C ITY OF N EW O RLEANS Reporting Period: April 1 – April 30th Office of Performance & Accountability ReqtoCheckSTAT www.nola.gov/opa
CITY OF NEW ORLEANS
Reporting Period: April 1 – April 30th
Office of Performance & Accountability
ReqtoCheckSTAT
www.nola.gov/opa
Context In order to deliver critical services for its citizens—such as constructing roads, rehabilitating homes, or picking up trash—the City often engages with private companies with specialized expertise. Because these and other services are so critical, Mayor Landrieu has made it a priority for vendors to be selected fairly, for contracts to be negotiated expeditiously and in the best interests of New Orleanians, and for vendors to be paid in a timely manner. What is ReqtoCheckStat? In order to improve the performance, accountability, and transparency of the City’s contracting system, Mayor Landrieu asked the Office of Performance and Accountability to design a performance management program for the entire process of contracting out services—from the requisition of budgeted funds to the issuance of check for services rendered. The result is ReqtoCheckStat, a performance management system where key City officials review data to assess how the City is meetings its goals and to hold departments accountable for their results. ReqtoCheckStat, which takes place monthly, are working meetings, intended to provoke constructive dialogue on what is working, what is not, and what the City needs to do to improve. Can I participate? This meetings are open to the public. Members of the public are invited to submit questions, which will be addressed by City officials.
Procurement Process Overview*
Requisition
•Department identifies need, and creates a requisition
•Requisition to use budgeted funds is approved by different offices
Procurement / DBE
•Approved requisition is reviewed by the Bureau of Purchasing
•Requisition is converted to Purchase Order (PO), Bid or Request for Proposal (RFP), depending upon scope of work and dollar amount
Contract Creation and
Routing
• Department routes contract materials through the system in order to obtain a contract
Contract Processing
and Approval
•Contract is reviewed for form, legality by Law Department
•CAO, City Attorney, Executive Counsel, Mayor/ Council review and approve contract
Payment
•Department reviews invoice and submits payment voucher to Accounts Payable (AP) to process payment
•Accounts Payable processes requests and makes payment
*See a more detailed process map on slide 30
Note : The reporting period covering the period 12.15.2011 to 1.31.2012 includes 1 ½ months of activity .
Requisition Approval
• Requisition Approved and Processed per Period
• Requisition Approval Queue by Approval Level
• Approval Time of Requisitions
Requisition Procurement
/ DBE
Contract Creation and
Routing
Contract Processing
and Approval Payment
Source : City of New Orleans Procurement System 5.1.2012
Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment
Approval Queue Continues to Decrease Reaching 66 Requisitions as of 4.30.2012
54 36
130
48 51 47
158
56
214
132
40 19
1 33
42
213
92
344
213
133
66
0
50
100
150
200
250
300
350
400
11.15.2011 12.15.2012 1.31.2012 2.29.2012 3.31.2012 4.30.2013
Finance
Budget
Department
Requisitions in Q to be Approved
11
1
6
1
0 5 10 15
2 Days or Less
3- 5 Days
6-10 Days
Over 10 Days
Age of Requisitions in Q Budget Office (Total 19)
213 133 66
1087 1167 943 1010
Ending Approval Q2.29.2012
New Requisitions Created Requisitions Approved Ending Approval Q3.31.2012
New Requisitions Created Requisitions Approved Ending Approval Q4.30.2012
Requisition Approval Queue General Fund for Period Ending 4.30.2012
