    SUMMER INTERNSHIP REPORT

    A STUDY OF: CUSTOMER SATISFACTION IN PROJECT BUSINESS

    Submitted by

    Shefali AggarwalA0101913102

    MBA Class of 2015

    Under the Supervision of

    Dr. Shalini TrivediAssistant Professor

    Department of Economics

    In Partial Fulfillment of the Requirements for the Degree ofMaster of Business Administration

    AMITY BUSINESS SCHOOL

    AMITY UNIVERSITY UTTAR PRADESH

    SECTOR 125, NOIDA - 201303, UTTAR PRADESH, INDIA

  • 8/11/2019 Report on Siemens Project Managemenmt

    2/75

    ii

    DECLARATION

    The title of Summer internship is Astudy of: customer satisfaction in project business.

    I declare that (a) the work presented for assessment in this Summer Internship is my original

    work, that it has not previously been presented for any other assessment and that my debts (for

    words, data, arguments and ideas) have been appropriately acknowledged; (b) work conforms to

    the guidelines laid by the University, and (c) Plagiarism for this report has been checked using

    Turnitin software and is 7 %. The summary of report is attached along with for reference.

    Date: 30-07-2014 Shefali Aggarwal

    A0101913102

    MBAGEN (Class of 2015)

  • 8/11/2019 Report on Siemens Project Managemenmt

    3/75

    iii

    CERTIFICATE

    This is to certify that Shefali Aggarwalstudent of Masters of Business Administration (Gen) at

    Amity Business School, Amity University Uttar Pradesh has completed the Summer Internship

    on A study of: customer satisfaction in project business, in Partial Fulfilment of the

    Requirements for the Degree of Master of Business Administrationgeneral under my guidance.

    The report has been checked for the plagiarism and it is acceptable.

    Dr. Shalini Trivedi

    Assistant Professor

    Department of Economics

  • 8/11/2019 Report on Siemens Project Managemenmt

    4/75

    iv

    ACKNOWLEDGEMENT

    I would like to express my deepest gratitude to my mentor Dr. Shalini Trivedi, Assistant

    Professor, Amity University for guiding me throughout my summer internship. she took time out

    of her highly busy schedules to help me during my summer internship.

    I would also like to thank my program leader Ms. Teena Bagga and the entire team and staff of

    Amity Business School, Amity University for their kind support.

    I would like to express my heartiest thanks to my supervisor, Mr. Rajnish Gupta (Senior

    Executive, Business Administration). He helped me at every step of my internship to provide mea great environment for learning, conducive to skill development and knowledge sharing and

    having a great industrial experience.

    I would also like to take the opportunity to thank Siemens Ltd., New Delhi, for making me a part

    of the Siemens family for this short period of 8 weeks.

    Last but not the least I would like to thank Siemens Staff and my fellow interns at New Delhi, for

    their continuous cooperation that helped me in successful completion of this training.

  • 8/11/2019 Report on Siemens Project Managemenmt

    5/75

    v

    Table of Contents

    ACKNOWLEDGEMENT ............................................................................................................. iv

    ABSTRACT .................................................................................................................................. vii

    CHAPTER 1 ................................................................................................................................... 1

    1.1. Introduction: ......................................................................................................................... 1

    1.1.1 PROJECT MANAGEMENT: ........................................................................................ 1

    CHAPTER 2 ................................................................................................................................... 6

    2.1. COMPANY PROFILE- SIEMENS LTD. ........................................................................... 6

    2.1.1. VALUES & VISION : ................................................................................................... 6

    2.1.2 SIEMENS ORGANIZATIONAL OVERVIEW: ........................................................... 7

    2.1.3 SIEMENSI&L OPERATIONS OVERVIEW: ............................................................. 10

    CHAPTER 3 ................................................................................................................................. 14

    2.1. Literature Review: .............................................................................................................. 14

    CHAPTER 3 ................................................................................................................................. 18

    3.1. Research Design: ................................................................................................................ 18

    3.2 Objectives: ....................................................................................................................... 18

    3.3 Research Design: ............................................................................................................. 19

    3.4 Participants: ..................................................................................................................... 20

    3.5 Data Collection: ............................................................................................................... 20

    3.6 Instruments used: ............................................................................................................. 20

    3.7 Procedures: ...................................................................................................................... 20

    CHAPTER 4 ................................................................................................................................. 22

    Data Analysis: ........................................................................................................................... 22

    4.1 Various Phases of Project:................................................................................................... 22

    4.1.1 Project Sales: ................................................................................................................ 22

  • 8/11/2019 Report on Siemens Project Managemenmt

    6/75

    vi

    4.1.2 Project Execution:......................................................................................................... 29

    4.1.3. Warranty: ..................................................................................................................... 40

    4.2. PRODUCT OPERATIONS MANAGEMENT IN RESPONSE TO A SPECIFIC

    ENQUIRY: ................................................................................................................................ 41

    4.2.1. Marketing - Problem, Solution and Client interaction: ............................................... 41

    4.2.2. Design: ......................................................................................................................... 44

    4.3 PRODUCT OPERATIONS MANAGEMENT IN RESPONSE TO A GENERAL

    ENQUIRY: ............................................................................................................................ 46

    4.3.5. Bidding: ....................................................................................................................... 49

    4.3.6. Tender evaluation and decision: .................................................................................. 49

    4.3.7. Design: ......................................................................................................................... 50

    4.3.8. Sales: ............................................................................................................................ 50

    4.3.9. Installation: .................................................................................................................. 51

    4.3.10. Maintenance and Service under warranty: ................................................................ 51

    4.3.11. Post-Warranty Maintenance and Service: ................................................................. 51

    CHAPTER 5 ................................................................................................................................. 60

    5.1. Conclusion and Recommendations: ................................................................................... 60

    REFERENCES: ............................................................................................................................ 62

  • 8/11/2019 Report on Siemens Project Managemenmt

    7/75

    vii

    ABSTRACT

    Project management is the process of planning and organizing an organizations resources in

    order to move a specific task, event or duty towards completion. A project manager will help

    define the goals and objectives of the project, determine when the various project components

    are to be completed and by whom, and create quality control checks to ensure that completed

    components meet a certain standard. Customer satisfaction can be seen either as a goal or as a

    measurement tool in the Project business. This paper examines the performance of Siemens

    Limited, I&L division measured according to the degree of customer satisfaction as perceived by

    customers themselves. The purpose of the study is to explore the clients main

    satisfaction/dissatisfaction factors. The data is in the form of surveys gathered from theCompanys client. The views of customer with respect to the performance of company are

    measured in light of various factors such as quality assurance and handover, environment and

    safety at work, co-operation, personnel, site supervision and subcontracting. Several implications

    regarding customer satisfaction were drawn from the findings of the research. Customers were

    typically satisfied with the contractors abilities to co-operate and the skills of contractors

    workers and supervisors. In contrast, lower satisfaction could be found for the items related to

    quality assurance and handover procedures and material. In generally, the quality of contracted

    work and of overall service level has an effect on general satisfaction.

    Siemens is a global company headquartered in Munich, Germany. It primarily deals in Four

    Sectors- Energy, Healthcare, Industry and Infrastructure & Cities. However, this shall be

    discussed in more details in the pages that follow.

    The report discusses about the various milestones a project undergoes and the subsequent tasks

    and duties performed by Siemens for the unhindered execution of the same.

    The report is the summary of my learning experience at Siemens. During my internship, I learnt

    about using SAP software for generating goods receipt note (GRN), for making purchase orders,

    etc. I was taught about the process of Vendor Management and the management information

    system used by Siemens.

  • 8/11/2019 Report on Siemens Project Managemenmt

    8/75

    1

    CHAPTER 1

    1.1. Introduction:

    1.1.1 Project Management:

    The project management at Siemens supports the continuous improvement of Project

    Management processes, which can in turn help the organization to strive towards business

    excellence. It relates to the successful delivery of a project with a goal, scope, deadline,

    budget, and other constraints. These operations work to align resources, manage issues and

    risks, and basically coordinate all of the various elements necessary to complete the project

    on time and under budget while meeting the defined goals and objectives. Moreover, a

    project at Siemens can also be defined as managing a cluster of products. Asthey relate to

    products, projects can be undertaken to build a product that constitutes a varied cluster of

    products and sub-parts that can themselves either be of Siemens or some other company.

