SR 89 Fanny Bridge Community Revitalization Project Request for MOA Approval Department of Public Works October 26, 2021 Presented to the Placer County Board of Supervisors
6

Request for MOA Approval

Jun 12, 2022

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Request for MOA Approval

SR 89 Fanny Bridge Community Revitalization Project

Request for MOA Approval

Department of Public WorksOctober 26, 2021

Presented to the Placer County Board of Supervisors

Page 2: Request for MOA Approval

Fanny Bridge Project BackgroundLocation:

• Downtown Tahoe City over the Truckee River; adjacent to the Tahoe City dam.

Project Goals:• Provide second Truckee River bridge crossing• Improve pedestrian mobility• Improve traffic circulation and transit connections• Rebuild Fanny Bridge and provide ‘complete

street’ district

Page 3: Request for MOA Approval

Data collection location- North

Data collection location- South

SR 28 (N. Lake Boulevard)

Renderings showing remaining project elements to construct including roundabout at ‘wye’ intersection and Fanny Bridge rebuild/enhancement

Page 4: Request for MOA Approval

Project Status (Oct 2021)Remaining Project Elements and EE Cost ($15.47M):• Fanny Bridge (Bid Schedule A) ~ $6.495M• Wye Roundabout (Option X) ~ $5.59M• West Lake Blvd / A-Line (Option Y) ~ $2.35M• Lighting/Landscaping (Option Z) ~ $1.03M

Page 5: Request for MOA Approval

Data collection location- North

Data collection location- South

SR 28 (N. Lake Boulevard)

Potential A-Line or West Lake Blvd ‘complete street’ modifications

Project Schedule2022: Complete design and advertise for construction

2023-24: Construction

Page 6: Request for MOA Approval