Source : City of New Orleans Procurement System 5.1.2012
Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment
Number of Days to Approve Requisitions Meeting Target
3.4 3.0 2.1 2.45 1.88
0.6
0.6 0.7
1.0 0.55 0.57
0.6
3.99 3.76 3.10 3.00
2.45
1.21
0.0
1.0
2.0
3.0
4.0
5.0
11.15.2011 12.15.2012 1.31.2012 2.29.2012 3.31.2012 4.30.2012
Average Number of Days to Approve Requisitions by Reporting Period (Budget Office and Department of Finance)
Finance(1 Working Day Target)
Budget(2 Working Day Target)
3 Working Day Target
Days to Approve 11.15.2011 12.15.2011 1.31.2012 2.29.2012 3.31.2012 4.30.2012
1 or less 99% 99% 85% 99% 97% 96%
2 Days 1% 0% 7% 1% 2% 2%
3-5 Days 0% 1% 8% 0% 1% 2%
6-10 Days 0% 0% 0% 0% 0% 0%
11-15 Days 0% 0% 0% 0% 0% 0%
Over 15 Days 0% 0% 0% 0% 0% 0%
Finance20122011
Days to Approve 11.15.2011 12.15.2011 1.31.2013 2.29.2012 3.31.2012 4.30.2012
2 or less 69% 61% 71% 53% 74% 96%
3 Days 4% 6% 9% 15% 8% 3%
4-5 Days 8% 12% 9% 25% 11% 1%
6-10 Days 7% 17% 10% 7% 6% 0%11-15 Days 7% 4% 1% 0% 1% 0%
Over 15 Days 5% 0% 0% 0% 0% 0%
20122011
Budget
Requisition to Procurement
• Processing of Requisition by Bureau of Purchasing
• Status of Requisitions Awaiting Buyer Response
• Time to Convert Requisition to PO
• Status of Requests for Proposals
• Status of Bids
• DBE Compliance (Preliminary Data)
Requisition Procurement
/ DBE
Contract Creation and
Routing
Contract Processing
and Approval Payment
Source : Obtained from the Bureau of Purchasing 5.1.2012 and 5.10.2012
Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment
The Number of Requisitions in Queue Waiting to be Processed by the Bureau of Purchasing Marginally Increased to 141
207 133 141
1167 1241 1010 1002
Ending Approval Q2.29.2012
New Requisitions Approved Requisitions Processed Ending Approval Q3.31.2012
New Requisitions Approved Requisitions Processed Ending Approval Q4.30.2012
Bureau of Purchasing Requisition Processing General Fund for Period Ending 4.30.2012
Status Count
Awaiting Contract 77
Completed 41
Processing Procurement 14
Waiting for Support 9
Grand Total 141
Status Count
Property Management 3
Econ. Development 2
Nord 1
Police 1
NOPD 1
DPW 1
Grand Total 9
Status of Reqs Awaiting Buyer Processing
4.30.2012
Waiting for Support 92% 93% 93% 89% 85%
7% 3% 4% 5% 7% 1% 4% 3% 6% 8%
0%10%20%30%40%50%60%70%80%90%
100%
11.16.201112.15.2011
12.16.20111.31.2012
2.1.20122.29.2012
3.1.20123.31.2012
4.1.20124.30.2012
9 Days and Over 5 - 8 Days 0 -4 Days
The Bureau of Purchasing Processed Requisitions in Four Days or Less 85% of the Time (Average 1000 POs per month)
* 4.1.2012 -4.30.2012 Includes time Req. to PO & RFPs and Bids time Req. received to time send to OIG
Source : Bureau of Purchasing 5.1.2012 and 5.10.2012
Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment
* Includes cancelled RFPs for which proposals were not received
50% 67%
50% 50%
50% 33%
50% 43%
7%
0%
20%
40%
60%
80%
100%
1.31.2012 YTD (2.29.2012) YTD (3.31.2012) YTD (4.30.2012)
10 and Above
4 to 9
3 and below
Number of Proposals Received for RFPs Completed YTD 2012 (as of 4.30.2012). YTD 14 Completed
8
7 9*
5
4 8*
6
2 6
7
8 8
2
3
Ending RFP Q2.29.2012
RFP Requests RFP Completed/ Cancelled
Ending RFP Q3.31.2012
RFP Requests RFP Completed/ Cancelled
Ending RFP Q4.30.2012
The Number of RFPS in Process Decreased to 15 as of 4.30.2012
Waiting Committee Meeting
Waiting Opening Date
Total 21
Total 19
Waiting Information From Department / Other
Total 15
Department Brief Description
French Market Corp Multi-Use Parking Facility
Aviation Board Airport Pavement Index Study
Aviation Board Land Use
OCD Livable Neighborhoods Revitalized Corridors
OCD NOATF Legal Services Base Realignment
Police Survey
CAO Unemployment Management Personnel
