KEGIATAN : The Support to the Development of Islamic of Higher Education Project PEKERJAAN : Construction of Nine (9) New Buildings and Supporting Infrastructures of UIN Raden Fatah Palembang LOKASI : UIN Raden Fatah Palembang PREPARATION WORKS : 2,244 % : PT Patroon Arsindo KSO PT Griksa Cipta CENTRE ADMINISTRATION BUILDING : 10,895 % PMSC : PT Deta Decon INTEGRATED LIBRARY : 16,949 % - Team Leader : Mardiana Daoed INTEGRATED LABORATORY : 13,631 % RENCANA S/D MINGGU INI : Penyedia Jasa : PT Nindya Karya (Persero) FACULTY OF ISLAMIC ECONOMY AND BUSINESS : 14,693 % REALISASI S/D MINGGU INI : - PM : Satriyo Fajar Dewantoro FACULTY OF SCIENCE AND TECHNOLOGY : 14,124 % DEVIASI : No. Loan : IND - 0164, February 16th 2012 FACULTY OF TARBIYAH : 8,032 % Nilai Pekerjaan : Rp 289.618.674.000,00 FACULTY OF PSYCHOLOGY : 7,878 % Waktu Pelaksanaan : 480 Hari Kalender (16 Oktober 2018 - 7 Februari 2020) SUPPORTING INFRASTRUCTURE : 11,556 % Waktu Pemeliharaan : 365 Hari Kalender (8 Februari 2020 - 6 Februari 2021) 100,000 % Jangka Waktu Pelaksanaan : 480 hari kalender Laporan Mingguan Ke : 56 Waktu Pelaksanaan : 393 hari Sisa Waktu Pelaksanaan : 87 hari No 1 Undangan Rapat Koordinasi 2 3 4 5 6 1 Pekerjaan pemasangan AC Cassette & Split 11 Pekerjaan Fixed & Armature 1 Pekerjaan pemasangan AC Cassette & Split 11 Pekerjaan Fixed & Armature 2 Pengetesan rendam Water Proofing 12 Pekerjaan penutup atap 2 Pengetesan rendam Water Proofing 12 Pekerjaan Plafond 3 13 Pekerjaan plafond 3 13 Pekerjaan Water Proofing 4 Pemasangan instalasi air bersih, air kotor & air bekas 14 Pekerjaan Cat (Sealer, Interior & Exterior) 4 Pemasangan instalasi air bersih, air kotor & air bekas 14 Pekerjaan Cat (Sealer, Interior & Exterior) 5 Pemasangan instalasi hydrant 15 Pekerjaan Water Proofing 5 Pekerjaan arsitektur (Pasangan dinding, pintu, jendela) 15 Pekerjaan Keramik Lantai, Dinding Toilet 6 Pengetesan kuat tekan beton 16 Pekerjaan Fasade 6 Pemasangan instalasi hydrant 16 Pekerjaan Fasade 7 Pekerjaan instalasi listrik 17 Pekerjaan Partisi (Glass & Gypsum) 7 Pengetesan kuat tekan beton 17 Pekerjaan Partisi (Glass & Gypsum) 8 Pekerjaan Pemasangan Keramik Lantai, Dinding Toilet 18 Test Rendam 8 Pekerjaan Instalasi Listrik 18 Test Rendam 9 Pekerjaan arsitektur (Pasangan dinding, pintu, jendela) 9 Pekerjaan metal ceilling 10 Pekerjaan metal ceilling 10 Pekerjaan penutup atap 1. 1. 2. 2. Memo Pekerjaan Pasang Keramik Memo Pekerjaan Partisi Gypsum Jumlah AKTIVITAS PEKERJAAN MINGGU INI Service Crane Target progress sampai dengan akhir bulan November adalah 78,542% dan minggu ke 56 realisasi progress tercapai 75.026%. Genset Sisa progress yang harus dicapai setiap minggunya oleh kontraktor sampai akhir November adalah 1,758%, sehingga dilakukan percepatan penyelesaian pekerjaan khususnya pekerjaan bagian luar. RENCANA PEKERJAAN MINGGU DEPAN Mandor Jidar Untuk dimaksimalkan khususnya pada area Eye Catching dan konsisten terhadap kualitas material serta tenaga spesialis yang digunakan. PMSC NK Material Digunakan Peralatan Digunakan Pekerja PERMASALAHAN / HAMBATAN Memo Pekerjaan Railling DOKUMENTASI PELAKSANAAN PMSC Sell Concrete Mixer Machine Alat Las Alat Ukur Compressor PENYELESAIAN MASALAH Quality target pekerjaan arsitektur belum maksimal. Pekerjaan Railling Pekerjaan Railling Excavator Skop, Palu, Unting-unting, dll Scaffolding NK Water Proofing Bata ringan Mortar Kabel (Elektrikal) Tenaga Kerja Memo Pekerjaan Kusen Pintu dan Jendela RESUME LAPORAN HARIAN MINGGU INI 5 626 DATA UMUM Memo Pekerjaan Indoor AC DEDC PMSC KURVA S PROGRESS PEKERJAAN BOBOT PEKERJAAN 74,012% 75,026% Perihal 1,015% EVALUASI WAKTU PELAKSANAAN NK PMSC PIU, PPK, NK LAPORAN SURAT MENYURAT MINGGU INI Untuk Kuas dan roll Kusen Alumunium Gypsum Keramik Kaca Cat Keahlian Karyawan 58 ACP Pipa (Hydrant & Hollow) Dari PMSC NK NK PMSC Pekerjaan Keramik Meja Wastafel Palembang, 12 November 2020 Konsultan PMSC Mardiana Daoed Ir. Team Leader PENGGUNA JASA PROJECT MANAGEMENT AND SUPERVISION CONSULTANT RESUME LAPORAN MINGGU KE - 56 12 NOVEMBER 2019 - PERIODE 6 NOVEMBER 2019 Tampak Gedung TARBIYAH Tampak Gedung TARBIYAH Tampak Gedung SAINTEK Tampak Gedung ADM Tampak Gedung LIBRARY Tampak Gedung LABORATORY Tampak Gedung PSYCHOLOGY Tampak Gedung FEBI Pekerjaan Fasade Pekerjaan Cat Interior Pekerjaan Partisi Glass Pekerjaan Railling & Keramik Tangga Pekerjaan PlafondMetal Ceiling Pemasangan Partisi Gypsum Rapat Kordinasi Mingguan 74.012% 75.026% 1.161% 1.825%