    It has the following objectives:

    1. Harmonization and standardization of processes, methodologies and tools.

    2. Offering a platform for best practice exchange and transfer.

    3. Defining minimum requirements for project management.

    4. Providing a Career Model to support the development of Project Managers.

    5. Defining tools and systems for performance measurement and successful projects.

    6. Implementing assessments to measure the maturity of processes and areas to

    improve.

    Project Management at Siemens follows a generic Project Phase model. The model

    demarcates different phases and milestones that are crucial in the successful completion of

    the project along with any further detailing necessary. The individual process operations are

  • 8/11/2019 Report on Siemens Project Managemenmt

    9/75

    2

    staggered in a practical fashion, on the basis of the integrated project schedule. Hence this

    linear process approach also makes sense for projects business. To record the completion of a

    process step, each milestone is accorded mandatory results. This provides the basis for

    introducing Key Performance Indicators, allowing the quality of project processing as well as

    on-time performance to be measured.

    Fig 1.1: Project Sales Phase Model

    Image Source: (Examples of the Phases of Project Management Model)

    The project phase model is much more structured, methodological, demarcated and

    hierarchical than the steps of product operations in terms of aligning its various phases,

    especially when compared to product operations with tendering. Project Management at

    Siemens defines and integrates the processes involved in project handling in a uniform

    manner. Moreover, it has a swift and smooth handover in between the phases of the process.

    Siemens uses an internal tool known as Limits of Authority for the requisite approval of

    authorities regarding the terms and conditions of the project. It also uses tools like SAP,

    Nexus, Quality Gate etc. for the accomplishment of the project.

    Project Management at Siemens is defined for 3 types of projects:

  • 8/11/2019 Report on Siemens Project Managemenmt

    10/75

    3

    1. Plant and Solution projects: These are the major projects that require many stages

    such detailed planning, design, manufacture and sourcing, installation,

    commissioning etc. for major plant and solution project that Siemens has to build

    for its clients. Since these are Siemens flagship projects that can completely

    enunciate the sophisticated and complex PM operations at Siemens, the phases

    described below relate to plant and solution projects.

    2.

    Service projects: These are the projects where Siemens has to perform some kind

    of service so as to ramp up the operations of any project that is already functional

    at a clients place. The PM phases for service projects are pretty similar to those

    of the plant and solution projects, except for that dispatch, construction and

    commissioning of the project, are replaced with transition, transformation and

    handover phases.

    3. Small Projects: These are very small projects that are performed with limited

    resources and within very small time periods. In this PM, most of the phases of

    Plant and Solution projects are clubbed together to form a single phase with a

    single milestone.

    All the projects start in a similar fashion, however, the Small Projects and Plant Solution

    projects end at PM700 (End of Warranty) while the Service Projects end at PM1000 (End of

    Obligations).

    Fig 1.2: Various Phases of a Project

    Image source: (5 Basic Phases of Project Management)

  • 8/11/2019 Report on Siemens Project Managemenmt

    11/75

    4

    The INITIATION Phase:

    This process is primarily about identification of an opportunity (project). Opportunities are

    made available via news and media. This phase determines about the nature and scope of the

    project. It is essential to do this process very carefully for the successful execution andcompletion of the project. It is very important to know and understand about the project plus

    about the environment that surrounds the business before the project is carried out.

    The PLANNING Phase:

    This process mainly deals with the planning related to the project. After the initiation

    process, full planning is done regarding the project that is taken up. Also planning related to

    the best alternative course of action that should be taken is also decided. The main planning

    regarding time, cost and resources needs to be done. This is done to effectively manage risk

    during project execution. For the successful completion of the project, to achieve the goals

    and to avoid any failure, the project should be appropriately planned. Siemens uses a tool

    known as Limits Of Authority (LoA) which is the internal approval of authorities for the

    external processes.

    The EXECUTION Phase:

    Execution process involves the processes and tasks that are taken up for the completion of

    the work defined in the project management plan for accomplishing the project's

    requirements. Execution process involves coordination of people and other resources, as well

    as performing the activities of the project in accordance with the project management plan.

    For this phase Siemens uses Vendor Management and various other software to execute it in

    a well-organized and less chaotic manner.

    The CONTROLLING Phase:

    Monitoring and controlling involves measuring and observing the execution of the project.

    This is done to identify the problems that come and taking the corrective actions at an

    appropriate time to control the execution of the project. Any variances from the planned

    actions are measured regularly. For Phase in particular Siemens uses Management

    Information System (MIS).

  • 8/11/2019 Report on Siemens Project Managemenmt

    12/75

    5

    The CLOSING Phase:

    Ending the project and formally accepting it, is done under the closing process. Each project

    is to be completed within a scheduled time as per the defined contract terms and conditions.

  • 8/11/2019 Report on Siemens Project Managemenmt

    13/75

    6

    CHAPTER 2

    2.1. Company Profile- Siemens Ltd.

    Siemens Ltd. is a part of Siemens AG, A German multinational conglomerate company

    headquartered in Munich, Germany. It is a leading powerhouse in electronics and electrical

    engineering with a business volume aggregating about Rs.12000 Cr. It operates in the core

    business areas of Industry, Infrastructure & Cities, Energy and Healthcare.

    Siemens which originally founded on 12 October 1847 by Werner von Siemens placed its

    roots in India in 1867, when Werner von Siemens personally supervised the laying of the first

    telegraph line between London and Calcutta. The line, stretching for 11,000 km, was one of

    the fastest and amost reliable telegraph links in the world, and passed through four different

    sovereign territories and the Black Sea. The line was completed in 1870, overcoming

    financial, technical and logistical challenges. A message could be transmitted in 28 minutes

    instead of the 30 days that mail took between India and England.

    Siemens established its first office in 1922 in Mumbai and Kolkata. Its first assembly plant

    began operations in 1956. Within the space of a few decades the company grew from a tiny

    workshop under an arch of the Mahalaxmi Bridge in Mumbai, into Siemens Ltd. one of

    India's largest companies in electrical engineering and electronics. Today, the company has a

    sales and service network that spans the country, 21 manufacturing plants, eight centers of

    competence and 10 R&D centers.

    2.1.1. Values & Vision :

    We are faced with challenges of unknown dimensions due to demographic changes,

    urbanization, climate change and globalization. The economic and financial crisis is

    aggravating these global challenges by changing the economic conditions very rapidly,

    deeply and continually. The change we are currently experiencing will go on and continually

    transform our world.

  • 8/11/2019 Report on Siemens Project Managemenmt

    14/75

    7

    Against the background of these global changes, we are redefining the standard we have set

    ourselves and, as a result, our vision. Siemens the pioneer in

    Energy Efficiency.

    Industrial Productivity. Affordable and personalized healthcare.

    Intelligent infrastructure solutions.

    Values: We say it we mean it

    Responsible: Committed to ethical and responsible actions.

    Excellent: Achieving high performance and excellent results.

    Innovative: Being innovative to create sustainable value.

    2.1.2 Siemens Organizational Overview:

    Siemens Limited is divided into four business sectors that are each subdivided into divisions,

    business units and business segments. The structure is detailed as:

    Fig 2.1: Siemens Organizational Structure

    Image source: (Siemens. Siemens Ltd., 30 Jun. 2013)

    2.1.2.1. Energy:

  • 8/11/2019 Report on Siemens Project Managemenmt

    15/75

    8

    The energy sector at Siemens provides customers with products, services and

    solutions in the areas of power generation, power transmission, power distribution

    and oil and gas production. The energy sector is subdivided into:

    a. Energy Service

    b. Fossil Power Generation

    c. Oil & Gas

    d.

    Power Transmission

    e. Wind Power

    2.1.2.2 Industry Sector:

    The industry sector at Siemens helps industry and infrastructure customers to increase

    their economic and environmental competitiveness. It is again subdivided into:

    f. Drive Industrial Automation

    g. Technologies

    h. Customer Services

    i. Metals Technology

    2.1.2.3. Healthcare sector:

    The healthcare sector, as the name suggests caters to providing products and solutions

    for a variety of healthcare services. These services can range from prevention, early

    detection to diagnosis, treatment and aftercare. It is subdivided into:

    j. Clinical products

    k. Imaging and therapy

    l. Diagnosis

    m. Manufacturing units

    2.1.2.4. Infrastructure and Cities:

  • 8/11/2019 Report on Siemens Project Managemenmt

    16/75

    9

    The infrastructure and Cities (I&C) sector at Siemens caters to clients for sustainable

    urban development, by providing them expertise products and solutions for the same.

