysYesDelay waiting for access/
PSE-LNS-592-P04-PM72 daysNo Setting out2 daysNo Excavation6
daysNoScabbling & Dowelling47 daysNo Blinding2.06 daysNo
BASES35.75 daysYes Reinforcement31.35 daysNo Formwork29.63
daysNoCivil leave Rain0 daysNoPumping rain water and cleaning mud7
daysNo Formwork20.44 daysNoRebar16.88 daysNo Concrete13.41 daysNo
PLINTHS37.81 daysYes Reinforcement15.18 daysNo Formwork11.99 daysNo
Cast-in items4 daysNo Concrete24 daysNo COMPLETION10 daysYes
Backfill6 daysNo Punchlist3 daysNo Handover1 dayNoConstruction, GL
F- I.216.13 daysYes PREPERATION171 daysYesDelay waiting for access/
PSE-LNS-592-P04-PM161 daysNo Setting out1 dayNo Excavation3
daysNoScabbling & Dowelling3 daysNo Blinding3 daysNo BASES12.19
daysYes Reinforcement5 daysNo Formwork5 daysNo Concrete2.19 daysNo
PLINTHS15.94 daysYes Reinforcement5 daysNo Formwork5 daysNo Cast-in
items2 daysNo Concrete2.44 daysNo COMPLETION6 daysYes Backfill3
daysNo Punchlist2 daysNo Handover1 dayNoConstruction, GL W - Y204.5
daysYes PREPERATION161.69 daysYesDelay waiting for access/
PSE-LNS-592-P04-PM72.75 daysNo Setting out1 dayNoDelay-
C222-1.2-177/ TQ,162 . Cable anchor in way of bases14
daysNoScabbling & Dowelling1 dayNo BASES6 daysYes
Reinforcement3 daysNo Formwork2 daysNo Concrete1 dayNo PLINTHS14.81
daysYes Reinforcement3 daysNo Formwork3 daysNo Cast-in items2
daysNo Concrete1 dayNo COMPLETION6 daysYes Backfill3 daysNo
Punchlist2 daysNo Handover1 dayNo 88M BRIDGE / CAS BRIDGE (
NORTH)184.94 daysYesDelay waiting for access/ PSE-LNS-592-P04-PM161
daysNo Setting out1 dayNo Excavation3 daysNo Blinding1 dayNo BASES8
daysYes Reinforcement4 daysNo Formwork4 daysNo Concrete1.69 daysNo
PLINTHS10.94 daysYes Reinforcement3 daysNo Formwork4 daysNo Cast-in
items1 dayNo Concrete1 dayNo Re-instate3.69 daysNo DIESEL STORAGE
& OFFLOADING AREA220 daysYes CONSTRUCTION PERIOD210.63 daysYes
Structural Steel & Sheeting8 daysYes Install roof sheeting8
daysNoDFO PLINTHS210.63 daysYesAFC Drawings0 daysNoNUMSA Strike
Ends24.75 daysNoProcurement of Material (rebar & Cast in
items)8 wksNoDFO P39 Placed on hold ref letter:LNS-PSE-622-P04-PM0
daysNoSetting Out2 daysNoP32(3no),P33,P34,P35,P3617
daysYesScabbling3 daysNoDowelling1 dayNoPLINTHS13 daysYesrebar3
daysNoFormwork4 daysNoConcrete1 dayNoStrip5 daysNoP39160.75
daysYesPlinth on Hold / PSE-LNS-591-P04-PM/ PSE-LNS-592-P04-PM/
PSE-LNS-613-P04-PM149 daysNoScabbling1 dayNoDowelling1.25
daysNoPLINTHS9.5 daysYesrebar1.25 daysNoFormwork2.69
daysNoConcrete2.63 daysNoStrip2.94 daysNoP31 (8no)14.63
daysYesExcavation4 daysNoScabbling1 dayNoBlinding1 dayNoPLINTHS13
daysYesTQ132-TOC & Access issues Ressolved5 daysNorebar3
daysNoFormwork2 daysNoConcrete1 dayNoStrip2 daysNoP37 (2no)7.5
daysYesrebar2 daysNoFormwork2 daysNoConcrete1 dayNoStrip2
daysNoBackfilling3 daysNo P38132.5 daysYesDelay Access (Backfilling
required by Others)114.88 daysNoExcavation, Blinding & rebar5
daysNoFormwork2.94 daysNoConcrete1 dayNoStrip2.31
