KANSAS STATE UNIVERSITY FOUNDATION – RFP FOR CMAR – KSU OFFICE PARK PHASE II Request for Proposals Construction Manager at Risk Services for Kansas State University Office Park Phase II 1810 Kimball Avenue, Manhattan, Kansas Issued by: Director of Construction Kansas State University Foundation
23

Request for Proposals - KSU Foundation...Step One – RFP Issued The RFP, and any subsequently issued Addenda, will be posted on the KSUF website at: ... • Include cover letter on

Jul 01, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Request for Proposals - KSU Foundation...Step One – RFP Issued The RFP, and any subsequently issued Addenda, will be posted on the KSUF website at: ... • Include cover letter on

KANSAS STATE UNIVERSITY FOUNDATION – RFP FOR CMAR – KSU OFFICE PARK PHASE II

Request for Proposals

Construction Manager at Risk Services

for

Kansas State University Office Park

Phase II

1810 Kimball Avenue, Manhattan, Kansas

Issued by:

Director of Construction

Kansas State University Foundation

Page 2: Request for Proposals - KSU Foundation...Step One – RFP Issued The RFP, and any subsequently issued Addenda, will be posted on the KSUF website at: ... • Include cover letter on

KANSAS STATE UNIVERSITY FOUNDATION – RFP FOR CMAR – KSU OFFICE PARK PHASE II

Kansas State University Office Park – Phase II

Table of Contents

Project Scope / Description 1

Project Team Contacts 2

Tentative Project Timeline 2

Selection Process 3

Selection Committee 3

Proposal Format 4

Selection Criteria 4

• Section 1 Firm Information 4

• Section 2 Organization 4

• Section 3 Licensing 5

• Section 4 Experience 5

• Section 5 Financial Information 6

• Section 6 Experience…Construction Manager at Risk 7

• Section 7 Personnel 9

• Section 8 Owner / Construction Manager Agreement 9

• Section 9 References 9

Questions and Clarifications 10

Attachment “A” – Programming and Concept Presentation Images

Attachment “B” – Fee Structure Worksheet

Attachment “C” – General Conditions Structure Worksheet

Page 3: Request for Proposals - KSU Foundation...Step One – RFP Issued The RFP, and any subsequently issued Addenda, will be posted on the KSUF website at: ... • Include cover letter on

Page | 1 KANSAS STATE UNIVERSITY FOUNDATION – RFP FOR CMAR – KSU OFFICE PARK PHASE II

Project Scope / Description

Also reference presentation document in Attachment “A”.

The KSU Office Park offers a prime location for corporate partners with a desire to tap into the

opportunities available on the Manhattan campus of Kansas State University. Positioned in close

proximity to existing cutting-edge research facilities and the National Bio and Agro Defense Facility,

corporate partners will have the chance to build professional relationships as well as leverage the

strengths of KSU in the areas of student talent and technical innovation. The KSU Office Park is

projected to be completed in four phases.

The Phase I building, completed Fall 2015, is currently home to the Kansas State University Foundation

(KSUF) and at least six corporate university partners. It is a three-story, 60,000 sf building clad in

Kansas limestone and glass, designed by Hoefer, Wysocki Architecture – Leawood, KS. It is the basis of

design that subsequent buildings will be modeled on. Phase I also focused on site development and

the initial utility construction for further development within the park.

This Request for Proposal is to evaluate and invite firms in consideration for Construction Manager at

Risk Services for construction of Kansas State University Office Park – Phase II in Manhattan, Kansas.

The project expands the office park development and construction of the second building, also planned

as a three-story, 60,000 sf building, and located to the west of the Phase I building with a south

exposure to Kimball Avenue. Design of this building is also by Hoefer Wysocki Architecture. This

project is planned to utilize the same exterior finishes as the first, preserving a uniform and

complimentary appearance both in the office park and when viewed from afar. Balconies, with views

of Bill Snyder Family Stadium are planned for the second and third floor tenant spaces. Sidewalks are

planned to connect this building to the first through areas landscaped with native plantings.

