MAKING ENERGY INVESTMENT PROJECT
WORKS BY COGENERATION TECHNOLOGY
WITH ESCO
By Excellent Energy International Co., Ltd. (EEI)
"Renewable Energy Asia 2013”
BITEC, Bangkok,Thailand
5 June 2013
Thailand ESCO Pilot since 1999
ESCO Excellence Award 2009-2012
Page 2
©EEI All Rights Reserved
2 Strictly confidential – For discussion purposes only
• About EEI
• Successful ESCO projects - Cogeneration
• Why EEI ESCO?
• What is Cogeneration?
Agenda
Page 3
©EEI All Rights Reserved
3 Strictly confidential – For discussion purposes only
Excellent Energy International Co., Ltd. (EEI):-
A well-known ESCO (Energy Service Company) in Thailand established since 1999 with the registered capital of 26 MB
An ESCO who offers guaranteed-payback on EE/RE/AE* projects for clients in various Industries and Commercial buildings
The first one, and only ESCO in Thailand who
successfully implemented “Thailand ESCO
Pilot Project” with excellent base of support
from the Thai Government & the World Bank.
*Energy Efficiency/ Renewable Energy/ Alternative Energy
An ESCO with Over 6,000 MB of on-going projects distributed over Cogeneration system, Renewable Energy, Energy Management Information System (EMIS), Heat Recovery projects, etc
Awarded 4 consecutive years of “ESCO
Excellence Award 2009 - 2012”, by The
Federation of Thai Industries, supported by
the Ministry of Energy, to the leading ESCO
of Thailand.
The only ESCO in Thailand whom was invited to contribute a regional perspective as a Co-writer in two books of World- God Mother of ESCO, Dr. Shirley Hansen!!! Namely “ ESCOs Around The World: Lessons Learned in 49 Countries”(published in 2009) and “World ESCO Outlook” (just released and available now!!!)
Some of EEI Clients
Page 4
©EEI All Rights Reserved
4 Strictly confidential – For discussion purposes only
Certified Measurement and Verification
Professional
Page 5
©EEI All Rights Reserved
5 Strictly confidential – For discussion purposes only
Project in
EE: Energy Efficiency
RE: Renewable
Energy
AE: Alternative Energy
− ESCO Fund by DEDE
− BOI for EE, RE, Environmental, and ESCO Project
− VSPP Adder By MINISTRY OF ENERGY
− National Innovation Agency: NIA
Various support from Government such as
taxes, duties, and grant to accelerate economy
Industry Trend: Why should everyone start Energy Efficiency project now?
Energy price is moderately increased.
Effective CSR Solutions
Save : Energy, Environment ,The World
with Positive Cash Flow + Low Risk
New Energy Efficient Technologies.
Page 6
©EEI All Rights Reserved
6 Strictly confidential – For discussion purposes only
Comparison of Crude Price, Fuel Price and Ft
Page 7
©EEI All Rights Reserved
7 Strictly confidential – For discussion purposes only
EEI Movement
Excellence ESCO Award
EEI, Mr.Arthit Vechakij, received the token "ESCO Excellence Award 2009-2012" in
Thailand ESCO Fair 2009 - 2012, as the Leading Thai ESCO for 4 consecutive years.
This Award conducted by The Institute of Industrial Energy, The Federation of Thai
Industries, supported by Ministry of Energy.
