Page 1: Reporting with Project 2007 Dharmesh Patel Project Server Engineer Microsoft.

Reporting with Project 2007

Dharmesh PatelProject Server EngineerMicrosoft

Page 2: Reporting with Project 2007 Dharmesh Patel Project Server Engineer Microsoft.

Projects Contain Lots of Data

Page 3: Reporting with Project 2007 Dharmesh Patel Project Server Engineer Microsoft.

Important Business Questions

Are my projects on track?Are my team members appropriately busy?What are our top issues and risks?What are our keystone projects?What are our billings by team member type?What is the billing forecast by month?

Page 4: Reporting with Project 2007 Dharmesh Patel Project Server Engineer Microsoft.

It is Your Job to Interpret and Present the Data to a Variety of Audiences

Page 5: Reporting with Project 2007 Dharmesh Patel Project Server Engineer Microsoft.

Project, alone, and paired with Excel and Visio can Help

Before you report Visual Reports

Page 6: Reporting with Project 2007 Dharmesh Patel Project Server Engineer Microsoft.

Before you report Visual Reports

Page 7: Reporting with Project 2007 Dharmesh Patel Project Server Engineer Microsoft.

Before you report

BaselinesStatus DateCustom Fields

Page 8: Reporting with Project 2007 Dharmesh Patel Project Server Engineer Microsoft.

Baselines

Page 9: Reporting with Project 2007 Dharmesh Patel Project Server Engineer Microsoft.

Baselines

Page 10: Reporting with Project 2007 Dharmesh Patel Project Server Engineer Microsoft.

Status Date

Page 11: Reporting with Project 2007 Dharmesh Patel Project Server Engineer Microsoft.

Status Date

Page 12: Reporting with Project 2007 Dharmesh Patel Project Server Engineer Microsoft.

Custom Fields

Page 13: Reporting with Project 2007 Dharmesh Patel Project Server Engineer Microsoft.

Before you report Visual Reports

Page 14: Reporting with Project 2007 Dharmesh Patel Project Server Engineer Microsoft.

Using Project to Report

FiltersOnly look at task/resources that meet certain criteria

GroupsGroup by different fields to see rollups

Styles and FormattingHighlight data that you want to be noticed

Copy PictureShare the project plan with others

Page 15: Reporting with Project 2007 Dharmesh Patel Project Server Engineer Microsoft.

Before you report

Visual Reports

Page 16: Reporting with Project 2007 Dharmesh Patel Project Server Engineer Microsoft.

Visual Reports

Allows you to easily create reports that are:

• Customizable• Professional looking• Provide live analysis of Project data

Easily?

• Use familiar Excel and Visio UI• Templates are provided

Page 17: Reporting with Project 2007 Dharmesh Patel Project Server Engineer Microsoft.

Visual Reports

Features:

• Create PivotTables and PivotCharts in Excel• Create PivotDiagrams in Visio• Save the Cube and Database for future use• Share templates

Requirements:

• Microsoft Office Excel 2003 or later• Microsoft Office Visio Professional 2007

Page 18: Reporting with Project 2007 Dharmesh Patel Project Server Engineer Microsoft.

How It Works

AccessDatabase

(.mdb)

Excel

Visio

Local OLAP Cube (.cub)

Page 19: Reporting with Project 2007 Dharmesh Patel Project Server Engineer Microsoft.

Dimensions – data you slice by

• Task Name, Is Critical?, Months

Measures – data that is rolled up

• Work, actual cost

Properties – Additional information that is available about dimensions. This data is not rolled up.

• Dates, % Complete, text fields

Dimensions, Measures, and Properties

Page 20: Reporting with Project 2007 Dharmesh Patel Project Server Engineer Microsoft.

What is a cube?

Chris Aston

Brad Sutton

Resources

Jan. Feb.

Work

180 hrs100 hrs

80 hrs

Phase1

Phase2

Tasks

50 hrs

30 hrs

60 hrs

40 hrs

TotalGroup:IW

Page 21: Reporting with Project 2007 Dharmesh Patel Project Server Engineer Microsoft.

Sample Report

Page 22: Reporting with Project 2007 Dharmesh Patel Project Server Engineer Microsoft.

Common Questions

Reporting in Project client versus Project serverI added a field to my report but I can’t find it.Who and how can these Reports be viewed?

Page 23: Reporting with Project 2007 Dharmesh Patel Project Server Engineer Microsoft.
Page 24: Reporting with Project 2007 Dharmesh Patel Project Server Engineer Microsoft.

Sharing Your Reports

As an ImageAs an interactive file

Page 25: Reporting with Project 2007 Dharmesh Patel Project Server Engineer Microsoft.

Before you report Visual Reports

Page 26: Reporting with Project 2007 Dharmesh Patel Project Server Engineer Microsoft.

Putting it All Together

What tasks are behind?

Which resources

are behind?

Do we have room

in the project plan for

additional work?

How has my schedule

changed over time?

Page 27: Reporting with Project 2007 Dharmesh Patel Project Server Engineer Microsoft.

Lets take it to the next level.......

Page 28: Reporting with Project 2007 Dharmesh Patel Project Server Engineer Microsoft.

Reporting TechnologiesMicrosoft Office Project ProfessionalProject Web Access - Project and Resource CenterProject Web Access - Data Analysis ViewsProject Portfolio Server ReportsMicrosoft Office Excel Client and ServerMicrosoft SQL Server Reporting Services

Report BuilderReport Designer

Microsoft Office SharePoint ServerMicrosoft Office PerformancePoint

…and hundreds of third party solutions

Page 29: Reporting with Project 2007 Dharmesh Patel Project Server Engineer Microsoft.

END USER TOOLS AND PERFORMANCE MANAGEMENT APPS

ExcelPerformancePoint

Server

BI PLATFORM

SQL Server Reporting Services

SQL Server Analysis Services

SQL Server DBMS

SQL Server Integration Services

SharePoint Server

DELIVERY

Reports Dashboards Excel Workbooks

AnalyticViews Scorecards Plans

End-to-End Business Intelligence Offering

Page 30: Reporting with Project 2007 Dharmesh Patel Project Server Engineer Microsoft.

Questions

Email: [email protected]

Thank You

Page 31: Reporting with Project 2007 Dharmesh Patel Project Server Engineer Microsoft.

© 2007 Microsoft Corporation. All rights reserved. Microsoft, Windows, Windows Vista and other product names are or may be registered trademarks and/or trademarks in the U.S.

and/or other countries. The information herein is for informational purposes only and represents the current view of Microsoft Corporation as of the date of this presentation. Because Microsoft must respond to changing market conditions, it should not be

interpreted to be a commitment on the part of Microsoft, and Microsoft cannot guarantee the accuracy of any information provided after the date of this presentation.

MICROSOFT MAKES NO WARRANTIES, EXPRESS, IMPLIED OR STATUTORY, AS TO THE INFORMATION IN THIS PRESENTATION.