Contractor selection is for both Pre-Construction and full project delivery of Construction Management

at Risk Services, pending approval to move into the construction phase by the KSUF Board of Directors.

Quality of specified building materials upon completion of construction documentation is expected to

be consistent with new buildings of this type and of the Kansas State University Office Park. Targeted

GMP is expected to be near $12 million for purposes of Fee and General Conditions Proposal from

prospective CM at Risk firms.

At all times during construction, the KSU Office Park shall remain open to normal business. This will

necessitate the mitigation of construction traffic, noise, windborne dust particulates and other

potentially disruptive construction activities. Successful firms will demonstrate the utmost

understanding and sensitivity to anticipate and exceed our needs and desires, as well as those of our

neighbors, in continuing to maintain a professional business environment.

The KSU Foundation (Owner) is constructing the Project. The Owner will construct the Project under

the guidance and direct supervision of its Designated Representative, the KSUF Director of

Construction.

Page 4: Request for Proposals - KSU Foundation...Step One – RFP Issued The RFP, and any subsequently issued Addenda, will be posted on the KSUF website at: ... • Include cover letter on

Page | 2 KANSAS STATE UNIVERSITY FOUNDATION – RFP FOR CMAR – KSU OFFICE PARK PHASE II

Project Team Contacts:

Kansas State University Foundation

John L. Angelos

Director of Construction

1800 Kimball Ave., Suite 200

Manhattan, KS 66502

Office: 785/532-7557

Mobile: 785/477-3942

Email: [email protected]

Hoefer Wysocki Architecture

Mark Pfeil, AIA

Senior Associate

Office: 913/307-3700

Mobile: 816/809-9468

Email: [email protected]

Tentative Project Timeline:

Schematic Design March 2016

Design Development April 2016

Construction Documents May 2016

Initial GMP Set June 2016

Start Construction Summer 2016

Anticipated Project Duration 1 Year

Page 5: Request for Proposals - KSU Foundation...Step One – RFP Issued The RFP, and any subsequently issued Addenda, will be posted on the KSUF website at: ... • Include cover letter on

Page | 3 KANSAS STATE UNIVERSITY FOUNDATION – RFP FOR CMAR – KSU OFFICE PARK PHASE II

Selection Process:

Step One – RFP Issued

The RFP, and any subsequently issued Addenda, will be posted on the KSUF website at:

http://www.found.ksu.edu/financials/real_estate/rfqs.html

Step Two – Contractors visit site and Mandatory Pre-Bid Conference

Location, Date and Time:

Kansas State University Foundation

1800 Kimball Ave., Suite 200

Manhattan, KS 66502

Tuesday, March 1, 2016 @ 2:00 PM

Step Three – Proposal Submission

Proposals Due: Monday, March 7, 2016 @ 5:00 PM

Location for Proposal Delivery:

Kansas State University Foundation

Attn: John Angelos – Director of Construction

1800 Kimball Ave., Suite 200

Manhattan, KS 66502

Hand delivered proposals should be turned in at the KSUF Reception Desk on second floor.

Note: KSUF Offices close at 5:00 PM.

Step Four – Short List Selection by selection committee

Anticipated Notification Date: Tuesday, March 8, 2016

Step Five – Interview Short List CM firms

Interviews: Thursday, March 10, 2016 – 1:00 PM – 5:00 PM

Selection Committee:

KSU Foundation – John Angelos, Director of Construction

Architect of Record – Hoefer Wysocki Architecture Team Project Manager

Kansas State University – Ryan Swanson, AIA; Assoc. Vice President and University Architect

Final selection of a Construction Manager shall be based on a combination of proposal

evaluation and face-to-face interview ranking with each firm’s proposed project team.