    The I&C sector is divided into the following:

    a.

    Rail Systems

    b. Low & Medium Voltage

    c. Smart Grid

    d. Building Technologies

    e. Osram (Lighting)

    f. Mobility & Logistics: The division provides hardware, software and service

    bundles for the optimization and automation of traffic and transport networks onroad and rail as well as for airports and harbors. The Division is in charge of all

    the businesses of mobility and logistics management for people and goods. These

    include rail automation, infrastructure logistics, and intelligent traffic and

    transportation systems along with all the electro-mobility infrastructure activities.

    The Division has been further divided into 3 Business Units (BU):

    i. Rail Automation (RA)

    ii.

    Complete Transportation & e-vehicle infrastructure (CTE)

    iii. Infrastructure & Logistics (IL): The business unit Infrastructure &

    Logistics (IL) offers solutions for reliable transport of goods and

    information. It provides comprehensive single-source solutions, ranging

    from engineering, mechatronics and IT systems to operation and

    maintenance services. The major business areas (segments) of IL are:

    1. Logistics and Airport Solutions

    2. Ports Logistics

    3.

    Customer Services

    4. Logistics IT

  • 8/11/2019 Report on Siemens Project Managemenmt

    17/75

    10

    5. Postal Solutions:It includes the automated sorting mechanism for

    the postal system.

    2.1.3 Siemens I&L Operations Overview:

    The operations at Siemens Infrastructure and Logistics division are demarcated into the

    following two types:

    2.1.3.1 Project Management:

    Project operations relates to the successful delivery of a project a one-time

    endeavor with a goal, scope, deadline, budget, and other constraints. A project

    manager who oversees these operations will work to align resources, manage issues

    and risks, and basically coordinate all of the various elements necessary to complete

    the project. Moreover, a project manager ensures that the project is delivered on time

    and under budget while meeting the defined goals and objectives.

    A project at Siemens may also be defined as managing a cluster of products. As

    they relate to products, projects can be undertaken to build a product, to add new

    features to a product, to create new versions or extensions of a product, to install a

    product or to service a product. When the project is complete, the project manager

    will usually move to a new project, which may be related to a different product.

    2.1.3.2 Product Operations Management:

    Product operations management at Siemens takes care of the entire process of a

    product from the beginning till the end, where a product is marketed, designed and/or

    refined and finally sold to the client.

    The product operations mainly pertain to the products that are entirely of Siemens, i.e.

    the products that are designed, technologically developed and manufactured by

    Siemens and constitute of Siemens sub-parts. Thus, the product operations can also be

    said to be related tosmallSiemens products. This is because the development, design,

    manufacture and implementation of big products sold by Siemens can take much time

    and the products would constitute of many sub-parts both from Siemens and from

    other companies. As a result, the operations for each would constitute an entirely new

    project, and would come under the realm of Project Operations. Thus, as we will see

  • 8/11/2019 Report on Siemens Project Managemenmt

    18/75

    11

    later, the design phase and installation and service phase needed in theproduct

    operations do not necessarily take much time because of the small products.

    The scope of product operations begins once the project to manufacture/implement

    the product is complete. A product manager is at the helm of a Siemens productoperations and his responsibility is to oversee the overall and ongoing success of a

    product. A product manager manages the product through the entire lifecycle. Other

    projects related to the product may be initiated, with the product manager being the

    one constant stream throughout, defining the project goals and guiding the team to

    accomplish the business objectives that have been defined.

    Fig 2.2: Project Life Cycle at Siemens

    Image Source: (Siemens. Siemens Ltd., 30 Jun. 2013)

  • 8/11/2019 Report on Siemens Project Managemenmt

    19/75

    12

    The product at Siemens can be one of the following types:

    Standard:

    A standard product is a pre-existing product at Siemens where no changes are

    made before offering it to the customer. Thus, a standard product always comes

    with a well-defined set of physical design features, specifications, controls and

    performance guidelines that cannot be altered as per the requirements of the

    customer. These design, requirements and guidelines are documented in a product

    catalogue that is offered to the customer as a potential solution to their

    requirements. Thus this type of a product is referred to as a Direct Sell to the

    customer by Siemens since it is sold without any alterations.

    The standard product may sometimes be readily available in the companyinventory. Otherwise it has to be manufactured once the customer places an order

    for the product. Moreover, even though no changes to the design and functionality

    of the product are made, the price of the product may not be standard as it may

    vary according to different criteria across regions such as geographical locations,

    rules and tariffs, the client profile, contacts and previous relations with Siemens

    etc. among others.

    Customized:

    A customized product at Siemens is the one where minor modifications are made

    to the design, functionality or physical specifications etc. of a pre-existing

    Siemens base product so as to make it suited for the demands and problems of the

    specific customer. Thus, a design phase is added during the operations

    management of this type of products so as to make the desired modifications as

    per the requirements of the customer.

    i.

    Specially developed:

    A specially developed product at Siemens is a new product developed using pre-

    existing base parts, technology and expertise at Siemens to suit the specific needs

    of a particular customer. Along the same lines, specially developed products can

    also be drastically modified versions of a pre-existing Siemens base product. This

  • 8/11/2019 Report on Siemens Project Managemenmt

    20/75

    13

    type of product does not have any product catalogue or any other specifications.

    Thus, a design phase is required in these products as well to plan/design the

    product using just a problem description, previous experiences with similar

    products and a vision of a solution that has been developed by Siemens in

    conjunction with the customer. Moreover, this type of products requires a greater

    amount of time spent on the design phase as compared to the customized products

    because the product has to be built/implemented from scratch.

  • 8/11/2019 Report on Siemens Project Managemenmt

    21/75

    14

    CHAPTER 3

    2.1. Literature Review:

    Customer satisfaction has become one of the key issues for companies in their efforts to

    improve quality in the competitive marketplace. Customer satisfaction is considered to affect

    customer retention and, therefore, profitability and competitiveness (Sullivan & Andreson,

    1993). According to (Jones & Sasser, 1995), complete customer satisfaction is the key to

    securing customer loyalty and generating superior long-term financial performance. It is also

    apparent that high customer satisfaction leads to the strengthening of the relationship

    between a customer and a company, and this deep sense of collaboration has been found to

    be profitable (e.g. Storbacka et al. 1994).

    Accordingly, customer satisfaction is an important factor in the development of the

    construction process and the customer relationship. It is natural that managers in the project-

    based industry should be concerned about customer satisfaction because of its expected

    influence on future projects and word-of-mouth reputation. However, so far, customer

    satisfaction in the project-based industry is under-researched. For example, (Torbica & Stroh,

    2001) emphasize that the use of soft performance criteria, such as customer satisfaction, is

    at an early evolutionary stage in construction. In addition, the main focus on customer

    satisfaction approaches in the construction has been on house building.

    Up-to-date information about customer satisfaction is important for successful management

    of complex projects. The importance of customer satisfaction is emphasized in the case of

    project-based organizations, where a customer often plays an integral role in the project

    delivery process. Turner and Keegan (2001, p. 256) elegantly define project-based

    organization as an organization in which: the majority of products made or services supplied

    are against bespoke designs for customers According to (Winch, Usmani, & Edkins, 1998)

    the client organization can have a great deal of influence on project success. Information

    about sources customer satisfaction or dissatisfaction can be used to ensure that both project

    product and the delivery process meet customer expectations.

  • 8/11/2019 Report on Siemens Project Managemenmt

    22/75

  • 8/11/2019 Report on Siemens Project Managemenmt

    23/75

    16

    In accordance with (Kujala & Ahola, 2004), we define customer satisfaction measurement

    system to include entire process consisting of:

    Gathering information concerning customer satisfaction

    Assessing the validity and reliability of this information

    Using this information in decision-making processes

    This wider definition emphasizes the use of information. (Gronholdt, Martensen, &

    Kristensen, 2000) has demonstrated that there are significant challenges related to the use of

    customer satisfaction information in organizational decision making processes. A company

    must periodically measure customer satisfaction in order to learn how satisfied its customers

    are. (Torbica & Stroh, 2001) argue that, in construction, the extent of customer satisfaction is

    only known late in the project when most of the customers money has already been spent.