Award 2009 Award 2010 Award 2011 Award 2012
Page 8
©EEI All Rights Reserved
8 Strictly confidential – For discussion purposes only
EEI’s Solution
ECMs for Industrial Facility
ECMs for Commercial Building
Ozone for Laundry
Heat Pump
Gas Turbine
Steam Turbine
Gas Engine
Biogas
Coal
Biomass
Natural Gas
Cogeneration System
Absorption Chiller Waste Heat
Recovery / ORC
Refrigeration & HVAC
Boiler System
Motor Optimization Lighting
EMIS (Energy Management Information System) Productivity
Improvement
Power Generation –
Renewable Energy
Plant Simple Cycle
Gasification
Biomass Power
Waste to Energy
Solar Power Plant
Page 9
©EEI All Rights Reserved
9 Strictly confidential – For discussion purposes only
Plant Monitoring System
EEI’s Service
1 ESCO Performance Guaranteed
2 ESCO Performance Base
3 Project Management Consultancy & System Integration
4 Investment & Financial Arrangement
5 Independent Engineering/Lender Engineer
6 O&M Management Service
Investment
Potential Study,
Feasibility Study
Engineering
Design,
Conceptual
Design
Construction
and Installation
Supervision &
Management
Bidding and
Procurement
Management
Commissioning
Operation &
Maintenance
Supervision
7
Contract
management
Permit,BOI and
Regulation
management
Page 10
©EEI All Rights Reserved
10 Strictly confidential – For discussion purposes only
• About EEI
• Successful ESCO projects- Cogeneration
• Why EEI ESCO?
• What is Cogeneration?
Agenda
Page 11
©EEI All Rights Reserved
11 Strictly confidential – For discussion purposes only
Business Case Example: Thailand ESCO Pilot Project
Bangkok Produce Merchandising Public Co., Ltd.
(SET: BKP)
Cogeneration Power Plant
4.5 MW, 12 TPH, Gas Turbine
Generator (GTG) (Fuel: Natural Gas)
BKP Cogeneration, the one-and-only Thailand ESCO Pilot
Project since 1999, has been supported by World Bank, Thai
Government , EGAT, and private co-operations as to drive
ESCO business in Thailand. Located: Saraburi, Thailand
Gas Turbine Generator (GTG)
Cogeneration Power Plant Project Investment Cost = 183 MB
Energy Cost Savings = 37 MB/Year
Payback Period = 4.95 Year
IRR = 20%
Operation and Maintenance Phase
Page 12
©EEI All Rights Reserved
12 Strictly confidential – For discussion purposes only
9 New Cogeneration Power Plants after
The Success of BKP Pilot Project
After the pilot project has been greatly succeed, CP Group has consider to expand the implementation of Energy Efficiency Management Project through a Cogeneration Power Plant in it others 9 daughter companies.
Why CPF Group has repeated EEI ESCO Service?
EEI Value receiving from BKP ESCO Pilot Project EEI walks the talk - Real deficit saving compensated by EEI under EPC-
Guaranteed savings Bargaining power in combined Bidding and Procurement Getting large energy cost savings as soon as Project Commercial Operation Date (COD) Starting
Page 13
©EEI All Rights Reserved
13 Strictly confidential – For discussion purposes only
C.P. RETAILING AND MARKETING CO.,LTD.
Cogeneration Power Plant
6 MW, 4.2 TPH, Gas Engine (GE)
(Fuel:Natural Gas)
Project Investment Cost = 242 MB
Energy Cost Savings = 61 MB/Year
Payback Period = 5 Years
IRR 15 Years = 20.6 %
[email protected] %Discount Rate = 672 MB
Start Savings = March 2015
Business Case Example: Cogeneration Power Plant for 7-11
Development Phase
CPRAM has entrusted EEI to be a consultant under ESCO Performance Guaranteed Contract for
project of cogeneration power plant using natural gas in frozen food processing for 7-11 around
Thailand.
Page 14
©EEI All Rights Reserved
14 Strictly confidential – For discussion purposes only
Thai Central Chemical Public Company Limited (TCCC)
Business Case Example: Cogeneration Power Plant for Fertilizer Plant
TCCC has high potential to develop the Cogeneration
Power Plant project with Gas Engine Technology. EEI
whose expertise in the Cogeneration Power Plant, has
been engaged to provide ESCO Performance Guaranteed
service.