Page 6: Request for Proposals - KSU Foundation...Step One – RFP Issued The RFP, and any subsequently issued Addenda, will be posted on the KSUF website at: ... • Include cover letter on

Page | 4 KANSAS STATE UNIVERSITY FOUNDATION – RFP FOR CMAR – KSU OFFICE PARK PHASE II

Proposal Format

Include responses to all information contained with Selection Criteria (section 1-9) in a clear and

concise format. Complete answers to all Selection Criteria are required for submission to be deemed

valid. Non-=conforming responses and responses received late shall not be evaluated. Delivery to the

KSU Foundation by the submission deadline as noted in the RFP is the sole responsibility of the

submitter. All material in response to this RFP shall become the property of the Kansas State

University Foundation.

• Submit four (4) copies.

• Cover of each copy shall prominently display submitting Firm Name and Project Name.

• Bind document in an 8-1/2 x 11 sheet format. 11 x 17 sheets are acceptable for proposed

timelines, graphics and other applicable information if folded and bound into document.

• Document section (1 through 9) should be tabbed for clarity and ease of reference.

• Include cover letter on respondent’s official letterhead. Letter should include the primary

contact person, email address, mailing address, phone and fax numbers of the submitting firm.

Selection Criteria

Include all information noted below in your respondent proposals.

Section 1 – Firm Information

Name of Firm

Address of Principal Office

Phone, Fax

Form of Business Organization

Year Founded

Section 2 – Organization

1. How many years has your organization been in business in construction in its current capacity?

2. How many years has your organization been in business under its present name? Under what

other or former names has your organization operated?

3. If your organization is a corporation, answer the following:

a. Date of Incorporation

b. State of Incorporation

c. Names of organization’s officers

Page 7: Request for Proposals - KSU Foundation...Step One – RFP Issued The RFP, and any subsequently issued Addenda, will be posted on the KSUF website at: ... • Include cover letter on

Page | 5 KANSAS STATE UNIVERSITY FOUNDATION – RFP FOR CMAR – KSU OFFICE PARK PHASE II

4. If your organization is a partnership, answer the following:

a. Date of Organization

b. Type of Partnership (if applicable)

c. Names of Managing Partners

5. If your organization is individually owned, answer the following:

a. Date of Organization

b. Name of Owner

Section 3 – Licensing

1. List all jurisdictions and trade categories in which your organization is legally qualified to do

business and indicate registration or license number as applicable.

2. List jurisdictions in which your organization’s partnership or trade name is filed.

Section 4 – Experience

1. List the categories of work that your organization normally performs with its own forces. Would

you propose to do any work with your own forces or to bid all work to subcontractors? If you

propose self-performed work, please list proposed labor type and hourly rates provided in the

example below. How would you determine and demonstrate to the KSU Foundation that we would

receive the best value for work done by your own forces?

Self-Performed Work – in addition to General Conditions

Laborer General $/HR

Laborer Demolition $/HR

Laborer Masonry $/HR

Laborer Concrete Formwork $/HR

Laborer Concrete Placement & Finish $/HR

Laborer Reinforcing Steel $/HR

Laborer Rough Carpentry $/HR

Laborer Finish Carpentry $/HR

Laborer Stone Erection $/HR

Laborer Precast Erection $/HR

Laborer Steel Erection $/HR

Other Proposed Laborer: ______________________ $/HR

Other Proposed Laborer: ______________________ $/HR

Page 8: Request for Proposals - KSU Foundation...Step One – RFP Issued The RFP, and any subsequently issued Addenda, will be posted on the KSUF website at: ... • Include cover letter on

Page | 6 KANSAS STATE UNIVERSITY FOUNDATION – RFP FOR CMAR – KSU OFFICE PARK PHASE II

2. List any subcontractors in which your organization has some ownership and list the categories of

work these subcontractors normally perform.

3. Claims and suits (if the answer to any of the questions below is yes, please attach details).

a. Has your organization ever failed to complete any work awarded to it?

b. Are there any judgments, claims, arbitration proceedings or suits pending or outstanding

against your organization or its officers?

c. Has your organization filed any lawsuits or requested arbitration with regard to

construction contracts within the last five years?

4. Within the last five years, has any officer or principal of your organization been an officer or

principal of another organization when it failed to complete a construction contract? (If the answer

is yes, please attach details).

