Page 1: Reporting Tool P6 Visualizer

Reporting Tool P6 Visualizer

Marina Sominsky NASA Cost & Schedule Symposium, Aug. 14 2019

Page 2: Reporting Tool P6 Visualizer

Click to edit Master title styleBiography

• Industry / Company Employment - Cobec Consulting Inc. (2017 – Present)

- Kitchell (2008 – 2017)

- Freescale Semiconductor (2004-2007)

• Education / Certification - BS, Chemical Engineering, KU

- EIT, PMP, PS P

• Professional Experience - Sr. Consultant, Cobec, FAA TAMR program

• Something You Don’t Know About Me - Avid user of MOS (My Oracle Support)

2

Page 3: Reporting Tool P6 Visualizer

Click to Introduction

• Release 8.3 of Oracle® Primavera P6℠ in 2013 introduces P6 Visualizer℠.

• P6 Visualizer is a graphical reporting tool: - Gantt charts with Grid option

- Timescaled Logic Diagram (TSLD)

- Schedule Comparison (former Claim Digger)

• This overview is not exhaustive, but rathe r focuses on a few selected Visualizer features: - Stacked columns in Grid

- List of steps as a field in the activity table

- Zoomed area within existing timescale in TSLD

- Formatted bars and labels

3

Page 4: Reporting Tool P6 Visualizer

Introduction

• Layouts are created using

- P6 Visualizer with Primavera P6 Professional 18.8.2

- P6 database hosted in MS SQL Server 2014

- Sample P6 data for engineering and construction

• Also applicable to:

- Oracle Primavera EPPM

- Oracle P6 database

- SQLite P6 database

• P6 users can follow instructions in this presentatio n using P6 Visualizer release 16.1 and later

4

Page 5: Reporting Tool P6 Visualizer

Presentation Outline

• P6 Visualize r Overview - Launching & Access Options

- Feature s & Issues Resolved

• P6 Visualize r Layouts - Gant t ‘Activities with Steps and Notes’

- TSLD ‘Baseline Comparison’

- Schedule Comparison

• P6 Visualize r Print Options - XML & batch file samples

- List of steps as a field in the activity table

- Automation via Windows Task Scheduler

• Conclusio n

• Questions / Comments 5

Page 6: Reporting Tool P6 Visualizer

P6 Visualizer Overview

Launching & Access Options

Features & Issues Resolved

6

Page 7: Reporting Tool P6 Visualizer

Launchin g & Access Options

• Visualize r is a desktop application included as part of P6 installation.

• With release 15.1, P6 Administrators can contro l permissio n to Visualize r via Module Access:

• Launch fro m Start menu or via P6 Tools -> Visualizer.

7

Page 8: Reporting Tool P6 Visualizer

Launchin g & Access Options

• Click +

• Select layou t type

• Select proje ct

• Move i t to the right

• Click Next

8

Page 9: Reporting Tool P6 Visualizer

Launchin g & Access Options

• Type name

• Click Draw

9

Page 10: Reporting Tool P6 Visualizer

Features

• Oracle Learning Library (OLL) contains training

content for Visualizer: https://oracle.com/goto/oll

10

Page 11: Reporting Tool P6 Visualizer

Issues Resolved

• All subsequent patch sets include the fixes

from prior patch sets.

• These four bugs have been corrected across

several releases of P6:

11

Page 12: Reporting Tool P6 Visualizer

P6 Visualizer Layouts

Gantt ‘Activities with Steps and Notes’

TSLD ‘Two Week Look Ahead’

Schedule Comparison

12

Page 13: Reporting Tool P6 Visualizer

‘Activitie s wit h Step s and Notes’

• Filters are applied to activities (steps/notes only)

• Activities filtered out are show n as a reference

• Custom formatting is applied to labels

• Timescale is customized

• Grid columns are stacked

13

Page 14: Reporting Tool P6 Visualizer

‘Activ ities with Steps and Notes’

• Options -> Filters tab - Custom filter ‘Activities with Steps’

14

Page 15: Reporting Tool P6 Visualizer

‘Activ ities with Steps and Notes’