    When companies know which attributes of a service or product affect customer satisfaction,

    Their challenge is to modify their current offering in a way that would lead to maximum

    customer satisfaction. According to an earlier study, based on RALAs feedback data (Kujala

    & Ahola, 2004), factors of quality and co-operation have a strong effect on overall

    satisfaction. Therefore, these factors can be used as a basis for improving overall satisfaction.

    The study emphasises the fact that the contractors ability to co- operate can reduce the

    adverse impact of poor quality assurance in the completion stage. There also exists adependency between the quality of the overall service level and the quality of the contracted

    work.

    In order to measure customer satisfaction in construction, the main subjects must be

    identified. A customer may be defined as the owner of the project and the one that needs the

    constructed facility. In simple terms, the customer is the buyer of the product or service.

    (Chase & Bowen, 1991) describes the customer as a body that incorporates the interests of

    the buyer of construction services, prospective users and other interest groups. Ireland (1992)lists the potential customers that have expectations and requirements that affect the outcome

    of a project. This wider perspective on the customer includes: the co-contractors and

    partners, project director, project team members, contractors and subcontractors, vendors and

    suppliers, users of the product and services and society. It is also important to note that there

    are generally several persons involved in a buying decision.

  • 8/11/2019 Report on Siemens Project Managemenmt

    24/75

    17

    This buying centre includes all persons involved in the procurement of the service and

    consists of the following: decider, influencer, purchaser, gatekeeper and user. Customer

    satisfaction is affected by the roles of individual members of the buying centre in terms of

    interests and goals, the decision process and structures (Lin & Jones, 1997).

  • 8/11/2019 Report on Siemens Project Managemenmt

    25/75

    18

    CHAPTER 3

    3.1.Research Design:

    The process used to collect information and data for the purpose of making business decisions.

    Research can be one of the most interesting features of any degree course as it offers you a

    measure of control and autonomy over what you learn. It gives you an opportunity to confirm,

    clarify, pursue or even discover new aspects of a subject or topic you are interested in.

    The methodology may include publication research, interviews, surveys and other research

    techniques and could include both present and historical information. Research is not confined to

    science and technology only. There are vast areas of research in other disciplines such as

    languages, literature, history and sociology. Whatever might be the subject, research has to be an

    active, diligent and systematic process of inquiry in order to discover, interpret or revise facts,

    events, behaviours and theories. Applying the outcome of research for the refinement of

    knowledge in other subjects, or in enhancing the quality of human life also becomes a kind of

    research and development. Research is done with the help of study, experiment, observation,

    analysis, comparison and reasoning. Research is in fact ubiquitous. The methodologies are of

    two types which are basically used: Positivistic and Phenomenological.

    3.2 Objectives:

    3.2.1 Primary Objectives:

    To get a fair understanding of the entire Project Management process.

    To understand the important attributes related to the customer satisfaction in project

    business by analyzing the surveys and feedback from the customer.

    3.2.2Secondary Objectives:

  • 8/11/2019 Report on Siemens Project Managemenmt

    26/75

    19

    To get a holistic view of day to day activities performed by Mobility and Logistic

    division under Siemens AG

    To get familiarized with tools such as SAP (System Application and Product) and various

    other corporate tools.

    3.3 Research Design:

    While doing research, there are different types of research which are used. Hence in every

    research specific approach is used.

    Descriptive Research: Descriptive research can be used to identify and classify the

    elements or characteristics of the subject, e.g. number of days lost because of industrial

    action. Quantitative techniques are most often used to collect, analyze and summaries

    data.

    Analytical Research: Analytical research often extends the Descriptive approach to

    suggest or explain why or how something is happening, e.g. underlying causes of

    industrial action. An important feature of this type of research is in locating and

    identifying the different factors (or variables) involved.

    Predictive Research: The aim of Predictive research is to speculate intelligently on future

    possibilities, based on close analysis of available evidence of cause and effect, e.g.

    predicting when and where future industrial action might take place.

    The research design adopted in this research project is a mix of exploratory, analytical and

    descriptive research designs. The exploratory is the design in which the major emphasis is on

    gaining ideas and insights. It is conducted to provide a better understanding of the situation. It

    isnt design to come up with the final answers or decisions. Through this approach, researchers

    hope to produce hypothesis about what is going on in a situation. It was conducted by the use of

    exploratory techniques like brainstorming to generate a number of possible occasions and their

    reasons, choice of promotional offers that affect the preferences of consumers towards fast food

  • 8/11/2019 Report on Siemens Project Managemenmt

    27/75

    20

    industry. The objective of exploratory research is to identify key issues and key variables. For

    example, one outcome might be a better system of measurement for a specific variable.

    Descriptive research seeks to provide an accurate description of observations of a phenomena.

    The object of the collection of census data is to accurately describe basic information about anational population at a particular point in time. The objective of much descriptive research is to

    map the terrain of a specific phenomenon. A study of this type could start with questions such

    as: What similarities or contrasts exist between A and B, where A and B are different

    departments in the same organisation, different regional operations of the same firm, or different

    companies in the same industry. Such descriptive comparisons can produce useful insights and

    lead to hypothesis-formation.

    3.4 Participants:

    Sample size: -Sample size determination is the act of choosing the number of observations or

    replicates to include in a statistical sample. In this project the sample comprises of the senior

    executives, project manager, project supervisor and the top management of the company, which

    must be around 50. From this sample size we will try to conclude about the whole population.

    Sample Coverage: The sample coverage refers to the area covered by the target population. Inthis research project the target population is Siemens' client of RMGL project.

    3.5 Data Collection:

    Field survey:In this research project, I have scrutinized the primary data of the company which

    includes company's contracts, reports and customer feedback surveys..

    3.6 Instruments used:

    The research instrument used in this project is survey method.

    3.7 Procedures:

    Software used: Software is any set of machine readable instructions mostly in the form of a

    computer program that directs a computers processor to perform specific operations. The

  • 8/11/2019 Report on Siemens Project Managemenmt

    28/75

    21

    software used in this research is IBM SPSS Statistics v19. It is a software package used for

    statistical data analysis. (SPSS: Statistical Package for the Social Sciences). So I will fill all the

    details in SPSS software and analyse the different statistical data required for the project.

  • 8/11/2019 Report on Siemens Project Managemenmt

    29/75

    22

    CHAPTER 4

    Data Analysis:

    (Understanding how the project business is handled in Siemens Limited and how it helps in

    achieving customer satisfaction)

    4.1 Various Phases of Project:

    The basic project management model phases are as follows (Please note that the milestones

    for each phase are given in brackets):

    4.1.1 Project Sales:

    Project Sales is the same as marketing, bidding and sales phase as seen in product

    operations. Here the teams at Siemens start with lead management, followed by

    marketing, bidding and on until finally the bid decision has been made. If Siemens

    wins the bid, the process moves onto the project handover and official start of the

    project at Siemens.

    i. Pre-Acquisition (Milestone 1Acquisition Go/No Go decision):

    This is the pre-acquisition stage that starts with the Lead Management, i.e.

    generation of potential business clientele through marketing efforts at Siemens.

    Here again, as in product operations, the marketing teams at Siemens keep a

    watch on the latest trends in the market, the competitors and potential client

    organizations. The main idea is to find an existing demand or an opportunity that

    could create a potential sale for a Siemens product.

    The key steps taken by the marketing team at this stage are, first, to analyze

    inquiry/identify expected business that can be a potential lead for the acquisition.

    Second, they have to identify the internal business coordinators that could have an

    impact, either positive or negative, on the potential acquisition process.

    Third, the team at Siemens has now to create or adapt a business plan that would

    come in handy in the future steps of the process. Moreover, they have to assess

    the expected business that can be generated out of the potential acquisition.

