Top Banner
9-1 Resource Allocation Some definitions Resource allocation, loading, leveling Expediting and crashing projects Goldratt’s “Critical Chain”
40

Resource Allocation

Jan 02, 2016

Download

Documents

slade-farrell

Resource Allocation. Some definitions Resource allocation, loading, leveling Expediting and crashing projects Goldratt’s “Critical Chain”. Some Definitions. Resource allocation permits efficient use of physical assets Within a project, or across multiple projects - PowerPoint PPT Presentation
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Resource Allocation

9-1

Resource Allocation

Some definitions Resource allocation, loading,

leveling Expediting and crashing projects Goldratt’s “Critical Chain”

Page 2: Resource Allocation

9-2

Some Definitions

Resource allocation permits efficient use of physical assets Within a project, or across multiple projects Drives both the identification of resources,

and timing of their application There are generally two conditions:

“Normal” “Crashed”

Page 3: Resource Allocation

9-3

Normal and Crashing

Normal: Most likely task duration, like “m” in Chapter 8

Crash: Expedite an activity, by applying additional resources Specialized or additional equipment More people (e.g., borrowed staff,

temps) More hours (e.g., overtime, weekends)

Page 4: Resource Allocation

9-4

No Free Lunch: Crashing Creates a Ripple Effect

Crashing buys time, but nothing comes free

Potential cost areas Additional equipment/material Extra labor Negative effects on other projects Reduced morale, from excessive hours/shifts Lower quality, from the pressure of time,

inexperienced and tired staff “If you want it bad, you’ll get it bad . . .”

Page 5: Resource Allocation

9-5

Case: Architectural Associates, Inc.

Projects uniformly run late, thus over budget

Is that the problem, or just the symptom?

Page 6: Resource Allocation

9-6

Case: Architectural Associates, Inc. (cont’d)

PROBLEM: Deterministic task schedules cause workers to plan to meet schedule – nothing more, nothing less Parkinson’s Law: “Work expands to fill the

time available.” RESULT: Issues arising early in each task

can be worked around, but late-occurring issues can’t be absorbed in schedule And most issues do arise late

Page 7: Resource Allocation

9-7

Case: Architectural Associates, Inc. (concluded)

The Solution: Use probabilistic time estimates

(optimistic, pessimistic, most likely) Have staff schedule work for

effectiveness and efficiency, not just to fill x-number of days

Page 8: Resource Allocation

9-8

When Trying to Crash a Project . . .

Two basic principles 1. Generally, focus on the critical path

Usually not helpful to shorten non-critical activities

Exception: When a scarce resource is needed elsewhere, e.g., in another project

2. When shortening project duration, choose least expensive way to do it

Page 9: Resource Allocation

9-9

Compute Cost per Day of Crashing a Project

Compute cost/time slope for each expeditable activity

Slope = crash cost – normal cost crash time – normal time

Page 10: Resource Allocation

9-10

An Example (Table 9-1)

Activity Predecessor Days(normal, crash)

Cost(normal, crash)

a - 3, 2 $40, 80

b a 2, 1 20, 80

c a 2, 2 20, 20

d* a 4, 1 30, 120

e** b 3, 1 10, 80

* Partial crashing allowed** Partial crashing not allowed

Page 11: Resource Allocation

9-11

Example (cont’d): Cost per Day to Crash (Table 9-2)

Activity $ Saved/Day

a 40

b 60

c -

d 30

e 70 (2 days)

Page 12: Resource Allocation

9-12

A CPM Example, Figure 9-1

Page 13: Resource Allocation

9-13

CPM Cost-Duration, Figure 9-2

Page 14: Resource Allocation

9-14

Another Approach to Expediting: Fast-tracking/Concurrency

Different terms for similar concept “Fast-tracking” (construction),

“Concurrent engineering” (manufacturing)

Both refer to overlapping project phases E.g., design/build, or build/test

Page 15: Resource Allocation

9-15

Fast-tracking/Concurrency (cont’d)

Pros: Can shorten project duration Can reduce product development cycles Can help meet clients’ demands

Cons: Can increase cost through redesigns,

excessive changes, rework, out-of-sequence installation, and more

Page 16: Resource Allocation

9-16

“Cost, Schedule, or Performance: Pick Any Two . . .”

