Work Instruction for Responsibility Matrix of (APQP) S.NO. Description Responsibility AA A B C Mkt. Production Purchase Tool Management Maintence Tool Room Planning programme 1 2 Formation of CFT 3 4 Feasibility Review 5 6 Timing chart / Plan 7 Design goals 8 9 10 11 12 13 Preliminary Process Flow 14 Tool /jig/ fixture mapping 15 16 Product Design & Development 1 2 3 DFMEA 4 Design verification 5 Design Reviews 6 Design Change History /ECN 7 8 9 10 13 Process Design & Development 1 2 Process flow chart 3 Floor Plan Layout 4 Charactersitics Matrix 5 6 Process Change / IPP 7 Pre-Launch Control Plan 8 Work instructions 9 Check sheets 10 11 Packaging Specifications Product & Process Validation 1 Standarization Review 2 Productivity Goals 3 Product Trail Run 4 5 6 Production Control Plan 7 8 Production Part Approval 9 Packaging Evaluation 10 Quality Planning Signoff 11 Review with customer 12 AA Absolutely New Component:No experience of production A That is the part happens to be similar to what had been produced so far but there happens to be large scale difference in raw material machining methodology, in th * A component similar to the component produced so far but there happens to be. * That whenever the to be changed in production site. * That whenever the place.country of development happens to be different from the place/country of production. * That whenever the enviornment (Containing contaminants like Metalic chips dust) or else the degress of Moisture Temprature pressure and the safety contents B * That whenever there happens to be Minor Deviation in the component produced so far.(To implement only for inspection of initial product . Prime Responsibility Co-Responsibility Point to be implemented Review Required / Important from disc Purpose: To define the rank of new product for development & activities & responsibilities for product development, Engg.change and any process change of existing items. Scope: This WI is applicable for development of new product, Engg.change and any process change of existing items. And where any confusion refer procedure PR: CM: 10 Method: Description, Rank of development and responsibility is defined as below Rank of Development Design & Dev. Materiel Percurment Reicept Inspection Calibration Receipt of RFQ / self design and development idea Listing of customer wants/need/desire Submission of quotation and Contract Review Design consideration / Govt. regulation / Priorities Desire/ Past problem History/ review /refelection in new project ( Develop product specification linked to customer) Develop Product and Process concept Preliminary bill of materials Preliminary listing of special product and process characterstics Program Risk Evaluation and approval 3-D Math data (analysis with enviornment / package data), Drawing with tear down part (child part) Prototype build / Time plan / Prototype Control Plan / Testing of prototype Product Drawings and specification / Tool Go- Ahead Engineering Drawings (Tools drawing, tool materials and specification) Tool / Jig progress Check ( Tool dev plan Vs Actual) Inspection Standards / Tool maturation Report. Product/Process quality system plan ( Process maturation plan ) Process FMEA / RPN reduction plan MSA / SPC plan (Gages / testing equipment verification) Preliminary Process Capability Study Measurement systems Evaluation Production Validation Testing Feedback Analysis,corrective action C * That whenever happens to be extremely minor change in detail related to the component, so much so that event the inspection becomes not mandatory (It becomes one of variation in regards to 4M) D:\APQP docum ent\ 2CV TA R GETS.ppt D:\APQ P document\ product and process D :\APQ P document\ FLO W DIA.xls D:\APQ P document\ Special productand D:\APQP docum ent\ program risk evaluat D:\APQ P docum ent\ 3d review w ith envir D:\APQ P docum ent\ dFMEA 4th edition bl D:\APQP docum ent\ design REVIEW chec D:\APQ P docum ent\ GD&T.xls D:\APQ P document\ dESIG N VER IFICA TIO