5. Current Work: List the major construction projects your organization has in progress, giving the

name and location of project, owner, architect, contract amount, percent complete and scheduled

completion date.

6. Work Over the Last Five Years: List major projects constructed by your organization and/or

submitted team over the last five years. For each project, provide the name, nature of the

project/function of the building, size (total GSF), location, cost, completion date, owner, architect

and method of selection (i.e. CM at Risk, bid, Design-Build or other).

7. Sustainable Construction Principles: What is your firm’s philosophy concerning LEED Certification

and/or Sustainable construction practices (ex: use of low VOC materials, IAQ during construction,

construction waste diversion, etc.)? Are any of your proposed team LEED Accredited? What has

been your experience in constructing LEED Certified buildings? What has been your experience in

constructing buildings that are not technically LEED certified, but follow similar sustainable

practices for construction activities?

Section 5 – Financial Information

1. Attach a financial statement, preferably audited, including your organization’s latest balance sheet

and income statement showing the following items:

a. Current assets (e.g. cash, joint venture accounts, accounts receivable, notes receivable,

accrued income, deposits, materials in inventory, and prepaid expenses)

b. Noncurrent assets (e.g. net fixed assets, other assets)

c. Current liabilities (e.g. accounts payable, notes payable (current), accrued expenses,

provision for income taxes, advances, accrued salaries and accrued payroll taxes)

Page 9: Request for Proposals - KSU Foundation...Step One – RFP Issued The RFP, and any subsequently issued Addenda, will be posted on the KSUF website at: ... • Include cover letter on

Page | 7 KANSAS STATE UNIVERSITY FOUNDATION – RFP FOR CMAR – KSU OFFICE PARK PHASE II

d. Noncurrent liabilities (e.g. notes payable)

e. Capital accounts and retained earnings (e.g. capital, capital stock, authorized and

outstanding shares par value, earned surplus and retained earnings)

2. Name and address of firm preparing attached financial statement and date thereof.

3. Is the attached financial statement for the identical organization named under item 1 above? If

not, explain the relationship and financial responsibility of the organization whose financial

statement is provided (e.g. parent, subsidiary).

4. Will the organization whose financial statement is attached act as guarantor of the contract for

construction?

5. Provide name, address and phone for bond reference.

6. Surety: name of bonding company, name and address of agent. A bond for 100% of the

construction cost will be required upon submission of the GMP. Proof of ability to bond shall be

required prior to selection.

Section 6 – Experience with Concepts for Working as a Construction Manager at Risk

1. Describe your organization’s concepts for working in a team relationship with the owner and

architect during the design and construction of major projects.

2. Describe your organization’s methods for estimating costs and for scheduling during the

design/document phases (SD, DD, and CD).

3. Specifically during Contract Documentation Phase: At what document completion percent will you

be able to establish an Initial GMP? At what document completion percent will you be able to

provide a Final GMP?

4. Which of your project(s) listed above best exemplify these concepts and experience?

5. Documents / Instruments of Construction

a. Cost Estimates: Attach a sample conceptual cost estimate prepared during the design

phase of a project and a sample of the final cost estimate/breakdown used to fix the

contract amount for the construction of the same project. (The identity of the project may

be concealed).

Page 10: Request for Proposals - KSU Foundation...Step One – RFP Issued The RFP, and any subsequently issued Addenda, will be posted on the KSUF website at: ... • Include cover letter on

Page | 8 KANSAS STATE UNIVERSITY FOUNDATION – RFP FOR CMAR – KSU OFFICE PARK PHASE II

b. Bid Scoping: Attach a sample bid scope document prepared by your firm for inclusion in bid

booklet and/or final bid document package. (Preferably a project of similar type – the

actual identity of the project may be concealed.)

c. Bid Form: Attach a sample (proposed) subcontractor bid form to be included in bid booklet

and/or final bid document package.

d. Sample Subcontract Agreement: Attach a typical subcontract form utilized by your firm.