Assuming fixed performance specifications, tradeoff areas must be in time or cost

Time-limited or resource-limited If all three dimensions are fixed,

the system is “overdetermined” Normally, no tradeoffs are possible But, something has to give . . .

Page 17: Resource Allocation

9-17

Resource Loading

Resource loading: types and quantities of resources, spread by schedule across specific time periods One project, or many Identifies and reduces excess

demands on a firm’s resources

Page 18: Resource Allocation

9-18

Resource Usage Calendar, Figure 9-3

Page 19: Resource Allocation

9-19

AOA Network, Figure 9-4

Page 20: Resource Allocation

9-20

Modified PERT/CPM AOA, Figure 9-5

Page 21: Resource Allocation

9-21

Resource Leveling

Resource leveling minimizes period-by-period variations in resource loading, by shifting tasks within their slack allowances

Advantages Less day-to-day resource manipulation

needed Better morale, fewer HR problems/costs Leveling resources also levels costs,

simplifies budgeting and funding

Page 22: Resource Allocation

9-22

Load Diagrams, Figure 9-6

Page 23: Resource Allocation

9-23

Network Before and After Resource Loading, Figure 9-7

Page 24: Resource Allocation

9-24

Load Diagrams, Figure 9-8

Page 25: Resource Allocation

9-25

Resource Loading Chart, Figure 9-9

Page 26: Resource Allocation

9-26

Constrained Resource Scheduling

Two basic approaches Heuristic

Rule-based, rules of thumb Priority rules, tie-breakers

Optimization Not finding an answer that works, but the

best answer

Page 27: Resource Allocation

9-27

MSP Gantt with Resources, Figure 9-10

Page 28: Resource Allocation

9-28

MSP Load Diagram, Showing Resource Conflict, Figure 9-11

Page 29: Resource Allocation

9-29

MSP Load Diagram, Leveled, Figure 9-12

Page 30: Resource Allocation

9-30

Network for Resource Load Simulation, Figure 9-13

Page 31: Resource Allocation

9-31

Load Chart, Figure 9-14

Page 32: Resource Allocation

9-32

Task a Decomposed, Figure9-15

Page 33: Resource Allocation

9-33

Hierarchy of Gantt Charts, Figure 9-16

Page 34: Resource Allocation

9-34

Sources and Uses of Resources, Figure 9-17

Page 35: Resource Allocation

9-35

Project Life Cycles, Figure 9-18

Page 36: Resource Allocation

9-36

Flow Diagram for SPAR-1, Figure 9-19

Page 37: Resource Allocation

9-37

Goldratt’s Critical Chain

There are systemic problems that plague project schedule performance These problems are not randomly

distributed If they were random, there would be

as many projects finishing early as late

Page 38: Resource Allocation

9-38

Some Systemic Causes of Late Projects

1. Thoughtless Optimism Overpromising at project start “Success-oriented” schedules Lack of management reserves

2. Setting capacity equal to demand Ignoring concepts of resource loading

and leveling

Page 39: Resource Allocation

9-39

Some Systemic Causes of Late Projects (cont’d)

3. “The Student Syndrome” Delaying start of non-critical tasks Parkinson’s Law: “Work expands to

fill the time available” 4. Multitasking to reduce idle time

Switching back and forth between projects creates delays

Page 40: Resource Allocation

9-40

Some Systemic Causes of Late Projects (concluded)

5. Complexity of schedule drives delay Uncertainty and complex paths join to make

trouble 6. People need reason to strive

There’s often no advantage seen to finishing early

7. Game playing E.g., lower levels pad estimates, senior

management slashes them Both can be equally arbitrary