REMINGTON AVENUE Street Improvement Project Project Workplan| March 2019
15

Remington Avenue Streetscape Project€¦ · 06.03.2019  · Remington Avenue: Discovery Phase . Discovery Walk • Walk segments of the street with the public to witness issues firsthand

Oct 18, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Remington Avenue Streetscape Project€¦ · 06.03.2019  · Remington Avenue: Discovery Phase . Discovery Walk • Walk segments of the street with the public to witness issues firsthand

REMINGTON AVENUE Street Improvement Project

Project Workplan| March 2019

Page 2: Remington Avenue Streetscape Project€¦ · 06.03.2019  · Remington Avenue: Discovery Phase . Discovery Walk • Walk segments of the street with the public to witness issues firsthand

Your City: Our Process

1.LISTEN

2.ANALYZE

3.DESIGN

4.REVIEW

5.REFINE

Page 3: Remington Avenue Streetscape Project€¦ · 06.03.2019  · Remington Avenue: Discovery Phase . Discovery Walk • Walk segments of the street with the public to witness issues firsthand

/'

<

Your City: Our Process We are here

Define & Analyze

Project Identification Maintain &

Improve

Operation & Maintenance

Project Planning Public Input

Blueprint 2028 Industry Standards

Bid & Plan & Build Validate

Project Construction

Design & Refine

Project Design

Page 4: Remington Avenue Streetscape Project€¦ · 06.03.2019  · Remington Avenue: Discovery Phase . Discovery Walk • Walk segments of the street with the public to witness issues firsthand

Street Improvements: Proposed Boundary

Page 5: Remington Avenue Streetscape Project€¦ · 06.03.2019  · Remington Avenue: Discovery Phase . Discovery Walk • Walk segments of the street with the public to witness issues firsthand

Remington Avenue: Discovery Phase

Analysis of Existing Conditions • Right-of-Way widths

• Traffic Counts

• Crash Data

• Presence of sidewalks and utilities,

• Etc.

Page 6: Remington Avenue Streetscape Project€¦ · 06.03.2019  · Remington Avenue: Discovery Phase . Discovery Walk • Walk segments of the street with the public to witness issues firsthand

Remington Avenue: Discovery Phase

Discovery Walk • Walk segments of the street with the

public to witness issues firsthand

• Assess desire lines and pedestrian access

at multiple points along the street

Page 7: Remington Avenue Streetscape Project€¦ · 06.03.2019  · Remington Avenue: Discovery Phase . Discovery Walk • Walk segments of the street with the public to witness issues firsthand

Remington Avenue: Framework Phase

Public Design Listening Workshop • Interactive public listening session to

identify issues

• Present multiple concept elements

based on place and type

• Visual Preference Voting

Page 8: Remington Avenue Streetscape Project€¦ · 06.03.2019  · Remington Avenue: Discovery Phase . Discovery Walk • Walk segments of the street with the public to witness issues firsthand

Remington Avenue: Inviting Success Phase

Draft Vision Plan • Public Unveiling of the Remington Vision

• Voting on at least 2 variations

• Result in a Preferred Public Concept

Page 9: Remington Avenue Streetscape Project€¦ · 06.03.2019  · Remington Avenue: Discovery Phase . Discovery Walk • Walk segments of the street with the public to witness issues firsthand

____ _ 70'---------------

Existing Street Conditions Smith Avenue to Reid Street

Page 10: Remington Avenue Streetscape Project€¦ · 06.03.2019  · Remington Avenue: Discovery Phase . Discovery Walk • Walk segments of the street with the public to witness issues firsthand

--- - -oo··- - - -------

Existing Street Conditions Reid Street to Rose Avenue

Page 11: Remington Avenue Streetscape Project€¦ · 06.03.2019  · Remington Avenue: Discovery Phase . Discovery Walk • Walk segments of the street with the public to witness issues firsthand

1J·t,·- -l..-

l--------==97•- •i·~· ___ _J

Existing Street Conditions Rose Avenue to E. Pinetree Boulevard

Page 12: Remington Avenue Streetscape Project€¦ · 06.03.2019  · Remington Avenue: Discovery Phase . Discovery Walk • Walk segments of the street with the public to witness issues firsthand

What could be Street Improvements? Enhancements to the public space

Street Resurfacing Improved Intersections

. fi: .. ""."'~~· ..... :. ~· rr. , •.

Stormwater Management Street Trees

Multi-Use Trail

Bike Lanes

Page 13: Remington Avenue Streetscape Project€¦ · 06.03.2019  · Remington Avenue: Discovery Phase . Discovery Walk • Walk segments of the street with the public to witness issues firsthand

Why Do this Street Improvement?

SOCIAL and

ECONOMIC BENEFITS:

Create a more accessible environment

Increase safety

Investment in the community

Create an attractive corridor

Page 14: Remington Avenue Streetscape Project€¦ · 06.03.2019  · Remington Avenue: Discovery Phase . Discovery Walk • Walk segments of the street with the public to witness issues firsthand

Preliminary High Level Schedule We are here

March-May 2019 Public Engagement Planning & Events

Dec 2018-Mar 2019 Preliminary Engineering Analysis

June-Nov 2019 Plan Design & Project Updates

Nov 2019-Feb 2020 Project Bids

Feb 2020 City Council Approves Bid Proposal

Feb-Dec 2020 Construction Period

May-June 2019 Concept Plan approved by City Council

Page 15: Remington Avenue Streetscape Project€¦ · 06.03.2019  · Remington Avenue: Discovery Phase . Discovery Walk • Walk segments of the street with the public to witness issues firsthand

Questions?

Kenny Thompson City Planner and Senior Planner

for the Remington Improvement Project [email protected]

229-227-7009

Wayne Newsome City Engineer and Project Lead

[email protected] 229-227-7009