  • 8/11/2019 Report on Siemens Project Managemenmt

    30/75

    23

    Fourth, the team has to generate information for the Siemens product portfolio

    process. This would be the tool necessary to present to and convince the clients

    for the acquisition. Fifth, the team has to record the pre-acquisition and project

    data that can be compared to the final data once the project is started or finished.

    Moreover, this data can be kept for future reference for similar projects.

    The few key deliverables that have to be completed so that the project can move

    on to the next phase are:

    1) Investment approval from the senior management for defined sales resources

    to be utilized for making the sale.

    2) An outline of the description about the customer, as well as the business

    context in which the client operates for whom the project is about to be

    undertaken.

    3) Identification of the expected order from the client, and an outline description

    of the same. This would detail the scope of supply for the order, as well as

    estimate the anticipated sales numbers from the client.

    Based on the above deliverables, an acquisition go/no go decision is taken for

    the project from the client, and is the milestone for this stage.

    ii.

    Project Acquisition (Milestone 2

    Bid Decision):If an acquisition go decision is taken, Siemens starts the process to acquire the

    project. The tender offered by the client is purchased so as to make a detailed

    study of its requirements. The tender document, along with all other supporting

    documentation is circulated to the bid team at Siemens.

    The bid team then, first, evaluates the expected business that can be generated out

    of the given project for Siemens after a careful estimate. This is required for

    taking a bid/no bid decision, and so the bid team requires a detailed look at the

    tender documents and specifications. Special attention has to be paid to the profit

    potential vs. risks and potential hindrances of the contract.

    Second, the bid team has to analyze and structure the customer requirements. For

    instance, a contract can sometimes contain terms that Siemens is not ready, or

  • 8/11/2019 Report on Siemens Project Managemenmt

    31/75

    24

    unable, to fulfill. Again, the bid team analyses the requirements to bid for the

    tender such as past audited accounts, accreditation, certifications, references for

    similar projects in the past etc.

    To check if Siemens can fulfill the requirements in the tender, a ComplianceMatrix is developed. This is just a simple matrix that can be used to verify the

    requirements of any regulation and finally summarizes, in a tabular form, to what

    we agree on the terms of the tender and to what we dont.

    Third, before making the bid/no bid decision, the team has to assess the

    customers business field. Thus they have to assess the strengths, weaknesses and

    competitive positioning w.r.t. Siemens. A SWOT (Strengths, Weaknesses,

    Opportunities and Threats) study can be done to achieve this.

    Fourth, the bid team has to develop a rough financing concept for the project.

    Fifth, the bid team has to define the bid scope and determine responsibilities for

    the upcoming bid estimation, generation, and marketing and approval process.

    Sixth, the team has to perform a rough risk assessment for the project that would

    include potential risks and their impact severity on the project.

    Seventh, the bid team finally has to obtain an approval for the bid budget.

    The key deliverables that have to defined and/or provided in this stage are:

    1) Investment approval from the senior management for defined bid preparation

    resources to be utilized in the bidding process.

    2) Details of the bidding process and requirements. This must include a clear

    definition of the resources required for the bid team, the project schedule and

    time in place for the bidding process and planned bid costs to be incurred

    during bidding.

    3)

    A detailed Compliance Matrix, to describe and tabulate the terms of tender

    with which Siemens can fulfill and which it cant.

    4) A supplemented Expected Order document.

    5) A documented customer inquiry.

  • 8/11/2019 Report on Siemens Project Managemenmt

    32/75

    25

    6) Analysis of context in which the clients business is operating. This is very

    important to understand the client, and hence a thorough SWOT analysis

    has to be conducted. SWOT analysis is a structured planning method used to

    evaluate the Strengths, Weaknesses, Opportunities and Threats involved in

    the project that are favorable and unfavorable to achieving that objective.

    7) An analysis of the planned project/service share and volume involved.

    8)

    A rough risk estimate for undertaking the project.

    9) A rough cost estimate in undertaking the project.

    10)Analysis of expected profit that could be generated from this project.

    At the end of this phase, the bid team at Siemens has to come up with a

    Bid/No bid decision.

    iii. Bid Preparation (Milestone 3Bid Approval):

    If bid decision is taken, the team starts the bid preparation phase. During this

    phase, Siemens has to prepare a quote for the price to be bid for the project. Thus,

    a bid project is set up in this phase, and then subsequently the team sets up and

    completes different bid parts individually. The price to be quoted by Siemens is

    an estimate achieved by detailed analysis and documentation of the total price

    expected to be incurred for the product including the additional design phase. This

    price includes the estimates for everything ranging from the costs of expected

    man-hours to the price lists of parts, materials and other costs involved. These

    estimates are provided by Siemens based on its previous technical expertise in the

    field.

    At least 10% of the design is completed is completed in this phase. This is to

    show our interest before the clients, and to have a strong base for our pre-bid

    negotiations, our estimates for the price quoted on the bid and our expected ROI

    from the project.

    Pre-bid meetings are held for different purposes before Siemens makes the final

    bid/no bid decision. First, they are used for clarification about the terms and

    requirements placed forth by the buyer in the tender without disclosing the price

    estimate of Siemens. Moreover, they are used for negotiations between the buyer

  • 8/11/2019 Report on Siemens Project Managemenmt

    33/75

    26

    and Siemens. The negotiations can be about different aspects of the tender, such

    as the value, terms, conditions, pre-requisites etc. Additionally, a pre-bid meeting

    can be used by the buyer to gauge the expression of interest from the supplier.

    Once the tender document, the bid, and the additional documentationrequirements have been completed by the bid team, they go for an approval from

    all the organizations involved in the process. Once all the approvals have been

    generated, all documentation is forwarded for approval again from the Siemens

    management. The bid approval thus received would ultimately lead to the creation

    of an LOA or a Letter of Agreement.

    The key deliverables in this phase are:

    1)

    Detailed project description that would contain the project plan and the

    solution.

    2) Detailed project cost calculation, including details for the project sales and the

    Economic Value Add (EVA) for the project.

    3) Completed bid documentation, which would include the completed tendering

    document, the additional documentation for certifications and accreditation,

    and references for similar works in the past.

    4) Defined Negotiation Framework", which would detail the negotiation points,

    topics and strategies for the negotiation process.

    5) Approval by all organizations involved in the process.

    6) Current Risk Assessment. This can be achieved via identifying the hazards,

    likelihood of occurrence, deciding who and what will be impacted and in what

    severity, evaluating the risks and deciding on the required precautions, and

    finally recording the findings.

    7) Current project classification, i.e. defining the category under which the

    project falls. The categories can be Plant and Solution projects, Service

    projects or Small projects.

    8) Approval for submission of bid to customer by the Siemens management.

    9) Signed bid approval

  • 8/11/2019 Report on Siemens Project Managemenmt

    34/75

    27

    Thus, the milestone of this phase is the Bid Approval, and once it has been

    achieved, the project can move onto the next phase.

    iv. Contract Negotiation (Milestone 4Project Won/Lost):

    This phase starts with the Siemens team handing over the bid to the customers.

    Thus, now is the time for the contract to be negotiated and drafted.

    As a result, the team starts to prepare for and realize the customer presentation, if

    in case it has not already been done during the marketing and lead management

    phase at the start of the project management process.

    Once the bid has been submitted, the customer goes over it and processes it for

    any changes it may want in the bid that has to be incorporated in the contract. The

    customer may decide to give feedback to Siemens. Siemens in return has to

    process the customer feedback carefully and in detail again in order to decide

    whether or not to make the desired changes from the bid to the contract. The

    changes can with respect to the resources, legal aspects, solutions etc.

    Now comes the time for contract negotiations between the customer and Siemens.

    The teams at Siemens have to develop a negotiation strategy that has to be

    adhered to while negotiating with the customer for the changes from the bid to be

    incorporated in the contract. Siemens organizes and conducts contract

    negotiations with the customers, wherein both parties try to get the best out of the

    deal for themselves.

    Finally, toward the end of this phase, the teams at Siemens have to obtain

    approval for contract signing with the clients from the senior management at

    Siemens.

    The key deliverables of this phase are:

    1) A signed acknowledgement of order

    2) Final contract documentation, which is received after making negotiations

    with the customer and making changes to the bid.