Awaiting Committee Meeting
Department Brief Description Comment
OCD Online Auction Services N.O. East Awaiting Decision
Public Works Curbside Management & Enforcement Awaiting Decision
Waiting on Support / Response from Departments
Source : Bureau of Purchasing 5.1.2012 and 5.10.2012
Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment
* Includes cancelled Bids for which proposals were not received
Department Brief Description Comment
Homeland Security Access Alarm Services Award Recommendation
Homeland Security 2 Chem ID Devices Award Recommendation
Capital Hubbell Library Renovations Award Recommendation
Capital Temporary Stables Building Award Recommendation
Capital Joseph Bartholomew Maint. Bldg. Award Recommendation
Parks & Parkways 3rd & 4th District Tree Trim/ Removal Award Recommendation
Aviation Board Taxiway Golf Extension East Award Recommendation
Aviation Board Security Perimeter Fence replacement Award Recommendation
Awaiting on Department
57% 52% 50% 51%
43% 48% 47% 46%
3% 3%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
1.31.2012 YTD (2.29.2012) YTD (3.31.2012) YTD (4.40.2012)
10 andAbove
4 to 9
3 andbelow
Number of Proposals Received for Bids completed YTD 2012 (as of 4.30.2012). YTD 37 Completed
9 8 8
9
14 9*
18
3
13*
6
5
2
4
Ending Bid Q2.29.2012
Bid Requests Bids Completed/ Cancelled
Ending Bid Q3.31.2012
Bid Requests Bids Completed/ Cancelled
Ending Bid Q4.30.2012
The Number of Bids in Process Decreased to 18 as of 4.30.2012
Waiting Opening Date
Waiting Information From Department
Total 23 Total 28 Total 18
In Process Bureau of Purchasing/DBE
Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment
Source : Office of Supplier Diversity 5.16.2012
Cumulative YTD Percentage of DBE Award Value as of 4.30.2012
1,190,946
4,756,283
7,905,779
$15,245,959
-
2,000,000
4,000,000
6,000,000
8,000,000
10,000,000
12,000,000
14,000,000
16,000,000
18,000,000
January February March April
DBE Commitment for Bids/RFPS Opened and that Have Been Reviewed by the Office of Supplier Diversity
Cumulative Estimated Contract Value 35% Target DBE Award Value Committed
35% Target
39% YTD Actual
Bid/RFP Closed 2012 51DBE Complete
(Included in Summary as of 4/30/2012)21
Aviation Board
(Excluded Form Summary 4/30/2012)9
Processing (RFP Prices/ DBE Review / Recently Opened)
(Excluded From Summary 4/30/2012)17
Other (Re-Bid )
(Excluded From Summary 4/30/2012) 4 5 9
3 4
3
3
4 3
3
1
8 3.2 Days
15 5.6 Days
8 5.1 Days
7 4 Days
0
5
10
15
20
1.31.2012 2.29.2012 3.31.2012 4.30.2012
Over 10Days
4-10 Days
0-3 Days"Target"
Time to Process DBE Validation by the Office of Supplier Diversity 2012 Requests Completed (Working Days)
units
Contract Package Routing
• Average Contract Routing Time
Requisition Procurement /
DBE Contract Creation
and Routing
Contract Processing and
Approval Payment
Source : ECMS 5.1.2012
Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment
Average Time to Approve Contracts Meeting Target
1.9 1.8 2.3
1.1 0.6
0.6 0.5
0.4
0.4
0.5
0.7
0.3
0.6
0.4 0.9
0.7
0.7
0.8
0.5 0.5
4.0
3.3
4.1
2.4 2.5
-
0.50
1.00
1.50
2.00
2.50
3.00
3.50
4.00
4.50
12/15/2011 1/31/2012 2/29/2012 3/31/2012 4/30/2012
Average Approval Time of Contracts by Approval Level in Days (by period)
CAO (1 day target)
Civil Service (1day target)
Finance (1 daytarget)
Bureau ofPurchasing (1 daytarget)
4 day aggregate target
Routing Aggregate Time 4.9 Days 5.15.2011
1 4 Days
4 0 Days
1 1 Days
1 9 Days
Purchasing
Finance
Civil Service
CAO
0 1 2 3 4 5
7 Contract Request are in Q as of 4.30.2012 Days to Approve 2.29.2012 3.31.2012 4.30.2012 Days to Approve 2.29.2012 3.31.2012 4.30.2012
0-1 Days 90% 93% 91% 0-1 Days 92% 97% 93%
2- 3 Days 3% 7% 9% 2- 3 Days 8% 3% 7%