• Options -> Filters tab - Custom filter ‘Activities with Notes’

15

Page 16: Reporting Tool P6 Visualizer

‘Activ ities with Steps and Notes’

• Option s -> Lines tab -> Connection s sub-tab - ‘Show filter ed activities ’ section

16

Page 17: Reporting Tool P6 Visualizer

‘Activ ities with Steps and Notes’

• Option s -> Bars & Labels tab - ‘Global Labels’ in Available Bars section

- Add Anticipated Problems under Notebook Topics

grouping

- Set label’ s positio n and formatting (as shown) 17

Page 18: Reporting Tool P6 Visualizer

‘Activ ities with Steps and Notes’

• Option s -> Timescale tab

- Defin e Start / Finish i n General sectio n (as shown)

- Set ‘Date Interval’ in Backgroun d section 18

Page 19: Reporting Tool P6 Visualizer

‘Activ ities with Steps and Notes’

• Option s -> Chart & Grid t ab -> Content sub-tab - Ad d an d stack fields

- Format fields

• Save & Draw!

19

Page 20: Reporting Tool P6 Visualizer

‘Activ ities with Steps and Notes’

20

Page 21: Reporting Tool P6 Visualizer

‘Tw o Week Look Ahead’

• Filter is applied to activities (2 weeks ahead)

• Zoomed area within timescale is displayed

• Activities are sorted in specified order

• Custom formatting is applied to labels and bars 21

Page 22: Reporting Tool P6 Visualizer

‘Tw o Week Look Ahead’

• Option s -> Page Setup tab -> Page sub-tab Scale to 1 ‘Letter’ sized sheet -

22

Page 23: Reporting Tool P6 Visualizer

‘Tw o Week Look Ahead’

• Option s -> Page Setup tab -> Spacing sub-tab - Set Line Spacing to ‘ 5’ t o maximize vertical spac e

on the diagram 23

Page 24: Reporting Tool P6 Visualizer

‘Tw o Week Look Ahead’

• Option s -> Filters tab Cust om filter ‘2 Weeks Ahead’ -

24

Page 25: Reporting Tool P6 Visualizer

‘Tw o Week Look Ahead’

• Option s -> Group & Sort tab -> Sort sub-tab - Specify th e ord er of activities display ed (as shown)

25

Page 26: Reporting Tool P6 Visualizer

‘Tw o Week Look Ahead’

• Option s -> Lines tab -> Connection s sub-tab

- ‘Show connecti on details for all visible activities’ 26

Page 27: Reporting Tool P6 Visualizer

‘Tw o Week Look Ahead’

• Options -> Bars & Labels tab -> Bars View - New bar with type ‘Project Baseline’ in Properties section

- Set Row to ‘2’ in Arrangement section

- Set Height to ‘5’ in Shape section (not shown)

- Customize formatting in Fill section (as shown) 27

Page 28: Reporting Tool P6 Visualizer

‘Tw o Week Look Ahead’

• Options -> Bars & Labels tab -> Labels View

- Set Height to ‘15’ for ‘Critical Remaining Work’ bar

- Extend Activity Name’s Maximum Label Width to ‘175’

- Add and format Remaining Duration label (as shown) 28

Page 29: Reporting Tool P6 Visualizer

‘Tw o Week Look Ahead’

• Options -> Timescale tab -> Primary sub-tab

- Define Start / Finish in General section (as shown )

- Uncheck Top box for Date Interval ‘Week’

- Click + to the right of the Primary sub-tab to create Zoo m Area 1

29

Page 30: Reporting Tool P6 Visualizer

Click to edit Master title style‘Tw o Week Look Ahead’

• Options -> Timescale tab -> Zoom Area 1 sub-tab - Define Start / Finish in General section (as shown )

- Set Background Color to ‘grey’ in Styling section

- Set Row 1 and Row 2 in Background section (as shown)

- Save & Draw! 30

Page 31: Reporting Tool P6 Visualizer

‘Tw o Week Look Ahead’