6. Fees: It is anticipated that the Kansas State University Foundation will enter into a two part AIA

133-2009 edition – with GMP exhibit to follow at completion of construction documentation – with

the selected construction manager, and upon KSUF Board of Directors approval to move forward

with construction. Based on this understanding, provide a proposed fee quote as a percent (%) of

the Cost of Work for construction. This sum will include overhead, profit, and corporate

supervision. A Preconstruction Services lump sum fee shall also be noted separately. Use the

following matrix as a guide for your proposal (Attachment “B”).

7. General Conditions: As a Cost of Work. Provide a detailed listing of all general conditions your firm

proposes to provide. Use the following matrix as a guide for your proposal (Attachment “C”) if a

Cost of Work General Condition, as suggested in the matrix, is to be performed by a subcontractor,

then note as such and provide a value to be allocated to that subcontract, either by scope or by

allowance. The intent of this section is to identify all potential General Conditions both performed

by the GC and/or allocated as a direct subcontract cost in a clear straightforward manner for all

submitting CM’s. If a listed General Condition line item is not intended to be provided as any type

of reimbursable cost then note as such.

8. Change Orders: Discuss your organization’s concept for Change Order Requests evaluation and

their resultant Change Orders – both Owner requested and Contractor initiated. Provide a

proposed percentage (%) profit for Change Order increases to the GMP (if proposed is different

than base fee percentage (%) for cost of work – if the same, state “same as fee percentage (5) for

cost of work”) (Attachment “B”).

9. Savings: Describe your organization’s concept for the disposition of savings realized during

construction. Is the full amount or a percentage thereof returned to the owner?

10. Contingencies: Respond to each of the following items by separate paragraph:

a. Preconstruction Services:

i. Describe your organization’s concept for cost contingencies during all design phases

(SD, DD and CD’s). Are there separate contingencies for owner and Contractor or

are they the same? What is the maximum amount of contingency your organization

proposes for this phase?

Page 11: Request for Proposals - KSU Foundation...Step One – RFP Issued The RFP, and any subsequently issued Addenda, will be posted on the KSUF website at: ... • Include cover letter on

Page | 9 KANSAS STATE UNIVERSITY FOUNDATION – RFP FOR CMAR – KSU OFFICE PARK PHASE II

b. Construction:

i. What is the maximum amount of construction contingency your organization

proposes for this phase?

ii. How do you propose to document changes to project contingency within the GMP

during construction?

iii. When is an expense proposed as a Contingency Fund Allocation Request to draw on

project contingency and when is it proposed as a Change Order Request to the

GMP?

iv. How are buy-out funds to be allocated to the contractors, owners, or a general

construction contingency fund to be used by both the contractor and the owner?

v. What is your organization’s concept for the disposition of contingency funds after

the completion of the project?

Section 7 – Personnel

Given the scope and schedule of the project, identify the specific Project Manager, Estimator, Field

Engineer and Superintendent(s) who would work on the project. Also, list any additional staff you may

require for a project of this magnitude (i.e. safety officer, assistant superintendent, etc.). Provide a

resume and references for each individual.

Section 8 – Owner / Construction Manager Agreement

The KSU Foundation proposes utilizing the AIA Document A133-2009 Edition “Standard Form of

Agreement Between Owner and Construction Manager as Constructor” where the basis for payment is

the COST OF THE WORK PLUS A FEE with a Guaranteed Maximum Price (as modified by the KSU

Foundation). In conjunction with the AIA Document A201-2007 Edition General Conditions of the

Contract for Construction (as modified by the KSU Foundation). Please note any major exceptions or

issues you would raise relative to these documents. The Kansas State University Foundation will

provide the DRAFT copy of these documents for this project as a Bid Addendum that will be issued at

the Mandatory Pre-Bid Conference.

Section 9 – References

For six (6) of the projects listed above (re: Section 4 / Item 5) identify a representative of the owner

and a representative of the architect (provide name, phone/fax numbers) whom we could contact as

references regarding your organization’s services. Ideally, some of the references should be for a

construction project of comparable scope.