daysNoBackfilling2 daysNo Fencing172.13 daysYesDelay:Waiting for
the Tarrace level from PSE/LNS43.88 daysNoTQ 113 Terrace Level23
daysNo Fence Posts11 daysNo Wire Fencing7.25 daysNo Gates1 dayNo
COMPLETION9.38 daysYes Punchlist6 daysNo QC Documentation6 daysNo
Final Handover0 daysNo COAL STOCK YARD353.38 daysYes PROCUREMENT
AND SETTING OUT128.94 daysYes Receiving of drawings0 daysNo Wap
document preparation7 daysNo Procurement of Resources16 daysNo
Approval of WAP1 dayNo Submit excavation Permit5 daysNoObstacles
preventing construction of CSY Sleepers ref
letter:PSE-LNS-486-P04-PM0 daysNoRemoval of Obstacles on the way of
CSY Sleepers114.75 daysNo Access0 daysNoTQ 116 CSY Sleepers
Coordinates Error-Raised0 daysNoTQ 116 CSY Sleepers Coordinates
Error-Response2 daysNo Setting out1 dayNo 230 NO. OFF
SLEEPERS329.13 daysYes AFC Drawings0 daysNo Procure Material33.75
daysNo Precast cast sleepers76.5 daysNo Setting out2 daysNo
Excavation52 daysNo Blinding89 daysNo Install precast87 daysNo
Backfill28 daysNoPumping rain water and cleaning mud8 daysNoDelay
due to Rain ref letter:PSE-LNS-631-P04-PM1 dayNo Blinding15 daysNo
Install precast15 daysNo Backfill15 daysNoSLEEPERS S213 to
S223127.94 daysYesSleepers Placed on Hold - ( PSE-SS-TN-287)0
daysNoSleepers Placed on Hold & Lifted101.94 daysNoSetting out
& CAT Scan1 dayNoExcavation5 daysNoBlinding2 daysNoRebar to
Bases3 daysNoFormwork to Bases3 daysNoCast Concrete to Bases1
dayNoStrip Formwork to Bases2 daysNoRebar to Plinths3
daysNoFormwork to Plinths3 daysNoCast-in items2 daysNoCast concrete
to Plinths1 dayNoBackfill5 daysNoINTAKE PLINTHS - PF 42 (
Additional )75.31 daysYesAFC Drawing0 daysNoProcurement of
Material15 daysNoTQ 153 Deeper Open Excavation36 daysNoSetting out
& CAT Scan1 dayNoExcavation1 dayNoBlinding1 dayNoRebar to
Bases1 dayNoFormwork to Bases1 dayNoCast Concrete to Bases1
dayNoStrip Formwork to Bases1 dayNoRebar to Plinths1 dayNoFormwork
to Plinths2 daysNoCast-in items1 dayNoCast concrete to Plinths1
dayNoBackfill1 dayNoSLEEPERS S224 & S22551 daysYesTQ 153 Deeper
Open Excavation36 daysNoSetting out & CAT Scan1
dayNoExcavation1 dayNoBlinding1 dayNoRebar to Bases2 daysNoFormwork
to Bases1 dayNoCast Concrete to Bases1 dayNoStrip Formwork to
Bases1 dayNoRebar to Plinths1 dayNoFormwork to Plinths2
daysNoCast-in items1 dayNoCast concrete to Plinths1 dayNoBackfill2
daysNo CONSTRUCTION ( Retaining Wall )308.75 daysYes AFC Drawings0
daysNo Procure Material60.75 daysNo WAP Preperation4 daysNo WAP
Document Approval21 daysNoDirectional Drilling12 daysNo Setting
Out2 daysNo BASE ( South )123.08 daysYes Excavation3 daysNoTQ 135
Concrete Wall Height108 daysNo Blinding1 dayNo Reinforcement4
daysNo Formwork3 daysNo Cast Concrete1 dayNo Strip Formwork2 daysNo
BASE ( North )123.15 daysYes Excavation3 daysNo Blinding1 dayNo
Reinforcement4 daysNo Formwork3.06 daysNo Cast Concrete1 dayNo
Strip Formwork2 daysNo WALLS ( South )14.61 daysYes Reinforcement3