  • 8/11/2019 Report on Siemens Project Managemenmt

    35/75

    28

    3) Described changes to the bid (resources, legal aspects, solutions, etc.) that

    have to be incorporated in the contract, presumably after negotiating is done

    with the clients.

    4) A new and revised risk evaluation. This evaluation would be more detailed

    than the previous phase and would include risk assessment, likelihood of

    occurrence and actions to reduce risk.

    5)

    Approval of the projects revised risk evaluation by Risk Review Board in

    charge.

    6) Adapted escalation level that has to be defined for the project.

    Once the contract negotiation phase if over, the final milestone is that the Project

    is won/lost. In any case, i.e. even If the project is won or lost, the process now

    moves on to the next phase.

    v. Project Handover- Marketing team to Execution team (Milestone 5 Start

    Project):

    The process now moves on to the project handover phase. The first step taken

    during this phase is to allocate an Overall Project Manager and a Commercial

    Project Manager. These project managers are responsible for overseeing the

    project from now on. A project manager works to align resources, manage issues

    and risks, and basically coordinate all of the various elements necessary to

    complete the project. Moreover, a project manager ensures that the project is

    delivered on time and under budget while meeting the defined goals and

    objectives.

    The Siemens team then updates the project data, and the project documentation is

    then handed over to the project manager. This would include all updated project

    information including bid and the latest contract documents, along with the

    changes between the two. Moreover, and importantly though, the project scope of

    delivery and cost calculation is finalized and adapted for the project.

    In the case of either won or lost projects after the previous phase, a final dialog is

    held with the bid manager. This is done in order to analyze won/lost orders, and

    the analysis has to be documented so that it can aid Siemens future endeavors in

  • 8/11/2019 Report on Siemens Project Managemenmt

    36/75

  • 8/11/2019 Report on Siemens Project Managemenmt

    37/75

    30

    Second, the project manager now opens a project account that has to be used for

    all the budgeting needs and monetary allocations for the project till it is

    completed.

    Third, the project manager performs a detailed check of the site that would beused for the construction of the project. Fourth, the manager has to keenly and in

    detail verify and clarify the contract in legal and commercial terms. This can be

    done either with related Siemens departments, the bid team or the clients.

    Fifth, the project manager has to complete the as-sold cost calculation, i.e.

    difference between the cost quoted on the bid, and the cost now that the project is

    about to start. The as-sold cost calculation is done via completing the Order

    Value Sheet. The Order Value Sheet defines the overall value of the project in

    terms of its total costs. Apart from defining the value and costs, the OVS also

    analyses the difference between the price quoted by Siemens in the tender and the

    current price when Siemens has won the tender and the project is about to be

    undertaken. This price difference may occur due to factors such as inflation etc.

    between the times specified. Thus, the Order Value Sheet defines the current

    profit margin and the change in profit margins for Siemens due to difference in

    these prices i.e. the one quoted on the bid and the current price.

    For instance, lets suppose the cost for the project was $100 in 2012, and Siemens

    intended to keep a 20% profit margin. Hence the final price quoted on the bid for

    the tender in 2012 was:

    $100 + (0.2x$100) = $120.

    Once the tender has been awarded and the project is about to be undertaken in

    2013, the costs may have risen to $110, whereas the final price would remain the

    same as stated in the tender. Hence, the profit margin for Siemens would go down

    to:

    ($120-$110)/$110 = 9.1%

    This change in margin from 20% to 9.1% would be reported on the Order Value

    Sheet by the project manager.

  • 8/11/2019 Report on Siemens Project Managemenmt

    38/75

  • 8/11/2019 Report on Siemens Project Managemenmt

    39/75

    32

    Eighth, the project manager now has to perform, or get a different entity or

    organization to perform, a project assessment. This is done through Project

    Management Assessment (PMA). PMA performs an in-depth analysis of current

    project management methods, resources, tools and technology to uncover gaps,

    potential risks and opportunities for improvement in the project. PMA

    evaluatesthe existing project methodology against the industry best practices in

    order to provide proper recommendations that can then be implemented by the

    project manager.

    To summarize, the key deliverables for the Project Opening and Clarification

    phase are:

    1) Project organization completed. This would include bringing people in the

    project team and defining and demarcating their roles and responsibilities.

    2) Detailed agreement with customer on the scope of deliveries/services and

    specifications.

    3) Change and claim strategy completed.

    4) Contract structures adapted. This would include the latest contract structure

    agreed upon with client after making changes to the bid.

    5) Target agreements drawn up.

    6)

    Project structure created. This is done by defining the scope of the project, and

    then completing the Work Breakdown Structure (WBS) to demarcate the

    phases or work packages in the project. Moreover, a Project Schedule (MS-

    Project) is defined by combining the phases of the WBS with their respective

    start dates and durations in a graphical form.

    7) As-sold cost calculation finalized using order value sheet (OVS).

    8) Project Assessment (PMA).

    The milestone reached at the end of Project opening and clarification stage is

    stated as Entry order clarified.

    vii. Detailed Planning (Milestone 7 Approval of detailed planning):

    Once the entry order is clarified, the project enters the detailed planning stage. As

    the name suggests, a majority of design for the project is completed in this phase.

  • 8/11/2019 Report on Siemens Project Managemenmt

    40/75

    33

    The planning here refers to the project design and plan, and not to the definition

    of project structure, which is done in the previous stage.

    In this stage, first, the project manager has to determine the technical basis for the

    project. Then he has to define and take care of the solutions and implementationof approval for the project. For instance, the project manager now has to get an

    Approval for erection for the project from the appropriate authorities.

    Moreover, the manager will have to get approval for purchasing documents as

    well.

    Second, the manager and his project team now have to perform a detailed design

    to be implemented in the project. Although some of the minor design was already

    completed during the project sales phase, the remainder majority of the design is

    completed at this stage. This is because the project manager and his team are now

    absolutely clear as to the requirements of the client and the deliverables due from

    Siemens as per the contract.

    Third, the project team now has to create and release detailed specifications for

    the project. Everything, from the projects technical requirements and pre-

    requisite inputs to its physical performance metrics and dimensions are clearly

    defined in the detailed specifications created by the project team in this stage.

    Fourth, in continuation with the previous stage, the project manager now has to

    freeze the basic schedule of the project that was defined in the last stage. The

    project schedule that has been revised and reviewed since the last stage is now

    deemed final.

    Fifth, the project manager has to complete the sourcing concept for the project.

    This means that the manager would have to define the material and other input

    requirements for the project and their potential sourcing options. These sourcingoptions may include factors such as the potential suppliers, transportation etc. For

    instance, apart from approval of the purchasing documents, the project manager

    would have to list the selected suppliers and service providers for the project.

  • 8/11/2019 Report on Siemens Project Managemenmt

    41/75

    34

    Sixth, again in continuation with previous stage, the manager has to complete the

    quality plan, i.e. a basic plan that intends to keep the final deliverable and the

    process to achieve it adhering to a minimum quality requirement. Moreover, the

    manager has to complete the detailed risk analysis for the project.

    To summarize, the key deliverables of the stage to reach its milestone are:

    1) Approved documents for erection.

    2) Approved documents for purchasing.

    3) Selected suppliers/service providers.

    4) Completed service concept.

    At the end of this stage, an Approval of detailed planning would be received as

    the milestone for this stage.

    viii. Purchasing and Manufacture (Milestone 8Dispatch Approval):

    The approval of detailed planning shifts the project into the Purchasing and

    Manufacture stage. As the name suggests, the stage is used to conduct purchasing

    of products not manufactured by Siemens, as well as sourcing and manufacturing

    for most of the products that have to be developed locally at Siemens.

    In this stage, first, the Project team manufactures own products of Siemens.

    Second, the project manager places orders for the products that have to be sourced

    from outside the company. Third, the project manager has to keep tracing the

    progress of manufacture of the products within the company. If necessary, he has

    to try and expedite the process so as to be completed qualitatively and well within

    time. Fourth, the manager needs to perform the works acceptance for the

    products. This means that when the manager gets the notice of completion

    ready for the products, he would review the scope for the products as needed by

    the project. He would then evaluate the products, whether from within the

    company or from outside, on the criteria of their fulfilling their scope in terms of

    performance and other metrics. If the products are as per the requirements of the

    project, the manager provides works acceptance. The works acceptance can be in

    the form of a certificate of acceptance.