Page 12: Request for Proposals - KSU Foundation...Step One – RFP Issued The RFP, and any subsequently issued Addenda, will be posted on the KSUF website at: ... • Include cover letter on

Page | 10 KANSAS STATE UNIVERSITY FOUNDATION – RFP FOR CMAR – KSU OFFICE PARK PHASE II

Questions and Clarifications

Please submit all questions and requests for clarifications in writing, via email, to the KSUF Director of

Construction, John Angelos, at [email protected] no later than 5:00 PM on February 26, 2016.

Responses will be compiled and issued together in a Bid Addendum that will be issued at the

Mandatory Pre-Bid Conference.

Page 13: Request for Proposals - KSU Foundation...Step One – RFP Issued The RFP, and any subsequently issued Addenda, will be posted on the KSUF website at: ... • Include cover letter on

KANSAS STATE UNIVERSITY FOUNDATION – RFP FOR CMAR – KSU OFFICE PARK PHASE II

Attachment “A”

PROGRAMMING AND CONCEPT PRESENTATION IMAGES

Page 14: Request for Proposals - KSU Foundation...Step One – RFP Issued The RFP, and any subsequently issued Addenda, will be posted on the KSUF website at: ... • Include cover letter on

KSU O� ce Park | Phase IIFebruary 17th, 2016

1st Floor Concept Diagram

Architectural Site Planscale: 1” = 20’-0”

North

Page 15: Request for Proposals - KSU Foundation...Step One – RFP Issued The RFP, and any subsequently issued Addenda, will be posted on the KSUF website at: ... • Include cover letter on

KSU O� ce Park | Phase IIFebruary 17th, 2016

Overall Site Summary

SITE: 16.42 ACRESBUILDING: 220,000 SFPARKING: 732 SPACES

KIMBALL AVENUE

DE

NIS

ON

AV

EN

UE

PHASE 4

SITE: 3.0 ACRESBUILDING: 40,000 SFPARKING: 186 SPACES

PHASE 1

SITE: 4.72 ACRESBUILDING: 60,000 SFPARKING: 172 SPACES

PHASE 3

SITE: 3.3 ACRESBUILDING: 60,000 SFPARKING: 198 SPACES

PHASE 2

SITE: 3.3 ACRESBUILDING: 60,000 SFPARKING: 176 SPACES

Site Analysisscale: 1” = 30’-0”

North

Page 16: Request for Proposals - KSU Foundation...Step One – RFP Issued The RFP, and any subsequently issued Addenda, will be posted on the KSUF website at: ... • Include cover letter on

KSU O� ce Park | Phase IIFebruary 17th, 2016

Phase II Conceptual RenderingView looking North

Page 17: Request for Proposals - KSU Foundation...Step One – RFP Issued The RFP, and any subsequently issued Addenda, will be posted on the KSUF website at: ... • Include cover letter on

KSU O� ce Park | Phase IIFebruary 17th, 2016

� �

� �

� �

�������

��������

�������

��������

��������

��������

���� �

�� �������

������������ �������� ������� ������� �������� ������� ������� �������� �������

��������

������

��������

�������

��������

� �

�������

������ �

��������

������ �

������ ��������

���

���

��������

�����

�����

�����

����������� ��� ����

������

�����

��� ���

��� ���

������� ���

�����������

����

����������

������

����!

���"� �

������

����� �

������

#�������

��������

� ���� �

� ��������� �������� �������� ����� � ������� ������� ������� ������� ������� ������� ������� �������

��������� ������ ����� ������� ������� �������� ������� ������� ��������

��� ������������

"��� �

������

����� �

������

����

����

����

����

North

First Floor Planscale: 1/4” = 1’-0”

Page 18: Request for Proposals - KSU Foundation...Step One – RFP Issued The RFP, and any subsequently issued Addenda, will be posted on the KSUF website at: ... • Include cover letter on