Project Investment Cost = 152 MB
Energy Cost Savings = 33 MB/Year
Payback Period = 6.64 Years
IRR 15 Years = 15.73 %
NPV (DR@ 6.5%) = 131 MB
Start Savings = March 2013
Cogeneration Power Plant
4 MW, 2.8 TPH, Gas Engine (GE)
(Fuel: Natural Gas)
Operation & Maintenance Phase
Page 15
©EEI All Rights Reserved
15 Strictly confidential – For discussion purposes only
PERFECT COMPANION GROUP CO., LTD.
Cogeneration Power Plant
6 MW, 4.8 TPH, Gas Engine (GE)
(Fuel: Natural Gas)
Project Investment Cost = 244 MB
Energy Cost Savings = 45 MB/Year
Payback Period = 5.4 Years
IRR 15 Years = 20 %
NPV (7% Discount Rate) = 3.17 MB
Start Savings = June 2016
Perfect Companion Group (PCG) is one of the biggest Pet Food Manufacturer in Thailand with
brands like Smartheart, MeO, etc. With an attempt to improve overall energy efficiency and to
increase reliability of this manufacturing unit, PCG had engaged with EEI to develop a Natural Gas
Cogeneration Power Plant which will utilize waste heat from power plant to serve their current
thermal requirement in form of steam and hot air. The excess electricity will be exported and sold to
the grid under a VSPP license.
Business Case Example: Cogeneration Power Plant for PETS FOOD
Development Phase
Page 16
©EEI All Rights Reserved
16 Strictly confidential – For discussion purposes only
Business Case Example: Cogeneration Power Plant for Modified Starch Plant
C. Gigantic Carbon Co., Ltd. (CGC)
Project Investment Cost = 195 MB
Energy Cost Savings = 55 MB/Year
Payback Period = 3 Years
IRR 15 Years = 27 %
NPV = 392 MB
Start Savings = Dec 2004
EEI was introduced by IFCT to C.Gi who is the starch
manufacturer would like to explore the Renewable Energy
project. According to C.Gi had consumed the steam so
high that C.Gi had the potential to develop the Biomass
Cogeneration.
Cogeneration Power Plant
2.8 MW, 28.7 TPH, High Pressure Boiler &
Steam Turbine Generator (HP-STG)
(Fuel: Solid)
Operation & Maintenance Phase
Page 17
©EEI All Rights Reserved
17 Strictly confidential – For discussion purposes only
Nan Yang Knitting Factory Co., Ltd. (NYK)
Cogeneration Power Plant
1.8 MW , 22 TPH, High Pressure Boiler & Steam Turbine
Generator (STG) (Multi-Solid-Fuel: Coal & Biomass)
Project Investment Cost = 155 MB
Energy Cost Savings = 49 MB/Year
Payback Period = 3.1 Years
IRR 15 Years = 31.7 %
NPV (15 Year DR@4%) = 334 MB
Start Savings = October 2006
End of Guaranteed Period = December 2011
3 years after EEI has implemented EMIS with guaranteed
savings to NYK, EEI obtained other opportunities in the 3rd
project by mean of energy efficiency consultancy along with
providing Guaranteed savings of Cogeneration System.
This Cogeneration System contributes in 10-30% reduction of
NYK Fuel consumption.
Located: Samutsakorn , Thailand
Business Case Example: Cogeneration Power Plant for Textile Plant
Dyeing & Printing
Weaving & Knitting
Spinning
Yarning Textile Process
Operation & Maintenance Phase
ESCO Project Award 2009 By F.T.I
Page 18
©EEI All Rights Reserved
18 Strictly confidential – For discussion purposes only
E-Saan Sugar Industry Co., Ltd. (ESI)
Business Case Example: Modified Cogeneration Power Plant for Sugar Refinery Plant
Project Investment Cost = 310 MB
Energy Cost Savings = 50 MB/Year
Payback Period = 6 Years
IRR 15 Years = 17%
NPV (20Year DR@ 6.5%) = 229 MB
Start Savings = Nov 2012
Cogeneration Power Plant
2.7 MW, 45 TPH High Pressure Boiler & Steam Turbine
Generator (HP-STG) (Fuel: Biomass)
ESI then has entered into the Energy Performance Contract with EEI.