4-7 Days 7% 0% 0% 4-7 Days 0% 0% 0%
Over 8 Days 0% 0% 0% Over 8 Days 0% 0% 0%
Days to Approve 2.29.2012 3.31.2012 4.30.2012 Days to Approve 2.29.2012 3.31.2012 4.30.2012
0-1 Days 97% 93% 93% 0-1 Days 62% 78% 88%
2- 3 Days 3% 7% 2% 2- 3 Days 18% 16% 9%
4-7 Days 0% 0% 5% 4-7 Days 10% 1% 3%
Over 8 Days 0% 0% 0% Over 8 Days 10% 5% 0%
Finance Distribution Approval
CAO Distribution Approval
Bureau of Purchasing Distribution Approval
Civil Service Distribution Approval
Contract Approval Process
• Contract Processing and Approval
Requisition Procurement /
DBE Contract Creation
and Routing
Contract Processing and
Approval Payment
Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment
Contracts: All Contracts Processed, Received and in Queue 5.15.2011 – 4.30.2012 (Legal Review, CAO, Vendor Signature, City Attorney, Executive Council, Mayor/City Council)
Source : Law Department and ECMS System 4.30.2012
152 155 157 161 154 154 151 133 109
170 188 183 212
112 109 76 74
112 108
40 47 90 93 81 99
39 63
141
80 114 96 111 116 123
94
0
50
100
150
200
250
300
350
5.15.2011 6.15.2011 7.15.2011 8.15.2011 9.15.2011 10.15.2011 11.15.2011 12.15.2011 1.31.2012 2.29.2012 3.31.2012 4.30.2012
All Contracts Processed, Received and in Q at the End of the Reporting Period as of 4.30.2012 (in units)
216 Contracts as 3.15.2011 2011 2012
In Queue Received
Closed
3 2 4
-7 -3 -18 -24
61
18
-5
29
-40
-20
0
20
40
60
80
6.15.2011 7.15.2011 8.15.2011 9.15.2011 10.15.2011 11.15.2011 12.15.2011 1.31.2012 2.29.2012 3.31.2012 4.30.2012
Net Change in Contracts Queue
2012 2011
Increase Q Decrease Q
Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment
Contracts : All Contracts in Process by Period (Legal Review, CAO, City Attorney, Executive Counsel, Mayor/Council Approval)
Source : Contract Management System ECMS 4.30.2012
69 43
74 109 94
118 26
25
42 26 45
52
12 13
24 24 11
13
12
6
10 13 13
7
14 22
20 16 20
22
0
50
100
150
200
250
300
11.15.2011 12.15.2011 1.31.2012 2.29.2012 3.31.2012 4.30.2012
Over 120 Days
91 - 120 Days
61 - 90 Days
31- 60 Days
0 - 30 Days
The Average Age of Contracts Awaiting Processing Decreased to 45 Days
Total 188 Average Days 46
Total 183 Average Days 48
216 Contracts 64 Average Days
3.15.2011
Total 133 Average Days 46
Total 109 Average Days 64
Total 170 Average Days 53
Total 212 Average Days 43
23 76
4 38 48 6 9 8
37 Days Since Entered for
Processing
23 Days Since Received by
The Law Department 34 Days
Since Received by CAO/Sent by Law
020406080
100120140160180
Manually RoutedEmergency
(Location NotSpecified)
Attorney Dp. City Att CAO Law Prepare forVendor
Vendor Sign Ordinance Executive Counsel Returned
Location and Average Age of Contracts in Process as of 4.30.2012
1Days Since Signed by the
Vendor
17 Days Since Completed
by Attorney
4 Days Since Reviewed
CAO
152 Days Since Submitted for
Legal Review
78 Days Signed Vendor /Approved CAO
Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment
Source : : Contract Management System ECMS 4.30.2012
Contracts : All Contracts Executed by Period (Legal Review, CAO, City Attorney, Executive Counsel, Mayor/Council Approval)
30% 41% 33% 42% 34%
70% 59% 34% 28% 34%
16% 10% 12% 11% 6% 9% 6% 14% 9%
60
39
56 62 58
51
-
10
20
30
40
50
60
70
80
90
100
11.15.2011 12.15.2011 1.31.2012 2.29.2012 3.31.2012 4.30.2012
Over 120 Days
91-120 Days
61-90 Days
31-60 Days
0-30 Days
The Average Time to Close Contracts During the Period Decrease to 51 Days from 58 Days. 28% of Contracts Were Closed in 30 Days or Less (80% Target)
66 Days 3.15.2011
28%
46%
18% 2%
6%
66
21
2 0 5
16 6
010203040506070
Manually RoutedEmergency
(Location Not Specified)
Legal Review D. City Att CAO To Send Vendor From Vendor Executive Con.