KSU O� ce Park | Phase IIFebruary 17th, 2016

� �

� �

� �

�� ���

������

��������

�������

�������

�������

��������

��������

��������

������

� �

������� ������ �������� ������� ������� ������� ������� ������� ��������

������� ������ ������ � ������� ������� ������� ������� ������� ��������

������ �

��������

������

�������

�������

��������

��������

��������

��������

���������

��������� ������� �������

���������

��

��

��������������

���� ����� ����� ���

�����

�� ��

�� ��

����

�����

�����

�����

������!���

�������

�����������

����

������

������

�������

�������� �������� �������� ������� ������� ������� ������� ������� �������� ������� ���������������

������������� ���

���������

�����

��

��

��

��

����

�������

Second Floor Planscale: 1/4” = 1’-0”

North

Page 19: Request for Proposals - KSU Foundation...Step One – RFP Issued The RFP, and any subsequently issued Addenda, will be posted on the KSUF website at: ... • Include cover letter on

KSU O� ce Park | Phase IIFebruary 17th, 2016

� �

� �

� �

�� ���

������

� �

��������

�������

�������

�������

��������

��������

��������

������

������� ������ �������� ������� ������� ������� ������� ������� �������� �������

������ ������ � ������� ������� ������� ������� ������� �������� �������

��������

�������

�������

��������

������

�������

�������

��������

��������

��������

��������

�������

��������� ������� ��������� �������

��

��

���������

�����

������� �������

���� ���������� ���

�����

�� ��

�� ��

����

�������

�����������

����

������

�����

�����

�����

������

�������

���������

���������

������� �������� �������� �������� ������� ������� ������� ������� ������� �������� ������� ��������

�������

������������ ���

��

��

��

��

����

�������

Third Floor Planscale: 1/4” = 1’-0”

North

Page 20: Request for Proposals - KSU Foundation...Step One – RFP Issued The RFP, and any subsequently issued Addenda, will be posted on the KSUF website at: ... • Include cover letter on

KANSAS STATE UNIVERSITY FOUNDATION – RFP FOR CMAR – KSU OFFICE PARK PHASE II

Attachment “B”

FEE STRUCTURE WORKSHEET

Page 21: Request for Proposals - KSU Foundation...Step One – RFP Issued The RFP, and any subsequently issued Addenda, will be posted on the KSUF website at: ... • Include cover letter on

Line A C.M. General Overheas as included in Base Fee %

(includes all items not reimbursed as cost of work per AIA 133

section 6.8)

All Related Corporate Executive Expense (Project Executive /

Principal in Charge)

Legal / Contracts / Subcontract Administration

Accounting

Scheduling

Purchasing

Estimating

Safety Engineer

3rd Party Peer Reviews (building envelope, structure, Mech, etc.

- if used)

Value Engineering Services

Bid Scoping / Bid Package Development / Bid Booklet For

Subcontract Bidding

Shop Drawing Reviews & Approvals, Collection & Distribution

As-Build CM Field Set Updates

Operation / Maintenance Manual Compilation & Review

All Code and Regulatory Reference Documents & Manuals

All Non-Site Computing Equipment and Software

All primary Office Clerical & Secretarial-Filing, Typing, Etc.

All Misc. Office Copying & Printing

All forms, Documents, Reports

Line B C.M. Profit/Margin (List amount of proposed profit)

Profit / Margin %

Line C Line A + Line B %

Line D

Proposed Fee for Changes in the Work (AIA 133 section 5.1.2) if

left blank assume same as Base Fee %

Line E

Limitations on Subcontractor overhead & profit for increases in

the cost of the Work (AIA 133 section 5.1.3)

Line F

Proposed Preconstruction Fee as a Lump Sum (AIA 133 section

4.2.1 $

KANSAS STATE UNIVERSITY FOUNDATION

FEE PROPOSAL WORKSHEET - Base Fee % and Preconstruction as pertaining to AIA 133-2009 Articles 4 & 5

Target construction GMP is $12m with a final value to be determined at time of GMP. Base your Proposed Fee valuations on this

value range assumption - you must complete lines C and F.