Contributing EEI’s combined experience in Biomass, Food Industry,
Seasonal Operation thus multiple Energy Consumption profiles,
Cogeneration, and VSPP, EEI started from exploring every possible
schemes for this improvement initiative under variety of constraints,
facts, and forecasts for ESI. Innovative technology such as
Gasification is also introduced into the picture to ensure
comprehensive coverage of all choices for Owner.
Development Phase
Page 19
©EEI All Rights Reserved
19 Strictly confidential – For discussion purposes only
Business Case Example: VSPP Power Plant from Rice Husk
TRC Clean Energy Co., Ltd. (TRCCE)
Project Investment Cost = 573 MB
Energy Cost Savings = 126 MB/Year
Payback Period = 4.5 Years
IRR 15 Years = 23 %
NPV (0% Discount Rate) = 1,586 MB
Start Savings = June 2011
TRCCE has developed the Biomass Cogeneration Power
Plant with Rice Husk which is the TRCCE by-product. EEI
has been engaged into the ESCO Performance Guaranteed
Contract since 2009. The project has started to save in June
2011. The plant contributes the gross electrical power
generation of 7.8 MW together with the steam 45 tons per
hour.
Cogeneration Power Plant
7.8 MW, 45 TPH, High Pressure Boiler & Steam Turbine
Generator (HP-STG) (Fuel: Biomass)
Operation & Maintenance Phase
Page 20
©EEI All Rights Reserved
20 Strictly confidential – For discussion purposes only
Business Case Example: Cogeneration Power Plant for Saw Mill
Plan Ecoenergy Co., Ltd. (PEC)
Cogeneration Power Plant
5.2 MW, 3.4 TPH, Gasification + Gas Engine
(Fuel: Biomass)
Project Investment Cost = 340 MB
Energy Cost Savings = 75 MB/Year
Payback Period = 4.8 Years
IRR 15 Years = 19.6 %
NPV (15 Year [email protected] %) = 326 MB
Start Savings = June 2013
Plan Ecoenergy project will be the first successful large scale
commercial project of gasification project in Thailand. The
project needs the real expert who can develop, implement, and
guarantee the technical thus financial feasibility of gasification
project. The Power Plant will be designed to export electricity
to Grid and supply steam to existing process of saw mill.
Implementation Phase
Supported by
Page 21
©EEI All Rights Reserved
21 Strictly confidential – For discussion purposes only
Business Case Example: Cogeneration Power Plant from Wood Chip
Nongbua Green Power Co., Ltd. (NGP)
Project Investment Cost = 67 MB
Energy Cost Savings = 9.7 MB/Year
Payback Period = 7.4 Years
IRR 15 Years = 10.9 %
NPV (15 Year [email protected] %) = 20.3 MB
Start Savings = March 2013
Nongbua Green Power Co., Ltd. has implemented
Community Based Biomass Power Plant, which is the
successful cooperation between Thailand and Austria.
This energy project was supported by the National
Innovation Agency (NIA) and local community as well.
Cogeration Power Plant
1 MW Gasification + Gas Engine
(Fuel: Biomass)
Supported by
Implementation Phase
Page 22
©EEI All Rights Reserved
22 Strictly confidential – For discussion purposes only
Business Case Example: Cogeneration Power Plant from Rice Husk
Boon Chareon Green Energy Co., Ltd. (BGC)
Project Investment Cost = 391 MB
Energy Cost Savings = 56.33 MB/Year
Payback Period = 6.15 Years
IRR 15 Years = 12.67 %
NPV (15 Year DR@7%) = 128.7 MB
Start Savings = December 2013
Boon Chareon Green Energy Co., Ltd. (BGC) has
engaged with EEI to develop cogeneration power plant
with gasification technology. This power plant uses
biomaterial from milling and agriculture as a fuel to
produce electricity 5.3 MW.