  • 8/11/2019 Report on Siemens Project Managemenmt

    42/75

    35

    Fifth, and perhaps the most importance step of the process is that the manager has

    now prepare the products for export to the project site. Thus, a packing list is

    maintained with the weights and dimensions of packing units. Moreover, export

    declarations and pro-forma invoice for customs clearance have to be prepared

    if the products are being shipped to a foreign country. Additionally, packaging

    and dispatch information has to be prepared and maintained in case there is a

    loss or damage to the goods during transit. Once these things are completed, a

    notification of the readiness for erection is generated.

    Thus, as stated above, the key deliverables involved for this stage of the project to

    reach its milestone are:

    1) Notification of completion ready, indicating that all the products required for

    the project are now ready to be reviewed, packaged and shipped to the project

    site.

    2) Packing list with current weights and dimensions of packing units.

    3) Export declarations prepared, if the products are being exported.

    4) Pro-forma invoice for customs clearance, if the products are being exported.

    5) Packaging and dispatch information, to keep and maintain a record of the

    goods in transit in case any loss or damage occurs to them.

    6)

    Notification of readiness for erection.

    Once the above steps are completed, a Dispatch approval is granted to the

    manager indicating that he can now ship the products to the project site. This

    Dispatch approval is the milestone 8 Dispatch Approval indicating that the

    project can now move on to the next phase.

    ix. Dispatch (Milestone 9Materials and Sources at site):

    During the Dispatch phase, first, the project manager obtains approval for

    dispatch that is granted as the milestone for the last phase. Once the Dispatch

    approval is received, the project manager plans, monitors and oversees the

    dispatch of materials and resources to the project site.

  • 8/11/2019 Report on Siemens Project Managemenmt

    43/75

    36

    Third, the project manager, along with his team, organizes infrastructure needed

    for the project. This can include organizing tools needed for the project, required

    approvals etc. Fourth, the project manager receives the goods at the project site.

    He reviews them and incorporates their details in the respective inventories.

    Moreover the manager inspects the dispatched goods for signs of damage, or any

    other mishap or malfunction that can prevent the particular resource from

    functioning properly as per its requirement in the project. Fifth, the project

    manager now plans the assignment of internal and external resources, depending

    upon their source of origin, to be implemented in the project.

    The key deliverables for this stage to reach its milestone are:

    1) Goods received and incorporated in inventories, indicating the acceptance and

    review of the goods on site.

    2) Site ready for erection.

    3) Resources available.

    The milestone 9 - Materials and resources at site indicates the completion of the

    dispatch phase.

    x. Erection/Construction/Installation (Milestone 10Erection Completed):

    As the name plainly suggest, this phase involves the actual construction, erection

    and installation of the project at the site. Moreover, the phase also contains the

    start of the commissioning process, such as preparation of commissioning

    instructions.

    Thus this stage involves only two, albeit very major and typically very long, steps.

    First, the project manager has to install the plant/system. For this he has to use the

    pre-defined detailed plans, designs and prototypes that had already been

    developed during the Detailed Planning stage. This may take a lot of time

    depending upon the nature, size and functionality of the project. Thus, it would

    not be improper to say that this is the longest phase of the project management

    cycle that requires constant effort and attention. Once the erection is completed,

    the various erection reports have to be prepared by the project team.

  • 8/11/2019 Report on Siemens Project Managemenmt

    44/75

    37

    The second step is to prepare commissioning of the project. In short words,

    Commissioning can be stated as the process of checking, inspecting and testing.

    Commissioning is the process of assuring that all the components and all the

    systems of the newly erected and installed project are designed, installed and

    operating as per the operational requirements of the client. Thus, commissioning

    is a complex set of engineering processes that ensures that all components of the

    project, from small parts to big modules are functioning as per their requirements.

    In this step, all the previous documents, including the erection documents, are

    handed over to the commissioning unit within the project team. The

    commissioning unit then prepares all the detailed commissioning instructions,

    and, once done, declares the site ready for commissioning.

    To summarize, the key deliverables for this phase to reach its milestone are:

    1) Erection completed at site. This would indicate the completion of construction

    and installation of the project at site.

    2) Erection reports prepared by the project team,

    3) Handover of all documents to commissioning. These documents would

    include the erection reports as well.

    4) Commissioning instructions prepare.

    5) Site ready for commissioning.

    Once the phase is completed, the milestone Milestone 10 Erection Completed

    at site is reached.

    xi. Commissioning (Milestone 11Commissioning Completed):

    Once the erection is completed at site, commissioning phase begins. In this phase,

    first, the newly constructed plant/system is commissioned. As stated in the

    previous phase, commissioning in project management is to inspect and test that

    various components, from small parts to bigger modules, of the newly constructed

    and installed project are performing as per the requirements of the client. Second,

    the commissioning unit within the project team now performs internal

    plant/system tests.

  • 8/11/2019 Report on Siemens Project Managemenmt

    45/75

  • 8/11/2019 Report on Siemens Project Managemenmt

    46/75

    39

    the clients, or by the clients teams themselves. Once the tests are performed, the

    acceptance test documentation is drawn up.

    Third, the project team at Siemens creates provisional customer documentation.

    This documentation would include information about the operation andfunctionality of the plant/system. Such information would include the expected

    inputs/outputs, the specifications of the plant/system, basics about the internal

    components and parts, as well as the tests performed on it.

    Fourth, Siemens now holds a final dialog with the customer. This is the last team

    that the project team at Siemens would talk to the clients before the project enters

    the warranty phase.

    Fifth, Siemens requests the client to sign and provide a Provisional Acceptance

    Certificate (PCA). This means that the current acceptance of the plant/system by

    the clients is only provisional, and the plant/system would only be finally

    accepted by the clients if it functions as per the requirements during the warranty

    period.

    The key deliverables for this stage to reach its milestone are:

    1) Provisional Customer Acceptance (PCA) signed and received by Siemens.

    This is only provisional, and the final acceptance would only be received after

    the warranty period.

    2) List of open points adopted together with customer.

    3) Acceptance test documentation completed. This would detail the information

    about the acceptance test and its results.

    4) Provisional customer documentation drawn up. This would include basic

    information about the specifications, functionality, parts and tests of the

    product.

    Once the stage is completed, Milestone 12 - Provisional Customer Acceptance

    (PCA) milestone is received.

  • 8/11/2019 Report on Siemens Project Managemenmt

    47/75

    40

    4.1.3. Warranty:

    This phase indicates the period in the project management life cycle where the

    plant/system project moves into its warranty. During this phase, the project has been

    handed over to the clients. Thus, Siemens is only indirectly involved in the project

    from now on till the end.

    xiii. Warranty Phase (Milestone 13Final Customer Acceptance):

    When the project has been handed over to the customer, there are still many tasks

    remaining that have to be completed by the Siemens project team.

    First, they have to work on reducing outstanding points in collaboration with the

    customer, so as to close the remaining loops in the project. Second, they have to

    create the final customer documentation. Since the only documentation that hasbeen provided to the customer till now is provisional, the Siemens team now has

    to make this final customer documentation as detailed and analyzed as possible.

    Third, the Siemens teams have to archive the project. This is essential for efficient

    record-keeping as Siemens works on a great many projects over the years. Thus,

    this would make it easier to access the work, data, facts and other key points

    about the project, and would come in handy in future projects that tote the same

    lines as this project.

    Fourth, the project team now has to create a final project report. This report would

    detail each and every aspect faced along the project management cycle of the new

    plant/system. All the aspects of every stage, including the project scope, plan,

    design, manufacturing, building, erection, installation, commissioning and

    warranty, are detailed in the report. This also makes it easier to document lessons

    learned from the project.

    Fifth, once all the above steps are accomplished, Siemens dissolves the project

    organization, and the project manager and his team can then be redistributed to

    other projects and departments. This can be termed as another milestone within

    this stage known as Project Closure.

  • 8/11/2019 Report on Siemens Project Managemenmt

    48/75

    41

    Sixth, at the end of the warranty period, Siemens concludes its warranty. Seventh,

    finally, once everything is completed satisfactorily and as per the requirements of

    the client, Siemens requests the client to sign and provide the Final Acceptance

    Certificate (FAC), which states that the client is now fully accepting all the

    responsibilities of the product in all means from now on.