1
Embed
Resume laporan RAFAH minggu ke-56siprafourinone.info/report/5f523e433037c.pdf · 2020. 9. 4. · Memo Pekerjaan Kusen Pintu dan Jendela RESUME LAPORAN HARIAN MINGGU INI 5 626 DATA
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
KEGIATAN : The Support to the Development of Islamic of Higher Education ProjectPEKERJAAN : Construction of Nine (9) New Buildings and Supporting Infrastructures of UIN Raden Fatah PalembangLOKASI : UIN Raden Fatah Palembang
PREPARATION WORKS : 2,244 % : PT Patroon Arsindo KSO PT Griksa CiptaCENTRE ADMINISTRATION BUILDING : 10,895 % PMSC : PT Deta DeconINTEGRATED LIBRARY : 16,949 % - Team Leader : Mardiana DaoedINTEGRATED LABORATORY : 13,631 % RENCANA S/D MINGGU INI : Penyedia Jasa : PT Nindya Karya (Persero)FACULTY OF ISLAMIC ECONOMY AND BUSINESS : 14,693 % REALISASI S/D MINGGU INI : - PM : Satriyo Fajar DewantoroFACULTY OF SCIENCE AND TECHNOLOGY : 14,124 % DEVIASI : No. Loan : IND - 0164, February 16th 2012FACULTY OF TARBIYAH : 8,032 % Nilai Pekerjaan : Rp 289.618.674.000,00FACULTY OF PSYCHOLOGY : 7,878 % Waktu Pelaksanaan : 480 Hari Kalender (16 Oktober 2018 - 7 Februari 2020) SUPPORTING INFRASTRUCTURE : 11,556 % Waktu Pemeliharaan : 365 Hari Kalender (8 Februari 2020 - 6 Februari 2021)
100,000 %
Jangka Waktu Pelaksanaan : 480 hari kalenderLaporan Mingguan Ke : 56Waktu Pelaksanaan : 393 hari
Sisa Waktu Pelaksanaan : 87 hari
No1 Undangan Rapat Koordinasi
2
3
4
5
6
1 Pekerjaan pemasangan AC Cassette & Split 11 Pekerjaan Fixed & Armature 1 Pekerjaan pemasangan AC Cassette & Split 11 Pekerjaan Fixed & Armature2 Pengetesan rendam Water Proofing 12 Pekerjaan penutup atap 2 Pengetesan rendam Water Proofing 12 Pekerjaan Plafond3 13 Pekerjaan plafond 3 13 Pekerjaan Water Proofing4 Pemasangan instalasi air bersih, air kotor & air bekas 14 Pekerjaan Cat (Sealer, Interior & Exterior) 4 Pemasangan instalasi air bersih, air kotor & air bekas 14 Pekerjaan Cat (Sealer, Interior & Exterior)5 Pemasangan instalasi hydrant 15 Pekerjaan Water Proofing 5 Pekerjaan arsitektur (Pasangan dinding, pintu, jendela) 15 Pekerjaan Keramik Lantai, Dinding Toilet6 Pengetesan kuat tekan beton 16 Pekerjaan Fasade 6 Pemasangan instalasi hydrant 16 Pekerjaan Fasade7 Pekerjaan instalasi listrik 17 Pekerjaan Partisi (Glass & Gypsum) 7 Pengetesan kuat tekan beton 17 Pekerjaan Partisi (Glass & Gypsum)8 Pekerjaan Pemasangan Keramik Lantai, Dinding Toilet 18 Test Rendam 8 Pekerjaan Instalasi Listrik 18 Test Rendam9 Pekerjaan arsitektur (Pasangan dinding, pintu, jendela) 9 Pekerjaan metal ceilling
10 Pekerjaan metal ceilling 10 Pekerjaan penutup atap
1. 1.
2. 2.
Memo Pekerjaan Pasang Keramik
Memo Pekerjaan Partisi Gypsum
Jumlah
AKTIVITAS PEKERJAAN MINGGU INI
Service Crane
Target progress sampai dengan akhir bulan November adalah 78,542% dan minggu ke 56 realisasi progress tercapai 75.026%.
Genset
Sisa progress yang harus dicapai setiap minggunya oleh kontraktor sampai akhir November adalah 1,758%, sehingga dilakukan percepatan penyelesaian pekerjaan khususnya pekerjaan bagian luar.
RENCANA PEKERJAAN MINGGU DEPAN
Mandor
Jidar
Untuk dimaksimalkan khususnya pada area Eye Catching dan konsisten terhadap kualitas material serta tenaga spesialis yang digunakan.
PMSC NK
Material Digunakan Peralatan Digunakan
Pekerja
PERMASALAHAN / HAMBATAN
Memo Pekerjaan Railling
DOKUMENTASI PELAKSANAAN
PMSC
Sell Concrete Mixer MachineAlat Las
Alat UkurCompressor
PENYELESAIAN MASALAH
Quality target pekerjaan arsitektur belum maksimal.