Average Days to Process Contracts Completed During the Period 4.1.2012 - 4.30.2012 (by Stage)
ECMS
2012 2013
Department / Agency Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
AVIATION 2 1 1 1 7 3 2 10 2 1
BLIGHT & REVITALIZATION 1 1 1 1 1 1
CANAL STREET DEVELOPMENT CORPORATION 1 1
CAO 4 12 1 2 1 1 1 2 3 1 1 1
CAPITAL PROJECT 1 4 16 6 5 8 5 3 2 9 6 15 16 6 2 7 1 1
City Council 6 1
CITY PLANNING 1
CIVIL SERVICE 1 5 1 1
COUNCIL UTILITY REGULATORY OFFICE' 1 1 6
DEFENSE BASE CLOSURE AND REALIGNMENT COMMISSION (BRAC) 1 1
DEPUTY MAYORS' & ASSISTANTS 1
DISASTER CDBG UNIT 1 1 2 4 1 4 5 3 1 1 1
ECONOMIC DEVELOPMENT 1 1 1 3 1 1
FACILITIES, INFRASTRUCTURE AND COMMUNITY DEVELOPMENT 5 3 3 1 1 1 4 1 1 2 2 2
FINANCE 1 1 2 2 1 1 1
FIRE DEPARTMENT 2 1 3 1 1 1 1 1 1 1
HEALTH DEPARTMENT 1 15 2 1 2 2 4 3 11 8 4 1 3 4 1 1
HISTORIC DISTRICT LANDMARK COMMISSION (HDLC)
HOMELAND SECURITY 1 1 4 1 3 5 14 3 3 6 5 3 4 1 1 3
HOMELAND SECURITY GRANTS APPROVAL 1 1 1
HUMAN RESOURCES 1
HUMAN SERVICES 2 1 1 1
LAW 1 3 3 2 9 5 3 4 7 4 10 4 5 1 1 1
MAYOR 2 1 2 2 2 8 6 1 2
MOSQUITO CONTROL BOARD 3
MUNICIPAL YACHT HARBOR MANAGEMENT CORPORATION(MYHMC) 1
NEIGHBORHOOD ENGAGEMENT OFFICE 1 1
NEIGHBORHOOD STABLIZATION 1 1 1 1 2 1 3 7 6 6
NEW ORLEANS BUILDING CORPORATION 3 1 1 1 2 1 1 1
NORD RECREATION DEPARTMENT 2 1 3 2 6 1 1 3 6
OFFICE OF CRIMINAL JUSTICE COORDINATOR 1 2 4 1
OFFICE OF INSPECTOR GENERAL 1
OFFICE OF TECHNOLOGY & INNOVATION 1 3 1 1 1 2 1 4 2 1
PARKS & PARKWAYS 2 2 1 1 3 2
PIAZZA D'ITALIA DEVELOPMENT CORPORATION 1 1 1
POLICE DEPARTMENT 3 2 5 1 1 1 1 1 3 7
PROPERTY MANAGEMENT 1 1 1 2 2 3 2 2 8 1 3 1 4 1
PUBLIC LIBRARY 1 1 1
PUBLIC WORKS 8 3 5 8 9 4 3 7 8 20 10 12 32 19 18 14 1
REGISTER OF VOTERS
RIVERGATE DEVELOPMENT CORPORATION 1
SAFETY & PERMITS 1 1
SANITATION DEPARTMENT 1 1 2 1 1 1
SERVE NOLA
Grand Total 26 45 40 27 42 41 17 37 43 79 63 103 93 82 65 37 8 3 2 1 6 1 4 4
New Tool To Review Contracts Expiring Every Month
Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment
Source : : Contract Management System ECMS 4.30.2012
Note: Each department is responsible for monitoring expiring contracts and making sure legacy contracts are renewed. This schedule should only be used as a guide.