    The key deliverables in this stage are:

    1) Final Acceptance Certificate (FAC) signed and provided by the customer to

    Siemens.

    2) Bank bonds obtained from the customer.

    3) Final customer documentation prepared and given to the customer about the

    plant/system.

    4) Final project report prepared and archived at Siemens.

    Once Project Closure is achieved, and Siemens has completed its warranty, the

    final milestone of this stage, and hence of the entire PM cycle is Milestone 13

    Final Customer Acceptance.

    4.2. PRODUCT OPERATIONS MANAGEMENT IN RESPONSE TO A SPECIFIC

    ENQUIRY:

    The operations model for a product at Siemens, in response to a specific enquiry for a pre-

    defined and agreed upon type of product catering to a specific problem, follows the following

    stages:

    4.2.1. Marketing - Problem, Solution and Client interaction:

    This is the first step of the process wherein a product is deemed sellable. This phase is

    conducted for all the three types of products at Siemens irrespective of their design

    needs. Additionally, the phase is conducted entirely by the marketing department at

    Siemens. The process follows the following phases:

    i. Phase IFinding the Problem:

    This phase may also be called as Lead Management, where Siemens tries to

    generate the leads for a potential business clientele through various marketing

    activities.

  • 8/11/2019 Report on Siemens Project Managemenmt

    49/75

    42

    This stage starts with the marketing team at Siemens conducting an extensive

    market research to gauge the existing market, technologies and products.

    Additionally, towards this end they also have to keep a constant watch on the

    competitors as well as new technologies entering the market. The marketing teams

    at Siemens have to keep themselves abreast through internet, publications, industry

    exhibitions, seminars etc. Moreover, the market research is more often than not

    conducted by a visit by Siemens team to the potential clients location. This is

    needed in order to understand the current scenario and how things are handled over

    there. It can also give an idea of the problems involved with the current situation,

    along with the ways in which it can be solved or just improvised upon.

    Thus, the results of this market research and analysis are used in order to find

    a). Existing demands or

    b). Problems with the potential market.

    These existing demands and problems can be in the form of potential needs based

    on inefficiencies within the operations of different organizations that can justify the

    sale of a Siemens product. Thus, the product concept would fulfill the demand

    created by this need and tend to improve the current processes within organizations,

    providing them with a ROI that can be measured on various aspects, such as time,capital, labor etc.

    ii. Phase IIDeveloping a solution:

    Based on the problems or demands found during the previous phase, Siemens now

    postulates a standard, customized or specially developed product that can act as a

    solution catering to this requirement. At this stage, the product has defined end-user

    functionality that provides a solution to the problem and is the means towards an

    end. Moreover, in case of standard products, it has clearly-defined specifications

    like its physical or performance attributes and requirements. Again, in case of

    customized or specially developed products, only the functionality is defined. Other

    aspects such as physical attributes and specifications are estimated using the

  • 8/11/2019 Report on Siemens Project Managemenmt

    50/75

    43

    experience of Siemens technical expertise, estimated available labor, capacity and

    time required that can validate the scope of the product.

    iii. Phase III - Client Interaction:

    This phase of the process starts with teams from Siemens interacting with the

    potential client organization and briefly pitching in the crux of the product idea

    before them. The interaction can be done in many ways like: a.) Industry

    exhibitions, b.) Formal/Informal dinners and lunches, c.) casual conversation and

    direct emails etc. Once the client seems interested after the brief, a detailed

    presentation of the idea is conducted for the client. This presentation outlines the

    problem with current processes and the estimated numbers that portray the extent to

    which this problem is hampering the profits, performance or efficiency of the

    organization.

    Once the problem has been conveyed across the table, the presentation outlines the

    Siemens product idea that could provide a potential solution. This presentation

    may also outline the estimated overall cost for the client if it goes for this product,

    after taking into consideration the costs that can be involved in the product R&D,

    design, manufacturing, implementation and maintenance. The Siemens marketing

    team also defines the expected client return-on-investment (ROI) from the product

    that can be measured on various aspects, such as time, capital, labor, quality,

    performance, efficiency etc. A cost vs. benefits analysis is presented along with

    additional benefits, such as the advantages of Siemens technology and the extensive

    after-sales service. Moreover it gives a comparison of the predicted performance of

    the company with and without the product.

    This presentation is followed by multiple contacts and mails to the clients to

    understand their requirements and to answer their queries. The third phase of the

    process involves a client visit to the Siemens AG headquarters in Germany where

    the product has to be developed. A team of executives from the client organization,

    accompanied by members of Siemens India, visit the manufacturing plant where the

    actual physical know-how, technical specifications and functionality of the product

    are detailed to the clients.

  • 8/11/2019 Report on Siemens Project Managemenmt

    51/75

    44

    4.2.2. Design:

    Design phase at Siemens seeks to develop detailed specifications that emphasize the

    physical solution for the clients requirements. During this phase, more than one

    design can be developed that can provide the same functionality and usability as per

    the needs of the user. It is up to the product manager and his team to decide upon the

    final design that has to be implemented based upon their technical expertise,

    individual experience or comparisons with the existing Siemens products.

    The design phase is conducted for customized and specially developed products.

    However, as already stated, the design phase is shorter for customized products as

    they just need to be modified from a pre-existing base product. On the other hand, the

    specially developed products have a longer design phase as they have to be designed,

    developed and implemented for many parts from scratch to fulfill the demands of the

    customer.

    During the initial stages of the design phase, R&D is conducted to analyze the

    resources required for the product design. Moreover, time and effort figures to

    develop the product are estimated. This process may also include Capability

    Research, i.e. the analysis of preexisting technology, knowledge and expertise at

    Siemens, and estimates of the remainder to be garnered.

    Once the design is deemed satisfactory, it is sent to the clients for approval. The

    customer reviews the design and may suggest some changes. Depending upon the

    extent and nature of the changes suggested, the process may take some time.

    Moreover, the design may keep moving back and forth between Siemens and the

    customer till a final design is agreed upon.

    4.2.3. Sales:

    Once the design phase is completed, the product moves into the sales phase.

    Depending on the nature of the sale, i.e. whether it is a one-time sale or a deal for

    continuous supply of the aforementioned products (existing or contingent), a Sales

    Contract or a Sales Agreement is drawn.

  • 8/11/2019 Report on Siemens Project Managemenmt

    52/75

    45

    A sales contract is a contract whereby Siemens transfers the product to the client at a

    price. It is a bilateral contract that can specify the following features and conditions:

    i. Product description

    ii. Price of the product

    iii. Quantity of the product

    iv. Payment terms and conditions

    v.

    Commercial

    vi. Factory

    vii. Tax different types of taxes, such as within a state or province, outside

    the state, ED etc.

    viii. The terms of delivery

    On the other hand, a Sales Agreement is drawn between Siemens and the client that

    defines the conditions for the sale of the product or a product line at a future time.

    These conditions may include all of the above stated within a sales contract.

    However, since the sales agreement is only a promise for sale at a future time, it does

    notspecify the quantity of products within the agreement. Thus, it does not create any

    right of the client in the product, till the product is finally sold via a sale contract.

    Moreover, till the sale is finally closed via a sales contract, the risk of the product

    remains with Siemens. As a result, a sales agreement can be used as a tool by

    Siemens to offer better prices to the client for the product line, without committing

    them to particular purchase quantities. Thus, all the future sales contracts for this

    product or product line can be drawn upon using the base of this sales agreement.

    4.2.4. Installation:

    As discussed earlier, the installation phase occurs only for Siemens-manufactured

    small products that are sold to the clients. Moreover, the installation option can come

    in packaged with the product. Otherwise it can be optional, to be purchased by the

    client in addition to the warranty offered on the product, as the clients may choose to

    do this task themselves. The small products mentioned above can be like small spare

    parts or sub-parts of a Siemens or another product. Only the installation for these

    small products comes under the domain of product operations. This is because the

  • 8/11/2019 Report on Siemens Project Managemenmt

    53/75

    46

    installation and service of large products, if chosen by the client to be performed by

    Siemens ,can be ext