Cost as %

5% Maximum

Page 22: Request for Proposals - KSU Foundation...Step One – RFP Issued The RFP, and any subsequently issued Addenda, will be posted on the KSUF website at: ... • Include cover letter on

KANSAS STATE UNIVERSITY FOUNDATION – RFP FOR CMAR – KSU OFFICE PARK PHASE II

Attachment “C”

GENERAL CONDITIONS STRUCTURE WORKSHEET

Page 23: Request for Proposals - KSU Foundation...Step One – RFP Issued The RFP, and any subsequently issued Addenda, will be posted on the KSUF website at: ... • Include cover letter on

Note: Do not include costs of proposed self-performed subcontract bid packages By CM By Subcontractor N/A

cost in $ cost in $

Comply with definition provided in Article 6 "costs to be reimbursed"

AIA 133 Section 6.2 Labor Costs 100% Site Supervision Staff

Project Manager - located on site full time $ $

Superintendent - located on site full time $ $

Site Secretary $ $

Other Proposed: _______________________________________ $ $

Other Proposed: _______________________________________ $ $

Surveyor / Building Layout $ $

Laborer General Carpentry $ $

laborer General Cleanup $ $

Laborer Final Cleanup $ $

Other Proposed Laborer: ________________________________ $ $

Other Proposed Laborer: ________________________________ $ $

AIA 133 Section 6.3 Subcontract Cost (not part of Gen. Conditions

AIA 133 Section 6.4 Cost of Material and Equipment (not part of Gen. Conditions

AIA 133 Section 6.5 Other Materials & Equipment, Temp Facilities & Related Items

Office Trailer Including all furniture, copy/fax/computer equip., etc. $ $

Site Phone / Fax / Cell phones / radios $ $

All Code and Regulatory Reference Documents & Manuals at site $ $

Copy paper / general office supplies $ $

Faxing / FedEx / mailing and postage - General use and Shop Drawing Related $ $

First Aid Supplies $ $

Fire Extinguishers $ $

General Site construction office Trash Disposal and Recycling $ $

Water cooler / refrigerator / microwave / coffee maker $ $

General Safety Equipment (harnesses, hats, Vests, Eye Protection, etc.) $ $

All Project Signs - informational, safety, warning, etc. $ $

Tool Utility Trailer Rental $ $

Portable Toilets $ $

Handrails - Safety Barriers - Opening Protection $ $

Recycling of Construction Material $ $

Disposal/Haul-off of Non-Recyclable Materials $ $

Temporary Site Fincing - Gates - Chains/Locks $ $

Traffic Control - barriers & signage (labor noted above) $ $

Roadway Maintenance (beyond job site if impacted - cleaning / repair / etc.) $ $

Silt Fence and Storm Water Protection and Compliance $ $

Temporary Roads for Construction (gravel, rock, fabric, etc.) $ $

Temp Power and Lighting $ $

Temp Water $ $

Temp Heating $ $

Temp Enclosures & Partitions $ $

Air Compressor $ $

Generator $ $

Dewatering Equipment and Pumps / Hoses $ $

Vehicular Transportation Site Specific Vehicle (cost for 12 months) $ $

Vehicular Transportation Site Specific Vehicle (cost for 12 months) $ $

Small Construction Tools & Equipment $ $

CM & General Use Skidsteer $ $

CM & General Use Forklift $ $

Crane and other hoisting by subcontractors $ $

Other Proposed Equipment ______________________________________ $ $

Other Proposed Equipment ______________________________________ $ $

Other Proposed Equipment ______________________________________ $ $

AIA 133 Section 6.6 Miscellaneous Costs

CM Performance Bond (to owner at Final GMP) $ $

Liability insurance (name owner as "additional insured" $ $

Testing & Balancing - by CM $ $

Materials Testing (concrete, engineered backfill compressive, etc.) - by Owner n/a n/a

Special Testing & Commissioning - by Owner n/a n/a

General Conditions - As a Cost of Work - Completed by CM $

General Conditions - As a Cost of Work - Proposed to be applied to Subcontract $

KANSAS STATE UNIVERSITY FOUNDATION

PROPOSED GENERAL CONDITIONS: as included in the cost to be reimbursed (Cost of the Work)