Cogeneration Power Plant
5.3 MW, 3.4 TPH Gasification (GF)
(Fuel: Biomass)
Utilities System in Rice Mill (Dryer & Boiler)
Development Phase
Supported by
Page 23
©EEI All Rights Reserved
23 Strictly confidential – For discussion purposes only
Industrial Waste Management to Energy Project - Daily 165 TPD
Waste to Energy System - Separate line
- Power Generator :
Incinerator and Steam Turbine Generator 5 MW.
Business Case Example: VSPP Power Plant from Industrial Waste
Project Investment Cost = 810 MB
Project net cash flow (Avg.) = 113 MB/Year
Payback Period = 5.27 Years
IRR 20 Years = 15.49%
NPV @ 7.5%Discount Rate = 450 MB
Entrepreneur has a capability on gathering industrial
waste disposal and confined in EEI to be a consultant for
Industrial Waste Management to Energy Project. This is
the first project in Thailand that produces electricity from
industrial waste.
Development Phase
Page 24
©EEI All Rights Reserved
24 Strictly confidential – For discussion purposes only
Business Case Example: VSPP Power Plant from Municipal Solid Waste
Municipal Solid Waste Project
- Daily 200 TPD
-Landfill : 500,000 Tons
Waste to Energy System -Separate line
- Power Generator :
Bio-Dry
MP Boiler and Steam Turbine Generator 6.5 MW.
Project Investment Cost = 933 MB
Project Net Cash Flow (Avg.) = 94 MB
Payback Period = 3.89 Years
IRR 25 Years = 19.78 %
NPV @ 12%Discount Rate = 299 MB
Entrepreneur focus is interested in implementing a
“Municipal Solid Waste or MSW cogeneration power plant
by Refuse Derived Fuel (RDF). The key success factors
of MSW project are started from project feasibility study
and confidence level of MSW quantity, quality and
concession.
Development Phase
Page 25
©EEI All Rights Reserved
25 Strictly confidential – For discussion purposes only
• About EEI
• Successful ESCO projects - Cogeneration
• Why EEI ESCO?
• What is Cogeneration?
Agenda
Page 26
©EEI All Rights Reserved
26 Strictly confidential – For discussion purposes only
Guaranteed Savings
Total Savings
Old Energy Cost New Energy Cost
No extra expense required for ESCO investment Total Investment Cost will be handled by EEI ( ESCO) / Investor solely. The payback to the project come only from Monthly Savings achieved. Guarantee Investment EEI guarantees that total investment will be paid up by Savings* Share risk, share loss, share benefit During the contract period, Client, Investor and EEI (ESCO) will share the savings achieved Client owns the Asset ‘til its life-time After the contract period, the asset will be totally transferred to client. All the savings gained goes to client only.
Financing Scheme for ESCO in Thailand:
ESCO Performance Guaranteed Concept
O&M Expense
Energy Cost (New)
O&M Expense
Other Energy Expense
Other Energy Expense
Bank Loan
Client as Equity
Equity
ESCO Shared Saving
Total Energy Expense
Page 27
©EEI All Rights Reserved
27 Strictly confidential – For discussion purposes only
EEI ESCO Performance Guaranteed
Concept
Page 28
©EEI All Rights Reserved
28 Strictly confidential – For discussion purposes only
Performance Guaranteed EEI fee 50 % of access Guaranteed Savings with obligation of deficit saving
Performance Base EEI Fee 25 % of access Target Savings without obligation of deficit saving
EEI ESCO Service Clarification
IGA
Bidding &
Procurements
Implementation
Operation & Maintenance
Project Management Consultancy & System Integration
ESCO Performance Base
ESCO Performance Guaranteed 1
2
3
Guaranteed %IRR Guaranteed Return Period Guaranteed/Target Savings
----------------------- Consulting Fee --------------------------->
SCOPE OF SERVICE
<----------EEI Fee---------
After bidding,% IRR will be converted
to return period for guarantee.
After COD, project investment cost will be concluded
Then EEi will identify guaranteed/target figure and
maintain guaranteed return period as same as
commitment in implementation period.