The check: Accounts payable
• General Fund Payments
• Processing by Accounts Payable
• Payment from Invoice Date
• Capital and Grants Expenditure Payments
• Processing by Accounts Payable
• Payment from Invoice Date
• Detail Review (invoices in the pipeline)
• CDBG Invoice Payments
• DPW Payments
• DPW Revolver Payments
• Capital Projects Payments
• Capital Projects Revolver Payments
Requisition Procurement Contract Creation
and Routing
Contract Processing and
Approval Payment
Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment
Source :Accounts Payable and Office of Performance and Accountability. Collected 5.4.2012
The Percentage of General Fund (and Agency) Payments Processed in 7 Days or Less Decreased to 28%
56% 37%
20%
45% 45% 28%
23%
40%
48%
53% 54% 70%
12% 23% 30%
1% 1% 2% 9% 2% 1%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
11.15.2011 12.15.2011 1.31.2012 2.29.2012 3.31.2012 4.30.2012
Working Days to Process General Funds and Agencies Check Payments by A/P Office for Periods Ending 11.15.2011 to 4.30.2012 (in %)
Sample 280 selections 95% confidence level +-5
Over 30 Days
16 - 30 Days
8-15 Days
7 Days or less
11 11 12
8 8 9
0
2
4
6
8
10
12
14
11.15.2011 12.15.2011 1.31.2012 2.29.2012 3.31.2012 4.30.2012
Average Number of Days to Process Invoices by A/P Department (GF Expenditures)
Target 7 Days
Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment
The Percentage of General Fund (and agency) Payments in 30 Days or Less Decreased to 50% in the Current Period
50% 46% 34% 40%
56% 50%
28% 36% 42%
45% 33%
32%
17% 10% 16% 8% 8% 14%
5% 8% 8% 7% 3% 4%
0%
20%
40%
60%
80%
100%
11.15.2011 12.15.2011 1.31.2012 2.29.2012 3.31.2012 4.30.2012
Percentage of Payments in Days From Invoice Date to Payment for General Fund (or Agency) Expenditures for Periods Ending
11.15.2011 - 4.30.2012(in %) Sample 280 selections 95% confidence level +-5
Over 121 Days
61 - 120 Days
31 to 60 Days
30 Days or Less
45 48 52
48 40
44
0
10
20
30
40
50
60
70
11.15.2011 12.15.2011 1.31.2012 2.29.2012 3.31.2012 4.30.2012
Average Number of Days to Pay Invoices From Invoice Date (GF Expenditures)
Target 30 Days
Source :Accounts Payable and Office of Performance and Accountability. Collected 5.4.2012
The Percentage of Capital and Grant Payments Processed in 7 Days or Less Remains Over the 90% Target
Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment
98% 97% 95% 92% 99% 98%
3% 4% 5% 1% 2% 2%
1% 1% 2%
0%
20%
40%
60%
80%
100%
11.15.2011 12.15.2011 1.31.2012 2.29.2012 3.31.2012 4.30.2012
Working Days to Process Capital Expenditures and Grants Check Payments by A/P Office for Periods Ending 11.15.2011 - 4.30.2012(in %)
Sample 100 selections 90% confidence level +--10
Over 30 Days
16 - 30 Days
8-15 Days
7 Days or less
2 2 3
4
2 2
0123456789
10
11.15.2011 12.15.2011 1.31.2012 2.29.2012 3.31.2012 4.30.2012
Average Number of Days to Process Invoices by A/P Department (Capital and Grant Expenditures)
Target 7 Days
Source :Accounts Payable and Office of Performance and Accountability. Collected 5.4.2012
Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment
The Percentage of Capital and Grant Payments Made in 30 days or Less from Invoice Date Increased to 58%, from 56% in the Prior Period
53% 49% 52% 49% 56% 58%
25% 29% 26% 32% 29% 18%
14% 8% 15% 14% 10% 12%
8% 15% 7% 6% 5% 12%
0%
20%
40%
60%
80%
100%
11.15.2011 12.15.2011 1.31.2012 2.29.2012 3.31.2012 4.30.2012
Percentage of Payments in Days From Invoice Date to Payment for Capital and Grant Expenditures for Periods Ending
11.15.2011 - 4.30.2012(in %) Sample 100 selections 90% confidence level +-10
Over 121 Days
61 - 120 Days
31 to 60 Days
30 Days or Less
50 57
51 47 47 44
-
10
20
30
40
50
60
11.15.2011 12.15.2011 1.31.2012 2.29.2012 3.31.2012 4.30.2012
Average Number of Days to Pay Invoices From Invoice Date (Capital and Grant Expenditures)
Target 45 Days
Source :Accounts Payable and Office of Performance and Accountability. Collected 5.4.2012
(**)Represents the percentage of payments over 60 days, from invoice date, for the specific department.