daysNo Formwork4 daysNo Cast Concrete1.54 daysNo Strip Formwork2.06
daysNo Backfill4 daysNo WALLS ( North )20.92 daysYes Reinforcement3
daysNo Formwork3 daysNo Cast Concrete1.38 daysNo Strip Formwork2
daysNo Backfill4 daysNo COMPLETION7 daysYes Punchlist3 daysNo QC
Documentation3 daysNo Handover1 dayNo ASH DUMP IRRIGATION PUMP
STATION408.25 daysYesNew Drawings Sunction Line to Ash Dam ref
letter:LNS-PSE-620-P04-PM0 daysNoAdditional Work Sunction Line to
Ash Dam Ref letter:PSE-LNS-565-P04-PM0 daysNo PROCUREMENT AND
SETTING OUT41.63 daysYes Steel shop detailing & Roof
sheeting41.63 daysNo Procurement of Resources11.25 daysNo Approval
of WAP0 daysNo Submit excavation Permit5.63 daysNo Access0 daysNo
Setting out2.06 daysNo CONSTRUCTION PERIOD393.25 daysYes EARTH
WORKS68.38 daysYes Clear and Grub2.25 daysNo Excavation24
daysNoPumping Rain Water(ADI)12.38 daysNoPumping rain water9
daysNoRe-Excavation(weather delay)2.25 daysNoPumping rain water
& cleaning mud19.13 daysNo Concrete Works138.81 daysYes
Foundation Slab34.88 daysYes Blinding2.25 daysNo Formwork to slab
& sump4.5 daysNo Reinforcement5.63 daysNo Cast-in Items1 dayNo
Concrete2 daysNo Strip3 daysNo Walls89.94 daysYes Internal
formwork7.88 daysNo Reinforcement13.5 daysNo External formwork7.88
daysNo Concrete1 dayNo Strip5 daysNo Backfill and Compact18 daysNo
Pump bases38.25 daysYes Reinforcement3 daysNo Formwork3 daysNo
Anchor bolts1 dayNo Concrete1 dayNoPumping rain wate & cleaning
mud4 daysNo Formwork & Anchor Bolts5 daysNoConcrete1 dayNo
Strip3.75 daysNo Switch Gear House224.13 daysYes Blinding1 dayNo
Rebar2 daysNoCivil leave Rain0 daysNoPumping rain water and
cleaning mud3 daysNo Rebar6 daysNo Formwork to floor slab19.44
daysNo Cast concrete slab7.25 daysNo Brickwork24 daysNo Doors &
Ventilations5 daysNo Soffit slab support5 daysNo Rebar3.94 daysNo
Formwork3.88 daysNo Cast concrete slab2.69 daysNo Strip2 daysNo
Curing14.75 daysNo Stairs case and Landings22 daysNo Water
proofing4 daysNo Screed to floor6 daysNo Misc works6
daysNoADI-SUNCTION LINE TO ASH DAM156.25 daysYesDate Received0
daysNoProcurement of Material5 wksNoExcavation Permit2
daysNoSetting Out1 dayNoExcavation5 daysNoTQ 142 HDPE Zvalue
-Ressolved53.81 daysNoPumping rain water & cleaning mud10
daysNoDelay due to Rain ref letter:PSE-LNS-631-P04-PM3 daysNoPuddle
spool request ( email by C. Lamani 05/11/2014)85.88 daysNoBM &
Setting out2 daysNoInstall and Grout Puddle stool4 daysNoBedding2
daysNoLaying Pipes2 daysNoBlanket Backfill3 daysNoFinal Backfill4
daysNo Structural Steel205.75 daysYesRedesign Ref
letter:PSE-LNS-558-P04-PM0 daysNo Approval of Design
LNS-PSE-648-P04-PM63.44 daysNoTQ 140 Dimension Descrepancy10 daysNo
Submission of Shop Drawings2.71 wksNo Approval of Shop Drawings9.24
wksNo Fabrication of structural steel members8.05 wksNo Erection of
structural steel29.31 daysNo Sundry metalworks12 daysNoRoof
Sheeting107.44 daysYes Procurement7.5 wksNo Install roof sheeting6