Page 29
©EEI All Rights Reserved
29 Strictly confidential – For discussion purposes only
Why EEI?
1. EEI has Professional personnel, who has true/real experiences in
various technologies to be responsible for every phase of project
including Payback period.
2. EEI can provide the Performance guaranteed to share risk , share
loss and share benefit as same as owner along payback period.
3. EEI achieves reputation for being regarded ESCO in Thailand by
government organization, leading financial institute, and industry expert
in local and global, and also receive additional projects (repeat orders).
4. EEI enables Project owners to run their core business on worry-free
mode, since EEI provides Performance Guaranteed to the project by
many experts.
5. EEI performance absolutely supports Business competition since
generated energy cost savings from EEI project will directly contribute to
lower production cost.
6. EEI can manage the optimized return for Project owners. With EEI
System integration, it isn’t necessary to have Turnkey contractor
anymore whereas we are also able to pursue the effective cost.
Page 30
©EEI All Rights Reserved
30 Strictly confidential – For discussion purposes only
<---------EEI Fee------ -------------------------- Consulting Fee --------------------->
Sign EPC
IGA
Bidding &
Procurement
Implementation
Operation & Maintenance
EEI: ESCO Procedure : Next Step for Client to start
project development and implementation
Step 1 Step 2 Step 3 Step 4 Step 5
1-3 Months 1-3 Months 3-24 Months 1 – 8 Years
Under the Agreed
Condition of __% IRR
1. EEI guaranteed period starts
from the date designed on
Notice to Proceed/EPC
including all phases during
contract
2. Shall EEI mistakenly
perform the task at any step,
Client will be subject for
no payment.
•Detailed Energy Audit
•Recommended Project
•Conceptual Design, Bill of
Quantity(BOQ)
•Technical Feasibility
•Financial Feasibility
•Commercial Feasibility
•Legal Feasibility
•M&V Plan
•Project Schedule
•Bid Design, Technical
Specification
•Request for Proposal
•Proposal Clarification with
Bidders
•Bid Evaluation Report
•Equipment Contract
Negotiation
•Equipment Contract
Preparation & Closing
•Review Detailed
Engineering
•Bidding & Procurement on
Minor Equipments & Service
•Construction and
Installation Management
•System Integration
•Commissioning
•O&M Development
•Post Commissioning
•O&M on site Supervision
•O&M remote Supervision
<---------Permit, BOI and Regulation management --------->
Page 31
©EEI All Rights Reserved
31 Strictly confidential – For discussion purposes only
• About EEI
• Successful ESCO projects - Cogeneration
• Why EEI ESCO?
• What is Cogeneration?
Agenda
Page 32
©EEI All Rights Reserved
32 Strictly confidential – For discussion purposes only
What is Cogeneration?
Cogeneration Power Plant
Cogeneration (Combined Heat and Power or CHP) is the simultaneous
production of electricity and heat, both of which are used. The central and most
fundamental principle of cogeneration is that, in order to maximize the many
benefits that arise from it, systems should be based according to the heat
demand of the application.
Page 33
©EEI All Rights Reserved
33 Strictly confidential – For discussion purposes only
The Cogeneration System, a.k.a.