Sample Results Payments Vouched Period 4.1.2012 – 4.30.2012
Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment
Source :Accounts Payable 5.4.2012
Sample 280 Selections 95% Confidence level +-5 Sample 100 Selections 90% Confidence level +--10
(*)Through a sample selection of approximatelly 370 invoices each reporting period, the Office of Performance and Accountability asks
departments with 3 (General Fund and Agencies) or 2 (Capital and Grant Expenditures) payments exceeding a 60 day payment window (invoice
date to payment date) to attend the periodic ReqtoCheck meeting to discuss challenges preventing invoices from being paid in a timely fashion. .
4 4 4 4
3 3
2 2 2 2 2 2
1 1 1 1 1 1
0
0.5
1
1.5
2
2.5
3
3.5
4
4.5
Capital DPW OCD Aviation Health Human
Services
NORDC ITI EMD Mosquito
Control
Mayor's
Office
Park and
Parkways
Library NOPD Property
Man.
Law Homeland
Security
Registrar
# of Reporting Periods Departments/AgenciesHad Multiple Payments Over 60 Days Since January 2012
Payments over 60 Days During Most Recent Reporting Period
General Fund & Agencies
Department No Yes
Parks 6 7 13 54%
Health 5 3 8 38%
Mayor 13 7 20 35%
Human Services 6 3 9 33%
Mosquito 7 3 10 30%
NORDC 17 4 21 19%
EMS 11 2 13 15%
Law 13 2 15 13%
Library 18 2 20 10%
Aviation 39 3 42 7%
Other Departments 92 17 109 16%
Total 227 53 280
Over 60 DaysGrand Total
(**) %
Dep. Late
Capital & Grants
Department No Yes
Homeland Security 6 4 10 40%
Capital 14 5 19 26%
OCD 16 5 21 24%
DPW 15 4 19 21%
Health 12 2 14 14%
Other Departments 14 3 17 18%
Grand Total 77 23 100
Over 60 DaysGrand Total
(**) %
Dep. Late
Significant Improvement in CDBG Payments in the Pipeline. Only a Few Outliers in the Over 60 Days Categories
Information obtained from Quickbase ( OCD ) 5.1.2012 – 5.11.2012
Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment
Over 60
days
Over 30
days
45 20 47 74 29 62
43 58 41
53 47 5 22
14 5 4 9 9 9 4
146 158 151 145
0
50
100
150
200
Jan-12 Feb-12 Mar-12 Apr-12
Over12091-120
61-90
31-60
OCD Aging of Invoices in the Pipeline
Processing Stage <=30 31-60 61-90 91-120 Over 120 Total
PM to Send to Owning Department 0
Owning Department to Send to Accounting 3 3
Accounting to Approve 18 18
State DRU to Send to State Finance 21 28 49
State Finance to Pay City 32 13 1 2 48
Payment to Hit City's Bank 12 12
City to Cut Check 0 5 4 2 4 15
Grand Total 74 58 5 4 4 145
Reasons for Delay
Dispute with the vendor 3
Misplaced / Nor Processed Timely
With the State 31 1 2
Contract being processed
Other 2 (B) 2 (A)
Paid as of 5.10.2012 27 2 1
(A): 2 invoices for NORA (DR #12); CNO received pymt 4/18/12; still not paid due to amount rec'd being greater than DR amount
(B): 2 invoices for NORA; see explanation above (DR #11)
Age
Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment
Information obtained from Quickbase (DPW Department) 5.1.2012 – 5.11.2012
Over 60 days
Over 30 days
Significant Improvement in DPW Payments in the Pipeline. Invoices in the Over 60 Days Categories Were Reduced by More Than 50%
20 11 18 19
12 9 3 3
7
4 5
2
1 2 1 3
24
25 26 9
64
51 53
36
010203040506070
Jan-12 Feb-12 Mar-12 Apr-12
Over12091-120
61-90
31-60
DPW City: Aging of Invoices in the Pipeline by Period
Processing Stage <=30 31-60 61-90 91-120 Over 120 Total
PM to Approve 3 1 6 10
Department to Create Receiver 6 2 2 3 2 15
Department to Deliver to Finance 1 1
Finance to Cut Check 3 3
Finance to Release Check 6 1 7
Grand Total 19 3 2 3 9 36
Reasons for Delay
Dispute with the vendor
Goods received at a later date / Services
were not renderedInvoice was missplaced / not processed
timely
Contract being processed 1 2 7
Other* 2 2 1 2
Paid 5.10.2012
*7 Invoices in "Other" Category - 6 are awaiting reimbursement from SWB before the invoices can be processed.