31

Page 32: Reporting Tool P6 Visualizer

Click to edit Master title styleSchedule Comparison

• Dates comparison (report fragment) 32

Page 33: Reporting Tool P6 Visualizer

Click to edit Master title styleSchedule Comparison

• Options -> Project tab - Select Revised Project

- Select Original Project or Baseline

- Click Add 33

Page 34: Reporting Tool P6 Visualizer

Click to edit Master title styleSchedule Comparison

• Option s -> General tab - Check ‘Grou p report b y activity’ i n Grouping section

- Select HTML optio n in Send Report To section 34

Page 35: Reporting Tool P6 Visualizer

Schedule Comparison

• Option s -> Advanced tab - Check desired parameters to be compared

• Save & Draw! 35

Page 36: Reporting Tool P6 Visualizer

Schedule Comparison

36

Page 37: Reporting Tool P6 Visualizer

P6 Visualizer Print Options

Setup Required

Considerations

37

Page 38: Reporting Tool P6 Visualizer

Click to edit Master title stylePrint Options : Setu p Required

• TSLD and Gantt reports can be automated via Windows® Task Scheduler

• Instructions are in Visualizer Help under ‘Working wit h P6 Visualizer Reports’ section: - https://docs.oracle.com/cd/E90748_01/visualizer_help/en

_US/index.htm

• There are three setup steps involved: - Actions.xml file – specifies format (electronic or physical

printout), as well as report(s) and project(s) for which the report is automated;

- Batch file – contains a series of commands to be executed;

- Task Scheduler service – automates Visualizer report to r un one time, daily, weekly or monthly.

38

Page 39: Reporting Tool P6 Visualizer

Click to edit Master title stylePrint Options : Setu p Required

• Actions.xml file sample

- Notepad saved as .xml

- Highlighted values vary with configuration

39

Page 40: Reporting Tool P6 Visualizer

Click to edit Master title stylePrint Options : Setu p Required

• Batch file sample

- Notepad saved as .bat

- Highlighted values vary with configuration

- Entire string that starts with Primavera.Visualizer.exe is

entered on one line (line #s are for reference only)

- If the process runs successfully, log message

‘Application Exits with error 0’ is returned

1

2

3

40

Page 41: Reporting Tool P6 Visualizer

Click to edit Master title stylePrint Options : Setu p Required

• Task Scheduler Service (installed with Microsoft operating systems) - Launch via Start menu

- Under Action, select Create Task

- Under Create Task, General tab • Check box Run with highest privileges

• Configure for appropriate Windows OS

- Under Create Task, Trigger tab • Se t Trigger tab to desired frequency / day / time

• Click Enabled

- Under Create Task, Actions tab • In th e Action List, selec t Start a program

• Brows e to the location of .bat file from st ep two

- Under Create Task, Conditions tab • Selec t Wake the compute r t o run this task

41

Page 42: Reporting Tool P6 Visualizer

Print Options : Considerations

• Considerations

- Check that report name and project ID referenc ed

i n st ep one are accurate an d exist i n P6 database

- Avoi d using special characters wh en naming P6

Visualiz er repor t, suc h as:

• Divide “/”

• Ampersand “&”

Incorrect report name: ‘Activities w/Steps & Notes’

Correct report name: ‘Activities with Steps and Notes’

• Verif y ‘XPS Writer and Viewer’ applicati on is

install ed on the computer with automat ed

reports. 42

Page 43: Reporting Tool P6 Visualizer

43

Conclusion

Page 44: Reporting Tool P6 Visualizer

Conclusion

• Visualize r is already at P6 Users’ disposal:

- Get familia r with i t, using test data loaded into

database.

• Automating Visualize r reports is a smal l st ep

tha t can have a significant impact o n

improving communicatio n among proj ect

stakeholders .

• Use thi s presentation as a first step in starting

to utilize Visualizer on regular basis.

44

Page 45: Reporting Tool P6 Visualizer

45

QUESTIONS/COMMENTS?

NASA Cost & Schedule Symposium, Aug. 14 2019

Page 46: Reporting Tool P6 Visualizer

46

Reporting Tool

P6 Visualizer

Marina Sominsky