Combined Heat & Power (CHP)
System, is a Simultaneous
generation of two different forms of
useful energy using one single
primary energy source
Cogeneration System efficiency is
increased to the 80%+ level
compared to the 30-60% level of
Traditional Separated Electricity and
Steam Generation System
Power Station 60
Heating Boiler 40
Steam 34
Electricity 24
Fuel = 100
Loss 42
Fuel = 68
Cogeneration or CHP Plant
Electricity 24
Steam 34
Loss 10
Traditional Separated
Electricity and Steam
Generation System
Benefit of Cogeneration Solution
Page 34
©EEI All Rights Reserved
34 Strictly confidential – For discussion purposes only
Preliminary Design for Cogeneration
Gas Engine Generation
Electricity
HRSG
Steam
Heat Exchanger
Hot Water Gas Engine
Natural Gas
Electricity
Steam
Factory
Absorption Chiller
Chilled
Water
Hot Water
Page 35
©EEI All Rights Reserved
35 Strictly confidential – For discussion purposes only
Preliminary Design for Cogeneration
Gas Turbine Generation
Electricity
HRSG
Steam
Heat Exchanger
Hot Water
Natural Gas
Electricity
Steam
Factory
Absorption Chiller
Chilled
Water
Gas Turbine Hot Water
Page 36
©EEI All Rights Reserved
36 Strictly confidential – For discussion purposes only
Preliminary Design for Cogeneration
High Pressure Boiler and Steam Generator
Electricity
Steam
Electricity
Steam
Factory
Solid Fuel
HP Boiler
ST Generator
HP Steam
Page 37
©EEI All Rights Reserved
37 Strictly confidential – For discussion purposes only
Preliminary Design for Cogeneration
Gasification + Syngas Engine Generation
Electricity
HRSG
Steam
Heat Exchanger
Hot Water
Syngas
Electricity
Steam
Factory
Absorption Chiller
Chilled
Water
Hot Water
Solid Fuel
Syngas Engine
Page 38
©EEI All Rights Reserved
38 Strictly confidential – For discussion purposes only
Cogeneration’s advantage
Generating significant cost savings, providing additional competitiveness
for industrial and offering affordable heat.
Increasing availability and reliability of utility supply to the process.
Lower CO2 emissions to the environment, Serving the Corporate Social
Responsibility (CSR) and providing Green Image to the company.
Cogeneration Project is entitled to gain various available privileges
supported by the Government
Very low risk investment solution under ESCO Performance Guaranteed
Contract. EEI ESCO would provide the optimization design, long term price
performance evaluation as well as performance guaranteed along the project
payback period.
Page 39
©EEI All Rights Reserved
39 Strictly confidential – For discussion purposes only
Example: Load Shading
BOP
LOAD
PEA
LOAD
1.7 MW
LOAD
1.0 MW
t
t
t
MW
PEA
Factory Load
GEN
G 2.0 MW G 2.0 MW
2.7
2.7
1.0
1.7
PEA
LOAD
1.0 MW
1.7
Synch.
(Close SWG)
Auto
Open SWG
Load Shedding
Open ACB
Back Synch.
Close SWG
Close ACB Synch. Load
Shedding Back
Synch.
Synch. period
Island Synch. period
Critical Load Non-Critical Load Non-Critical Load
PEA
Outage
PEA
Back to
normal
Load Shedding
Program
performed
Page 40
©EEI All Rights Reserved
40 Strictly confidential – For discussion purposes only
Example Case BKP: How Cogeneration Works?
Before Implementing Cogeneration System
3.2 Ton
BKP Factory
BUNKER OIL
TRANSFORMER TRANSMISSION
LINE PEA
Steam
12 Ton
Electricity
10 MW
5 Ton NATURAL GAS
5 Ton BUNKER OIL
10 Ton COAL
Page 41
©EEI All Rights Reserved
41 Strictly confidential – For discussion purposes only
Example Case BKP: How Cogeneration Works?
3.2 Ton BUNKER OIL
TRANSFORMER TRANSMISSION
LINE PEA
Steam
12 Ton
Electricity
10 MW
5 Ton NATURAL GAS
5.5 MW
10 Ton
4.5 MW
After Implementing Cogeneration System
BKP Factory
Page 42
©EEI All Rights Reserved
42 Strictly confidential – For discussion purposes only
Thank You
Excellent Energy International Co.,Ltd 12th Fl., Siripinyo Bldg., 475 Sri-Ayudhaya Rd., Thanon Phyathai, Rajthevee, Bangkok, THAILAND, 10400 T. +66 (0) 2201 3466-7, +66 (0) 2640 0270 F. +66 (0) 2201 3465 http://www.eei.co.th