1 is waiting for reimbursement from the State before the check can be released.
Age
Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment
Over 60 days
Significant Improvement in DPW Revolver Payments in the Pipeline. Invoices in the Over 60 Days Categories Were Reduced by More Than 50%
Over 30 days
Information obtained from Quickbase (DPW Department) 5.1.2012 – 5.11.2012
5 10 1
4 4 6 4
3 0
3 2
3
34 33 23
9
46 41 38
19
0
10
20
30
40
50
Jan-12 Feb-12 Mar-12 Apr-12
Over 120
91-120
61-90
31-60
30
DPW Revolver: Aging of Invoices in the Pipeline by Period
Processing Stage <=30 31-60 61-90 91-120 Over 120 Total
PM to Approve 0
Fiscal to Receive Invoice 1 8 9
Department to Create Receiver 6 2 1 9
State to Send to Hancock 1 1
Grand Total 1 6 0 3 9 19
Reasons for Delay
Dispute with the vendor
Goods received at a later date / Services
were not rendered
Invoice missplaced / not processed timely
Contract being processed 3 9
Other** 6
Paid 5.10.2012
*6 Invoices in Other Category - All 6 are pending approval to use Revolver funding before they can be processed.
Note: 29 "Vendor Dispute" Invoices are not included in the aging above- same vendor, same project.
Working with Legal to resolve.
Age
Capital Projects Maintains Good Track Record of Paying Invoices on Time.
Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment
Information obtained from Quickbase (DPW Department) 5.1.2012 – 5.11.2012
Over 60
days
Over 30
days
24 21 13
7
7 9
7
3
1 4
3
3
1
2
1
4
1
36 35
25
15
0
10
20
30
40
Jan-12 Feb-12 Mar-12 Apr-12
Over 120
91-120
61-90
31-60
30
Capital City: Aging of Invoices in the Pipeline by Period
Processing Stage <=30 31-60 61-90 91-120 Over 120 Total
Department to Create Receiver 2 1 3
Finance to Receive from Department 1 1
Finance to Cut Check 5 1 6
Finance to Release Check 2 1 1 1 5
Grand Total 7 3 3 1 1 15
Reasons for Delay
Dispute with the vendor 2
Goods received at a later date / Services were not
rendered
Invoice was missplaced / not processed timely
Contract being processed
Other 2 1 1 1
Paid by 5.10.2012 1
Age
Capital Projects Maintains Good Track Record Paying Revolver Invoices on Time
Information obtained from Quickbase (Capital Projects Department ) 5.1.2012 – 5.11.2012
Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment
Over 60
days
Over 30
days
Processing Stage <=30 31-60 61-90 91-120 Over 120 Total
Department to Create Receiver 1 1
Finance to Receive from Department 1 1
Finance to Send to State 1 1
State to Send to Hancock 7 1 8
Grand Total 8 1 0 0 2 11
Reasons for Delay
Dispute with the vendor 1 1
Goods received at a later date / Services were not
rendered
Invoice was missplaced / not processed timely
Contract being processed
Other 1
Paid by 5.10.2012
Age
16 15 17 8
8 2
5
1
2
2
4
0 1
3
2 1
2
33
21 24
11
05
10152025303540
Jan-12 Feb-12 Mar-12 Apr-12
Over 120
91-120
61-90
31-60
30
Capital Revolver: Aging of Invoices in the Pipeline by Period
Procurement Requisition
Contract Creation
and Routing
Contract
Processing
and Approval
Payment
Supplemental
Procurement
Evaluation Form Are you a city employee or a member of the public? On a scale 1-5, how useful was this meeting to you (1= least useful and 5= most useful)? What’s working? What’s not working?