daysNo Ridge cap, fascias6 daysNo Building Works37 daysYes
Brickwork25 daysNo Doors & Ventilations6 daysNo Epoxy Flooring6
daysNo Fencing21 daysYes Fence Posts10 daysNo Wire Fencing10 daysNo
Gates1 dayNo Handover9.38 daysYes Punchlist6 daysNo QC
Documentation6 daysNo Final Handover0 daysNo LP GAS PIPELINE58
daysYes PIPE SECTION58 daysYesDelayed Re-Access at LP Gas Area43.88
daysNo Denso Wrapping ( SVK )0 daysNo Backfill2 daysNo Instal fire
hydrandt Pedastal1 dayNoDelayed Re-Access at LP Gas Area
ref:PSE-LNS-508-P04-PM1 dayNo RING FEED HYDRANTS ( 23 no.)329.38
daysYes Received DR-LNS-0850 daysNo Revising DR-LNS-08528.13 daysNo
DR-LNS-085 Finalized0 daysNo Procure Pipe flanges11.25 daysNo
Receive Free Issue Material from Client0 daysNo Setting out6.75
daysNo CAT Scan & Excavation permit5.63 daysNoTQ 095 Hydrants
Clash with Potable Water Pipeline6.88 daysNoFH1-FH5284
daysYesObstacle on FH1-FH57.88 daysNoObstacles preventing
construction of FH1-FH5 ref letter:PSE-LNS-476-P04-PM0 daysNo Hand
Excavation4.22 daysNo Cut Ring Feed & Install Hydrants4.22
daysNo Inspection2.25 daysNo Hydro Test by Others1.41 daysNo Denso
Wrapping ( SVK )0 daysNoHandover FH1-FH3from PSE/LNS0 daysNo
Blanket,Pedestal and final backfill23 daysNoInstall Pedestal3
daysNo Handover0 daysNoFH12,FH14,FH15277.81 daysYes Hand
Excavation3.38 daysNo Cut Ring Feed & Install Hydrants3.38
daysNo Inspection2.25 daysNo Hydro Test by Others1.41 daysNo Denso
Wrapping ( SVK )0 daysNoHandover from PSE/LNS0 daysNo
Blanket,Pedestal and final backfill6 daysNoInstall Pedestal2 daysNo
Handover0 daysNoFH13,FH17,FH18,FH19261.06 daysYes Hand Excavation8
daysNo Hand Re- Excavation (rain damage)2 daysNo Cut Ring Feed
& Install Hydrants3 daysNo Inspection2 daysNo Hydro Test by
Others1 dayNo Denso Wrapping ( SVK )0 daysNoTQ 117 -Height
Requirement86.63 daysNoHandover from others0 daysNo
Blanket,Pedestal and final backfill3 daysNoSupply of Free Issue
material74 daysNoInstall FH Extension2 daysNoInstall Pedestal2
daysNo Handover0 daysNoFH20-FH23256 daysYes Hand Excavation3
daysNoPumping rain water & cleaning mud TH2-TH3,RING
MAIN,BB1(16 &23 April 2014 rain)1 dayNo Hand Re- Excavation
(rain damage)2 daysNo Cut Ring Feed & Install Hydrants4 daysNo
Inspection2 daysNo Hydro Test by Others1 dayNo Denso Wrapping ( SVK
)0 daysNoTQ 117 -Height Requirement86.63 daysNoHandover from
others0 daysNo Blanket,Pedestal and final backfill11 daysNoSupply
of Free Issue material74 daysNoInstall FH Extension1 dayNoInstall
Pedestal1 dayNo Handover0 daysNoFH6-FH11 & FH 16254.44 daysYes
Hand Excavation2 daysNo Cut Ring Feed & Install Hydrants2
daysNo Inspection2 daysNo Hydro Test by Others1 dayNo Denso
Wrapping ( SVK )0 daysNoHandover from PSE/LNS0 daysNo
Blanket,Pedestal and final backfill6 daysNo Handover0 daysNoInstall
Pedestal4 daysNo Final Handover0 daysNoCOMPLETION17.69 daysYes
De-Establishment15 daysNo Close-up Documentation10 daysNo Clear
Site0 daysNo